NATIONAL HIGHWAYS AUTHORITY OF INDIA

Project : Construction of Eight Lane access controlled Expressway forom Km 103.400 to Km 128.000 (Talasari to Karvad Section) of Vadodara Mumbai Expressway in the state of Maharashtra,UT of DNH and Gujarat on Hybrid Annuity Mode Under Bharatmala Pariyojana ( PHASE 1 - PACKAGE - X )

CLIENT NATIONAL HIGHWAYS AUTHORITY OF INDIA


INDEPENDENT ENGINEER M/s LEA Associates South Asia Pvt.Ltd.
CONCESSIONAIRE Vadodara Mumbai Expressway Pkg- 10 Pvt ltd
EPC CONTRACTOR Roadways Solution India Infra Limited Spot RFI -Summary Submisssion date 5/12/2024
Status
Contact No.of Selec
Sr.No Date of RFI No. Item No. Description of Activity from To Side length Layer / Requested By Time of Nos. L B D/H Qty. Rem
contractor's ted
. Inspection (m) Lift Inspection (App / (m) (m) (mm) (Cum) arks
Representative by
NA)
Structure

1 5/12/2024 VME/PKG10/STR/11133 Box Checking for reinforcement A1 wall 1st 120+600 A1 LHS 1st Sarajit Mondal 12:00 PM 7044522422
Culvert lift of Box culvert
Checking for shuttering & pouring of
2 5/12/2024 VME/PKG10/STR/11134 Box 120+600 A1 LHS 1st Sarajit Mondal 12:30 PM 7044522422
concrete grade M30 A1 Wall 1st lift of
Culvert
Box Culvert
29 1.45 0.3 12.615
Total 12.615

3 5/12/2024 VME/PKG10/STR/11135 Box Checking for reinforcement A1 Side R/W 105+250 LHS Raft Ashish Gupta 12:00 PM 9322613359
Culvert raft of Box Culvert
Checking for shuttering & pouring of
4 5/12/2024 VME/PKG10/STR/11136 Box 105+250 LHS Raft Ashish Gupta 12:30 PM 9322613359
concrete grade M30 A1 Side R/W raft of
Culvert
Box Culvert
4.4 1.1 0.7 3.4111
4.4 0.9 1 3.987
4.4 2.5 0.7 7.7525
Total 15.151
5 5/12/2024 VME/PKG10/STR/11137 MNB Checking for reinforcement of A2 Wall 122+186 LHS A2 2nd Sarajit Mondal 4:00 PM 7044522422
2nd Lift of MNB

Checking for shuttering & pouring of


6 5/12/2024 VME/PKG10/STR/11138 MNB concrete grade M35 of A2 Wall 2nd Lift 122+186 M-35 LHS A2 2nd Sarajit Mondal 4:30 PM 7044522422
of MNB
23 1.11 1.35 34.31
9.6 1.35 0.735 9.5256
Total 43.836
7 5/12/2024 VME/PKG10/STR/11139 Box Checking for Plate Load Test of Box 122+560 LHS Sarajit Mondal 4:00 PM 7044522422
Culvert Culvert (SBC = 14T /M^2)

Checking for shuttering & pouring of


8 5/12/2024 VME/PKG10/STR/11140 Box 122+560 M-15 LHS Sarajit Mondal 4:30 PM 7044522422
concrete grade M15 of PCC (SBC =
Culvert
14T /M^2) of Box Culvert
76 2.8 212.8
3 76 0.15 34.2
Total 247
9 5/12/2024 VME/PKG10/STR/11141 Box Checking for Plate Load Test of Box 122+560 RHS Sarajit Mondal 3:00 PM 7044522422
Culvert Culvert (SBC = 14T /M^2)
Checking for shuttering & pouring of
10 5/12/2024 VME/PKG10/STR/11142 Box 122+560 M-15 RHS Sarajit Mondal 3:30 PM 7044522422
concrete grade M15 of PCC (SBC =
Culvert
14T /M^2) of Box Culvert
76 2.8 212.8
3 76 0.15 34.2
Total 247
11 5/12/2024 VME/PKG10/STR/11143 Box Checking for Plate Load Test of Box 120+170 LHS Sarajit Mondal 12:00 PM 7044522422
Culvert Culvert (SBC = 18T /M^2)
12 5/12/2024 VME/PKG10/STR/11144 Box Checking for Plate Load Test of Box 120+170 RHS Sarajit Mondal 12:30 PM 7044522422
Culvert Culvert (SBC = 18T /M^2)