Construction Programme

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Annexure- A

3 Dumper 25T/Lead 5km (16cum/hr) 0.2 Hect 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -


Embankment Works + Sub Grade Works
1 Grader (140cum/hr) 1400 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
2 Excavator (100cum/hr) 1000 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
3 Vibratory Compactor (100cum/hr) 1000 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
4 Dumper 25T/Lead 5km (16cum/hr) 160 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
5 Water Tanker (20KL) (200cum/hr) 2000 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
GSB & WMM
1 Grader (100cum/hr) 1200 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
2 Vibratory Compactor (90cum/hr) 900 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
3 Dumper 30T/Lead 15km (13.5cum/hr) 135 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
4 Water Tanker (10000L) (200cum/hr) 2000 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
WMM
1 Grader (100cum/hr) 1200 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
2 Plant 200TPH (90cum/hr) 900 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
3 Front End Loader (90cum/hr) 900 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
4 Dumper 30T/Lead 15km (13.5cum/hr) 135 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
5 Vibratory Compactor (35cum/hr) 900 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
DBM Works
1 Hot mix plant (55.00 cum/hr)/ 160 MT/Hr 440 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
2 Paver 1m/min (16.38cum/hr) 163.8 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
3 Tandem Roller 10T (26.62cum/hr) 266.2 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
4 Pneumatic Tyre Roller 8 T (55.45cum/hr) 554.5 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
5 Front End Loader (90cum/hr) 900 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
6 Dumper 25T/Lead 20km (3cum/hr) 30 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
7 Water Tanker (10000L) (200cum/hr) 2000 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
BC Works
1 Hot mix plant (55cum/hr) 440 cum - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 -
2 Paver 1.5m/min (17.72cum/hr) 177.2 cum - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 -
3 Tandem Roller 10T (16.38cum/hr) 130 cum - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 -
4 Pneumatic Tyre Roller 8 T (48.75cum/hr) 487.5 cum - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 -
5 Front End Loader (90cum/hr) 900 cum - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 -
6 Dumper 25T/Lead 20km (6.72cum/hr) 67.2 cum - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 -
7 Water Tanker (10000L) (200cum/hr) 2000 cum - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 -
Prime & Tack Coat
1 Bitumen Sprayer (750sqm/hr) 7500 sqm - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
Concrete
1 Batching plant (30cum/hr - 2bp) 300 cum - 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 1 1 2 1 1
2 Transit Mixture (3.5cum/hr) 35 cum - 1 1 2 2 2 2 3 3 6 6 7 7 10 11 10 11 10 11 8 9 9 1 1
3 Front End Loader (90cum/hr) 900 cum - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Productivit
S.No Machinery Requirement y/day/no.
Unit Aug-22 Sep-22 Oct-22 Nov-22 Dec-22 Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24

ABSTRACT OF MAJOR EQUIPMENTS


1 GRADER 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 -
2 EXCAVATOR 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 - -
3 VIBRATORY COMPACTOR 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 -
4 WATER TANKER 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 2 -
5 TANDEM ROLLER - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 -
6 FRONT END LOADER - 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 1
7 BACKHOE LOADER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
8 PNEUMATIC TYRE ROLLER - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 -
9 ASPHALT PAVER (7M) - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
10 DUMPER 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 6 6 6 6 6 3 -
11 TRANSIT MIXTURE - 1 1 2 2 2 2 3 3 6 6 7 7 10 11 10 11 10 11 8 9 9 1 1
12 BITUMEN SPRAYER - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
13 WMM PLANT - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
14 HOT MIX PLANT - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 -
15 CONCRETE BATCHING PLANT - 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 1 1 2 1 1

Page 2 of 2