AL SHAREEF HEADQUARTERS.(3B+G+M+3FLOORS),QATAR.

13-Mar-19 MEP - DRAWING LOGs


MEP Service Re Submission Replied Over All No of days delayed by Vistas in
S No Discipline Floor Transmittal No. Drawing No Drawing Title
Reference v Date Date Status Resubmission
14 Electrical B3 BMS ASH-SPQ-KER-ELE-EG-SD-0067 ASH-SPQ-SD-B03-04BMS-0001-00-01 OF 01 00 THIRD BASEMENT FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170

SECOND BASEMENT FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT


Electrical B2 ACS ASH-SPQ-SD-B02-04ACS-0001-00-01 OF 03 02 SHEET 01 OF 03 5-Feb-19 2-Mar-19 C 79

SECOND BASEMENT FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT


30 Electrical B2 ACS ASH-SPQ-KER-AVT-SC-SD-0001 ASH-SPQ-SD-B02-04ACS-0001-00-02 OF 03 02 SHEET 02 OF 03 5-Feb-19 2-Mar-19 C 79

SECOND BASEMENT FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT


Electrical B2 ACS ASH-SPQ-SD-B02-04ACS-0001-00-03 OF 03 02 SHEET 03 OF 03 5-Feb-19 2-Mar-19 C 79

34 Electrical B2 BMS ASH-SPQ-KER-ELE-EG-SD-0066 ASH-SPQ-SD-B02-04BMS-0002-00-01 OF 01 00 SECOND BASEMENT FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170

FIRST BASEMENT FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT


Electrical B1 ACS ASH-SPQ-SD-B01-04ACS-0002-00-01 OF 03 02 SHEET 01 OF 03 5-Feb-19 2-Mar-19 C 79

FIRST BASEMENT FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT


53 Electrical B1 ACS ASH-SPQ-KER-AVT-SC-SD-0002 ASH-SPQ-SD-B01-04ACS-0002-00-02 OF 03 02 SHEET 02 OF 03 5-Feb-19 2-Mar-19 C 79

FIRST BASEMENT FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT


Electrical B1 ACS ASH-SPQ-SD-B01-04ACS-0002-00-03 OF 03 02 SHEET 03 OF 03 5-Feb-19 2-Mar-19 C 79

57 Electrical B1 BMS ASH-SPQ-KER-ELE-EG-SD-0065 ASH-SPQ-SD-B01-04BMS-0003-00-01 OF 01 00 FIRST BASEMENT FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170

Electrical GF ACS ASH-SPQ-SD-GF-04ACS-0003-00-01 OF 01 01 GROUND FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT 5-Feb-19 2-Mar-19 C 79
ASH-SPQ-KER-AVT-SC-SD-0024

Electrical GF BMS ASH-SPQ-SD-GF-04BMS-0004-00-01 OF 01 00 GROUND FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170
ASH-SPQ-KER-ELE-EG-SD-0068

5 Electrical MF ACS ASH-SPQ-KER-AVT-SC-SD-0025 ASH-SPQ-SD-MZ-04ACS-0004-00-01 OF 01 01 MEZZANINE FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT 5-Feb-19 2-Mar-19 C 79

8 Electrical MF BMS ASH-SPQ-KER-ELE-EG-SD-0069 ASH-SPQ-SD-MZ-04BMS-0005-00-01 OF 01 00 MEZZANINE FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170

23 Electrical 1F ACS ASH-SPQ-KER-AVT-SC-SD-0026 ASH-SPQ-SD-L01-04ACS-0005-00-01 OF 01 01 FIRST FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT 5-Feb-19 2-Mar-19 C 79

26 Electrical 1F BMS ASH-SPQ-KER-ELE-EG-SD-0070 ASH-SPQ-SD-L01-04BMS-0006-00-01 OF 01 00 FIRST FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170

43 Electrical 2F ACS ASH-SPQ-KER-AVT-SC-SD-0027 ASH-SPQ-SD-L02-04ACS-0006-00-01 OF 01 01 SECOND FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT 5-Feb-19 2-Mar-19 C 79

46 Electrical 2F BMS ASH-SPQ-KER-ELE-EG-SD-0071 ASH-SPQ-SD-L02-04BMS-0007-00-01 OF 01 00 SECOND FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170

62 Electrical 3F ACS ASH-SPQ-KER-AVT-SC-SD-0028 ASH-SPQ-SD-L03-04ACS-0007-00-01 OF 01 01 THIRD FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT 5-Feb-19 2-Mar-19 C 79

64 Electrical 3F BMS ASH-SPQ-KER-ELE-EG-SD-0072 ASH-SPQ-SD-L03-04BMS-0008-00-01 OF 01 00 THIRD FLOOR BMS SYSTEM LAYOUT 29-Oct-18 12/1/2018 C 170

80 Electrical LRF ACS ASH-SPQ-KER-AVT-SC-SD-0029 ASH-SPQ-SD-LRF-04ACS-0008-00-01 OF 01 01 ROOF FLOOR PLAN ACCESS CONTROL SYSTEM LAYOUT 5-Feb-19 2-Mar-19 C 79

124 Electrical Site Plan FA ASH-SPQ-KER-ELE-FA-SD-0059 ASH-SPQ-SD-SPR-04FA-0001-00-01 OF 01 00 SITE PLAN FIRE ALARM SYSTEM SHEET 01 OF 01 18-Aug-18 24-Sep-18 C 238

126 Electrical Details FA ASH-SPQ-KER-ELE-FA-SD-0057 ASH-SPQ-SD-MPD-04FA-0013-00-01 OF 01 01 FIRE ALARM MIMI PANEL DETAILS 15-Oct-18 18-Nov-18 C 183

132 Electrical Riser/Schedule ACS ASH-SPQ-KER-AVT-SC-SD-0030 ASH-SPQ-SD-SRD-04ACS-0009-00-01 OF 01 02 ACCESS CONTROL SYSTEM RISER DIAGRAM 5-Feb-19 6-Mar-19 C 75

139 Electrical Riser/Schedule BMS ASH-SPQ-KER-ELE-EG-SD-0073 ASH-SPQ-SD-SRD-04BMS-0011-00-01 OF 01 00 BMS SYSTEM SCHEMATIC DIAGRAM 29-Oct-18 12/1/2018 C 170

140 Electrical Riser/Schedule BMS ASH-SPQ-KER-ELE-EG-SD-0074 ASH-SPQ-SD-SRD-04BMS-0012-00-01 OF 01 00 BMS SYSTEM I/O POINTS SCHEDULE 29-Oct-18 12/1/2018 C 170

142 Electrical Riser/Schedule CO ASH-SPQ-KER-ELE-EG-SD-0024 ASH-SPQ-SD-SRD-04CO-0003-00-01 OF 01 01 CO SCHEMATIC DRAWING 8-Dec-18 12-Jan-19 C 128
AL SHAREEF HEADQUARTERS.(3B+

MEP Service
S No Discipline TYPE Transmittal No.
Reference

1 ELECTRICAL DT ASH-SPQ-KER-MEP-DT-0003
HEADQUARTERS.(3B+G+M+3FLOORS),QATAR.
23-Dec-18 MEP - OTHER LOGs (DT,RAR)
Submission Replied Date
Drawing No Rev Drawing Title Date
PANEL FABRICATION DRAWINGS FOR LV PANEL (MDB,EMDB),
DISTRIBUTION BOARDS,CAPACITOR BANKS,AUTOMATIC
0 TRANSFER SWITCH,SUB-MAIN DISTRIBUTION BOARD (LV 28/Nov/18 22/Dec/18
PANEL, SMDB, DB, CB, ATS)
Planned Over All
Activity 23-Dec-18 Remarks
Status
Date