RDSS scheme
(1) About Scheme
Part A Part B
(2) Finding Pattern: The funding pattern for the Rajasthan under RDSS is given below:
a. DISCOMs would publish quarterly un-audited accounts within 60 days of the end of each quarter during first
two years of operation of the scheme (i.e. for FY 2021-22 and FY 2022-23) and thereafter audited quarterly
accounts/limited review by practicing CA within 60 days from 3rd year onwards.
b. DISCOMs would publish audited annual accounts by end of December of the following year during first two
years of operation of the scheme (i.e. for FY 2021-22 and FY 2022-23) and thereafter audited annual accounts
by end of September of the following year from 3rd year onwards.
c. DISCOMs will have ensured that no new Regulatory Assets have been created in latest tariff determination
cycle.
Page 1 of 6
d. State Government to ensure 100% payment of subsidy for the previous year and advance payment of subsidy
up to current period in line with section 65 of EA2003 and wipe out the remaining subsidy amount by the end
of the project period.
e. All Govt Dept. / Attached Offices/ Local Bodies/ Autonomous Bodies/ Boards/ Corporations have made 100%
payment of current electricity dues for the year under evaluation.
f. Progress commensurate to commitment in putting Govt. Offices on prepaid meters as per REF
g. No. of days Payables to Creditors including Gencos for the year under evaluation is equal to or less than the
projected trajectory as per results evaluation framework.
h. Tariff order for the current year in which evaluation is being done and True up of penultimate year is
implemented w.e.f. 1st April of current FY.
II. Discom wise score for FY’22 (Minimum 60 marks out of 100 required)
• 5% on sanction of project.
• 5% on awarding contracts.
• 20% on qualifying the PQR and scoring minimum 60% marks for previous FY.
• 30% on qualifying the PQR and scoring minimum 60% marks for previous FY.
• 35% on qualifying the PQR for previous FY.
• 5% after submission of project completion report.
Page 2 of 6
(6) Sanction Amount by REC (Amount in Crs.)
Dist. Infra ▪ All work orders ▪ Except one ADC circle ▪ All work orders issued
Works issued including All work orders including Addl. S/s
(Circle wise Addl. S/s issued including ▪ Total awarded value: Rs.
appointment) ▪ Total awarded value: Addl. S/s 2,740 Cr
Rs. 2,730 Cr ▪ Total awarded value: Rs.
▪ Date of award:
▪ Date of award: 2,165 Cr
10.04.2023
31.03.2023 ▪ Date of award:
04.04.2023 • Date of award for addl.
▪ Date of award for S/s: 07.10.2023
addl. S/s: • Date of award for addl.
▪ Schedule date of
04.10.2023 S/s: 05.10.2023
completion:
▪ Schedule date of ▪ Schedule date of
09.07.2025
completion: completion:
30.06.2025 03.07.2025
(ii) PMA:
Page 3 of 6
• Survey BoQ for addl. S/s in • Survey BoQ for addl. S/s in • Survey BoQ for addl. S/s in
under process of submission by under process of submission by under process of submission by
contractor contractor contractor
• Erection work is under Process • Erection work is under process • Erection work is under process
• Material Procurement for manufacturer is in slow process due to high demand of the material.
• NABL testing of High value item is taking substantial time in getting test clearance due to limited number of
tests Labs.
• Procurement of Power Transformer is getting delayed as Turnkey contractor are not conducting short circuit
test on one Power Transformer in NABL lab as per requirement of bid document.
• Model code of conduct effected the overall work progress and material procurement in Rajasthan.
For activities of loss • Survey and approval: 3 Month from the date of award
• Supply, erection, testing & Commissioning: 24 months (25% work in each 6
2 reduction other than
Months)
33/11 Substation Total: 27 Months from date of award of contract including survey and
approval
(11) GOI Grant Received (in Rs. Cr) for LR works (Amount in Crs.)
Total Grant
S.No. Item JVVNL AVVNL JdVVNL
disbursed
GOI Grant Disbursed for LR
1 195(10%) 69(5%) 194(10%) 458
works
Total
S.No. Item JVVNL AVVNL JdVVNL Financial
Progress
1 Financial Progress 156 69 152 316.33
Page 4 of 6
1.3. Status of Modernization Works
(12) Status of Modernization works
• DPR submitted for approval from Monitoring Committee dt.18.02.2022 along with DPR Smart metering
and Distribution Infra Works.
• As per the RDSS guidelines, DPR for Modernization shall be sanctioned, subject to Discom
become eligible in evaluation for FY-2021-22 to be carried out in FY-2022-23.
• All the three Discom’s of Rajasthan state became eligible for Sanction of DPR as per evaluation carried out
for FY-2021-22
• Approval of DPR from MoP is under process.
GIS, Network analysis & Asset PeMT & SeMT approval received.
management, NMS & EMS Rs 80 Cr
Status of GIS, Network Analysis Revision of Technical specifications under
& Asset Management Network (JVVNL: 50Cr, AVVNL process as per SeMT direction .
Management System & AVVNL: 15 Cr,
Enterprise Management JdVVNL: 15 Cr.)
System(EMS)
Business Intelligence, Data Rs 15 Cr Preparation of Technical specifications
Analytics and Data under process and after finalization in
Warehousing Software - (JVVNL: 5Cr; common specification committee, NIT
AVVNL shall be issued by FY 24-25.
AVVNL: 5 Cr;
JdVVNL: 5 Cr.)
Page 5 of 6
Roaster Management & load RFP prepared and submitted for
Rs 90 Cr
forecasting System for Ag- discussion in next DCF.
Supply (JVVNL: 30Cr,
AVVNL: 30 Cr, JdVVNL
PT tracking and Health
JdVVNL: 30 Cr.)
Monitoring System
Cyber Security Assessment and Rs 18 Cr NIT for Part-1(Cyber Security Audit) &
Implementation of security opened. Technical evaluation completed.
measures (JVVNL: 6Cr, Financial Bid opened on 11.12.23
JdVVNL
AVVNL: 6 Cr,
JdVVNL: 6Cr.)