Dharoi Based Poshina Regional Water Supply Scheme Part: -2

Work Name: - Poshina RWSS Part-2


Pmc: - Krishna enviro engineers.
Epc: - D N Construction, Palanpur.
Sub Division: - P H S Sub Division, Gwssb Khedbhrama.
Division: -Gwssb Himmat Nagar.
Tender Amount: - 60,35,06,204,00/-.
Agreement: - B 2/58 of Year 2021-22.
LOI Date: - 09-03-2022.
Time Limit: - 18 months.
Pipe progress
Dia Type Supply Laying
500 Dik9 8193.5 7442
300 Dik9 10552.5 9540
150 Dik9 4048.5 4020
100 Dik7 7547 3870
150 Dik7 8269 8040
200 Dik7 5991.5 4200
250 Dik7 1966 1920
400 Dik7 6971.5 6810
110 upvc 10081 7650
160 upvc 22122 13660
508 MS 5112 0.00
219 MS 1524 0.00
273 MS 1200 0.00
323 MS 3744 0.00
168 MS 6420 0.00

Structure progress
Location Capacity Design work Remark
Khedva 25LL HW Yes Upto pcc
Bavalkanthiya 8LL HGLR Yes 5th lift RCC
hglr work
complete
Movatpura 25LL HW Yes Excavation
Dharoi Based Poshina Regional Water Supply Scheme Part: -2

Movatpura 12LL HGLR Yes Excavation


Mathasar 17LL HW Yes Pending
Padhara 3.00LL Yes Topslab
Jotasan 0.50LL Yes Pending