PBP Supervision Team

No SR / WI No Team Project Name Scope of work PMCoW Contractor Location Start End
Construction Construction
HES SWV HES Specialist. QA/QC
Superintendent Supervisor
-
FACILITY IMPROVEMENT CONSTRUCTION
Timbul M. Hutauruk /
Rental Gas Kompresor dan Rental Instrument Kegiatan supervisi konstruksi proyek Rental Gas Kompresor dan Muhammad Abdi, Roy Hanson, Dendi, YULISMAN-335-339
1 2023-JPK-17862 FIC Tony Andi Erizal Naskul Erizal Mahdi Mahidin / Perta MC Minas GS-1 30-May-23
Air Kompresor Rental Instrument Air Kompresor di Minas GS1,2,3,4,5,6 Hendra Yudha/Noviarman RAMADI SUSANTO-335-333
M. Khalik

Timbul M. Hutauruk /
Rental Gas Kompresor dan Rental Instrument Kegiatan supervisi konstruksi proyek Rental Gas Kompresor dan Syuaibun M, Roy Hanson, Dendi, BINTAR PURBA-335-124
2 2023-JPK-17862 FIC Tony Andi Yones Rosal Rosdi Yones Rosal Mahdi Mahidin / Perta MC Minas GS-2 4-Jul-23
Air Kompresor Rental Instrument Air Kompresor di Minas GS1,2,3,4,5,6 Hendra Yudha/Noviarman BUDI JON HENRY-335-217
M. Khalik
Timbul M. Hutauruk /
Rental Gas Kompresor dan Rental Instrument Kegiatan supervisi konstruksi proyek Rental Gas Kompresor dan Syuaibun M, Roy Hanson, Dendi,
3 2023-JPK-17862 FIC Tony Andi Edward H Sukiyatno Sukiyatno Mahdi Mahidin / RANTIYONO-335-178 Perta MC Minas GS-3 4-Jul-23
Air Kompresor Rental Instrument Air Kompresor di Minas GS1,2,3,4,5,6 Hendra Yudha/Noviarman
M. Khalik

Timbul M. Hutauruk / Syuaibun M, Dody L Simamora,


Rental Gas Kompresor dan Rental Instrument Kegiatan supervisi konstruksi proyek Rental Gas Kompresor dan
4 2023-JPK-17862 FIC Tony Andi Madong Ifwa Oktariadi Ifwa Oktariadi Mahdi Mahidin / Hendra Yudha/Noviarman, Roy BUDI JON HENRY-335-217 Perta MC Minas GS-4 30-May-23
Air Kompresor Rental Instrument Air Kompresor di Minas GS1,2,3,4,5,6
M. Khalik Hanson

Timbul M. Hutauruk /
Rental Gas Kompresor dan Rental Instrument ScopeKegiatan supervisi
of work konstruksi
as per describeproyek
below Rental
but notGas Kompresor
limited danSurvey
to : - Site Hasim Mudin, Roy Hanson, Dody L
5 2023-JPK-17862 FIC Tony Andi Jhoni Yuda Putra Burhanuddin Manik Jhoni Yuda Putra Mahdi Mahidin / Perta MC Minas GS-6 28-Jul-23
Air Kompresor Rental
to verifyInstrument
AFC drawing Air asKompresor
per actualdi condition
Minas GS1,2,3,4,5,6
- Survey underground Simamora, Hendra Yudha/Noviarman BANTU SIANTURI-335-114
M. Khalik
facilities - Develop and submit CWMS document and ITP QA/QC
procedure - Provide adequate resource (manpower and equipment) - Timbul M. Hutauruk / ASLIM-ADK-MD22-19836
Syuaibun M, Dendi, Hendra
6 3700132555 FIC Penggantian Fasilitas Flare Stack di GS-3 Minas Provide dedicated responsible person as per MSW guideline - Tony Andi Edward H Sukiyatno Edward H Mahdi Mahidin / LUNDU TUA SINAGA-ADK- ADM Minas GS-3 11-Oct-23
-Fabricate
Membuatand akses danpipeline,
area kerja Yudha/Noviarman, Roy Hanson
install civilmenggunakan
and structure,scaffolding
mechanical, (Setelah
electrical M. Khalik MD22-19538
air
anddiinstrumentation
dalam firepit dikosongkan) - Membersihkan
facilities - Support resource for endapan lumpur
commissioning
pada dasar firepit
and start-up (setelah
- Provide MTOair di dalam
from firepitand
warehouse dikosongkan)
project yard- -
Timbul M. Hutauruk / Syuaibun M, Dody L Simamora,
Membuang endapan lumpur di dalam area GS - Instalasi
Provide close out document report and markup as-built drawing lapisan
7 3700140886 FIC Perbaikan Fire Pit Minas GS2 Tony Andi Yones Rosal M. Restu M. Restu Mahdi Mahidin / Hendra Yudha/Noviarman, Roy RIO HANDOKO-WSP18370 PDC Minas GS-2 15-Mar-24
HDPE geomembrane untuk mengatasi kebocoran air yang terjadi
M. Khalik Hanson
pada firepit - Melakukan uji kebocoran pada (leak test) lapis HDPE
geomembrane yang sudah terpasang - Memperbaiki tanah di sekitar
firepit yangreroute
Demolish, tererosiexisting
akibat piping
rembesan air Pemindahan
sistem firepit lighting pole, Jumartoni / ZAHIRUDDIN-ADK-MD22-
8 3700133780 FIC Early work OPLL Petapahan Upgrade Tony Andi Hendri Dediriko Hendri Septiman Rudi, Wendri Hadi ADM Petapahan GS 9-Feb-24
alarm pole Pemindahan posisi fire monitor Install electrical cable Devitra 19594

Pemasangan Concrete Slab di KBGS untuk PHR Request Contractor to Install/Construct Concrete Slab. Civil Jumartoni / AMIR KHAIRUL-ADK-MD22-
9 3700141521 FIC Mechanical • Fabrikasi material piling Tony Andi Zulfiharmen Arlines Zulfiharmen Wispa Yanto ADM KB GS 24-Feb-24
pemasangan mud cooler (Install Concrete Slab). SOW as per AFC menjadi
and EWPscrew pile oleh
Approved. Devitra 14298
kontraktor WUR Civil • Land Clearing dan Earthwork dilakukan oleh
kontraktor WUR • Pembuatan concrete formwork dilakukan oleh
kontraktor WUR • Installasi screw pile dilakukan oleh kontraktor Timbul M. Hutauruk /
PEMBUATAN PONDASI TRANSFORMER 250
10 3700140731 FIC WUR • Installasi reinforcement steel bar dilakukan oleh kontraktor Tony Andi Triyono Rosdi Triyono Mahdi Mahidin / Hasim Mudin, Dody LS, Yon Ridar SAUT SITOMPUL-2309497 VI BRIJ KBJ 26-Mar-24
MVA-KOTA BATAK JUNCTION (KBJ)
WUR • Pekerjaan concrete dilakukan oleh kontraktor WUR M. Khalik
Electrical • Cable Locator • Lokasi pengerjaan proyek dilakukan
di area yang banyak peralatan kelistrikan Commisioning (Termasuk Timbul M. Hutauruk /
Fabrikasi dan Instalasi SID Platform (Lighting PSSR) Mark LUNDU TUA SINAGA-ADK-
11 3700131788 FIC Fabrikasi danupinstalasi
drawingSID
& As-built
Platformdrawing oleh kontraktor
untuk maintenance tiangWUR.
lampu Tony Andi Edward H Sukiyatno Edward H Mahdi Mahidin / Yon Ridar (E/I), Syuaibun (Civil) ADM Minas GS-3 3-May-24
Improvement) MD22-19538
M. Khalik

Supervision and Inspection for EPC Project


Supervision and Inspection for EPC Project Substation Upgrade Paket Jumartoni / MUHAMMAD ADRIANTO
12 SPHR00560A FIC Substation Upgrade Paket B - Old Kotabatak Tony Andi Zulfiharmen Arlines Zulfiharmen Wendri Hadi (E/I), Wispa Yanto (Civil) Multifab OKB Substation 2-May-24
B - Old Kotabatak Substation Devitra LUBIS-83624
Substation

GENERAL PROJECT CONSTRUCTION (GPC)


EKO SALIUS -01230610594
Timbul M. Hutauruk / LISDEN CHARLES EDUARD
Konstruksi New Wetland & Pre-Wetland On Ingan P. Muhammad Abdi, Dendi, Roy Hanson,
1 3700148937 GPC Wetland dan Tali Air (Off Plot) Romaison L. Tobing Naskul Ingan P. Sembiring Mahdi Mahidin / SIPAYUNG-01230610364 VDI Minas GS-1 6-Mar-24
Plot Sembiring Hendra Yudha/Noviarman
M. Khalik HOTBER SIREGAR-
Konstruksi Pre-Wetland & Wetland di Minas GS-3, termasuk: - 01221010970
pekerjaan earthwork (balance cut wetland, pembentukan jalan akses, Timbul M. Hutauruk /
Muhammad Abdi, Dendi, Roy Hanson, WIWIK SUHENDRI PPD -
2 3700127819 GPC Konstruksi Wetland Minas GS-3 excavation, dll) - pekerjaan civil/structure (konstruksi control box, Romaison L. Tobing Syafrizon Sukiyatno Syafrizon Mahdi Mahidin / PDC Minas GS-3 4-Jan-24
Hendra Yudha/Noviarman 722101113
instalasi fencing & barbed wire, fabrikasi steel structure, dll) - M. Khalik
pemasangan steel pipe
Lingkup Pekerjaan: culvert 30"
- Reaktivasi - pekerjaan
& Perbaikan Pitpendukung lainnya
Idle komponen
Reaktivasi Pit dan Konstruksi Wetland Minas pengecoran (concrete); konstruksi concrete walkway; pemasangan Timbul M. Hutauruk / FERI NOVPUTRA-ADK-MD22-
3 3700136444 GPC GS-4, Minas GS-1, Kotabatak GS Lingkup handrail; pemasangan saluran culvert inlet dan outlet dari pit - Romaison L. Tobing Defrion Ifwa Oktariadi Defrion Mahdi Mahidin / Syuaibun M 14274 ADK MD Minas GS-4 1-Dec-23
Multidisiplin Konstruksi concrete control box dan titik penaatan - Konstruksi steel M. Khalik DAFRIZAL-ADK-MD22-19498
Lingkup Pekerjaan: - Reaktivasi & perbaikan Pit Idle dengan
structure - Pemasangan pagar perimeter Wetland
pemindahan lumpur; penimbunan, pembentukan, dan pemadatan
HOTMAN SIREGAR-PB-NW-
dasar dan dinding pit; supply dan install lapisan HDPE geomembrane; Timbul M. Hutauruk /
1381
4 3700140352 GPC Reaktivasi Pit Minas GS-6 konstruksi concrete pemberat geomembrane dan walkway; Romaison L. Tobing Halasson Lubis Burhanuddin Manik Halasson Lubis Mahdi Mahidin / Syuaibun M PB Minas GS-6 6-Feb-24
TURGAS SIMANJUNTAK-PB-
pemasangan handrail; pemasangan saluran culvert inlet dan outlet M. Khalik
Lingkup NW-1342
dari pit -Pekerjaan:
Konstruksi -concrete
Reaktivasi & perbaikan
control Pit Idle dengan
box - Konstruksi steel structure
pemindahan
guardrail lumpur; penimbunan, pembentukan, dan pemadatan
dasar dan dinding pit; supply dan install lapisan HDPE geomembrane; Timbul M. Hutauruk /
5 3700140352 GPC Reaktivasi Pit Minas GS-6 konstruksi concrete pemberat geomembrane dan walkway; Romaison L. Tobing Halasson Lubis Burhanuddin Manik Burhanuddin Manik Mahdi Mahidin / Syuaibun M ANTONY MANULANG PB BP 4A-94 28-Feb-24
pemasangan handrail; pemasangan saluran culvert inlet dan outlet M. Khalik
dari pit - Konstruksi concrete control box - Konstruksi steel structure
guardrail
- Konstruksi water spreader - Reaktivasi PWTP 01 s/d 05 termasuk Timbul M. Hutauruk /
Hasim Mudin (Civil), Dody L. S (WI),
6 3700148197 GPC Reaktivasi Pit Minas GS-5 pemasagan pipa saluran dan shipon - konstruksi control box dan Romaison L. Tobing Halasson Lubis Miranda Geovani Miranda Geovani Mahdi Mahidin / ANTONY MANULANG PB Minas GS-5 3-May-24
Roy Hanson (Coating)
pemasangan pipa saluran M. Khalik

PROGRAM CONSTRUCTION (PC) Perbaikan segment pipa URC meliputi: - Excavation & Backfill -
Dismantle Casing refer to ROKA-GENFGENAALL-PPL-PCDPHR-0001-00 Timbul M. Hutauruk /
Dody L Simamora, Hasim Mudin, Roy
1 3700118938 PC URC Paket-6 South 2023 (15 Spots) - Install Sleeve refer to ROKA-GENFGENA000-PPL-PCDPHR-0001-06 - Tony Andi Jhoni Yuda Putra Miranda Geovani Miranda Geovani Mahdi Mahidin / ANTONI SIAGIAN-23.05040 BKP Minas 3D-64 17-Jul-23
Hanson, Yon Ridar
Touch-up pada bagian pengelasan dengan coating system 2.15 serta M. Khalik
inspeksi yang disyaratkan