Name of work : Construction of Concrete roads 1) SH-76 Angaon Junction to Pilanze Bk , Pilanze Kh to Bedarpada road in

Bhiwandi , District Thane under OARDS .

Name of Client: Mumbai Metropolitan Region Development Authority

Name of Consultant : Ekansh Concepts Limited, Mumbai.

1 Name of Road- SH-76 Angaon Junction to Pilanze Bk , Pilanze Kh road

Abstract Sheet .
Sr. No. Description of Items Unit Qty Rate Rs. Amount , Rs.

Section -I Site Clearence & Dismantling


Cleaning and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned up to a lead of 1000 metres including removal and
1 disposal of top organic soil not exceeding 150 mm in thickness. as per MORTH 201

Sq .m. 2,800.00 12.50 35,000.00

Cutting down trees including trunks and branches with girths above 30 cm to 60 cm
and stacking the materials neatly with all lifts and lead of 1000 m as dircted and
2 earth filling in the depression / pit if any. As per MORT&H 201

Nos. 3.00 511.00 1,533.00

Cutting down trees including trunks and branches with girths above 60 cm to 90 cm
and stacking the materials neatly with all lifts and lead of 1000m as dircted and
3 earth filling in the depression / pit if any. As per MORT&H 201

Nos. 4.00 847.00 3,388.00

Transplanting of Trees: Planting the tree in the pit filled with good soil, pressed
down layer by layer, insecticide to be sprayed before planting, broken limbs to be
removed, tree to be supported by three strong stakes driven into ground metre away
from the stem, transport to the site & planting, preparation of tree basin, watering
4 & maintaining for 1 month replacement of casualities till 1 month.

Nos. 7.00 882.00 6,174.00

Dismantling brick masonry in lime or cement mortar and stacking the materils as
5 directed with all leads, lifts etc.
Cum. 36.75 335.00 12,311.25

Dismantling stone masonry in lime or cement mortar including stacking the


6 materils as directed with all leads, lifts etc
Cum. 40.00 380.00 15,200.00

Dismantling the R.C.C. Work 1:2:4 and sorting out the materials such as steel etc.
7 as directed and stacking them within the specified lead as directed etc. complete.

Cum. 111.10 1,451.00 161,206.10

Dismantling of flexible pavements and disposal of dismantled materials up to a lead


8 of 1000 metres, stacking serviceable and unserviceable materials separately etc.
complete.
Cum 392.00 430.00 168,560.00

Removing Np-2 and Np-3 class pipes including stacking at road side as directed by
9 the Engineer in charge. Upto 900mm dia and above. etc complete.

Rmt 108.00 310.00 33,480.00

Total Ammount of SECTION-1 436,852.35


Section -II Earth Work
Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum
including dressing section to the required grade, camber and side slopes and
conveying the excavated materials with all lifts upto a lead of 50m. and spreading
10 -
for embankment or stacking as directed.

Cum. 4,504.00 119.00 535,976.00


-
Excavation for roadway in hard murum & Boulder including dressing section to the
required grade, camber and side slopes and conveying the excavated materials with
11 all lifts upto a lead of 50m.and spreading for embankment or stacking as directed. -

Cum. 1,986.00 139.00 276,054.00


Excavation for roadway in soft rock, including dressing section to the required
grade, camber and side slopes and conveying the excavated materials with all lifts
12 upto a lead of 50m. and spreading or stacking as directed. -

Cum. 1,344.00 177.00 237,888.00


-
Excavation for roadway in hard rock by wedging and chiselling or line drilling
including dressing section to the required grade, camber and side slopes and
13 conveying the excavated materials with all lifts upto a lead of 50m. and spreading -
for embankment or stacking as directed.

Cum. 258.00 1,419.00 366,102.00


-
Providing earth work in embankment with approved materials obtained from other
sources upto lead of 14 km. including all lifts, laying in layers of 20cm. to 30cm.
thickness breaking clods, dressing to the required lines, curves, grades & section,
14 watering and compaction with vibratory roller with V-Sat attachment to achieve -
not less than 97 % of standard proctor density etc. complete ( Material obtained
from Other sources)

Cum. 3,538.00 1,226.00 4,337,588.00


-
-
Conveying materials obtained from road cutting including all lifts, laying in layers
of 20cm. to 30cm. breaking clods, dressing to the required lines, curves, grades and
section, watering and compacting to not less than 97% of standard proctor density
15 for a lead of 300m. to 500m. inclusive, from the site of excavation to the site of -
deposition as directed.

Cum. 5,866.80 393.00 2,305,653.38


-
Conveying materials obtained from road cutting including all lifts, laying in layers
of 20cm. to 30cm. breaking clods, dressing to the required lines, curves, grades and
section, watering and compacting to not less than 97% of standard proctor density
for a lead from 500m. to 14 km inclusive, from the site of excavation to the site of
16 deposition as directed.( This Item will be operated only after approval of the -
Concerned Superintendent Engineer MMRDA )

Cum. 5,916.80 818.00 4,839,944.44


Total Ammount of SECTION-II 12,899,205.83

Section -III Road Pavement


Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering
17 and compacting with vibratory roller to the required density. By Mechanical Means
- Grading II (Using Screening Type B (11.2 mm) Aggregate)

Rate as per item no.3.19, sr.no.129 Pg. no.29 SSR 2022-23 Cum. 12.20 2,630.00 32,086.00
-
Providing and constructing 50 mm. thick Modified Penetration Macadam (MPM)
road surface including all mataerials, preparing the existing road surface, spreading
40mm. stone metal layers 30% crusher broken metal + 70% Hand broken (by
breaking rubble obtained by blasting) heating and spraying the bitumen of specified
grade @ 1.75 kg/sqm, spreading 12mm.size chips compacting with static roller
having weight 8 to 10 MT. to achive the desired degree of compaction as per
18 Technical Specification Clause 506 etc. complete. Including picking of existing -
WBM surface.(VG-30 bulk bitumen rates are considered to arrive at rates)

Cum. 22.00 238.00 5,236.00


-
Construction of Granular sub-base by providing close graded Material, mixing in a
mechanical mix plant at OMC, carriage of mixed Material to work site, spreading
in uniform layers with motor grader/ Paver on prepared surface and compacting
19 with vibratory roller to achieve the desired density, complete as per clause 401 -- -
Plant Mix Method and Grading - I Material

Cum. 2,203.20 2,529.00 5,571,892.80


-
Wet Mix Macadam -- Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material with
water at OMC in mechanical mix plant carriage of mixed Material by tipper to site,
laying in uniform layers with paver in sub- base / base course on well prepared
20 surface and compacting with vibratory roller to achieve the desired density. Laying -
By Grader/Paver.

Cum 215.00 2,488.00 534,920.00


Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm
21 thick including hand packing and compacting etc.complete. -

Cum. 256.46 1,845.00 473,168.70


-
Construction of dry lean cement concrete Sub- base over a prepared sub-grade with
coarse and fine aggregate ( natural sand/ VSI grade finely washed crushed sand)
conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, , cement
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant/ Weigh batch mixer, transported to site with all
leads and lifts, laid with a paver with electronic sensor /by suitable means as
22 approved by Engineer-incharge , compacting with vibratory roller, finishing, curing -
and including preparation of sub-grade surface if required etc. complete.

Cum. 811.25 4,261.00 3,456,736.25


-
Providing & laying R.C.C.running beam in M-40 cement concrete including
required formwork mixing, compacting & curing ,etc. complete reinforced with
12mm dia.(Minimum 4 Nos.)M.S. main bars & 6mm Dia M.S. rings at 15 cm c/c to
be anchored in slipper slab properly with M.S. reinforcement as per drawing etc.
complete as specified (Steelwillnotbepaidseparately). Contractor has to make his
23 own arrangement for portable water for construction/curing with hessian cloth, etc. -
& will not be paid separately.Beam Size: b) 23 cm. x 30 cm.

Rmt 2,950.00 779.00 2,298,050.00


-
Providing and laying 125 micron Low Density Polyethylene (LDPE) sheet
24 confirming to IS 3395 : 1997 below concrete pavement including all materials and -
labour complete
sqm 5,400.00 30.00 162,000.00
-
Providing and fixing in position TMT FE 500, 32 mm dia dowel bars precoated with
anticorrosive epoxy paint of required Dia. 60 cms. Long and at 30.00 cm. C/C and
wherever directed including handling, straightening, necessary cutting supported by
TMT FE 500, chairs with proper alignment by using properly designed assembly of
25 Bulkheads lubricating half length with bituminous paint as directed etc. complete. -

No 782.00 539.00 421,498.00


-
Providing & fixing high density polythene pipe of approved quality to fit around the
dowel bars of 32mm dia at the end of expansion joints, fully greased inside, cotton
waste in the pipe around the dowel bars & the pipe duly capped at the end as
26 directed.(H.D.P.pipe shall be 30 cm in length). As shown in the drawing. -

Nos 782.00 28.00 21,896.00


-
Providing and fixing in position TMT FE 500, tie bars precoated with anticorrosive
epoxy paint of 12 mm dia. 70 cms.long and at 30.00 cm. C/C and wherever directed
including handling, straightening wrapping with paper of approved quality for half
length, necessary cutting, handling, straightening , supported by assembly of TMT
27 FE 500, chairs with proper alignment etc. complete -

Nos 205.56 306.00 62,900.00


-
Providing and laying in-situ M40 Grade unreinforced plain cement concrete
pavement over a prepared sub base with 43 grade cement , coarse and fine
aggregate ( natural sand/ VSI grade finely washed crushed sand) conforming to IS
383, using fine and coarse aggregates combined gradation as per Table 600-3 of
MORTH Specification 2013, mixed in a batching and mixing plant/ non tilting
mixer and Weigh batcher as per approved mix design, admixtures, transporting to
site, spreading, laying with approved make paver,compacted and finished in a
continuous operation, finishing to lines and grades as directed by Engineer-in-
charge and curing by curing compound /by providing cement vata in cement
28 Mortar 1:8 @0.6m X 0.6m centre to centre, admeasuring 80 mm at bottom and 40 -
mm at top with depth of 75mm and maintaining the same throughout curing period
by any other method approved by Engineer-in-charge.

CUM 1,639.90 8,589.00 14,085,101.10


-
Providing polypropylene fibers 300e3 Multi- Dimensional Graded Fibrillated 100%
Virgin as per ASTMC1116 III Type 4.1.3 Std.at the rate of 125 gms per bag of
29 50Kgs of cement etc. -

Cum 2,623.84 392.00 1,028,545.28


-
Cutting transverse contraction joints 3 to 4 mm wide and depth 80 mm.in concrete
slab using concrete cutting machine with diamond studded saw within 48 hours of
casting of bay / slab etc. complete including subsequent widening of the groove 8 to
30 -
10 mm. wide at top having depth of 15 mm. as directed by Engineer incharge

Rmt 6,013.22 76.00 457,004.89


-
Providing to contraction joints polysuphide sealent (Pouring grade) confirming to
BS : 5212 - 1989 into sawed groove widened at top for sealent reservoir of specified
size and shape as per detailed drawing including fixing Polyethylene foam backer
rod of required diameter (appraox. 25% larger than the initial 3 mOne Metric
Tonneo 4 mm. joint) overlaid with bond breaking tape as per detailed drawing.
Item includes cleaning the joints with water jet / air compressor and allowing joint
31 to become thoroughly dry before sealent is applied and applying primer. (A) -
Contraction and longitudinal joints (15 mm. deep x 8 mm.wide)

Rmt 6,313.22 311.00 1,963,412.11


-
Providing & fixing in position premoulded asphalt filler 12mm thick conforming to
I.S.1838 of 1983 for placing of the expansion joint, around manholes & water
entrances, etc. put to the required depth & 25 mm below the camber, etc. complete
32 -
as directed.

SQM 40.00 314.00 12,560.00


-
Prime coat - Providing and applying primer coat with bitumen emulsion on

33 prepared surface of granular Base including cleaning of road surface and spraying, -

primer at the rate of 0.60 kg/sqm using mechanical means.


SQM 125.00 38.00 4,750.00
-
Providing and applying tack coat on the prepared surface heating by fames in
Boiler and spraying bitumen set footed in bitumen boller on B.T. surface 2.5 kg/10
34 sqm.(VG-30 bulk bitumen rates are considered to arrive at rates) -

SQM 320.00 41.00 13,120.00


-
BITUMINOUS MACADAM: Proving and laying bituminous macadam using
crushed aggregates of Grading 1, premixed with bituminous binder, transported to
site with VTS , laid over a previously prepared surface, finished to the required
grade, level, alignment, and rolling to achieve the desired compaction for 80/100
mm compacted thickness with 3.3 % using specified grade of Bitumen. -- USING
35 Batch mix type hot mix plant with SCADA, Sensor Paver, vibratory roller.(VG-30 -
bulk bitumen rates are considered to arrive at rates)

Cum. 25.80 8,805.00 227,169.00


DENSE BITUMINOUS MACADAM: Proving and laying dense bituminous
macadam using crushed aggregates of Grading 1, premixed with bituminous binder
of specified grade of Bitumen @ 4.50 per cent by weight of total mix and filler,
transported to site with VTS , laid over a previously prepared surface, finished to
the required grade, level, alignment, and rolling to achieve the desired density for
36 76-100 mm compacted thickness .USING Batch mix type hot mix plant with -
SCADA, Sensor Paver, Vibratory roller with Stone Dust filler.(VG-30 bulk bitumen
rates are considered to arrive at rates)

Cum. 21.00 11,047.00 231,987.00


-
BITUMINOUS CONCRETE:- Providing and laying bituminous concrete using
crushed aggregates of grading 1, premixed with bituminous binder @ 5.20 per cent
by weight of total mix and filler, transported to site with VTS , laid over a
previously prepared surface, finished to the required grade, level, alignment, and
rolling to achieve the desired compaction for 50 mm compacted thickness with
specified grade of Bitumen,Excluding prime / tack coat. For Bitumen of specified
37 grade -- USING Batch mix type hot mix plant with SCADA, Sensor Paver, -
Vibratory roller with Stone Dust filler. (VG-30 bulk bitumen rates are considered to
arrive at rates)

Cum. 18.50 12,169.00 225,126.50


-
Providing & fixing in the carriageway 100 mm thick interlocking concrete unishape
pavers( monolithic- single layer precast concrete blocks) of grey cement
colouredhaving average crushing strength not less than 50N/mm² as per technical
specificationand IS CODE 15658:2006, placed on average compacted thickness 25
mm well graded sand cushioning uniformly compacted with proper capacity
38 mechanical compactor with required level, grade and camber etc. complete as -
specified and as directed by the Engineer.

SQM 95.00 941.00 89,395.00


-
Providing Heavy Duty Fibre Glass Reinforced Plastic Temporary Barricade of 1.75
m hight, with base width of 430 mm as a provision to accept water ballasting of 101
Itrs-110 Ltrs approx. and arrangement for traffic diversion such as traffic signals
during construction at site, for day and night as per requirement. The raw material
shall be UV stabilized Linear Low Density Polyethylene and should meet the
requirements stipulated in standard IS: 10146-1982, IS:10141-1982 and should also
comply to FDA:CFR Title 21.177.1520. Olefin Polymers , with specific FRP Grade
300-104 reinforced -----------------and 2 nos on Extension top for holding light
brackets / Rod for cloth holding. The plastic barricades has a strong vertical rib of
39 1740 mm length at the rear centre & 72 No's ofa) For 725 mm height (LType Jersey -
Barrier ) ,Empty Weight:6.67 Kilogram/ Rgm,Weight Full : 35.89Kilogram/ Rgm
approx. (After Water / Sand Filling)

RMT 1,571.00 1,846.00 2,900,066.00

Total Ammount of SECTION-III 34,278,620.63


Section-IV - Storm Water Drain

Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
including shoring and strutting, dewatering as necessary and disposing off
40 excavated stuff as directed etc. complete. ( By Mechanical Means ) -

Rate as per item no.12.03, sr.no.407 Pg. no.84 State Schedule Rates for year 2022-23
cum 50.00 90.00 4,500.00

-
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
41 including shoring and strutting, dewatering as necessary and disposing off - -
excavated stuff as directed etc. complete. ( By /manaual Means )
Rate as per item no.12.02, sr.no.406 Pg. no.84 State Schedule Rates for year 2022-23
cum 30.00 239.00 7,170.00

-
Excavation for foundation in hard murum and boulders including shoring and
42 strutting, dewatering as necessary and disposing off excavated stuff as directed etc. -
complete.

Rate as per item no.12.06, sr.no.409 Pg. no.84 State Schedule Rates for year 2022-23
Cum 30.00 286.00 8,580.00

-
Excavation for foundation in soft rock including shoring and strutting, dewatering
43 as necessary and disposing off excavated stuff as directed etc. complete. -

Rate as per item no.12.08, sr.no.410 Pg. no.84 State Schedule Rates for year 2022-23
Cum 50.00 557.00 27,850.00

-
Excavation for foundation in hard rock by chiselling and wedging or line drilling
44 including shoring and strutting, dewatering as necessary and disposing off -
excavated stuff as directed etc. complete
Rate as per item no.12.11, sr.no.413 Pg. no.85 State Schedule Rates for year 2022-23
Cum 30.00 1,932.00 57,960.00

-
Providing rubble filling of trap/ granite/ quartzite gneiss stones for foundations
45 including filling voids with sand/grit and compaction etc complete -

Rate as per item no.11.01, sr.no.376 Pg. no.81 State Schedule Rates for year 2022-23
Cum 50.00 2,300.00 115,000.00

-
Providing and laying Cast in situ/Ready Mix cement concrete in M15 of trap/
granite/quartzite/gneiss metal for foundation / steps including steel centering,
formwork, laying/pumping, compacting, roughening them if special finish is to be
provided, finishing uneven and honeycombed surface and curing etc. complete. The
Cement Mortar 1:3 plaster is considered for rendering uneven and honeycombed
surface, only. Newly laid concrete shall be covered by gunny bag, plastic, tarpaulin
etc. (Wooden centering will not be allowed.),with fully automatic micro processor
46 based PLC with SCADA enabled reversible Drum Type mixer/concrete Batch mix -
plant (Pan mixer) etc. complete. With fine aggregate (Crushed sand VSI
Grade

Rate as per item no.11.02, sr.no.377 Pg. no.81 State Schedule Rates for year 2022-23
Cum 20.00 7,121.00 142,420.00

-
Providing and laying Cast in situ/Ready Mix cement concrete in M20 of trap/
granite/quartzite/gneiss metal for bed blocks, foundation blocks and such
other items including bailing out water, Steel centering, formwork, laying/
pumping, compacting, roughening them if special finish is to be provided, finishing
uneven and honeycombed surface and curing etc. complete. The Cement Mortar 1:3
plaster is considered for rendering uneven and honeycombed surface only. Newly
laid concrete shall be covered by gunny bag, plastic, tarpaulin etc. (Wooden
centering will not be allowed.), with fully automatic micro processor based PLC
47 with SCADA enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan -
mixer) etc. complete. With fine aggregate (Crushed sand VSI Grade)

Rate as per item no.24.04, sr.no.828 Pg. no.175 State Schedule Rates for year 2022-23
Cum 230.55 7,549.00 1,740,421.95

-
Providing and laying Cast in situ/Ready Mix cement concrete in M-20 of trap/
granite/ quartzite/ gneiss metal for R.C.C. pardi of required thickness including
steel centering, formwork, cover blocks, laying/pumping, compacting , curing ,
finishing and rougheningthem if special finish is to be provided and curing
complete.(Excluding reinforcement and structural steel).with fully automatic micro
48 processor based PLC with SCADA enabled reversible Drum Type mixer/ concrete -
Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Crushed sand VSI
Grade

Rate as per item no.25.11, sr.no.836 Pg. no.178 State Schedule Rates for year 2022-23
Cum 15.00 16,396.00 245,940.00

-
Providing and laying Cast in situ/Ready Mix cement concrete M-25 of trap/
granite /quartzite/ gneiss metal for R.C.C. slabs and landings as per detailed designs
and drawings including steel centering, formwork, cover blocks, laying/pumping,
compaction finishing the formed surfaces with cement mortar 1:3 of sufficient
minimum thickness to give a smooth and even surface or roughening if special finish
is to be provided and curing etc. complete,(Excluding reinforcement and structural
49 steel).with fully automatic micro processor based PLC with SCADA enabled -
reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete.
With fine aggregate (Crushed sand VSI Grade).

Rate as per item no.26.17, sr.no.860 Pg. no.185 State Schedule Rates for year 2022-23
Cum 20.00 13,442.00 268,840.00

Providing and fixing in position TMT - FE - 500 bar reinforcement of various


diameters for R.C.C. footings, foundations, slabs, beams columns, canopies,
staircase, newels, chajjas, lintels pardis, copings, fins, arches etc. as per detailed
designs, drawings and schedules. including cutting, bending, hooking the bars,
50 binding with wires or tack welding and supporting as required complete. -

Rate as per SSR 2022-23 item. No.14.17 MT 50.00 90,406.00 4,520,300.00


-
Supplying & Fixing 0.9 m x 0.6 m rectangular SFRC frame and cover as per
51 drawing fixed complete to manhole as specified and directed -

Rate as per item no.26.33, sr.no.871 Pg. no.188 State Schedule Rates for year 2022-23
Nos 15.00 7,031.00 105,465.00

-
Providing and fixing of cement concrete Kerb Stone of various grades of size:
500mm width x 325 height x 165mm thick (Half Batter, Bull Nose/ Full Batter)
manufactured in wet press vacuum dewatering technology plant / equivalant with
face pimple finish for high visibility with excellent quality and finish and edges
perfect and sharp. Grade – M-25 including excavation in any soil except rock,
laying a leveling course of M 15 grade RMC 100mm thick to required slope
(inclusive of form work), jointing in C.M. 1:2 proportion flush to concrete surface,
52 painting exposed surface with one coat of primer and two coats of 1st grade road -
marking paint in the yellow/ white/ black or any shade as directed. (Kerbstones
shall be procured from MCGM registered agencies).

Rate as per MCGM SOR-2018 item. No.R2-SE-10-12 RMT 75.00 996.00 74,700.00
-
Providing & fixing in the foothpath Concrete Paver blocks 200 X 200 X 80 mm
thick or any approved size in grey or any specified colour with shot blasted texture
or any aproved texture on top surface of approved pattern/shape and colour having
average crushing strength not less than 50N/mm² as per technical specification sand
IS CODE 15658:2006 manufactured in double layer precast concrete Paverblocks
12to15 mm thick top layer and consisting of cubical shape Quartz stone aggregate
8mm seve 100% passing and retained on 4.75mm sizesieve, silicasand. The bottom
layer should be 65 to 68 mm thick in grey cement having 12 mm sieve 100% passing
aggregates as per technical specifications, rested on average compacted thickness of
53 25mm well graded sand cushioning uniformly compacted with proper capacity -
mechanical compactor with required level, grade and camber etc. complete as
specified and as directed by the Engineer.

SQM 75 1,533.00 114,975.00


Total Ammount of SECTION-IV 7,434,121.95
Section-V- CD WORKS & Culverts
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
including shoring and strutting, dewatering as necessary and disposing off
54 excavated stuff as directed etc. complete. ( By Mechanical Means )

SSR /2022-23/Item no. 12.03 Sr.no.407 Page no.84 Cum 601.096 90.00 54,098.64
-
Excavation for foundation in soft rock including shoring and strutting, dewatering
55 as necessary and disposing off excavated stuff as directed etc. complete. -

SSR /2022-23/Item no. 12.08 Sr.no.410.Page no.84 Cum 342.184 557.00 190,596.49
-
Excavation for foundation in hard rock by chiselling and wedging or line drilling
including shoring and strutting, dewatering as necessary and disposing off
56 excavated stuff as directed etc. complete. -

SSR /2022-23/Item no. 12.11 Sr.no.413 Page No.85 Cum 111.26 1,932.00 214,962.05
-
Dewatering on BHP basis by using water pump including diversion of stream,
providing cofferdams, earthern bunds etc. as may be necessary for foundation and
other parts of the the works and pumping out water during and after excavation as
57 may be required by using 5.0 to 9.0 BHP pump etc. complete. (prior approval of -
Superintending Engineer will be necessary)

SSR /2022-2023/Item no. 12.23 Sr.no.417 Page No.86 Hour 400 201.00 80,400.00
-
Providing rubble filling of trap/ granite/ quartz it egneiss stones for foundations
58 -
includingh and packing filling gravel/sand in the voids etc. complete.
Rate as per SSR 2022-23 item. No.11.01 Sr.no.81 Cum 60.47 2,300.00 139,081.00
-
Providing and laying in situ cement concrete M15 proportion of trap / granite /
quartzite / gneiss metal for foundation and bedding including necessary formwork,
59 scaffolding, bailing out water,compacting, curing etc. complete as directed by -
Engineer in charge.

Rate as per SSR 2022-23 item. No.17.38 Cum 64.09 8,281.00 530,745.85
-
Providing and casting in situ / ready mix PCC M20 grade of trap metal for coping
to head walls / parapet including centering, form work, compaction and curing etc.
60 complete. (with reversible drum type mixer/ concrete batch mix plant (pan mixer) -
with SCADA with fine agreegates of required specifications (Natural sand / VSI
sand finely washed etc
Rate as per SSR 2022-23 item. No.11.31 Sr.No.-405 Page No.83 Cum 183.02 10,086.00 1,845,955.49
-
Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 1200 mm
61 diameter in proper line, level and slope etc. complete -
Rate as per SSR 2022-23 item. No.11.18 Sr.no.394 Page no.82 Rmt 58.00 12,306.00 713,748.00
-
Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 900 mm
62 diameter in proper line, level and slope etc. complete -

Rate as per SSR 2022-23 item. No.11.16 Sr.no.392 Page No.82 Rmt 51.00 8,635.00 440,385.00
-
Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 600 mm
diameter in proper line, level and slope including providing and fixing collars in
63 cement mortar 1:2 and curing etc. complete. -

Rate as per SSR 2022-23 item. No.11.09 Sr.no.384 Page No.81 Rmt. 82.00 2,942.00 241,244.00
-
Providing and laying 300mm dia NP2 Class R.C.C. hume pipes with Collar joints
conforming to IS 458:2003 and laid on approved bedding as per IS 783:1985 (reaff.
2010) including jointing the pipes and filleting with hemp and stiff mix of cement
mortar 1:2, including testing of pipes at contractors costs (in presence of munipal
64 staff) as per IS 3597 etc. complete as specified & as directed by Engineer in Charge. Rmt. -
(excluding necessary earthwork & bedding ).

MCGM USOR-2018 Itm No- R2-SWD-74 Rmt. 53.00 1,105.57 58,595.29


-
Providing and laying in situ / ready mix M-25 controlled reinforced cement concrete
of trap metal for raft slab including "V" haunches, formwork, scaffolding,
compaction by vibrating, finishing curing etc. complete. concrete batch mix plant /
pan mixer with fine agreegates of required specifications (Natural sand / VSI sand
65 finely washed etc ) etc. complete. (excluding reinforcement). a) RCC Grade with Rmt. -
reversible drum type mixer/ concrete batch mix plant (pan mixer) .

MCGM USOR-2018 Itm No- R2-SWD-72 Rmt. 10.4 7,079.00 73,621.60


-
Providing and laying in situ / ready mix M-25 cement concrete of trap
/granite/quartzite/ gneiss metal for cast in citu R.C.C. solid piers, column Wall etc .
including provision of V shaped false joints to form suitable panels on the faces to
approve design with compacting by vibrating and curing complete. Including
plywood/steel formwork, centering ( excluding dewatering by means of pump) and
including bailling out water and including CM 1:3 curing complete.
a) Height upto 5 M. (With Concrete Mixer)
i) Height up to 5 m, normal rate.
66 ii) Height 5 to 7.50 m, add 5 percent extra over basic rate. -
iii) Height 7.50 to 10 m, 7.50 percent extra.
iv) Over 10 m Height, add 10 percent extra for every 2.50m rise with fine agreegates
of required specifications (Natural sand / VSI sand finely washed etc )

Rate as per SSR 2022-23 item. No.17.33 Sr.no.621 Pg.131 Cum 91.735 9,084.00 833,320.74
-
Providing and laying in situ / ready mix M-30 controlled cement concrete of trap/
granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc. including
ramming, vibrating, curing, formwork, centering and finishing in cement plaster
excluding reinforcement etc. complete. (with fully automatic micro processor based
PLC with SCADA enabled concrete batch mix plant / pan mixer and fine agreegates
of required specifications ( VSI sand finely washed etc ) i) Height up to 5 m, normal
67 rate. ii) Height 5 to 7.50 m, add 5 percent extra over basic rate. iii) Height 7.50 to 10 -
m, 7.50 percent extra. iv) Over 10 m Height, add 10 percent extra for every 2.50m
rise

Cum 7.86 11,964.00 94,037.04


-
Providing & laying weep holes of 100 mm dia. AC /PVC pipes as per drawing for
68 Abutment, returns, return wall, etc. complete. -

RMT 50.000 533.00 26,650.00

Total Ammount of SECTION-V 5,537,441.19


Section -VI Road Furniture
Providing and fixing Caoutinary/Warning sign board in shape of equilateral
triangle of 90 cm sides made out sheet bonded with white retro reflective sheeting of
Class C (Type XI Microprismatic grade sheeting) having pressure
sensitive/heatactivated adhesive retoreflective specified background, border and
back side retoreflctive symbols, letters,numerals, arrow as per IRC:67-2012 Table
No 8.3 Supported with back support frame 25mmx25mmx3mm, duly painted on
back side with grey stove enamel paint and supported on one no. of M.S.angle iron
post of size 65mmX65mmX6mm, 3.45 m long, duly painted with with flat oil paint
having alternate black and white bands of 25 cm width including G.I. fixtures etc;
fixing the boards in M25 grade concrete block ofsize 60cmX60cmX75 cm including
69 transportation etc; complete. Class C (TypeX I Microprismatic grade sheeting) shall
have10 years written warranty from the manufacturer and authorised distributor
/convertor issued for field performance including the screen printed are as and cut-
out sheeting and cut-out durable transparent overlay film and this warranty
certificate in original shouldbe submitted to the Engineer incharge by the
contractor/supplier.

SSR 2018-19 Item No 6.29b Nos. 10.00 6,288.00 62,880.00


-
Providing and fixing Mandatory/Regulatory sign boards in circular shape of 600
mm dia made out of 3mm aluminum SHEET composite material bonded with white
retro reflective sheeting of Class C ( Type XI Micro prismatic grade sheeting)
having pressure sensitive/heat activated adhesive retoreflective specified back
ground, border and back side retoreflctive symbols, letters, numerals, arrow as per
IRC:67-2012 Table No 8.3 Supported with back support frame 25mm x 25mm x
3mm, duly painted on back side with grey stove enamel paint and supported on one
no. of M. S. angle iron post of size 65 mm X 65 mm X 6 mm, 3.45 m long, duly
painted with with flat oil paint having alternate black and white bands of 25 cm
width including G.I. fixtures etc; fixing the boards in M25 grade concrete block of
size 60cm X 60cm X 75cm including transportation etc; complete. Class C ( Type XI
70 Micro prismatic grade sheeting) shall have 10 years written warranty from the -
manufacturer and authorised distributor/convertor issued for field performance
including the screen printed areas and cut-out sheeting and cut-out durable
transparent overlay film and this warranty certificate in original should be
submitted to the Engineer in charge by the contractor/supplier.

Rate as per SSR 2022-23 item. No.6.28b Sr.no.-241 Pg.no.-53 Nos. 5.00 5,395.00 26,975.00
-
Providing and fixing of retro reflectorised informatory sign board
rectangular/Square in shape having area greater than 0.9 square meter made out of
2mm aluminum sheet bonded with white retroreflective sheeting of Class B( Type
IV High intensity micro prismatic grade sheeting HIP ) having pressure
sensitive/heat activated adhesive retoreflective specified background, border and
back side retoreflctive symbols, letters, numerals, arrow as per IRC:672012 Table
No 8.3, supported with back support frame 25mmx25mmx3mm, duly painted on
back side with two coats of grey stove enamel paint and supported on two no. mild
steelangleironpost75 mm x 75 mm x 6 mm, 3.5 mt long firmly fixed to the ground by
means of properly designed foundation with M25 grade cement concrete 45 cm x 45
71 cm x 60 cm, 60 cm below ground level as per approved drawing The angle iron post -
shall be duly painted with one coat of epoxy primer and two coats of epoxy finish
paint having alternate black and white bands of 25 cm width including GI fixures
and transportation etc. complete. The nut bolts of board with angle iron
post/supporting structure after fixing at site has to be electrically welded. Class B
(Type IV High intensity micro-prismatic grade sheeting- HIP) sheeting shall have 7
years written warranty from the manufacturer and authorized
distributor/convertor issued for field performance including the screen printed
areas and cut-out sheeting and cut-out durable transparent overlay film and this
warranty certificate in original should be submitted to the Engineer in charge by
the contractor/supplier.
sqm 8.00 12,363.00 98,904.00
-
Providing and fixing board displaying information, such as 'Name of work, Tender
cost, Name of Contractor, Work completion and liability period etc', having
rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild
steel sheet painted with one coat of Zinc chromate stoving primer and two coats of
enamel paint on front side and grey stove enamel on back side and border /
messages / symbols etc. with approved colour shade paint complete, on M.S.angle of
size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size
35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm
x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm
72 width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size -
60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour
etc complete. Spec. No. As directed by Engineer in Charge

Nos 2.00 9,962.00 19,924.00


Providing and applying hot applied thormoplastic compound 2.5 mm thick
including reflectorising glass beads @250 gms per sqm area thickness of 2.5
73 mm . The finished surface to be level,uniform and free from streaks and -
holes (white/yellow)

Sqm 602.00 666.00 400,932.00


Supplying and Fixing of Molded Shank Raised Pavement Markers / Cat's Eye
made of polycarbonate and ABS moulded body and reflective panels with micro
prismatic lens capable of providing total internal reflection of the light entering the
lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280
Type H and complying to Specifications of Category A of MORTH Circular No
RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not
exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum reflective area of 13
Sqcm on each side and the slope to the base shall be 35 +/- 5 degree. The strength of
detachment of the integrated cylindrical shanks, (of diameter not less than 19 +/- 2
mm and height not less than 30+/- 2 mm) from the body is to be a minimum value of
500 Kg. Fixing will be by drilling holes on the road for the shanks to go inside,
74 without nails and using epoxy resin based adhesive as per manufacturer's -
recommendation and complete as directed by the engineer.The contractor shall
submit a two year warranty for satisfactory field performance including stipulated
retro-reflectance of the reflecting panel, to the Engineer.

Nos. 718.00 366.00 262,788.00


Total Ammount of SECTION-VI 872,403.00

Section-VII Ancillary Work


Providing Fixing and Maintaining M.S. fabricated traffic barricating on either side
of the carriageway/portion of the carriage way closed to trafficetc. Complete as per
75 drawing and directed by Engineer. Fixing and maintaining 1800x1800 mm panel. -

Rmt 1,020.50 2,032.00 2,073,656.00


Shifting ,Fixing & Maintaining M.S. fabricated traffic barricating on sides of the
carriageway/portion of the carriage way closed to trafficetc. Complete as per
drawing and directed by Engineer.Labour for shifting, Fixing and maintaining
76 1.8x1.8m panel. -

Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19 Rmt 2,000.00 893.00 1,786,000.00
-
Providing traffic wardens for regulation of traffic during construction as per the
77 -
requirement of traffic police and as directed by the engineers
Per day 2,160.00 521.00 1,125,360.00

Providing and applying three coats of water proof cement paint of approved
78 manufacture and of approved colour to new plastered surfaces including -
scaffolding if necessary, cleaning and preparing the surface, watering for two
days etc. complete
Rate as per SSR 2022-23 item. No.35.15 Sr.no.-1085 Pg.no.-224 Sq .m. 300.00 105.00 31,500.00
Total Ammount of SECTION-VII 5,016,516.00

Section-VIII Water Supply and Sanitary Fitting


Providing and laying cast iron pipes of B class of 80mm diameter with sockets and Rmt
spigot ends/ flanges and cast centrifugally / vertically including specials, laying pipes
79 and back filling the trench complete including excavation.

Rate as per SSR 2022-23 item. No.41.01 Sr.no.-1307 Pg.no.-332 75.00 1,330.00 99,750.00
Providing and fixing on walls/ ceiling/ floors, 32 mm dia. heavy grade having Rmt
embossed as ISI Mark galvanised iron pipes weight of 3.89 Kilogram/meter with
necessary fittings . remaking good the demolished portion and applying primer of
anti-corrosive oil paint 2 coats Including necessary scaffolding and removing
80 existing pipe line if necessary and conveying and stacking the same in PWD chowky -
or as directed etc. complete.

Rate as per SSR 2022-23 item. No.41.13 Sr.no.-1319 Pg.no.-333 75.00 703.00 52,725.00
Providing and laying in trenches 20 mm dia. medium grade having embossed as ISI Rmt
Mark galvanised iron pipes ?of 1.63 Kilogram/meter necessary fitting remaking
good the demolished portion with filling trenches and with primer of anti-corrosive
oil paint, 2 coats Including removing existing pipe line if necessary and conveying
81 and stacking the same in PWD chowky or as directed etc. complete. -

Rate as per SSR 2022-23 item. No.41.19 Sr.no.-1325 Pg.no.-334 350.00 492.00 172,200.00
Total Ammount of SECTION-VIII 324,675.00

TOTAL 66,799,835.95
Name of work : Construction of Concrete roads 1) SH-76 Angaon Junction to Pilanze Bk , Pilanze Kh to Bedarpada road
in Bhiwandi , District Thane under OARDS .
Name of Client: Mumbai Metropolitan Region Development Authority
Name of Consultant : Ekansh Concepts Limited, Mumbai.
1 Name of Road- SH-76 Angaon Junction to Pilanze Bk , Pilanze Kh road
Measurement Sheet
Sr. Description of Items No. Length Width Height Qty Unit

Section -I Site Clearance


Proposed Road Length 1400.0 Rmt

Runner beam=.250mm +.250 mm 0.5 Rmt

Width of C.C. Road. 4.00 Rmt

Width of Site filling. Road. .50+.50 Rmt


Cleaning and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and stacking of serviceable
1 material to be used or auctioned up to a lead of 1000 metres including removal and
disposal of top organic soil not exceeding 150 mm in thickness. as per MORTH 201

Rate as per item no. 2.09, Page no.23 S.S.R.for year 2022-23
Provisional Quamtity.as per site Condition. 2 1400.0 1 2800 Sq .m.
TOTAL 2800 Sq .m.

Cutting down trees including trunks and branches with girths above 30 cm to 60 cm
2 and stacking the materials neatly with all lifts and lead of 1000 m as dircted and
earth filling in the depression / pit if any. As per MORT&H 201
Rate as per item no. 2.01,Page no-23 sr.no.78 S.S.R for year 2022-23
Provisional Quantity as per site Condition 3 3 Nos.
TOTAL 3 Sq .m.
Cutting down trees including trunks and branches with girths above 60 cm to 90 cm
3 and stacking the materials neatly with all lifts and lead of 1000m as dircted and
earth filling in the depression / pit if any. As per MORT&H 201

Rate as per item no.2.02,Page no-23 sr.no.79 S.S.R for year 2022-23
Provisional Quamtity.as per site Condition. 4 4 Nos.
TOTAL 4 Sq .m.
Transplanting of Trees: Planting the tree in the pit filled with good soil, pressed
down layer by layer, insecticide to be sprayed before planting, broken limbs to be
removed, tree to be supported by three strong stakes driven into ground metre
4 away from the stem, transport to the site & planting, preparation of tree basin,
watering & maintaining for 1 month replacement of casualities till 1 month.

Garden DSR MCGM 2013 Item GW-2-4


Provisional Quantity as per site Condition 7 7 Nos.
TOTAL 7 Nos.
Dismantling brick masonry in lime or cement mortar and stacking the materils as
5 directed with all leads, lifts etc.
Rate as per item no 46.09.Page no-296 Sr.no.1547 S.S.R for year 22-23
Old Culvert wall 4 6 0.5 1.5 18.00 Cum.
5 5 0.5 1.5 18.75 Cum.
Provisional Quantity as per site Condition Cum.
TOTAL 36.75 Cum.

Dismantling stone masonry in lime or cement mortar including stacking the


6 materils as directed with all leads, lifts etc Cum.

Rate as per item no 46.11 .Page no-296 Sr.no.1549 S.S.R for year 22-23
Old Culvert wall 4 5 0.5 1.5 15.00 Cum.
4 5 0.5 1.5 15.00 Cum.
Provisional Quantity as per site Condition 10.00 Cum.
TOTAL 40.00 Cum.
Dismantling the R.C.C. Work 1:2:4 and sorting out the materials such as steel etc.
7 as directed and stacking them within the specified lead as directed etc. complete.

Rate as per item no. 46.29, sr.no.1565 Pg. no.297 S.S.R for year 22-23 Cum.
Old Culvert wall and Encasing 3.0 6.0 3.0 1.2 64.8 Cum.
Old Culvert wall 2.0 6.0 0.5 2.2 13.2 Cum.
3.0 7.0 0.5 2.2 23.1 Cum.
Provisional Quantity as per site Condition 10.00 Cum.
TOTAL 111.10 Cum.
Dismantling of flexible pavements and disposal of dismantled materials up to a lead
8 of 1000 metres, stacking serviceable and unserviceable materials separately etc. 1
complete.
Rate as per item no.3.10, sr.no.123 Pg. no.28 S.S.R for year 22-23 .
Provisional Quantity as per site Condition 1.0 1400.0 4.0 0.070 392.0 Cum.
TOTAL 392.00 Cum.
Removing Np-2 and Np-3 class pipes including stacking at road side as directed by
9 the Engineer in charge. Upto 900mm dia and above. etc complete.
Rate as per item no.46.31 , sr.no.1567 Pg. no.297 S.S.R for year 22-23
Old Damaged Culverts pipe. 2 7 3 42.00 RMT

Old Culvertin 4 6 1 24.00 RMT

Old Culvertin 4 8 1 32.00 RMT


Provisional Quantity as per site Condition 10.00 RMT
TOTAL 108.00 RMT

Section -II Earth Work


Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum
including dressing section to the required grade, camber and side slopes and
10 conveying the excavated materials with all lifts upto a lead of 50m. and spreading Cum.
for embankment or stacking as directed.

Rate as per item no.2.16, sr.no.91 Pg. no.24 S.S.R for year 22-23
Cum.

CH.0.00 To CH..01500 1.0 1400.00 4.30 0.70 4214.00 Cum.


Approch Roads 2.0 25.00 4.00 0.70 140.00 Cum.
Provisional Quantity as per site Condition 150.00 Cum.
TOTAL 4504.00 Cum.
Excavation for roadway in hard murum & Boulder including dressing section to the
required grade, camber and side slopes and conveying the excavated materials with
11 all lifts upto a lead of 50m.and spreading for embankment or stacking as directed.

Rate as per item no.2.13, sr.no.88 Pg. no.24 S.S.R for year 22-23 Cum.
CH.0.00 To CH..01500 1.0 1400.0 4.30 0.30 1806.0 Cum.
Approch Roads 2.0 25.0 4.00 0.40 80.0 Cum.
Provisional Quantity as per site Condition 100.00 Cum.
TOTAL 1986.00 Cum.
Excavation for roadway in soft rock, including dressing section to the required
12 grade, camber and side slopes and conveying the excavated materials with all lifts Cum.
upto a lead of 50m. and spreading or stacking as directed.

Rate as per item no.2.14,sr.no.89 Pg. no.24 S.S.R for year 22-23
CH.0.00 To CH..01500 1.0 1400.0 4.30 0.20 1204.0 Cum.
Approch Roads 2.0 25.0 4.00 0.20 40.0 Cum.
Provisional Quantity as per site Condition 100.00 Cum.
TOTAL 1344.00 Cum.
Excavation for roadway in hard rock by wedging and chiselling or line drilling
including dressing section to the required grade, camber and side slopes and
13 conveying the excavated materials with all lifts upto a lead of 50m. and spreading Cum.
for embankment or stacking as directed.

Rate as per item no.2.16, sr.no.91 Pg. no.24 S.S.R for year 22-23
Bet. CH.0.00 To CH..01.500 If Required. 1 300.0 4.3 0.20 258.00 Cum.
TOTAL 258.00 Cum.
Providing earth work in embankment with approved materials obtained from other
sources upto lead of 14 km. including all lifts, laying in layers of 20cm. to 30cm.
thickness breaking clods, dressing to the required lines, curves, grades & section,
14 watering and compaction with vibratory roller with V-Sat attachment to achieve Cum.
not less than 97 % of standard proctor density etc. complete ( Material obtained
from Other sources)

Rate as per item no.2.28, sr.no.101 Pg. no.25 S.S.R for year 22-23
Bet. CH.0.00 To CH..01.500 If Required. 1.0 1400.0 4.30 0.30 1806.0 Cum.
Approch Roads 2.0 25.0 4.00 0.30 60.00 Cum.
Add Faning Portion at Junction area 6.0 20.00 2.00 0.30 72.00 Cum.
Leveling Work- Provisonal 200.00 Cum.
Traffic Diversion If Required. 1 500.0 5.00 0.50 1250.00 Cum.
Provisional Quantity as per site Condition 150.00 Cum.
TOTAL 3538.00 Cum.
Conveying materials obtained from road cutting including all lifts, laying in layers
of 20cm. to 30cm. breaking clods, dressing to the required lines, curves, grades and
section, watering and compacting to not less than 97% of standard proctor density
15 for a lead of 300m. to 500m. inclusive, from the site of excavation to the site of
deposition as directed.

Rate as per item no.2.26, sr.no.99 Pg. no.25 S.S.R for year 22-23
Total Quantity of Dismantaling During work ,Item no 5 To Item 08 579.85 Cum.
Total Quantity of Excavation During work ,Item no 10 To Item 13 8152.00 Cum.
Removing Old pipe Culvert desmantaling and Excavated Material. 4.00 6.00 4.00 1.50 144.00 Cum.
SWD Drain and Pipe work Excavation- Provisinol Qty. 150.00 Cum.
TOTAL 9025.85 Cum.
Consider 35% Quantity, as per space available near Project Alignment.
TOTAL 3159.05 Cum.

65% Quantity, as per Nonspace available near Project Alignment.


TOTAL 5866.80 Cum.

Conveying materials obtained from road cutting including all lifts, laying in layers
of 20cm. to 30cm. breaking clods, dressing to the required lines, curves, grades and
section, watering and compacting to not less than 97% of standard proctor density
for a lead from 500m. to 14 km inclusive, from the site of excavation to the site of
deposition as directed.( This Item will be operated only after approval of the
16 Concerned Superintendent Engineer MMRDA )

Total Quantity of Dismantaling During work ,Item no 5 To Item 08 579.85 Cum.


Total Quantity of Excavation During work ,Item no 10 To Item 13 8152.00 Cum.
SWD Drain and Pipe work Excavation- Provisinol Qty. 200.00 Cum.
Removing Old pipe Culvert desmantaling and Excavated Material. 4.00 6.00 4.00 1.50 144.00 Cum.
TOTAL 9075.85 Cum.
Deduct qty. consider in item no.16 3159.05 Cum.
Net Quantity. TOTAL 5916.80 Cum.
Section -III Pavement
Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing to proper grade and camber, applying and brooming requisite type of
screening/ binding Materials to fill up the interstices of coarse aggregate, watering
17 and compacting with vibratory roller to the required density. By Mechanical Means
- Grading II (Using Screening Type B (11.2 mm) Aggregate)

Item operates as per side Condition.


Below Road Crossing Utility pipe 8 6.00 1.00 0.15 7.20 Cum.
Provisional Quantity as per site Condition 5.00 Cum.
TOTAL 12.20 Cum.
Providing and constructing 50 mm. thick Modified Penetration Macadam (MPM)
road surface including all mataerials, preparing the existing road surface, spreading
40mm. stone metal layers 30% crusher broken metal + 70% Hand broken (by
breaking rubble obtained by blasting) heating and spraying the bitumen of specified
grade @ 1.75 kg/sqm, spreading 12mm.size chips compacting with static roller
18 having weight 8 to 10 MT. to achive the desired degree of compaction as per 0
Technical Specification Clause 506 etc. complete. Including picking of existing
WBM surface.(VG-30 bulk bitumen rates are considered to arrive at rates)

CH.0.00 To CH..1.500 Approch junction Area 4.00 10.00 5.00 0.05 10.00 Cum.

Spead Brakers 16.00 5.00 3.00 0.05 12.00 Cum.

TOTAL 22.00 Cum.


Construction of Granular sub-base by providing close graded Material, mixing in a
mechanical mix plant at OMC, carriage of mixed Material to work site, spreading
in uniform layers with motor grader/ Paver on prepared surface and compacting
19
with vibratory roller to achieve the desired density, complete as per clause 401 --
Plant Mix Method and Grading - I Material

Bet. CH.0.00 To CH..01.500 If Required. 1.0 1400.00 4.30 0.30 1806.00 Cum.
CH. 00 To CH. 1500 Utility duct in villge area.both side of road.If required. 2.0 600.00 0.50 0.30 180.00 Cum.
Below Road Crossing Utility pipe 8.0 6.00 1.00 0.15 7.200 Cum.
Approch Roads 2.0 25.00 4.00 0.30 60.00 Cum.
Provisional Quantity as per site Condition 150.00 Cum.
TOTAL 2203.20 Cum.

Wet Mix Macadam -- Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material with
water at OMC in mechanical mix plant carriage of mixed Material by tipper to site,
20 laying in uniform layers with paver in sub- base / base course on well prepared
surface and compacting with vibratory roller to achieve the desired density. Laying
By Grader/Paver.

Junction Area.
Bet. CH.0.00 To CH..01.500 If Required. 4.00 10.00 5.00 0.25 50.00 Cum.
Utility duct in villge area.both side of road. 2.00 600.00 0.50 0.275 165.00 Cum.
Total 215.00 Cum.

Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm


thick including hand packing and compacting etc.complete.
21

Item will be Required / operates as per side Condition.


At RCC Reataing wall ,below PCC 3.00 35.00 2.50 0.20 52.50 Cum
At RCC Reataing wall ,below PCC 3.00 25.00 1.80 0.20 27.00 Cum
RCC Culvert -6.00m x 2.m x 2.m 1.00 6.00 2.90 0.40 6.96 Cum
Traffic diversion road 1.00 170.00 5.00 0.20 170.00 Cum

TOTAL 256.46 Cum


Construction of dry lean cement concrete Sub- base over a prepared sub-grade with
coarse and fine aggregate ( natural sand/ VSI grade finely washed crushed sand)
conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, , cement
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7 C.C. Width =4000 m - Runnar
22 days, mixed in a batching plant/ Weigh batch mixer, transported to site with all beam .25+.25= PQC Width 3.5
leads and lifts, laid with a paver with electronic sensor /by suitable means as
approved by Engineer-incharge , compacting with vibratory roller, finishing, curing
and including preparation of sub-grade surface if required etc. complete.
Bet. CH.0.00 To CH..01.500 If Required. 1 1400.00 3.50 0.15 735.00 Cum.
Approch Roads 2.0 25.00 3.50 0.15 26.25 Cum.
Provisional Quantity as per site Condition 50.00 Cum.
TOTAL 811.25 Cum.
Providing & laying R.C.C.running beam in M-40 cement concrete including
required formwork mixing, compacting & curing ,etc. complete reinforced with
12mm dia.(Minimum 4 Nos.)M.S. main bars & 6mm Dia M.S. rings at 15 cm c/c to
be anchored in slipper slab properly with M.S. reinforcement as per drawing etc.
23 complete as specified (Steelwillnotbepaidseparately). Contractor has to make his
own arrangement for portable water for construction/curing with hessian cloth, etc.
& will not be paid separately.Beam Size: b) 23 cm. x 30 cm.

Rate from MGCM USOR 2018, Item No. R2-RW-10-06 Rmt


Bet. CH.0.00 To CH..01.500 If Required. 2 1400.00 2800.00 Rmt
Approch Roads 4 25.00 100.00 Rmt
Provisional Quantity as per site Condition 50.00 Rmt
TOTAL 2950.00 Rmt

Providing and laying 125 micron Low Density Polyethylene (LDPE) sheet
24 confirming to IS 3395 : 1997 below concrete pavement including all materials and
labour complete

Rate as per item no.5.19, sr.no.187 Pg. no.44 S.S.R for year 22-23

Bet. CH.0.00 To CH..01.500 If Required. 1 1400.00 3.50 4900.00 Sqm.

Approch Roads 4.0 25.00 3.50 350.00 Sqm.


Provisional Quantity as per site Condition 150.00 Sqm.
TOTAL 5400.00 Sqm.

Providing and fixing in position TMT FE 500, 32 mm dia dowel bars precoated with
anticorrosive epoxy paint of required Dia. 60 cms. Long and at 30.00 cm. C/C and
wherever directed including handling, straightening, necessary cutting supported
by TMT FE 500, chairs with proper alignment by using properly designed assembly Row
25 Per row 12
of Bulkheads lubricating half length with bituminous paint as directed etc. Required
nos
complete.

Rate as per item no.5.14, sr.no.182Pg. no.43 S.S.R for year 22-23 L 280.00 Nos
Bet. CH.0.00 To CH..01.500 If Required. 12 1400.00 56.00 672.00 672.0 Nos
Approch Roads 12 25.00 5.00 60.00 60.0 Nos
Provisional Quantity as per site Condition 50.0 Nos
TOTAL 782.0 Nos
Providing & fixing high density polythene pipe of approved quality to fit around the
dowel bars of 32mm dia at the end of expansion joints, fully greased inside, cotton
26 waste in the pipe around the dowel bars & the pipe duly capped at the end as
directed.(H.D.P.pipe shall be 30 cm in length). As shown in the drawing.

Rate from MGCM USOR 2018, Item No. R2-RW-10-15


Pipe as Per Dowels Bars 782.0 Nos
TOTAL 782.0 Nos
Providing and fixing in position TMT FE 500, tie bars precoated with anticorrosive
epoxy paint of 12 mm dia. 70 cms.long and at 30.00 cm. C/C and wherever directed
including handling, straightening wrapping with paper of approved quality for half
27 length, necessary cutting, handling, straightening , supported by assembly of TMT
FE 500, chairs with proper alignment etc. complete

Rate as per item no.5.16, sr.no.184 Pg. no.43 S.S.R for year 22-23 1400.00 Nos Nos
1 155.555556 155.555555556 Nos
Provisional Quantity as per site Condition 50.00 Nos
TOTAL 205.56 Nos
Providing and laying in-situ M40 Grade unreinforced plain cement concrete
pavement over a prepared sub base with 43 grade cement , coarse and fine
aggregate ( natural sand/ VSI grade finely washed crushed sand) conforming to IS
383, using fine and coarse aggregates combined gradation as per Table 600-3 of
MORTH Specification 2013, mixed in a batching and mixing plant/ non tilting
mixer and Weigh batcher as per approved mix design, admixtures, transporting to
site, spreading, laying with approved make paver,compacted and finished in a
28 continuous operation, finishing to lines and grades as directed by Engineer-in-
charge and curing by curing compound /by providing cement vata in cement
Mortar 1:8 @0.6m X 0.6m centre to centre, admeasuring 80 mm at bottom and 40
mm at top with depth of 75mm and maintaining the same throughout curing period
by any other method approved by Engineer-in-charge.

Rate as per item no.5.03,sr.no.171 Pg.no.38 S.S.R for year 22-23


Bet. CH.0.00 To CH..01.500 If Required. 1 1400.00 3.54 0.30 1486.80 Cum.
Approch Roads 2.0 25.00 3.54 0.30 53.10 Cum.
Provisional Quantity as per site Condition 100.00 Cum.
TOTAL 1639.90 Cum.
Providing polypropylene fibers 300e3 Multi- Dimensional Graded Fibrillated 100%
29 Virgin as per ASTMC1116 III Type 4.1.3 Std.at the rate of 125 gms per bag of
50Kgs of cement etc.
MCGM USOR Road Works 2018 Itm No- R2-RW-10-40
Total In kg 1 1639.90 1.6 2623.84 KG
Total PQC 1639.90 Cum
Runner beam 2 1500.00 0.25 0.3 225.00 Cum
TOTAL 2623.84 Cum
Cutting transverse contraction joints 3 to 4 mm wide and depth 80 mm.in concrete
slab using concrete cutting machine with diamond studded saw within 48 hours of
30 casting of bay / slab etc. complete including subsequent widening of the groove 8 to 1864.90
10 mm. wide at top having depth of 15 mm. as directed by Engineer incharge

Rate as per item no.5.17, sr.no.185 Pg.no.43 S.S.R for year 22-23

Longitunal Joint.
Bet. CH.0.00 To CH..01.500 If Required.

both sides Runner Beam sides 2 1400.00 2800.00 Rmt


Centre of both PQC Panal 1 1400.00 1400.00 Rmt
Approch Roads 3 25.00 75.00 Rmt
Transvers Cutting @5 m C/C. Nos.

311.11

Bet. CH.0.00 To CH..01.500 If Required. 1 1400.00 355.6 4.00 1422.22 Rmt


Approch Roads 4.0 25.00 4.00 4.00 16.00 Rmt
Provisional Quantity as per site Condition 300.00 Rmt
TOTAL 6013.22 Rmt
Providing to contraction joints polysuphide sealent (Pouring grade) confirming to
BS : 5212 - 1989 into sawed groove widened at top for sealent reservoir of specified
size and shape as per detailed drawing including fixing Polyethylene foam backer
rod of required diameter (appraox. 25% larger than the initial 3 mOne Metric
Tonneo 4 mm. joint) overlaid with bond breaking tape as per detailed drawing.
31 Item includes cleaning the joints with water jet / air compressor and allowing joint
to become thoroughly dry before sealent is applied and applying primer. (A)
Contraction and longitudinal joints (15 mm. deep x 8 mm.wide)

Rate as per item no.5.18, sr.no.186 Pg.no.44 S.S.R for year 22-23

Quantity as per Joint Cutting Item. 6013.22 Rmt


Provisional Quantity as per site Condition 300.00 Rmt

TOTAL 6313.22 Rmt


Providing & fixing in position premoulded asphalt filler 12mm thick conforming to
I.S.1838 of 1983 for placing of the expansion joint, around manholes & water
32 entrances, etc. put to the required depth & 25 mm below the camber, etc. complete 6313.22
Length of
as directed. Nos
Joint
MCGM USOR Itm No- R2-RW-10-13

CH.0.00 To CH.1.500 25 1400.00 4.00 0.3 30.00 SQM


Provisional Quantity as per site Condition 10.00 SQM
Total 40.00 SQM
Prime coat - Providing and applying primer coat with bitumen emulsion on
33 prepared surface of granular Base including cleaning of road surface and spraying,
primer at the rate of 0.60 kg/sqm using mechanical means.
Rate as per item no.3.29, sr.no.139 Pg.no.30 State Schedule Rates for year 2022-23

Junction Area.
Bet. CH.0.00 To CH..01.500 If Required. 2.00 10.00 5.00 100.00 Sqm
Provisional Quantity as per site Condition 25.00 Sqm
Total 125.00 Sqm
Providing and applying tack coat on the prepared surface heating by fames in
34 Boiler and spraying bitumen set footed in bitumen boller on B.T. surface 2.5 kg/10
sqm.(VG-30 bulk bitumen rates are considered to arrive at rates)

Junction Area.

Bet. CH.0.00 To CH..01.500 If Required. 3.00 10.00 5.00 150.00 Sqm

Spead Brakers 8.00 5.00 3.00 120.00 Sqm


Provisional Quantity as per site Condition 50.00 Sqm

Total 320.00 Sqm


BITUMINOUS MACADAM: Proving and laying bituminous macadam using
crushed aggregates of Grading 1, premixed with bituminous binder, transported to
site with VTS , laid over a previously prepared surface, finished to the required
grade, level, alignment, and rolling to achieve the desired compaction for 80/100
35 mm compacted thickness with 3.3 % using specified grade of Bitumen. -- USING
Batch mix type hot mix plant with SCADA, Sensor Paver, vibratory roller.(VG-30
bulk bitumen rates are considered to arrive at rates)

Rate as per item no.3.40, sr.no.154 Pg.no.33 S.S.R for year 22-23

Junction Area.

Bet. CH.0.00 To CH..01.500 If Required. 4.00 10.00 5.00 0.065 13.00 Cum.

Speed Braker 8.00 5.00 3.00 0.065 7.80 Cum.


Provisional Quantity as per site Condition 5.00 Cum.

Total 25.80 Cum.


DENSE BITUMINOUS MACADAM: Proving and laying dense bituminous
macadam using crushed aggregates of Grading 1, premixed with bituminous binder
of specified grade of Bitumen @ 4.50 per cent by weight of total mix and filler,
transported to site with VTS , laid over a previously prepared surface, finished to
36 the required grade, level, alignment, and rolling to achieve the desired density for
76-100 mm compacted thickness .USING Batch mix type hot mix plant with
SCADA, Sensor Paver, Vibratory roller with Stone Dust filler.(VG-30 bulk bitumen
rates are considered to arrive at rates)

Rate as per item no.3.44, sr.no.156 Pg.no.34 S.S.R for year 22-23

Junction Area.
Bet. CH.0.00 To CH..01.500 If Required. 4.00 10.00 5.00 0.05 10.00 Cum.
Speed Braker 8.00 5.00 3.00 0.05 6.00 Cum.
Provisional Quantity as per site Condition 5.00 Cum.
Total 21.00 Cum.
BITUMINOUS CONCRETE:- Providing and laying bituminous concrete using
crushed aggregates of grading 1, premixed with bituminous binder @ 5.20 per cent
by weight of total mix and filler, transported to site with VTS , laid over a
previously prepared surface, finished to the required grade, level, alignment, and
rolling to achieve the desired compaction for 50 mm compacted thickness with
37 specified grade of Bitumen,Excluding prime / tack coat. For Bitumen of specified
grade -- USING Batch mix type hot mix plant with SCADA, Sensor Paver,
Vibratory roller with Stone Dust filler. (VG-30 bulk bitumen rates are considered to
arrive at rates)

Rate as per item no.3.48, sr.no.158 Pg.no.34 S.S.R for year 22-23
Junction Area.
Bet. CH.0.00 To CH..01.500 If Required. 3.00 10.00 6.00 0.05 9.00 Cum.
Speed Braker 6.00 5.00 3.00 0.05 4.50 Cum.
Provisional Quantity as per site Condition 5.00 Cum.
Total 18.50 Cum.
Providing & fixing in the carriageway 100 mm thick interlocking concrete unishape
pavers( monolithic- single layer precast concrete blocks) of grey cement
colouredhaving average crushing strength not less than 50N/mm² as per technical
specificationand IS CODE 15658:2006, placed on average compacted thickness 25
mm well graded sand cushioning uniformly compacted with proper capacity
38 mechanical compactor with required level, grade and camber etc. complete as 4
specified and as directed by the Engineer.

Rate from MGCM 2018, Item No. R2-RW-3-19


Junction Area.
Bet. CH.0.00 To CH..01.500 If Required.
Road Side Utility Duct 2.00 70.00 0.50 70.00 Sqm
Provisional Quantity as per site Condition 25.00 Sqm
Total 95.00 Sqm
Providing Heavy Duty Fibre Glass Reinforced Plastic Temporary Barricade of 1.75
m hight, with base width of 430 mm as a provision to accept water ballasting of 101
Itrs-110 Ltrs approx. and arrangement for traffic diversion such as traffic signals
during construction at site, for day and night as per requirement. The raw material
shall be UV stabilized Linear Low Density Polyethylene and should meet the
requirements stipulated in standard IS: 10146-1982, IS:10141-1982 and should also
comply to FDA:CFR Title 21.177.1520. Olefin Polymers , with specific FRP Grade
39 300-104 reinforced -----------------and 2 nos on Extension top for holding light
brackets / Rod for cloth holding. The plastic barricades has a strong vertical rib of
1740 mm length at the rear centre & 72 No's ofa) For 725 mm height (LType Jersey
Barrier ) ,Empty Weight:6.67 Kilogram/ Rgm,Weight Full : 35.89Kilogram/ Rgm
approx. (After Water / Sand Filling)

Rate as per item no.50.46, sr.no.1785 Pg.no.343 S.S.R for year 22-23

Bet. CH.0.00 To CH..01.500 If Required. 2.0 1400.0 2800.0 RMT


End of road 2.0 6.0 12.0 RMT
Village area. 3.0 10.0 30.0 RMT
Retaining wall side 2.0 75.0 150.0 RMT
Provisional Quantity as per site Condition 150.0 RMT

Total 3142.00 RMT


Consider 50% of total Quantity. Total 1571.00 RMT
Section-IV - Storm Water Drain
40 Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
including shoring and strutting, dewatering as necessary and disposing off
excavated stuff as directed etc. complete. ( By Mechanical Means )
Rate as per item no.12.03, sr.no.407 Pg. no.84 S.S.R for year 22-23

Provisional Quantity as per site Condition 50.00 Cum


Total 50.00 Cum
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
41 including shoring and strutting, dewatering as necessary and disposing off
excavated stuff as directed etc. complete. ( By /manaual Means )

Rate as per item no.12.02, sr.no.406 Pg. no.84 S.S.R for year 22-23
Provisional Quantity as per site Condition 30.00 Cum

Total 30.00 Cum


Excavation for foundation in hard murum and boulders including shoring and
42 strutting, dewatering as necessary and disposing off excavated stuff as directed etc.
complete.

Rate as per item no.12.06, sr.no.409 Pg. no.84 S.S.R for year 22-23

Provisional Quantity as per site Condition 30.00 Cum

Total 30.00 Cum


Excavation for foundation in soft rock including shoring and strutting, dewatering
43 as necessary and disposing off excavated stuff as directed etc. complete.

Rate as per item no.12.08, sr.no.410 Pg. no.84 S.S.R for year 22-23
Provisional Quantity as per site Condition 50.00 Cum
Total 50.00 Cum
Excavation for foundation in hard rock by chiselling and wedging or line drilling
44 including shoring and strutting, dewatering as necessary and disposing off
excavated stuff as directed etc. complete

Rate as per item no.12.11, sr.no.413 Pg. no.85 S.S.R for year 22-23
Provisional Quantity as per site Condition 30.00 Cum

Total 30.00 Cum


Providing rubble filling of trap/ granite/ quartzite gneiss stones for foundations
45 including filling voids with sand/grit and compaction etc complete

Rate as per item no.11.01, sr.no.376 Pg. no.81 S.S.R for year 22-23

Provisional Quantity as per site Condition 50.00 Cum

Total 50.00 Cum

Providing and laying Cast in situ/Ready Mix cement concrete in M15 of trap/
granite/quartzite/gneiss metal for foundation / steps including steel centering,
formwork, laying/pumping, compacting, roughening them if special finish is to be
provided, finishing uneven and honeycombed surface and curing etc. complete. The
Cement Mortar 1:3 plaster is considered for rendering uneven and honeycombed
surface, only. Newly laid concrete shall be covered by gunny bag, plastic, tarpaulin
46
etc. (Wooden centering will not be allowed.),with fully automatic micro processor
based PLC with SCADA enabled reversible Drum Type mixer/concrete Batch mix
plant (Pan mixer) etc. complete. With fine aggregate (Crushed sand VSI
Grade

Rate as per item no.11.02, sr.no.377 Pg. no.81 S.S.R for year 22-23

Provisional Quantity as per site Condition 20.00 Cum


Total 20.00 Cum
Providing and laying Cast in situ/Ready Mix cement concrete in M20 of trap/
granite/quartzite/gneiss metal for bed blocks, foundation blocks and such
other items including bailing out water, Steel centering, formwork, laying/
pumping, compacting, roughening them if special finish is to be provided, finishing
uneven and honeycombed surface and curing etc. complete. The Cement Mortar 1:3
plaster is considered for rendering uneven and honeycombed surface only. Newly
47 laid concrete shall be covered by gunny bag, plastic, tarpaulin etc. (Wooden
centering will not be allowed.), with fully automatic micro processor based PLC
with SCADA enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan
mixer) etc. complete. With fine aggregate (Crushed sand VSI Grade)

Rate as per item no.24.04, sr.no.828 Pg. no.175 S.S.R for year 22-23
Road Sleepar Slab 2 1400.00 0.53 0.15 222.60 Cum
Approch Roads 4 25.00 0.53 0.15 7.95 Cum

Total 230.55 Cum


Providing and laying Cast in situ/Ready Mix cement concrete in M-20 of trap/
granite/ quartzite/ gneiss metal for R.C.C. pardi of required thickness including
steel centering, formwork, cover blocks, laying/pumping, compacting , curing ,
finishing and rougheningthem if special finish is to be provided and curing
48 complete.(Excluding reinforcement and structural steel).with fully automatic micro
processor based PLC with SCADA enabled reversible Drum Type mixer/ concrete
Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Crushed sand VSI
Grade

Rate as per item no.25.11, sr.no.836 Pg. no.178 S.S.R for year 22-23

Provisional Quantity as per site Condition 15.00 Cum


Total 15.00 Cum

Providing and laying Cast in situ/Ready Mix cement concrete M-25 of trap/
granite /quartzite/ gneiss metal for R.C.C. slabs and landings as per detailed designs
and drawings including steel centering, formwork, cover blocks, laying/pumping,
compaction finishing the formed surfaces with cement mortar 1:3 of sufficient
minimum thickness to give a smooth and even surface or roughening if special
finish is to be provided and curing etc. complete,(Excluding reinforcement and
49
structural steel).with fully automatic micro processor based PLC with SCADA
enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer) etc.
complete. With fine aggregate (Crushed sand VSI Grade).

Rate as per item no.26.17, sr.no.860 Pg. no.185 S.S.R for year 22-23
Provisional Quantity as per site Condition 20.00 Cum
Total 20.00 Cum

Providing and fixing in position TMT - FE - 500 bar reinforcement of various


diameters for R.C.C. footings, foundations, slabs, beams columns, canopies,
staircase, newels, chajjas, lintels pardis, copings, fins, arches etc. as per detailed
50 designs, drawings and schedules. including cutting, bending, hooking the bars,
binding with wires or tack welding and supporting as required complete.

Consider 40.00 MT
150 kg/ Cum
Provisional Quantity as per site Condition, R.E.Wall etc. 10.00 MT
50.00 MT
Say Total 50.00 MT

Supplying & Fixing 0.9 m x 0.6 m rectangular SFRC frame and cover as per
51 drawing fixed complete to manhole as specified and directed
Rate as per item no.26.33, sr.no.871 Pg. no.188 S.S.R for year 22-23 Nos
Chember Caver 5 m C/C
Provisional Quantity as per site Condition 10.00
Total Length of Drain 10.00
Chember Caver 5 m C/C 4
Provisional Quantity as per site Condition 10.00 Nos

Total 15.00 Nos

Providing and fixing of cement concrete Kerb Stone of various grades of size:
500mm width x 325 height x 165mm thick (Half Batter, Bull Nose/ Full Batter)
manufactured in wet press vacuum dewatering technology plant / equivalant with
face pimple finish for high visibility with excellent quality and finish and edges
perfect and sharp. Grade – M-25 including excavation in any soil except rock,
laying a leveling course of M 15 grade RMC 100mm thick to required slope
52
(inclusive of form work), jointing in C.M. 1:2 proportion flush to concrete surface,
painting exposed surface with one coat of primer and two coats of 1st grade road
marking paint in the yellow/ white/ black or any shade as directed. (Kerbstones
shall be procured from MCGM registered agencies).

Rate as per MCGM SOR-2018 item. No.R2-SE-10-12

Provisional Quantity as per site Condition 75.00 MTR

Total 75.00 MTR


Providing & fixing in the foothpath Concrete Paver blocks 200 X 200 X 80 mm
thick or any approved size in grey or any specified colour with shot blasted texture
or any aproved texture on top surface of approved pattern/shape and colour having
average crushing strength not less than 50N/mm² as per technical specification sand
IS CODE 15658:2006 manufactured in double layer precast concrete Paverblocks
12to15 mm thick top layer and consisting of cubical shape Quartz stone aggregate
8mm seve 100% passing and retained on 4.75mm sizesieve, silicasand. The bottom
53 layer should be 65 to 68 mm thick in grey cement having 12 mm sieve 100% passing
aggregates as per technical specifications, rested on average compacted thickness of
25mm well graded sand cushioning uniformly compacted with proper capacity
mechanical compactor with required level, grade and camber etc. complete as
specified and as directed by the Engineer.

MCGM USOR-2018 R2-RW-10-50

Provisional Quantity as per site Condition 75.00 SQM

Total 75.0 SQM

Section-V- CD Works and Culvert, Bridges

Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
54 including shoring and strutting, dewatering as necessary and disposing off .
excavated stuff as directed etc. complete. ( By Mechanical Means )
SSR /2022-23/Item no. 12.03 Sr.no.407 Page no.84

1200 mm Pipes 2*3 Cum


Pipe Culverts 1200 mm Pipes 2.00 6.00 5.14 1.2 74.02 Cum
Pipe Culverts 900 mm Pipes 2.00 6.00 4.45 1.2 64.08 Cum
Pipe Culverts 600 mm Pipes 4.00 6.00 3.55 1.00 85.20 Cum
RCC Culvert -6.00m x 2.m x 2.m

1.00 6.00 3.00 1.95 35.10 Cum


RCC Retaining Wall 2.00 20.00 2.50 2.00 200.00 Cum
RCC Retaining Wall 3.00 15.00 1.80 1.70 137.70 Cum
Provisional Quantity as per site Condition 5.00 Cum
Total 601.096 Cum

Excavation for foundation in soft rock including shoring and strutting, dewatering
55 as necessary and disposing off excavated stuff as directed etc. complete.

SSR /2022-23/Item no. 12.08 Sr.no.410.Page no.84


1200 mm Pipes 2*3
Pipe Culverts 1200 mm Pipes 2 6 5.14 0.8 49.34 Cum
Pipe Culverts 900 mm Pipes 2 6 4.45 0.8 42.72 Cum
Pipe Culverts 600 mm Pipes 4 6 3.55 0.6 51.12 Cum
RCC Culvert -6.00m x 2.m x 2.m
1.00 6 3.00 1.00 18.00 Cum
RCC Retaining Wall 2.00 20.00 2.50 1.00 100.00 Cum
RCC Retaining Wall 3.00 15.00 1.80 1.00 81.00 Cum
Total 342.18 Cum
Excavation for foundation in hard rock by chiselling and wedging or line drilling
56 including shoring and strutting, dewatering as necessary and disposing off
excavated stuff as directed etc. complete.
SSR /2022-23/Item no. 12.11 Sr.no.413 Page No.85
1200 mm Pipes 2*3
Pipe Culverts 1200 mm Pipes 2 6 5.14 0.3 18.50 Cum
Pipe Culverts 900 mm Pipes 2 6 4.45 0.3 16.02 Cum
Pipe Culverts 600 mm Pipes 4 6 3.55 0.2 17.04 Cum
RCC Culvert -6.00m x 2.m x 2.m
` 1.00 6 3.00 0.30 5.40 Cum
RCC Retaining Wall 2.00 20.00 2.50 0.30 30 Cum
RCC Retaining Wall 3.00 15.00 1.80 0.30 24.30 Cum
` Total 111.26 Cum

Dewatering on BHP basis by using water pump including diversion of stream,


providing cofferdams, earthern bunds etc. as may be necessary for foundation and
other parts of the the works and pumping out water during and after excavation as
57
may be required by using 5.0 to 9.0 BHP pump etc. complete. (prior approval of
Superintending Engineer will be necessary)

SSR /2022-2023/Item no. 12.23 Sr.no.417 Page No.86 Per day


Days
Hours
Provisional Quantity as per site Condition 50 8 400 Hrs

Total 400 Hrs


Providing rubble filling of trap/ granite/ quartz it egneiss stones for foundations
includingh and packing filling gravel/sand in the voids etc. complete.
58

Rate as per SSR 2022-23 item. No.11.01 Sr.no.81 Cum


1200 mm Pipes 2*3 Cum
Pipe Culverts 1200 mm Pipes 2 6 5.14 0.25 15.42 Cum
Pipe Culverts 900 mm Pipes = 2*3 2 6 4.45 0.25 13.35 Cum
Pipe Culverts 600 mm Pipes 4 6 3.55 0.25 21.30 Cum
RCC Culvert -6.00m x 2.m x 2.m

1.00 6 3.00 0.30 5.4 Cum


Provisional Quantity as per site Condition 5.00 Cum

Total 60.47 Cum

Providing and laying in situ cement concrete M15 proportion of trap / granite /
quartzite / gneiss metal for foundation and bedding including necessary formwork,
scaffolding, bailing out water,compacting, curing etc. complete as directed by
59 Engineer in charge.

Rate as per SSR 2022-23 item. No.17.38


1200 mm Pipes 2*3
Pipe Culverts 1200 mm Pipes 2.00 6.00 5.14 0.15 9.25 Cum
Pipe Culverts 900 mm Pipes 2.00 6.00 4.45 0.15 8.01 Cum
Pipe Culverts 600 mm Pipes 4.00 6.00 3.55 0.15 12.78 Cum
RCC Culvert -6.00m x 2.m x 2.m
RCC Culvert -6.00m x 2.m x 2.m 1.00 6.00 3.00 0.15 2.70 Cum
RCC Retaining Wall 2.00 20.00 3.20 0.15 19.20 Cum
RCC Retaining Wall 3.00 15.00 1.80 0.15 12.15 Cum
Total 64.09 Cum
Providing and casting in situ / ready mix PCC M20 grade of trap metal for coping
to head walls / parapet including centering, form work, compaction and curing etc.
complete. (with reversible drum type mixer/ concrete batch mix plant (pan mixer)
60 with SCADA with fine agreegates of required specifications (Natural sand / VSI
sand finely washed etc

Rate as per SSR 2022-23 item. No.11.31 Sr.No.-405 Page No.83


Pipes Encasing 2*3
Pipe Culverts 1200 mm Pipes 2.0 6.0 5.14 1.44 88.82 Cum
Deduction Pipe Area -6.0 6.0 1.327 -47.76 Cum
Pipe Culverts 900 mm Pipes 2.0 6.0 4.45 1.13 60.34 Cum
Deduction Pipe Area -6.0 6.0 0.754 -27.14 Cum
Pipe Culverts 600 mm Pipes 4.0 6.0 3.55 0.81 69.01 Cum
Deduction Pipe Area -12.0 6.0 0.363 -26.13 Cum
Pipe Culverts 300 mm Pipes 8.0 6.0 0.56 0.51 13.71 Cum
Deduction Pipe Area -9.0 6.0 0.091 -4.90 Cum
RCC Culvert -6.00m x 2.m x 2.m
Foundation/ Raft 1.0 6.0 3.00 0.30 5.40 Cum
RCC Retaining Wall- RAFT 2.00 20.00 2.90 0.30 34.80 Cum
RCC Retaining Wall- RAFT 3.00 15.00 1.50 0.25 16.88 Cum
Total 183.02 Cum

Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 1200 mm
61 diameter in proper line, level and slope etc. complete
Rate as per SSR 2022-23 item. No.11.18 Sr.no.394 Page no.82
1200 mm Pipes 2*3
Pipe Culverts 1200 mm Pipes =2*3=6 6 6 36.00 RMT
Provisional Quantity as per site Condition 22.00 RMT
Total 58.00 RMT
Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 900 mm
62 diameter in proper line, level and slope etc. complete
Rate as per SSR 2022-23 item. No.11.16 Sr.no.392 Page No.82
Pipe Culverts 900 mm Pipes =2*3=6 nos 6 6 36.00 RMT
Provisional Quantity as per site Condition 15.00 RMT

Total 51.00 RMT

Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 600 mm
63 diameter in proper line, level and slope including providing and fixing collars in
cement mortar 1:2 and curing etc. complete.

Rate as per SSR 2022-23 item. No.11.09 Sr.no.384 Page No.81

600 mm Pipes 4*3


Pipe Culverts 600 mm Pipes 12 6 72.00 RMT
Provisional Quantity as per site Condition 10.00 RMT

Total 82.00 RMT


Providing and laying 300mm dia NP2 Class R.C.C. hume pipes with Collar joints
conforming to IS 458:2003 and laid on approved bedding as per IS 783:1985 (reaff.
2010) including jointing the pipes and filleting with hemp and stiff mix of cement
mortar 1:2, including testing of pipes at contractors costs (in presence of munipal
64 staff) as per IS 3597 etc. complete as specified & as directed by Engineer in Charge.
(excluding necessary earthwork & bedding ).

MCGM USOR-2018 Itm No- R2-SWD-74


Utility Crossing 9.25
8 6 48.00 RMT
Provisional Quantity as per site Condition 5.00 RMT
Total 53.00 RMT

Providing and laying in situ / ready mix M-25 controlled reinforced cement concrete
of trap metal for raft slab including "V" haunches, formwork, scaffolding,
compaction by vibrating, finishing curing etc. complete. concrete batch mix plant /
pan mixer with fine agreegates of required specifications (Natural sand / VSI sand
65 finely washed etc ) etc. complete. (excluding reinforcement). a) RCC Grade with
reversible drum type mixer/ concrete batch mix plant (pan mixer) .

Rate as per SSR 2022-23 item. No.17.33 Sr.no.621 Pg.131

RCC Culvert -6.00m x 2.m x 2.m

Foundation/ Raft 1.00 6 3.00 0.30 5.4 Cum


Provisional Quantity as per site Condition 5.00 Cum

Total 10.4 Cum

Providing and laying in situ / ready mix M-25 cement concrete of trap
/granite/quartzite/ gneiss metal for cast in citu R.C.C. solid piers, column Wall etc .
including provision of V shaped false joints to form suitable panels on the faces to
approve design with compacting by vibrating and curing complete. Including
plywood/steel formwork, centering ( excluding dewatering by means of pump) and
including bailling out water and including CM 1:3 curing complete.
a) Height upto 5 M. (With Concrete Mixer)
i) Height up to 5 m, normal rate.
66 ii) Height 5 to 7.50 m, add 5 percent extra over basic rate.
iii) Height 7.50 to 10 m, 7.50 percent extra.
iv) Over 10 m Height, add 10 percent extra for every 2.50m rise with fine agreegates
of required specifications (Natural sand / VSI sand finely washed etc )

Rate as per SSR 2022-23item. No.17.48 Sr.no.-636 Pg.no-137


RCC Culvert -6.00m x 2.m x 2.m
Foundation/ Raft 2.00 6 0.35 1.80 7.56 Cum
RCC Retaining Wall- WALL 2.00 20.00 0.40 2.80 44.80 Cum
RCC Retaining Wall- WALL 3.00 15.00 0.35 2.50 39.38 Cum

Total 91.735 Cum

Providing and laying in situ / ready mix M-30 controlled cement concrete of trap/
granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc. including
ramming, vibrating, curing, formwork, centering and finishing in cement plaster
excluding reinforcement etc. complete. (with fully automatic micro processor based
PLC with SCADA enabled concrete batch mix plant / pan mixer and fine agreegates
67 of required specifications ( VSI sand finely washed etc ) i) Height up to 5 m, normal
rate. ii) Height 5 to 7.50 m, add 5 percent extra over basic rate. iii) Height 7.50 to 10
m, 7.50 percent extra. iv) Over 10 m Height, add 10 percent extra for every 2.50m
rise

Rate as per SSR 2022-23 item. No.14.17 Sr.no.-465 Pg.no.94

RCC Culvert -6.00m x 2.m x 2.m

Slab 1.00 6.000 2.70 0.30 4.86 Cum


Provisional Quantity as per site Condition 3.00 Cum

Total 7.86 Cum

Providing & laying weep holes of 100 mm dia. AC /PVC pipes as per drawing for
68 Abutment, returns, return wall, etc. complete.

Rate as per SSR 2022-23 item. No.17.37 Sr.no.-625 Pg.no.-132


Provisional Quantity as per site Condition 50 RMT
Total 50 RMT

Section-VI - Road furniture


Providing and fixing Caoutinary/Warning sign board in shape of equilateral
triangle of 90 cm sides made out sheet bonded with white retro reflective sheeting of
Class C (Type XI Microprismatic grade sheeting) having pressure
sensitive/heatactivated adhesive retoreflective specified background, border and
back side retoreflctive symbols, letters,numerals, arrow as per IRC:67-2012 Table
No 8.3 Supported with back support frame 25mmx25mmx3mm, duly painted on
back side with grey stove enamel paint and supported on one no. of M.S.angle iron
post of size 65mmX65mmX6mm, 3.45 m long, duly painted with with flat oil paint
69 having alternate black and white bands of 25 cm width including G.I. fixtures etc;
fixing the boards in M25 grade concrete block ofsize 60cmX60cmX75 cm including
transportation etc; complete. Class C (TypeX I Microprismatic grade sheeting) shall
have10 years written warranty from the manufacturer and authorised distributor
/convertor issued for field performance including the screen printed are as and cut-
out sheeting and cut-out durable transparent overlay film and this warranty
certificate in original shouldbe submitted to the Engineer incharge by the
contractor/supplier.

Rate as per SSR 2022-23 item. No.6.30e Sr.no.260 Pg.55

Provisional Quantity as per site Condition 10 10 Nos

Total 10 Nos

Providing and fixing Mandatory/Regulatory sign boards in circular shape of 600 Nos
mm dia made out of 3mm aluminum SHEET composite material bonded with white
retro reflective sheeting of Class C ( Type XI Micro prismatic grade sheeting)
having pressure sensitive/heat activated adhesive retoreflective specified back
ground, border and back side retoreflctive symbols, letters, numerals, arrow as per
IRC:67-2012 Table No 8.3 Supported with back support frame 25mm x 25mm x
3mm, duly painted on back side with grey stove enamel paint and supported on one
no. of M. S. angle iron post of size 65 mm X 65 mm X 6 mm, 3.45 m long, duly
painted with with flat oil paint having alternate black and white bands of 25 cm
width including G.I. fixtures etc; fixing the boards in M25 grade concrete block of
70
size 60cm X 60cm X 75cm including transportation etc; complete. Class C ( Type XI
Micro prismatic grade sheeting) shall have 10 years written warranty from the
manufacturer and authorised distributor/convertor issued for field performance
including the screen printed areas and cut-out sheeting and cut-out durable
transparent overlay film and this warranty certificate in original should be
submitted to the Engineer in charge by the contractor/supplier.

Rate as per SSR 2022-23 item. No.6.28b Sr.no.-241 Pg.no.-53


Provisional Quantity as per site Condition 5 5 No
Total 5 No

Providing and fixing of retro reflectorised informatory sign board


rectangular/Square in shape having area greater than 0.9 square meter made out of
2mm aluminum sheet bonded with white retroreflective sheeting of Class B( Type
IV High intensity micro prismatic grade sheeting HIP ) having pressure
sensitive/heat activated adhesive retoreflective specified background, border and
back side retoreflctive symbols, letters, numerals, arrow as per IRC:672012 Table
No 8.3, supported with back support frame 25mmx25mmx3mm, duly painted on
back side with two coats of grey stove enamel paint and supported on two no. mild
71 steelangleironpost75 mm x 75 mm x 6 mm, 3.5 mt long firmly fixed to the ground by
means of properly designed foundation with M25 grade cement concrete 45 cm x 45
cm x 60 cm, 60 cm below ground level as per approved drawing The angle iron post
shall be duly painted with one coat of epoxy primer and two coats of epoxy finish
paint having alternate black and white bands of 25 cm width including GI fixures
and transportation etc. complete. The nut bolts of board with angle iron
post/supporting structure after fixing at site has to be electrically welded. Class B
(Type IV High intensity micro-prismatic grade sheeting- HIP) sheeting shall have 7
years written warranty from the manufacturer and authorized
Rate as per SSR 2022-23 item. No.6.34a Sr.no.-276 Pg.no.-58
Provisional Quantity as per site Condition 8 8 SQM
Total 8 SQM

Providing and fixing board displaying information, such as 'Name of work, Tender
cost, Name of Contractor, Work completion and liability period etc', having
rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild
steel sheet painted with one coat of Zinc chromate stoving primer and two coats of
enamel paint on front side and grey stove enamel on back side and border /
messages / symbols etc. with approved colour shade paint complete, on M.S.angle of
size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size
72 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm
x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm
width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size
60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour
etc complete. Spec. No. As directed by Engineer in Charge

Rate as per SSR 2022-23 item. No.6.36 Sr.no.-284 Pg.no.-60 Nos


Provisional Quantity as per site Condition 2 2 Nos
Total 2 Nos
Providing and applying hot applied thormoplastic compound 2.5 mm thick
including reflectorising glass beads @250 gms per sqm area thickness of 2.5 mm .
73 The finished surface to be level,uniform and free from streaks and holes
(white/yellow)

Rate as per SSR 2022-23 item. No.6.12a Sr.no.-215 Pg.no.-48 Sqm


Both side Stips 2 1400.00 0.15 420.00 Sqm
Speed bRaker 8.00 4.00 2.50 0.5 40.00 Sqm
Rambalars 105 4.00 0.10 42.00 Sqm
100.00 Sqm

Total 602.00 Sqm

Supplying and Fixing of Molded Shank Raised Pavement Markers / Cat's Eye
made of polycarbonate and ABS moulded body and reflective panels with micro
prismatic lens capable of providing total internal reflection of the light entering the
lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280
Type H and complying to Specifications of Category A of MORTH Circular No
RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not
exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum reflective area of 13
Sqcm on each side and the slope to the base shall be 35 +/- 5 degree. The strength of
detachment of the integrated cylindrical shanks, (of diameter not less than 19 +/- 2
74 mm and height not less than 30+/- 2 mm) from the body is to be a minimum value of
500 Kg. Fixing will be by drilling holes on the road for the shanks to go inside,
without nails and using epoxy resin based adhesive as per manufacturer's
recommendation and complete as directed by the engineer.The contractor shall
submit a two year warranty for satisfactory field performance including stipulated
retro-reflectance of the reflecting panel, to the Engineer.
Rate as per SSR 2022-23 item. No.6.09 Sr.no.212 Pg.no.47
Both side Stips 350 1400 350.00 Nos
Speed Raker 108.0 108.00 Nos
Rambalars 160.0 160.00 Nos
Provisional Quantity as per site Condition 100.0 Nos
Total 718.00 Nos

Section-VII Ancillary Work


Providing Fixing and Maintaining M.S. fabricated traffic barricating on either side
of the carriageway/portion of the carriage way closed to trafficetc. Complete as per
drawing and directed by Engineer. Fixing and maintaining 1800x1800 mm panel.
75

Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19


Provisional Quantity as per site Condition 1 1400.0 1400.00 Rmt
End of Work area. 8 10.0 80.00 Rmt
Village AREA 1 90.0 90.00 Rmt

Total 1570.00 Rmt

Consider 65% of total Quantity. Total 1020.50 Rmt

Shifting ,Fixing & Maintaining M.S. fabricated traffic barricating on sides of the
carriageway/portion of the carriage way closed to trafficetc. Complete as per
76 drawing and directed by Engineer.Labour for shifting, Fixing and maintaining
1.8x1.8m panel.

Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19


Provisional Quantity as per site Condition 2000.00 Rmt
Total 2000.00 Rmt

Providing traffic wardens for regulation of traffic during construction as per the
77 requirement of traffic police and as directed by the engineers

Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19

Provisional Quantity as per site Condition day Month Nos


Consider 28days per Month X 9 Months x 4 Nos .per day and Night 30 9 6 1620.00 Per day

Supervisor 30 9 2 540.00 Per day

Total 2160.00 Per day

Providing and applying three coats of water proof cement paint of approved
manufacture and of approved colour to new plastered surfaces including scaffolding
78 if necessary, cleaning and preparing the surface, watering for two days etc.
complete

Rate as per SSR 2022-23 item. No.35.15 Sr.no.-1085 Pg.no.-224 Sq .m.


Provisional Quantity as per site Condition 300.0 Sq .m.
Total 300.0 Sq .m.
Section-VIII - Water Supply and Sanitary Fitting

Providing and laying cast iron pipes of B class of 80mm diameter with sockets and
79 spigot ends/ flanges and cast centrifugally / vertically including specials, laying pipes
and back filling the trench complete including excavation.

Rate as per SSR 2022-23 item. No.41.01 Sr.no.-1307 Pg.no.-332 Rmt


In Village Area Provisional Quantity Consider as per site Condition 75.0 Rmt

Total 75.0 Rmt

Providing and fixing on walls/ ceiling/ floors, 32 mm dia. heavy grade having
embossed as ISI Mark galvanised iron pipes weight of 3.89 Kilogram/meter with
necessary fittings . remaking good the demolished portion and applying primer of
80 anti-corrosive oil paint 2 coats Including necessary scaffolding and removing
existing pipe line if necessary and conveying and stacking the same in PWD chowky
or as directed etc. complete.

Rate as per SSR 2022-23 item. No.41.13 Sr.no.-1319 Pg.no.-333


In Village Area Provisional Quantity Consider as per site Condition 75.0 Rmt

Total 75.0 Rmt

Providing and laying in trenches 20 mm dia. medium grade having embossed as ISI
Mark galvanised iron pipes ?of 1.63 Kilogram/meter necessary fitting remaking
good the demolished portion with filling trenches and with primer of anti-corrosive
81 oil paint, 2 coats Including removing existing pipe line if necessary and conveying
and stacking the same in PWD chowky or as directed etc. complete.

Rate as per SSR 2022-23 item. No.41.19 Sr.no.-1325 Pg.no.-334


In Village Area Provisional Quantity Consider as per site Condition 350.0 Rmt
Rmt
Total 350.0
Name of work : Construction of Concrete roads 1) SH-76 Angaon Junction
District Thane under O

Lead Chart

Total Lead
Sr.No Material Unit
in Km

1 Muroom Cum 14.00

2 Crushed Aggregates Cum 14.00

3 Artificial Sand Cum 14.00

4 Cement M.T 45.00

5 Reinforcment Steel M.T 45.00

6 RCC Pipe (900 mm)-NP 3 Rmt 25.00

7 RCC Pipe (1000mm) NP 3 Rmt 25.00

8 RCC Pipe (1200 mm) NP 3 Rmt 25.00

9 RCC Pipe (600 mm) NP 3 Rmt 25.00

10 RCC Pipe (300 mm) NP 3 Rmt 25.00

11 RCC Pipe (150 mm) NP 2 Rmt 25.00


12 Paver Block Nos 25.00

13 Gravel And Crushed Metal Cum 16.00

14 Dumping of Material Cum 15.00

15 Rubble Stone Cum 14.00

16 Asphalt Drum 90.00

PMC

DEPUTY ENGINEER
MMRDA
SH-76 Angaon Junction to Pilanze Bk , Pilanze Kh to Bedarpada road in Bhiwandi ,
District Thane under OARDS .

Lead Chart

Total Lead Initial Lead Initial Lead Net


Source
Charges in Km Charges Lead

371.49 0.05 17.79 354.00 Bhivandi

387.64 0.05 18.56 369.00 Bhivandi

387.64 0.05 18.56 369.00 Bhivandi

622.10 0.05 9.63 612.00 Thane

622.10 0.05 9.63 612.00 Thane

144.86 0.05 8.54 136.00

260.76 0.05 10.67 250.00

325.95 0.05 14.23 312.00

86.92 0.05 14.23 73.00 Bhivandi

37.25 0.05 1.42 36.00

20.89 0.05 1.56 19.00


413.27 0.05 13.75 400.00

566.86 0.05 18.56 548.00 Bhivandi

Bhivandi Local
393.44 0.05 17.79 376.00
Area

408.43 0.05 22.71 386.00 Bhivandi

205.45 0.05 1.93 204.00 Chembur

EXECUTIVE ENGINEER
MMRDA
ad in Bhiwandi ,

Remark

Borow
Area

0.612
Per Kg.
Borow
Area

NEER
Name of work : Construction of Concrete roads 1) SH-76 Angaon Junction to Pilanze Bk , Pilanze Kh to
Bedarpada road Thane under OARDS .

Consider- 1) Base Rates from SSR-2022-2023 , 2) Assume addition lead charges as per site location and material Sources 3)
Increase of percentages over the normal schedule of rates 5% for Municipal Corporation Areas.

RATE ANALYSIS

Section I - Site Clearence & Dismantling

Sr. No. Description Unit Details Rate (Rs.)


1 Cleaning and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned up to a lead of 1000 metres
including removal and disposal of top organic soil not exceeding 150 mm in
thickness. as per MORTH 201

Rate as per item no. 2.09, Page no.23 State Schedule Rates for year 2022-23 Sqm 12.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.12
Total 11.88
Add labour cess 1% 0.12
Rate per Sqm 12.00
Sqm say 12.50
2 Cutting down trees including trunks and branches with girths above 30 cm to
60 cm and stacking the materials neatly with all lifts and lead of 1000 m as
dircted and earth filling in the depression / pit if any. As per MORT&H 201
30 to 60 cm
Rate as per item no. 2.01,Page no-23 sr.no.78 State Schedule Rates for year 2022-
23 511.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -5.11
Total 505.89
Add labour cess 1% 5.11
Rate per nos. 511.00
Nos say 511.00
3 Cutting down trees including trunks and branches with girths above 60 cm to
90 cm and stacking the materials neatly with all lifts and lead of 1000m as
dircted and earth filling in the depression / pit if any. As per MORT&H 201
60 to 90 cm
Rate as per item no.2.02,Page no-23 sr.no.79 State Schedule Rates for year 2022-23
Nos
847.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -8.47
Total 838.53
Add labour cess 1% 8.47
Rate per nos. 847.00
Nos say 847.00

Transplanting of Trees: Planting the tree in the pit filled with good soil, pressed
down layer by layer, insecticide to be sprayed before planting, broken limbs to
be removed, tree to be supported by three strong stakes driven into ground
4 metre away from the stem, transport to the site & planting, preparation of tree
basin, watering & maintaining for 1 month replacement of casualities till 1
month.

Garden DSR MCGM 2013 Item GW-2-4 Nos 882.00


Say 882.00
5 Dismantling brick masonry in lime or cement mortar and stacking the materils
as directed with all leads, lifts etc.

Rate as per item no 46.09 .Page no-296 Sr.no.1547 State Schedule Rates for year
Cum
2022-23 335.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.35
Total 331.65
Add labour cess 1% 3.35
Rate per Cum. 335.00
Cum say 335.00
6 Dismantling stone masonry in lime or cement mortar including stacking the
materils as directed with all leads, lifts etc
Rate as per item no 46.11 .Page no-296 Sr.no.1549 State Schedule Rates for year
Cum
2022-23 380.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.80
Total 376.20
Add labour cess 1% 3.80
Rate per Cum. 380.00
Cum say 380.00
7 Dismantling the R.C.C. Work 1:2:4 and sorting out the materials such as steel
etc. as directed and stacking them within the specified lead as directed etc.
complete.
Rate as per item no. 46.29, sr.no.1565 Pg. no.297 State Schedule Rates for year
Cum
2022-23 1451.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -14.51
Total 1436.49
Add labour cess 1% 14.51
Rate per Cum. 1451.00
Cum say 1451.00
8 Dismantling of flexible pavements and disposal of dismantled materials up to a
lead of 1000 metres, stacking serviceable and unserviceable materials separately
etc. complete.
Rate as per item no.3.10, sr.no.123 Pg. no.28 State Schedule Rates for year 2022-23
Cum
430.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -4.30
Total 425.70
Add labour cess 1% 4.30
Rate per Cum. 430.00
Cum say 430.00
9 Removing Np-2 and Np-3 class pipes including stacking at road side as directed
by the Engineer in charge. Upto 900mm dia and above. etc complete.

Rate as per item no.46.31 , sr.no.1567 Pg. no.297 State Schedule Rates for year One Running
Metre
2022-23 310.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.10
Add labour cess 1% 3.10
Rate per RMT 310.00
RMT say 310.00

Section -II - Earth Work


Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum
including dressing section to the required grade, camber and side slopes and
10 conveying the excavated materials with all lifts upto a lead of 50m. and
spreading for embankment or stacking as directed.
Rate as per item no.2.16, sr.no.91 Pg. no.24 State Schedule Rates for year 2022-23
Cum
119.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -1.19
Total 117.81
Add labour cess 1% 1.19
Rate per Cum. 119.00
Cum say 119.00
11 Excavation for roadway in hard murum & Boulder including dressing section
to the required grade, camber and side slopes and conveying the excavated
materials with all lifts upto a lead of 50m.and spreading for embankment or
stacking as directed.
Rate as per item no.2.13, sr.no.88 Pg. no.24 State Schedule Rates for year 2022-23
Cum
139.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -1.39
Total 137.61
Add labour cess 1% 1.39
Rate per Cum. 139.00
Cum say 139.00
12 Excavation for roadway in soft rock, including dressing section to the required
grade, camber and side slopes and conveying the excavated materials with all
lifts upto a lead of 50m. and spreading or stacking as directed.
Rate as per item no.2.14,sr.no.89 Pg. no.24 State Schedule Rates for year 22-23
Cum
177.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -1.77
Total 175.23
Add labour cess 1% 1.77
Rate per Cum. 177.00
Cum say 177.00
13 Excavation for roadway in hard rock by wedging and chiselling or line drilling
including dressing section to the required grade, camber and side slopes and
conveying the excavated materials with all lifts upto a lead of 50m. and
spreading for embankment or stacking as directed.
Rate as per item no.2.16, sr.no.91 Pg. no.24 State Schedule Rates for year 2022-23
Cum
1419.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -14.19
Total 1404.81
Add 5% for Municipal Corporation Areas 0.00
Add labour cess 1% 14.19
Rate per Cum. 1419.00
Cum say 1419.00
14 Providing earth work in embankment with approved materials obtained from
other sources upto lead of 14 km. including all lifts, laying in layers of 20cm. to
30cm. thickness breaking clods, dressing to the required lines, curves, grades &
section, watering and compaction with vibratory roller with V-Sat attachment
to achieve not less than 97 % of standard proctor density etc. complete
( Material obtained from Other sources)
Rate as per item no.2.28, sr.no.101 Pg. no.25 State Schedule Rates for year 2022-23
Cum
757.00 0
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -7.57
Total 749.43
Add lead 14 Km.for Murrum. 1.2 391.00 469.20
Add Labour cess 1% 7.57
Rate per Cum. 1226.20
Cum say 1226.00
Conveying materials obtained from road cutting including all lifts, laying in
layers of 20cm. to 30cm. breaking clods, dressing to the required lines, curves,
grades and section, watering and compacting to not less than 97% of standard
15 proctor density for a lead of 300m. to 500m. inclusive, from the site of
excavation to the site of deposition as directed.

Rate as per item no.2.26, sr.no.99 Pg. no.25 State Schedule Rates for year 22-23 Cum 393.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.93
Total 389.07
Add Labour cess 1% 3.93
Rate per Cum 393.00
Cum say 393.00
Conveying materials obtained from road cutting including all lifts, laying in
layers of 20cm. to 30cm. breaking clods, dressing to the required lines, curves,
grades and section, watering and compacting to not less than 97% of standard
proctor density for a lead from 500m. to 14 km inclusive, from the site of
16 excavation to the site of deposition as directed.( This Item will be operated only
after approval of the Concerned Superintendent Engineer MMRDA )

Rate as per item no.2.26, sr.no.99 Pg. no.25 State Schedule Rates for year 2022-23 -
Cum
RATE UP TO 500 M 393.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.93
Total 389.07
Add lead up to14 Km.for Murrum./ excavated 1.2 354.00 424.80
Add Labour cess 1% 3.93
Rate per Cum
817.80
Cum say 818.00
Section-III - Road Pavement
17 Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness,
hand packing to proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of coarse aggregate,
watering and compacting with vibratory roller to the required density. By
Mechanical Means - Grading II (Using Screening Type B (11.2 mm) Aggregate)
Rate as per item no.3.19, sr.no.129 Pg. no.29 SSR 2022-23 Cum 2140.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -21.40
Total 2118.60
Add lead chrges for 14 km lead 1.2 408.00 489.60
Add Labour cess 1% 21.40
Rate per Cum 2629.60
Cum Say 2630.00
18 Providing and constructing 50 mm. thick Modified Penetration Macadam
(MPM) road surface including all mataerials, preparing the existing road
surface, spreading 40mm. stone metal layers 30% crusher broken metal + 70%
Hand broken (by breaking rubble obtained by blasting) heating and spraying
the bitumen of specified grade @ 1.75 kg/sqm, spreading 12mm.size chips
compacting with static roller having weight 8 to 10 MT. to achive the desired
degree of compaction as per Technical Specification Clause 506 etc. complete.
Including picking of existing WBM surface.(VG-30 bulk bitumen rates are
considered to arrive at rates)
Rate as per item no.3.37a, sr.no.149 Pg. no.32 State Schedule Rates for year 2022-23
sqm 210.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -2.10
Total 207.90
Add lead chrges for metal 14km . 1.2 0.050 408.00 24.48
Add lead chrges for Bituman 90 km . 1.75 2.04 3.57
Add Labour cess 1% 2.10
Rate per sqm 238.05
SQM Say 238.00
19 Construction of Granular sub-base by providing close graded Material, mixing

in a mechanical mix plant at OMC, carriage of mixed Material to work site,

spreading in uniform layers with motor grader/ Paver on prepared surface and

compacting with vibratory roller to achieve the desired density, complete as per

clause 401 -- Plant Mix Method and Grading - I Material


Rate as per item no.3.01, sr.no.113 Pg. no.27 State Schedule Rates for year 2022-23
Cum
2039.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -20.39
Total 2018.61
Add lead chrges for 14 km lead 1.2 408 489.60
Add Labour cess 1% 20.39
Rate per Cum 2528.60
CUM Say 2529.00
20 Wet Mix Macadam -- Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification including premixing the
Material with water at OMC in mechanical mix plant carriage of mixed
Material by tipper to site, laying in uniform layers with paver in sub- base /
base course on well prepared surface and compacting with vibratory roller to
achieve the desired density. Laying By Grader/Paver.
Rate as per item no.3.23, sr.no.133 Pg. no.30 State Schedule Rates for year 2022-23
Cum
2045.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -20.45
Total 2024.55
Add lead chrges for 14 km lead Cum 1.2 369.00 442.80
Add Labour cess 1% 20.45
Rate per Cum 2487.80
Cum Say 2488.00
21 Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20
cm thick including hand packing and compacting etc.complete.
Rate as per SSR 2022-23 item. No.21.38 sr.no.752 Page no.157. Cum 1382.00
Deduct labour Cess @ 1% ( SSR 20-21 pg no 3) -13.82
Total 1368.18
Add lead chrges for 14 km lead 1.2 386.00 463.20
Add Labour cess 1% 13.82
Rate per Cum 1845.20
Cum Say 1845.00
22 Construction of dry lean cement concrete Sub- base over a prepared sub-grade
with coarse and fine aggregate ( natural sand/ VSI grade finely washed crushed
sand) conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, ,
cement content not to be less than 150 kg/ cum, optimum moisture content to be
determined during trial length construction, concrete strength not to be less
than 10 Mpa at 7 days, mixed in a batching plant/ Weigh batch mixer,
transported to site with all leads and lifts, laid with a paver with electronic
sensor /by suitable means as approved by Engineer-incharge , compacting with
vibratory roller, finishing, curing and including preparation of sub-grade
surface if required etc. complete.
Rate as per item no.5.13, sr.no.181 Pg.no.43 State Schedule Rates for year 2022-23
Cum
3659.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -36.59
Total 3622.41
Add lead for cement-45 km kg 150 0.612 91.80
Add Metal lead charges for 14 km 0.90 408.00 367.20
Add Sand lead charges for 14 km 0.35 408.00 142.80
Add back Labour cess 1% 36.59
Rate per Cum 4260.80
Cum Say 4261.00
23 Providing & laying R.C.C.running beam in M-40 cement concrete including
required formwork mixing, compacting & curing ,etc. complete reinforced with
12mm dia.(Minimum 4 Nos.)M.S. main bars & 6mm Dia M.S. rings at 15 cm c/c
to be anchored in slipper slab properly with M.S. reinforcement as per drawing
etc. complete as specified (Steelwillnotbepaidseparately). Contractor has to
make his own arrangement for portable water for construction/curing with
hessian cloth, etc. & will not be paid separately.Beam Size: b) 23 cm. x 30 cm.
Rate from MGCM USOR 2018, Item No. R2-RW-10-06 Rmt 844.00
Deduct labour Cess @ 1% ( SSR 20-21 pg no 3) -8.44
Deduct GST 12% -101.28
Total 734.28
Add Extra Lead Charge for
Add lead for cement-45 km 0.0021429 612.00 1.31
Add Metal lead charges for 14 km 0.0621118 408.00 25.34
Add Sand lead charges for 14 km 0.0241546 408.00 9.86
Add Labour cess 1% 8.44
Rate per Rmt 779.23
RMT Say 779.00
24 Providing and laying 125 micron Low Density Polyethylene (LDPE) sheet
confirming to IS 3395 : 1997 below concrete pavement including all materials
and labour complete
Rate as per item no.5.19, sr.no.187 Pg. no.44 State Schedule Rates for year 2022-23
Sqm
30.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.30
Total 29.70
Add Labour cess 1% 0.30
Rate per Sqm 29.70
SQM Say 30.00
25 Providing and fixing in position TMT FE 500, 32 mm dia dowel bars precoated
with anticorrosive epoxy paint of required Dia. 60 cms. Long and at 30.00 cm.
C/C and wherever directed including handling, straightening, necessary cutting
supported by TMT FE 500, chairs with proper alignment by using properly Nos
designed assembly of Bulkheads lubricating half length with bituminous paint
as directed etc. complete.

Rate as per item no.5.14, sr.no.182Pg. no.43 State Schedule Rates for year 22-23 538.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -5.38
Total 532.62
Add Lead Charges for Reinforcment 45 Km. 1 1.482 0.703 1.04
Add Labour cess 1% 5.38
Rate per Nos 539.04
Nos Say 539.00
26 Providing & fixing high density polythene pipe of approved quality to fit around
the dowel bars of 32mm dia at the end of expansion joints, fully greased inside,
cotton waste in the pipe around the dowel bars & the pipe duly capped at the
end as directed.(H.D.P.pipe shall be 30 cm in length). As shown in the drawing.

Rate from MGCM USOR 2018, Item No. R2-RW-10-15 Nos 31.00
DEDUCTED GST12% 3.32
Rate per Nos 27.68
Nos Say 28.00
27 Providing and fixing in position TMT FE 500, tie bars precoated with
anticorrosive epoxy paint of 12 mm dia. 70 cms.long and at 30.00 cm. C/C and
wherever directed including handling, straightening wrapping with paper of
approved quality for half length, necessary cutting, handling, straightening ,
supported by assembly of TMT FE 500, chairs with proper alignment etc.
complete
Rate as per item no.5.16, sr.no.184 Pg. no.43 State Schedule Rates for year 2022-23
Nos
306.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.06
Total 302.94
Add Lead Charges 45 Km. 1 0.623 0.703 0.44
Add Labour cess 1% 3.06
Rate per Nos 306.44
Nos Say 306.00
28

Providing and laying in-situ M40 Grade unreinforced plain cement concrete
pavement over a prepared sub base with 43 grade cement , coarse and fine
aggregate ( natural sand/ VSI grade finely washed crushed sand) conforming to
IS 383, using fine and coarse aggregates combined gradation as per Table 600-3
of MORTH Specification 2013, mixed in a batching and mixing plant/ non
tilting mixer and Weigh batcher as per approved mix design, admixtures,
transporting to site, spreading, laying with approved make paver,compacted
and finished in a continuous operation, finishing to lines and grades as directed
by Engineer-in-charge and curing by curing compound /by providing cement
vata in cement Mortar 1:8 @0.6m X 0.6m centre to centre, admeasuring 80 mm
at bottom and 40 mm at top with depth of 75mm and maintaining the same
throughout curing period by any other method approved by Engineer-in-
charge.
Rate as per item no.5.03,sr.no.171 Pg.no.38 State Schedule Rates for year 22-23 Cum 7793.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -77.93
Total 7715.07
Add lead for cement-45 km 0.450 612.00 275.40
Add Metal lead charges for 14 km 0.85 408.00 346.80
Add Sand lead charges for 14 km 0.425 408.00 173.40
Add Labour labour cess 1% 77.93
Rate per Cum 8588.60
Cum Say 8589.00
29 Providing polypropylene fibers 300e3 Multi- Dimensional Graded Fibrillated
100% Virgin as per ASTMC1116 III Type 4.1.3 Std.at the rate of 125 gms per
bag of 50Kgs of cement etc.
MCGM USOR Road Works 2018 Itm No- R2-RW-10-40 Cum 439.00
DEDUCTED GST @12% 47.04
Rate per Cum 391.96
Cum Say 392.00
30 Cutting transverse contraction joints 3 to 4 mm wide and depth 80 mm.in
concrete slab using concrete cutting machine with diamond studded saw within
48 hours of casting of bay / slab etc. complete including subsequent widening of
the groove 8 to 10 mm. wide at top having depth of 15 mm. as directed by
Engineer incharge
Rate as per item no.5.17, sr.no.185 Pg.no.43 State Schedule Rates for year 2022-23
Rmt
76.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.76
Total 75.24
Add Labour labour cess 1% 0.76
Rate per Rmt 76.00
RMT Say 76.00
31 Providing to contraction joints polysuphide sealent (Pouring grade) confirming
to BS : 5212 - 1989 into sawed groove widened at top for sealent reservoir of
specified size and shape as per detailed drawing including fixing Polyethylene
foam backer rod of required diameter (appraox. 25% larger than the initial 3
mOne Metric Tonneo 4 mm. joint) overlaid with bond breaking tape as per
detailed drawing. Item includes cleaning the joints with water jet / air
compressor and allowing joint to become thoroughly dry before sealent is
applied and applying primer. (A) Contraction and longitudinal joints (15 mm.
deep x 8 mm.wide)
Rate as per item no.5.18, sr.no.186 Pg.no.44 State Schedule Rates for year 2022-23
Rmt
311.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.11
Total 307.89
Add Labour labour cess 1% 3.11
Rate per Rmt 311.00
RMT Say 311.00
32 Providing & fixing in position premoulded asphalt filler 12mm thick
conforming to I.S.1838 of 1983 for placing of the expansion joint, around
manholes & water entrances, etc. put to the required depth & 25 mm below the
camber, etc. complete as directed.
MCGM USOR Itm No- R2-RW-10-13 sqm 352.00
DEDUCTED GST @ 12% 37.71
Rate SQM Rmt 314.29
Say 314.00
33 Prime coat - Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including cleaning of road surface and
spraying, primer at the rate of 0.60 kg/sqm using mechanical means.
Rate as per item no.3.29, sr.no.139 Pg.no.30 State Schedule Rates for year 2022-23
Sqm.
33.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.33
Total 32.67
Add cost of transport of Bitumen
for 90 km lead Sqm. 0.0006 204.0 0.12
Difference of Bitumen Cost.= 61680-52764=8916 /MT 0.0006 8916.0 5.35
Add Labour labour cess 1% 0.33
Rate per Sqm 38.47
SQM Say 38.00
34 Providing and applying tack coat on the prepared surface heating by fames in
Boiler and spraying bitumen set footed in bitumen boller on B.T. surface 2.5
kg/10 sqm.(VG-30 bulk bitumen rates are considered to arrive at rates)
Rate as per item no.3.30, sr.no.140 Pg.no.30 State Schedule Rates for year 2022-23
Sqm.
18.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.18
Total 17.82
Add cost of transport of Bitumen
for 90 km lead Sqm. 0.0025 204.00 0.51
Difference of Bitumen Cost.= 61680-52764 = 8916 /MT 0.0025 8916.00 22.29
Add Labour labour cess 1% 0.18
Rate per Sqm 40.80
SQM Say 41.00
35 BITUMINOUS MACADAM: Proving and laying bituminous macadam using
crushed aggregates of Grading 1, premixed with bituminous binder,
transported to site with VTS , laid over a previously prepared surface, finished
to the required grade, level, alignment, and rolling to achieve the desired
compaction for 80/100 mm compacted thickness with 3.3 % using specified
grade of Bitumen. -- USING Batch mix type hot mix plant with SCADA, Sensor
Paver, vibratory roller.(VG-30 bulk bitumen rates are considered to arrive at
rates)
Rate as per item no.3.40, sr.no.154 Pg.no.33 State Schedule Rates for year 2022-23
Cum
7644.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -76.44
Total 7567.56
Add cost of transport of Bitumen 3.30%
for 90 km lead CUM 0.06105 204.00 12.45
Difference of Bitumen Cost.= 61680-52764 = 8916 /MT 0.06105 8916 544.32
Add Lead for Crush Aggregate 1.48 Cum 1.48 408.00 603.84
Add Labour labour cess 1% 76.44
Rate per Cum Total 8805.00
Cum Say 8805.00
36 DENSE BITUMINOUS MACADAM: Proving and laying dense bituminous
macadam using crushed aggregates of Grading 1, premixed with bituminous
binder of specified grade of Bitumen @ 4.50 per cent by weight of total mix and
filler, transported to site with VTS , laid over a previously prepared surface,
finished to the required grade, level, alignment, and rolling to achieve the
desired density for 76-100 mm compacted thickness .USING Batch mix type hot
mix plant with SCADA, Sensor Paver, Vibratory roller with Stone Dust filler.
(VG-30 bulk bitumen rates are considered to arrive at rates)
Rate as per item no.3.44, sr.no.156 Pg.no.34 State Schedule Rates for year 2022-23
Cum
9664.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -96.64
Total 9567.36
Add cost of transport of Bitumen 4.50%
for 90 km lead CUM 0.0832 204.00 16.97
Difference of Bitumen Cost.= 61680-52764=8916 /MT 0.0832 8916 741.81
Add Lead for Crush Aggregate 1.53 Cum (.61+.459+.459) 1.53 408 624.24
Add Labour labour cess 1% 96.64
Rate per Cum Total 11047.00
Cum Say 11047.00
37 BITUMINOUS CONCRETE:- Providing and laying bituminous concrete using
crushed aggregates of grading 1, premixed with bituminous binder @ 5.20 per
cent by weight of total mix and filler, transported to site with VTS , laid over a
previously prepared surface, finished to the required grade, level, alignment,
and rolling to achieve the desired compaction for 50 mm compacted thickness
with specified grade of Bitumen,Excluding prime / tack coat. For Bitumen of
specified grade -- USING Batch mix type hot mix plant with SCADA, Sensor
Paver, Vibratory roller with Stone Dust filler. (VG-30 bulk bitumen rates are
considered to arrive at rates)
Rate as per item no.3.48, sr.no.158 Pg.no.34 State Schedule Rates for year 2022-23
10599.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -105.99
Total 10493.01
Add cost of transport of Bitumen 5.20%
for 90 km lead CUM 0.102 204.00 20.81
Difference of Bitumen Cost.= 61680-52764=8916 /MT 0.102 8916 909.43
Add Lead for Crush Aggregate 1.48 Cum 1.57 408.00 640.56
Add Labour labour cess 1% 104.93
Rate per Cum 12169.00
Cum Say 12169.00
38 Providing & fixing in the carriageway 100 mm thick interlocking concrete
unishape pavers( monolithic- single layer precast concrete blocks) of grey
cement colouredhaving average crushing strength not less than 50N/mm² as per
technical specificationand IS CODE 15658:2006, placed on average compacted
thickness 25 mm well graded sand cushioning uniformly compacted with proper
capacity mechanical compactor with required level, grade and camber etc.
complete as specified and as directed by the Engineer.
Rate from MGCM 2018, Item No. R2-RW-3-19 Sqm 1054.00
DEDUCTED GST @12% 112.93
Rate per Nos 941.07
SQM Say 941.00
39 Providing Heavy Duty Fibre Glass Reinforced Plastic Temporary Barricade of
1.75 m hight, with base width of 430 mm as a provision to accept water
ballasting of 101 Itrs-110 Ltrs approx. and arrangement for traffic diversion
such as traffic signals during construction at site, for day and night as per
requirement. The raw material shall be UV stabilized Linear Low Density
Polyethylene and should meet the requirements stipulated in standard IS:
10146-1982, IS:10141-1982 and should also comply to FDA:CFR Title
21.177.1520. Olefin Polymers , with specific FRP Grade 300-104 reinforced
-----------------and 2 nos on Extension top for holding light brackets / Rod for
cloth holding. The plastic barricades has a strong vertical rib of 1740 mm length
at the rear centre & 72 No's ofa) For 725 mm height (LType Jersey
Barrier ) ,Empty Weight:6.67 Kilogram/ Rgm,Weight Full : 35.89Kilogram/
Rgm approx. (After Water / Sand Filling)
Rate as per item no.50.46, sr.no.1785 Pg.no.343 State Schedule Rates for year
2022-23 1846.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -18.46
Total 1827.54
Add Labour labour cess 1% 18.46
Rate per Sqm 1846.00
SQM Say 1846.00
Section-IV - Storm Water Drain
40 Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
including shoring and strutting, dewatering as necessary and disposing off
excavated stuff as directed etc. complete. ( By Mechanical Means )

Upto 1.50 m lift Normal Rate


Rate as per item no.12.03, sr.no.407 Pg. no.84 State Schedule Rates for year 2022-23
Cum
90.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.90
Total 89.10
Add labour cess 1% 0.90
90.00
Rate per Cum. Cum 90.00
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum

41 including shoring and strutting, dewatering as necessary and disposing off

excavated stuff as directed etc. complete. ( By /manaual Means )


Upto 1.50m lift Normal Rate
Rate as per item no.12.02, sr.no.406 Pg. no.84 State Schedule Rates for year 2022-23
Cum
239.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) ` -2.39
Total 236.61
Add labour cess 1% 2.39
Rate per Cum 239.00
Cum Say 239.00
42 Excavation for foundation in hard murum and boulders including shoring and
strutting, dewatering as necessary and disposing off excavated stuff as directed
etc. complete.

Upto 1.50m lift Normal Rate


Rate as per item no.12.06, sr.no.409 Pg. no.84 State Schedule Rates for year 2022-23
Cum
286.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) ` -2.86
Total 283.14
Add 5% for Municipal Corporation Areas 0.00
Add labour cess 1% 2.86
Rate per Cum 286.00
Cum Say 286.00
43 Excavation for foundation in soft rock including shoring and strutting,
dewatering as necessary and disposing off excavated stuff as directed etc.
complete.
Upto 1.50m lift Normal Rate
Rate as per item no.12.08, sr.no.410 Pg. no.84 State Schedule Rates for year 2022-23
Cum
557.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -5.57
Total 551.43
Add labour cess 1% 5.57
Rate per Cum 557.00
Cum Say 557.00
44 Excavation for foundation in hard rock by chiselling and wedging or line
drilling including shoring and strutting, dewatering as necessary and disposing
off excavated stuff as directed etc. complete
Upto 1.50m lift Normal Rate
Rate as per item no.12.11, sr.no.413 Pg. no.85 State Schedule Rates for year 2022-23
Cum 1932.00

Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -19.32


Total 1912.68
Add labour cess 1% 19.32
Rate per Cum 1932.00
Cum Say 1932.00
45 Providing rubble filling of trap/ granite/ quartzite gneiss stones for foundations

including filling voids with sand/grit and compaction etc complete


Rate as per item no.11.01, sr.no.376 Pg. no.81 State Schedule Rates for year 2022-23
Cum 1701.00

Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -17.01


Total 1683.99
Add lead chrges for 14 km lead . 1.2 499 598.80
Add Labour cess 1% 17.01
Rate per Cum 2299.80
Cum Say 2300.00
46 Providing and laying Cast in situ/Ready Mix cement concrete in M15 of trap/
granite/quartzite/gneiss metal for foundation / steps including steel centering,
formwork, laying/pumping, compacting, roughening them if special finish is to
be provided, finishing uneven and honeycombed surface and curing etc.
complete. The Cement Mortar 1:3 plaster is considered for rendering uneven
and honeycombed surface, only. Newly laid concrete shall be covered by gunny
bag, plastic, tarpaulin etc. (Wooden centering will not be allowed.),with fully
automatic micro processor based PLC with SCADA enabled reversible Drum
Type mixer/concrete Batch mix plant (Pan mixer) etc. complete. With fine
aggregate (Crushed sand VSI Grade
Rate as per item no.24.04, sr.no.828 Pg. no.175 State Schedule Rates for year 2022-
Cum
23 1 6359.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -63.59
Total 6295.41
Add lead for cement-45 km Cum 0.33 703.00 231.99
Add Metal lead charges for 14 km Cum 0.85 408.00 346.80
Add Sand lead charges for 14 km Cum 0.45 408.00 183.60
Add back Labour labour aminities & cess 1% 63.59
Rate per Cum 7121.39
Cum Say 7121.00
47 Providing and laying Cast in situ/Ready Mix cement concrete in M20 of trap/
granite/quartzite/gneiss metal for bed blocks, foundation blocks and such
other items including bailing out water, Steel centering, formwork, laying/
pumping, compacting, roughening them if special finish is to be provided,
finishing uneven and honeycombed surface and curing etc. complete. The
Cement Mortar 1:3 plaster is considered for rendering uneven and
honeycombed surface only. Newly laid concrete shall be covered by gunny bag,
plastic, tarpaulin etc. (Wooden centering will not be allowed.), with fully
automatic micro processor based PLC with SCADA enabled reversible Drum
Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete. With fine
aggregate (Crushed sand VSI Grade)
Rate as per item no.24.10, sr.no.831 Pg. no.176 State Schedule Rates for year 2022-
Cum
23 6721.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -67.21
Total 6653.79
Add lead for cement-45 km cum 0.41 703.0 288.23
Add Metal lead charges for 14 km Cum 0.9 408.0 367.20
Add Sand lead charges for 14 km Cum 0.425 408.0 173.40
Add back Labour labour aminities & cess 1% 66.54
Rate per Cum 7549.16
Cum Say 7549.00
48 Providing and laying Cast in situ/Ready Mix cement concrete in M-20 of trap/
granite/ quartzite/ gneiss metal for R.C.C. pardi of required thickness including
steel centering, formwork, cover blocks, laying/pumping, compacting , curing ,
finishing and rougheningthem if special finish is to be provided and curing
complete.(Excluding reinforcement and structural steel).with fully automatic
micro processor based PLC with SCADA enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate
(Crushed sand VSI Grade
Rate as per item no.26.17, sr.no.860 Pg. no.185 State Schedule Rates for year 2022-
Cum
23 15567.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -155.67
Total 15411.33
Add lead for cement-45 km cum 0.41 703.0 288.23
Add Metal lead charges for 14 km Cum 0.9 408.0 367.20
Add Sand lead charges for 14 km Cum 0.425 408.0 173.40
Add back Labour labour aminities & cess 1% 155.67
Rate per Cum 16395.83
Cum Say 16396.00
49 Providing and laying Cast in situ/Ready Mix cement concrete M-25 of trap/
granite /quartzite/ gneiss metal for R.C.C. slabs and landings as per detailed
designs and drawings including steel centering, formwork, cover blocks,
laying/pumping, compaction finishing the formed surfaces with cement mortar
1:3 of sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing etc. complete,
(Excluding reinforcement and structural steel).with fully automatic micro
processor based PLC with SCADA enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate
(Crushed sand VSI Grade).

Rate as per SSR 2022-23 item. No.14.17 Cum 12617.00


Deduct labour Cess @ 1% ( SSR 20-21 pg no 3) -126.17
Total 12490.83
Add lead for cement-45 km cum 0.435 703.0 305.81
Add Metal lead charges for 14 km Cum 0.851 408.0 347.21
Add Sand lead charges for 14 km Cum 0.425 408.0 173.40
Add back Labour labour aminities & cess 1% 124.91
Rate per Cum 13442.15
Cum Say 13442.00
50 Providing and fixing in position TMT - FE - 500 bar reinforcement of various
diameters for R.C.C. footings, foundations, slabs, beams columns, canopies,
staircase, newels, chajjas, lintels pardis, copings, fins, arches etc. as per detailed
designs, drawings and schedules. including cutting, bending, hooking the bars,
binding with wires or tack welding and supporting as required complete.
Rate as per item no.26.33, sr.no.871 Pg. no.188 State Schedule Rates for year 2022-
MT
23 1 89703.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -897.03
Total 88805.97
Add Lead Charges 45 Km. MT 1 703 703.00
Add back Labour labour aminities & cess 1% 897.03
Rate per MT 90406.00
MT Say 90406.00
51 Supplying & Fixing 0.9 m x 0.6 m rectangular SFRC frame and cover as per
drawing fixed complete to manhole as specified and directed
Rate as per MCGM SOR-2018 item. No.R2-SE-10-12 7875.00
DEDUCTED GST @12% 843.75
Total 7031.25
Rate per Nos 7031.25
Nos. Say 7031.00
52 Providing and fixing of cement concrete Kerb Stone of various grades of size:
500mm width x 325 height x 165mm thick (Half Batter, Bull Nose/ Full Batter)
manufactured in wet press vacuum dewatering technology plant / equivalant
with face pimple finish for high visibility with excellent quality and finish and
edges perfect and sharp. Grade – M-25 including excavation in any soil except
rock, laying a leveling course of M 15 grade RMC 100mm thick to required
slope (inclusive of form work), jointing in C.M. 1:2 proportion flush to concrete
surface, painting exposed surface with one coat of primer and two coats of 1st
grade road marking paint in the yellow/ white/ black or any shade as directed.
(Kerbstones shall be procured from MCGM registered agencies).
MCGM USOR-2018 R2-RW-10-50 Rmt 1116.00
DECUCTED GST @12% 119.57
Rate per MT 996.43
RMT Say 996.00
53 Providing & fixing in the foothpath Concrete Paver blocks 200 X 200 X 80 mm
thick or any approved size in grey or any specified colour with shot blasted
texture or any aproved texture on top surface of approved pattern/shape and
colour having average crushing strength not less than 50N/mm² as per technical
specification sand IS CODE 15658:2006 manufactured in double layer precast
concrete Paverblocks 12to15 mm thick top layer and consisting of cubical shape
Quartz stone aggregate 8mm seve 100% passing and retained on 4.75mm
sizesieve, silicasand. The bottom layer should be 65 to 68 mm thick in grey
cement having 12 mm sieve 100% passing aggregates as per technical
specifications, rested on average compacted thickness of 25mm well graded
sand cushioning uniformly compacted with proper capacity mechanical
compactor with required level, grade and camber etc. complete as specified and
as directed by the Engineer.
MCGM USOR-2018 Itm No- R2-RW-3-29 Sqm 1717.00
DEDUCTED GST @12% 183.96
Rate per Sqm 1533.04
SQM Say 1533.00
Section-V- CD Works and Culvert, Bridges

Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
including shoring and strutting, dewatering as necessary and disposing off
54 excavated stuff as directed etc. complete. ( By Mechanical Means )

SSR /2022-23/Item no. 12.03 Sr.no.407 Page no.84 Cum 90.00


Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -0.90
Total 89.10
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 0.89
Rate per Cum 89.99
CUM Say 90.00
55
Excavation for foundation in soft rock including shoring and strutting,
dewatering as necessary and disposing off excavated stuff as directed etc.
complete.
SSR /2022-23/Item no. 12.08 Sr.no.410.Page no.84 Cum 557.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -5.57
Total 551.43
Add back Labour labour aminities & cess 1% 5.51
Rate per Cum 556.94
Cum Say 557.00
56 Excavation for foundation in hard rock by chiselling and wedging or line
drilling including shoring and strutting, dewatering as necessary and disposing
off excavated stuff as directed etc. complete.
SSR /2022-23/Item no. 12.11 Sr.no.413 Page No.85 Cum 1932.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -19.32
Total 1912.68
Add back Labour labour aminities & cess 1% 19.13
Rate per Cum 1931.81
Cum Say 1932.00
57 Dewatering on BHP basis by using water pump including diversion of stream,
providing cofferdams, earthern bunds etc. as may be necessary for foundation
and other parts of the the works and pumping out water during and after
excavation as may be required by using 5.0 to 9.0 BHP pump etc. complete.
(prior approval of Superintending Engineer will be necessary)

SSR /2022-2023/Item no. 12.23 Sr.no.417 Page No.86 Hour 201.00


Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -2.01
Total 198.99
Add back Labour labour aminities & cess 1% 1.99
Rate per Cum 200.98
Hour Say 201.00
58 Providing rubble filling of trap/ granite/ quartz it egneiss stones for foundations

includingh and packing filling gravel/sand in the voids etc. complete.


Rate as per SSR 2022-23 item. No.11.01 Sr.no.81 Cum 1701.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -17.01
Total 1683.99
Add lead chrges for 14 km lead and 0.20 for loose qty. Cum 1.2 499.00 598.80
Add back Labour labour aminities & cess 1% 16.84
Rate per Cum 2299.63
Cum Say 2300.00
59 Providing and laying in situ cement concrete M15 proportion of trap / granite /
quartzite / gneiss metal for foundation and bedding including necessary
formwork, scaffolding, bailing out water,compacting, curing etc. complete as
directed by Engineer in charge.
Rate as per SSR 2022-23 item. No.17.38 Cum 1 7519.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -75.19
Total 7443.81
Add lead for cement-60 km 0.33 703 231.99
Add Metal lead charges for 16 km 0.85 408 346.80
Add Sand lead charges for 16 km 0.45 408 183.60
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 74.44
Rate per Cum 8280.64
Cum Say 8281.00
60
Providing and casting in situ / ready mix PCC M20 grade of trap metal for
coping to head walls / parapet including centering, form work, compaction and
curing etc. complete. (with reversible drum type mixer/ concrete batch mix
plant (pan mixer) with SCADA with fine agreegates of required specifications
(Natural sand / VSI sand finely washed etc
Rate as per SSR 2022-23 item. No.11.31 Sr.No.-405 Page No.83 Cum 9258.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -92.58
Total 9165.42
Add lead for cement-45 km Cum 0.41 703 288.23
Add Metal lead charges for 14 km 0.90 408 367.20
Add Sand lead charges for 14 km Cum 0.425 408 173.40
Add back Labour labour aminities & cess 1% 91.65
Rate per Cum 10085.90
Cum Say 10086.00
61
Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 1200 Rmt
mm diameter in proper line, level and slope etc. complete
Rate as per SSR 2022-23 item. No.11.18 Sr.no.394 Page no.82 1 11790.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -117.90
Total 11672.10
add for lead of 25 Km 517.00
Add back Labour labour aminities & cess 1% 116.72
Rate per Rmt 12305.82
RMT Say 12306.00
62 Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 900 mm
diameter in proper line, level and slope etc. complete
Rate as per SSR 2022-23 item. No.11.16 Sr.no.392 Page No.82
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) 1 8272.00
Total -82.72
add for lead of 25 Km 310.00
Add back Labour labour aminities & cess 1% 136.00
Rate per Rmt 8635.28
Rate per Rmt RMT Say 8635.00
63 Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 600 mm
diameter in proper line, level and slope including providing and fixing collars in
cement mortar 1:2 and curing etc. complete.
Rate as per SSR 2022-23 item. No.11.09 Sr.no.384 Page No.81
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) 1 2733.00
Total -27.33
add for lead of 25 Km 163.00
Add back Labour labour aminities & cess 1% 73.00
0.00
2941.67
Rate per Rmt RMT Say 2942.00
64 Providing and laying 300mm dia NP2 Class R.C.C. hume pipes with Collar
joints conforming to IS 458:2003 and laid on approved bedding as per IS
783:1985 (reaff. 2010) including jointing the pipes and filleting with hemp and
stiff mix of cement mortar 1:2, including testing of pipes at contractors costs (in
presence of munipal staff) as per IS 3597 etc. complete as specified & as
directed by Engineer in Charge. (excluding necessary earthwork & bedding ).
MCGM USOR-2018 Itm No- R2-SWD-74 Rmt 1180.00
DEDUCTED GST @12% 126.43
add for lead of 35 Km 52.00
Rate per Rmt RMT 1105.57
65 Providing and laying in situ / ready mix M-25 controlled reinforced cement
concrete of trap metal for raft slab including "V" haunches, formwork,
scaffolding, compaction by vibrating, finishing curing etc. complete. concrete
batch mix plant / pan mixer with fine agreegates of required specifications
(Natural sand / VSI sand finely washed etc ) etc. complete. (excluding
reinforcement). a) RCC Grade with reversible drum type mixer/ concrete batch
mix plant (pan mixer) .
Rate as per SSR 2022-23 item. No.17.33 Sr.no.621 Pg.131 Cum 6241.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) -62.41
Total 6178.59
Add lead for cement-45 km 0.41 703 288.23
Add Metal lead charges for 14 km 0.9 408 367.20
Add Sand lead charges for 14 km 0.45 408 183.60
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 61.79
Rate per Cum 7079.41
Rate per Cum CUM Say 7079.00
66 Providing and laying in situ / ready mix M-25 cement concrete of trap
/granite/quartzite/ gneiss metal for cast in citu R.C.C. solid piers, column Wall
etc . including provision of V shaped false joints to form suitable panels on the
faces to approve design with compacting by vibrating and curing complete.
Including plywood/steel formwork, centering ( excluding dewatering by means
of pump) and including bailling out water and including CM 1:3 curing
complete.
a) Height upto 5 M. (With Concrete Mixer)
i) Height up to 5 m, normal rate.
ii) Height 5 to 7.50 m, add 5 percent extra over basic rate.
iii) Height 7.50 to 10 m, 7.50 percent extra.
iv) Over 10 m Height, add 10 percent extra for every 2.50m rise with fine
agreegates of required specifications (Natural sand / VSI sand finely washed
etc )

Rate as per SSR 2022-23item. No.17.48 Sr.no.-636 Pg.no-137 Cum 8246.00


Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -82.46
Total 8163.54
Add lead for cement-45 km cum 0.41 703 288.23
Add Metal lead charges for 14 km Cum 0.9 408 367.20
Add Sand lead charges for 14 km Cum 0.45 408 183.60
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 81.64
9084.21
Rate per Cum Say 9084.00
67 Providing and laying in situ / ready mix M-30 controlled cement concrete of
trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc.
including ramming, vibrating, curing, formwork, centering and finishing in
cement plaster excluding reinforcement etc. complete. (with fully automatic
micro processor based PLC with SCADA enabled concrete batch mix plant /
pan mixer and fine agreegates of required specifications ( VSI sand finely
washed etc ) i) Height up to 5 m, normal rate. ii) Height 5 to 7.50 m, add 5
percent extra over basic rate. iii) Height 7.50 to 10 m, 7.50 percent extra. iv)
Over 10 m Height, add 10 percent extra for every 2.50m rise

Rate as per SSR 2022-23 item. No.14.17 Sr.no.-465 Pg.no.94 Cum 11122.00
Deduct labour Cess @ 1% ( SSR 22-23pg no 2) -111.22
Total 11010.78
Add lead for cement-45 km cum 0.45 703 316.35
Add Metal lead charges for 14 km Cum 0.86 408 350.88
Add Sand lead charges for 14 km Cum 0.43 408 175.44
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 110.11
11963.56
Rate per Cum CUM Say 11964.00
68 Providing & laying weep holes of 100 mm dia. AC /PVC pipes as per drawing
for Abutment, returns, return wall, etc. complete.
Rate as per SSR 2022-23 item. No.17.37 Sr.no.-625 Pg.no.-132 Rmt 533.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -5.33
Total 527.67
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 5.28
532.95
Rate per Rmt RMT Say 533.00
Section-VI - Road furniture
69 Providing and fixing Caoutinary/Warning sign board in shape of equilateral
triangle of 90 cm sides made out sheet bonded with white retro reflective
sheeting of Class C (Type XI Microprismatic grade sheeting) having pressure
sensitive/heatactivated adhesive retoreflective specified background, border and
back side retoreflctive symbols, letters,numerals, arrow as per IRC:67-2012
Table No 8.3 Supported with back support frame 25mmx25mmx3mm, duly
painted on back side with grey stove enamel paint and supported on one no. of
M.S.angle iron post of size 65mmX65mmX6mm, 3.45 m long, duly painted with
with flat oil paint having alternate black and white bands of 25 cm width
including G.I. fixtures etc; fixing the boards in M25 grade concrete block ofsize
60cmX60cmX75 cm including transportation etc; complete. Class C (TypeX I
Microprismatic grade sheeting) shall have10 years written warranty from the
manufacturer and authorised distributor /convertor issued for field
performance including the screen printed are as and cut-out sheeting and cut-
out durable transparent overlay film and this warranty certificate in original
shouldbe submitted to the Engineer incharge by the contractor/supplier.

Rate as per SSR 2022-23 item. No.6.30e Sr.no.260 Pg.55 Nos 6289.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) -62.89
Total 6226.11
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 62.26
6288.37
Rate per Nos Nos. Say 6288.00
70 Providing and fixing Mandatory/Regulatory sign boards in circular shape of
600 mm dia made out of 3mm aluminum SHEET composite material bonded
with white retro reflective sheeting of Class C ( Type XI Micro prismatic grade
sheeting) having pressure sensitive/heat activated adhesive retoreflective
specified back ground, border and back side retoreflctive symbols, letters,
numerals, arrow as per IRC:67-2012 Table No 8.3 Supported with back support
frame 25mm x 25mm x 3mm, duly painted on back side with grey stove enamel
paint and supported on one no. of M. S. angle iron post of size 65 mm X 65 mm
X 6 mm, 3.45 m long, duly painted with with flat oil paint having alternate
black and white bands of 25 cm width including G.I. fixtures etc; fixing the
boards in M25 grade concrete block of size 60cm X 60cm X 75cm including
transportation etc; complete. Class C ( Type XI Micro prismatic grade sheeting)
shall have 10 years written warranty from the manufacturer and authorised
distributor/convertor issued for field performance including the screen printed
areas and cut-out sheeting and cut-out durable transparent overlay film and
this warranty certificate in original should be submitted to the Engineer in
charge by the contractor/supplier.

600 mm dia made out of 3mm aluminum composite material


Rate as per SSR 2022-23 item. No.6.28b Sr.no.-241 Pg.no.-53 Nos 5396.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -53.96
Total 5342.04
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 53.42
Rate per Nos 5395.46
Nos Say 5395.00
71 Providing and fixing of retro reflectorised informatory sign board Sqm
rectangular/Square in shape having area greater than 0.9 square meter
made out of 2mm aluminum sheet bonded with white retroreflective
sheeting of Class B( Type IV High intensity micro prismatic grade
sheeting HIP ) having pressure sensitive/heat activated adhesive
retoreflective specified background, border and back side retoreflctive
symbols, letters, numerals, arrow as per IRC:672012 Table No 8.3,
supported with back support frame 25mmx25mmx3mm, duly painted on
back side with two coats of grey stove enamel paint and supported on two
no. mild steelangleironpost75 mm x 75 mm x 6 mm, 3.5 mt long firmly
fixed to the ground by means of properly designed foundation with M25
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing The angle iron post shall be duly painted with
one coat of epoxy primer and two coats of epoxy finish paint having
alternate black and white bands of 25 cm width including GI fixures and
transportation etc. complete. The nut bolts of board with angle iron
post/supporting structure after fixing at site has to be electrically welded.
Class B (Type IV High intensity micro-prismatic grade sheeting- HIP)
sheeting shall have 7 years written warranty from the manufacturer and
authorized distributor/convertor issued for field performance including
the screen printed areas and cut-out sheeting and cut-out durable
transparent overlay film and this warranty certificate in original should
be submitted to the Engineer in charge by the contractor/supplier.

Rate as per SSR 2022-23 item. No.6.34a Sr.no.-276 Pg.no.-58 12364.00


Deduct labour Cess @ 1% ( SSR 22-23pg no 2) -123.64
Total 12240.36
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 122.40
Rate per Sqm 12362.76
Rate per Sqm SQM Say 12363.00
72 Providing and fixing board displaying information, such as 'Name of work,
Tender cost, Name of Contractor, Work completion and liability period etc',
having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm)
thick mild steel sheet painted with one coat of Zinc chromate stoving primer
and two coats of enamel paint on front side and grey stove enamel on back side
and border / messages / symbols etc. with approved colour shade paint
complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced
M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle
iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate
black and white bands of 25 cm width including all fixtures etc.and fixing the
boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including,
excavation, refilling, transportation, and labour etc complete. Spec. No. As
directed by Engineer in Charge
Rate as per SSR 2022-23 item. No.6.36 Sr.no.-284 Pg.no.-60 9963.00
Deduct labour Cess @ 1% ( SSR 22-23pg no 2) -99.63
Total 9863.37
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 98.63
Rate per No 9962.00
Rate per No Nos Say 9962.00
73 Providing and applying hot applied thormoplastic compound 2.5 mm thick
including reflectorising glass beads @250 gms per sqm area thickness of 2.5 mm
. The finished surface to be level,uniform and free from streaks and holes
(white/yellow)
Rate as per SSR 2022-23 item. No.6.12a Sr.no.-215 Pg.no.-48 Sqm 666.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -6.66
Total 659.34
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 6.59
Rate per Sqm 665.93
Say 666.00
74 Supplying and Fixing of Molded Shank Raised Pavement Markers / Cat's Eye
made of polycarbonate and ABS moulded body and reflective panels with micro
prismatic lens capable of providing total internal reflection of the light entering
the lens face and shall support a load of 16000 kg tested in accordance to ASTM
D 4280 Type H and complying to Specifications of Category A of MORTH
Circular No RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and
length shall not exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum
reflective area of 13 Sqcm on each side and the slope to the base shall be 35 +/- 5
degree. The strength of detachment of the integrated cylindrical shanks, (of
diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from
the body is to be a minimum value of 500 Kg. Fixing will be by drilling holes on
the road for the shanks to go inside, without nails and using epoxy resin based
adhesive as per manufacturer's recommendation and complete as directed by
the engineer.The contractor shall submit a two year warranty for satisfactory
field performance including stipulated retro-reflectance of the reflecting panel,
to the Engineer.

Rate as per SSR 2022-23 item. No.6.09 Sr.no.212 Pg.no.47 Nos. 1 366 366.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -3.66
Total 362.34
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 3.62
Rate per Nos 365.96
Nos say 366.00
Section-VII Ancillary Work
75 Providing Fixing and Maintaining M.S. fabricated traffic barricating on either
side of the carriageway/portion of the carriage way closed to trafficetc.
Complete as per drawing and directed by Engineer. Fixing and maintaining
1800x1800 mm panel.
Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19 1766.79
Increases 15% due to above rate 2018-2019 265.02
Total 2031.81
Rmt Say 2032.00
76 Shifting ,Fixing & Maintaining M.S. fabricated traffic barricating on sides of
the carriageway/portion of the carriage way closed to trafficetc. Complete as
per drawing and directed by Engineer.Labour for shifting, Fixing and
maintaining 1.8x1.8m panel.
Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19 776.79
Increases 15% due to above rate 2018-2019 116.52
Total 893.31
Rmt Say 893.00
77
Providing traffic wardens for regulation of traffic during construction as per
the requirement of traffic police and as directed by the engineers
Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19 453.21
Increases 15% due to above rate 2018-2019 67.98
Total 521.19
Nos Per day Say 521.00
78
Providing and applying three coats of water proof cement paint of approved
manufacture and of approved colour to new plastered surfaces including
scaffolding if necessary, cleaning and preparing the surface, watering for two
days etc. complete
Rate as per SSR 2022-23 item. No.35.15 Sr.no.-1085 Pg.no.-224
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 104.00
Total 104.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 1.04
Rate per NO 105.04
Nos Say 105.00
Section-VIII - Water Supply and Sanitary Fitting

79 Providing and laying cast iron pipes of B class of 80mm diameter with sockets
and spigot ends/ flanges and cast centrifugally / vertically including specials,
laying pipes and back filling the trench complete including excavation.

Rate as per SSR 2022-23 item. No.41.01 Sr.no.-1307 Pg.no.-332


Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 1317.00
Total 1317.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 13.17
Rate per Rmt 1330.17
RMT Say 1330.00
80

Providing and fixing on walls/ ceiling/ floors, 32 mm dia. heavy grade having
embossed as ISI Mark galvanised iron pipes weight of 3.89 Kilogram/meter
with necessary fittings . remaking good the demolished portion and applying
primer of anti-corrosive oil paint 2 coats Including necessary scaffolding and
removing existing pipe line if necessary and conveying and stacking the same in
PWD chowky or as directed etc. complete.
Rate as per SSR 2022-23 item. No.41.13 Sr.no.-1319 Pg.no.-333
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 696.00
Total 696.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 6.96
Rate per Rmt 702.96
RMT Say 703.00
81
Providing and laying in trenches 20 mm dia. medium grade having embossed as
ISI Mark galvanised iron pipes ?of 1.63 Kilogram/meter necessary fitting
remaking good the demolished portion with filling trenches and with primer of
anti-corrosive oil paint, 2 coats Including removing existing pipe line if
necessary and conveying and stacking the same in PWD chowky or as directed
etc. complete.
Rate as per SSR 2022-23 item. No.41.19 Sr.no.-1325 Pg.no.-334
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 487.00
Total 487.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 4.87
Rate per Rmt 491.87
RMT Say 492.00

PMC
DEPUTY ENGINEER EXECUTIVE ENGINEER
MMRDA MMRDA
Name of work : Construction of Concrete roads 1) SH-76 Angaon Junction to Pilanze Bk , Pilanze Kh to
Bedarpada road Thane under OARDS .

Consider- 1) Base Rates from SSR-2022-2023 , 2) Assume addition lead charges as per site location and material Sources 3)
Increase of percentages over the normal schedule of rates 5% for Municipal Corporation Areas.

RATE ANALYSIS

Section I - Site Clearence & Dismantling

Sr. No. Description Unit Details Rate (Rs.)


1 Cleaning and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned up to a lead of 1000 metres
including removal and disposal of top organic soil not exceeding 150 mm in
thickness. as per MORTH 201

Rate as per item no. 2.09, Page no.23 State Schedule Rates for year 2022-23 Sqm 12.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.12
Total 11.88
Add labour cess 1% 0.12
Rate per Sqm 12.00
Sqm say 12.50
2 Cutting down trees including trunks and branches with girths above 30 cm to
60 cm and stacking the materials neatly with all lifts and lead of 1000 m as
dircted and earth filling in the depression / pit if any. As per MORT&H 201
30 to 60 cm
Rate as per item no. 2.01,Page no-23 sr.no.78 State Schedule Rates for year 2022-
23 511.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -5.11
Total 505.89
Add labour cess 1% 5.11
Rate per nos. 511.00
Nos say 511.00
3 Cutting down trees including trunks and branches with girths above 60 cm to
90 cm and stacking the materials neatly with all lifts and lead of 1000m as
dircted and earth filling in the depression / pit if any. As per MORT&H 201
60 to 90 cm
Rate as per item no.2.02,Page no-23 sr.no.79 State Schedule Rates for year 2022-23
Nos
847.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -8.47
Total 838.53
Add labour cess 1% 8.47
Rate per nos. 847.00
Nos say 847.00
Nos Say 3110.00
Transplanting of Trees: Planting the tree in the pit filled with good soil, pressed
down layer by layer, insecticide to be sprayed before planting, broken limbs to
be removed, tree to be supported by three strong stakes driven into ground
4 metre away from the stem, transport to the site & planting, preparation of tree
basin, watering & maintaining for 1 month replacement of casualities till 1
month.

Garden DSR MCGM 2013 Item GW-2-4 Nos 882.00

5 Dismantling brick masonry in lime or cement mortar and stacking the materils
as directed with all leads, lifts etc.

Rate as per item no 46.09 .Page no-296 Sr.no.1547 State Schedule Rates for year
Cum
2022-23 335.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.35
Total 331.65
Add labour cess 1% 3.35
Rate per Cum. 335.00
Cum say 335.00
6 Dismantling stone masonry in lime or cement mortar including stacking the
materils as directed with all leads, lifts etc
Rate as per item no 46.11 .Page no-296 Sr.no.1549 State Schedule Rates for year
Cum
2022-23 380.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.80
Total 376.20
Add labour cess 1% 3.80
Rate per Cum. 380.00
Cum say 380.00
7 Dismantling the R.C.C. Work 1:2:4 and sorting out the materials such as steel
etc. as directed and stacking them within the specified lead as directed etc.
complete.
Rate as per item no. 46.29, sr.no.1565 Pg. no.297 State Schedule Rates for year
Cum
2022-23 1451.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -14.51
Total 1436.49
Add labour cess 1% 14.51
Rate per Cum. 1451.00
Cum say 1451.00
8 Dismantling of flexible pavements and disposal of dismantled materials up to a
lead of 1000 metres, stacking serviceable and unserviceable materials separately
etc. complete.
Rate as per item no.3.10, sr.no.123 Pg. no.28 State Schedule Rates for year 2022-23
Cum
430.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -4.30
Total 425.70
Add labour cess 1% 4.30
Rate per Cum. 430.00
Cum say 430.00
9 Removing Np-2 and Np-3 class pipes including stacking at road side as directed
by the Engineer in charge. Upto 900mm dia and above. etc complete.

Rate as per item no.46.31 , sr.no.1567 Pg. no.297 State Schedule Rates for year One Running
Metre
2022-23 310.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.10
Add labour cess 1% 3.10
Rate per RMT #REF!
RMT say #REF!

Section -II - Earth Work


Excavation for roadway in earth, soil of all sorts, sand, gravel or soft murum
including dressing section to the required grade, camber and side slopes and
10 conveying the excavated materials with all lifts upto a lead of 50m. and
spreading for embankment or stacking as directed.
Rate as per item no.2.16, sr.no.91 Pg. no.24 State Schedule Rates for year 2022-23
Cum
119.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -1.19
Total 117.81
Add labour cess 1% 1.19
Rate per Cum. 119.00
Cum say 119.00
11 Excavation for roadway in hard murum & Boulder including dressing section
to the required grade, camber and side slopes and conveying the excavated
materials with all lifts upto a lead of 50m.and spreading for embankment or
stacking as directed.
Rate as per item no.2.13, sr.no.88 Pg. no.24 State Schedule Rates for year 2022-23
Cum
139.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -1.39
Total 137.61
Add labour cess 1% 1.39
Rate per Cum. 139.00
Cum say 139.00
12 Excavation for roadway in soft rock, including dressing section to the required
grade, camber and side slopes and conveying the excavated materials with all
lifts upto a lead of 50m. and spreading or stacking as directed.
Rate as per item no.2.14,sr.no.89 Pg. no.24 State Schedule Rates for year 22-23
Cum
177.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -1.77
Total 175.23
Add labour cess 1% 1.77
Rate per Cum. 177.00
Cum say 177.00
13 Excavation for roadway in hard rock by wedging and chiselling or line drilling
including dressing section to the required grade, camber and side slopes and
conveying the excavated materials with all lifts upto a lead of 50m. and
spreading for embankment or stacking as directed.
Rate as per item no.2.16, sr.no.91 Pg. no.24 State Schedule Rates for year 2022-23
Cum
1419.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -14.19
Total 1404.81
Add 5% for Municipal Corporation Areas 70.24
Add labour cess 1% 14.19
Rate per Cum. 1489.24
Cum say 1489.00
14 Providing earth work in embankment with approved materials obtained from
other sources upto lead of 14 km. including all lifts, laying in layers of 20cm. to
30cm. thickness breaking clods, dressing to the required lines, curves, grades &
section, watering and compaction with vibratory roller with V-Sat attachment
to achieve not less than 97 % of standard proctor density etc. complete
( Material obtained from Other sources)
Rate as per item no.2.28, sr.no.101 Pg. no.25 State Schedule Rates for year 2022-23
Cum
757.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -7.57
Total 749.43
Add lead 14 Km.for Murrum. 1.2 391.00 469.20
Add Labour cess 1% 7.57
Rate per Cum. 1226.20
Cum say 1226.00
Conveying materials obtained from road cutting including all lifts, laying in
layers of 20cm. to 30cm. breaking clods, dressing to the required lines, curves,
grades and section, watering and compacting to not less than 97% of standard
15 proctor density for a lead of 300m. to 500m. inclusive, from the site of
excavation to the site of deposition as directed.

Rate as per item no.2.26, sr.no.99 Pg. no.25 State Schedule Rates for year 22-23 Cum 393.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.93
Total 389.07
Add Labour cess 1% 3.93
Rate per Cum 393.00
Cum say 393.00
Conveying materials obtained from road cutting including all lifts, laying in
layers of 20cm. to 30cm. breaking clods, dressing to the required lines, curves,
grades and section, watering and compacting to not less than 97% of standard
proctor density for a lead from 500m. to 14 km inclusive, from the site of
16 excavation to the site of deposition as directed.( This Item will be operated only
after approval of the Concerned Superintendent Engineer MMRDA )

Rate as per item no.2.26, sr.no.99 Pg. no.25 State Schedule Rates for year 2022-23 -
Cum
RATE UP TO 500 M 393.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.93
Total 389.07
Add lead up to14 Km.for Murrum./ excavated 1.2 354.00 424.80
Add Labour cess 1% 3.93
Rate per Cum
817.80
Cum say 818.00
Section-III - Road Pavement
17 Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness,
hand packing to proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of coarse aggregate,
watering and compacting with vibratory roller to the required density. By
Mechanical Means - Grading II (Using Screening Type B (11.2 mm) Aggregate)
Rate as per item no.3.19, sr.no.129 Pg. no.29 SSR 2022-23 Cum 2140.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -21.40
Total 2118.60
Add lead chrges for 14 km lead 1.2 408.00 489.60
Add Labour cess 1% 21.40
Rate per Cum 2629.60
Cum Say 2630.00
18 Providing and constructing 50 mm. thick Modified Penetration Macadam
(MPM) road surface including all mataerials, preparing the existing road
surface, spreading 40mm. stone metal layers 30% crusher broken metal + 70%
Hand broken (by breaking rubble obtained by blasting) heating and spraying
the bitumen of specified grade @ 1.75 kg/sqm, spreading 12mm.size chips
compacting with static roller having weight 8 to 10 MT. to achive the desired
degree of compaction as per Technical Specification Clause 506 etc. complete.
Including picking of existing WBM surface.(VG-30 bulk bitumen rates are
considered to arrive at rates)
Rate as per item no.3.37a, sr.no.149 Pg. no.32 State Schedule Rates for year 2022-23
sqm 210.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -2.10
Total 207.90
Add lead chrges for metal 14km . 1.2 0.050 408.00 24.48
Add lead chrges for Bituman 90 km . 1.75 2.04 3.57
Add Labour cess 1% 2.10
Rate per sqm 238.05
SQM Say 238.00
19 Construction of Granular sub-base by providing close graded Material, mixing

in a mechanical mix plant at OMC, carriage of mixed Material to work site,

spreading in uniform layers with motor grader/ Paver on prepared surface and

compacting with vibratory roller to achieve the desired density, complete as per

clause 401 -- Plant Mix Method and Grading - I Material


Rate as per item no.3.01, sr.no.113 Pg. no.27 State Schedule Rates for year 2022-23
Cum
2039.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -20.39
Total 2018.61
Add lead chrges for 14 km lead 1.2 408 489.60
Add Labour cess 1% 20.39
Rate per Cum 2528.60
CUM Say 2529.00
20 Wet Mix Macadam -- Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification including premixing the
Material with water at OMC in mechanical mix plant carriage of mixed
Material by tipper to site, laying in uniform layers with paver in sub- base /
base course on well prepared surface and compacting with vibratory roller to
achieve the desired density. Laying By Grader/Paver.
Rate as per item no.3.23, sr.no.133 Pg. no.30 State Schedule Rates for year 2022-23
Cum
2045.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -20.45
Total 2024.55
Add lead chrges for 14 km lead Cum 1.2 369.00 442.80
Add Labour cess 1% 20.45
Rate per Cum 2487.80
Cum Say 2488.00
21 Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20
cm thick including hand packing and compacting etc.complete.
Rate as per SSR 2022-23 item. No.21.38 sr.no.752 Page no.157. Cum 1382.00
Deduct labour Cess @ 1% ( SSR 20-21 pg no 3) -13.82
Total 1368.18
Add lead chrges for 14 km lead 1.2 386.00 463.20
Add Labour cess 1% 13.82
Rate per Cum 1845.20
Cum Say 1845.00
22 Construction of dry lean cement concrete Sub- base over a prepared sub-grade
with coarse and fine aggregate ( natural sand/ VSI grade finely washed crushed
sand) conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, ,
cement content not to be less than 150 kg/ cum, optimum moisture content to be
determined during trial length construction, concrete strength not to be less
than 10 Mpa at 7 days, mixed in a batching plant/ Weigh batch mixer,
transported to site with all leads and lifts, laid with a paver with electronic
sensor /by suitable means as approved by Engineer-incharge , compacting with
vibratory roller, finishing, curing and including preparation of sub-grade
surface if required etc. complete.
Rate as per item no.5.13, sr.no.181 Pg.no.43 State Schedule Rates for year 2022-23
Cum
3659.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -36.59
Total 3622.41
Add lead for cement-45 km kg 150 0.612 91.80
Add Metal lead charges for 14 km 0.90 408.00 367.20
Add Sand lead charges for 14 km 0.35 408.00 142.80
Add back Labour cess 1% 36.59
Rate per Cum 4260.80
Cum Say 4261.00
23 Providing & laying R.C.C.running beam in M-40 cement concrete including
required formwork mixing, compacting & curing ,etc. complete reinforced with
12mm dia.(Minimum 4 Nos.)M.S. main bars & 6mm Dia M.S. rings at 15 cm c/c
to be anchored in slipper slab properly with M.S. reinforcement as per drawing
etc. complete as specified (Steelwillnotbepaidseparately). Contractor has to
make his own arrangement for portable water for construction/curing with
hessian cloth, etc. & will not be paid separately.Beam Size: b) 23 cm. x 30 cm.
Rate from MGCM USOR 2018, Item No. R2-RW-10-06 Rmt 844.00
Deduct labour Cess @ 1% ( SSR 20-21 pg no 3) -8.44
Deduct GST 12% -101.28
Total 734.28
Add Extra Lead Charge for
Add lead for cement-45 km 0.0021429 612.00 1.31
Add Metal lead charges for 14 km 0.0621118 408.00 25.34
Add Sand lead charges for 14 km 0.0241546 408.00 9.86
Add Labour cess 1% 8.44
Rate per Rmt 779.23
RMT Say 779.00
24 Providing and laying 125 micron Low Density Polyethylene (LDPE) sheet
confirming to IS 3395 : 1997 below concrete pavement including all materials
and labour complete
Rate as per item no.5.19, sr.no.187 Pg. no.44 State Schedule Rates for year 2022-23
Sqm
30.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.30
Total 29.70
Add Labour cess 1% 0.30
Rate per Sqm 29.70
SQM Say 30.00
25 Providing and fixing in position TMT FE 500, 32 mm dia dowel bars precoated
with anticorrosive epoxy paint of required Dia. 60 cms. Long and at 30.00 cm.
C/C and wherever directed including handling, straightening, necessary cutting
supported by TMT FE 500, chairs with proper alignment by using properly Nos
designed assembly of Bulkheads lubricating half length with bituminous paint
as directed etc. complete.

Rate as per item no.5.14, sr.no.182Pg. no.43 State Schedule Rates for year 22-23 538.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -5.38
Total 532.62
Add Lead Charges for Reinforcment 45 Km. 1 1.482 0.703 1.04
Add Labour cess 1% 5.38
Rate per Nos 539.04
Nos Say 539.00
26 Providing & fixing high density polythene pipe of approved quality to fit around
the dowel bars of 32mm dia at the end of expansion joints, fully greased inside,
cotton waste in the pipe around the dowel bars & the pipe duly capped at the
end as directed.(H.D.P.pipe shall be 30 cm in length). As shown in the drawing.

Rate from MGCM USOR 2018, Item No. R2-RW-10-15 Nos 31.00
DEDUCTED GST12% 3.32
Rate per Nos 27.68
Nos Say 28.00
27 Providing and fixing in position TMT FE 500, tie bars precoated with
anticorrosive epoxy paint of 12 mm dia. 70 cms.long and at 30.00 cm. C/C and
wherever directed including handling, straightening wrapping with paper of
approved quality for half length, necessary cutting, handling, straightening ,
supported by assembly of TMT FE 500, chairs with proper alignment etc.
complete
Rate as per item no.5.16, sr.no.184 Pg. no.43 State Schedule Rates for year 2022-23
Nos
306.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.06
Total 302.94
Add Lead Charges 45 Km. 1 0.623 0.703 0.44
Add Labour cess 1% 3.06
Rate per Nos 306.44
Nos Say 306.00
28

Providing and laying in-situ M40 Grade unreinforced plain cement concrete
pavement over a prepared sub base with 43 grade cement , coarse and fine
aggregate ( natural sand/ VSI grade finely washed crushed sand) conforming to
IS 383, using fine and coarse aggregates combined gradation as per Table 600-3
of MORTH Specification 2013, mixed in a batching and mixing plant/ non
tilting mixer and Weigh batcher as per approved mix design, admixtures,
transporting to site, spreading, laying with approved make paver,compacted
and finished in a continuous operation, finishing to lines and grades as directed
by Engineer-in-charge and curing by curing compound /by providing cement
vata in cement Mortar 1:8 @0.6m X 0.6m centre to centre, admeasuring 80 mm
at bottom and 40 mm at top with depth of 75mm and maintaining the same
throughout curing period by any other method approved by Engineer-in-
charge.
Rate as per item no.5.03,sr.no.171 Pg.no.38 State Schedule Rates for year 22-23 Cum 7793.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -77.93
Total 7715.07
Add lead for cement-45 km 0.450 612.00 275.40
Add Metal lead charges for 14 km 0.85 408.00 346.80
Add Sand lead charges for 14 km 0.425 408.00 173.40
Add Labour labour cess 1% 77.93
Rate per Cum 8588.60
Cum Say 8589.00
29 Providing polypropylene fibers 300e3 Multi- Dimensional Graded Fibrillated
100% Virgin as per ASTMC1116 III Type 4.1.3 Std.at the rate of 125 gms per
bag of 50Kgs of cement etc.
MCGM USOR Road Works 2018 Itm No- R2-RW-10-40 Cum 439.00
DEDUCTED GST @12% 47.04
Rate per Cum 391.96
Cum Say 392.00
30 Cutting transverse contraction joints 3 to 4 mm wide and depth 80 mm.in
concrete slab using concrete cutting machine with diamond studded saw within
48 hours of casting of bay / slab etc. complete including subsequent widening of
the groove 8 to 10 mm. wide at top having depth of 15 mm. as directed by
Engineer incharge
Rate as per item no.5.17, sr.no.185 Pg.no.43 State Schedule Rates for year 2022-23
Rmt
76.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.76
Total 75.24
Add Labour labour cess 1% 0.76
Rate per Rmt 76.00
RMT Say 76.00
31 Providing to contraction joints polysuphide sealent (Pouring grade) confirming
to BS : 5212 - 1989 into sawed groove widened at top for sealent reservoir of
specified size and shape as per detailed drawing including fixing Polyethylene
foam backer rod of required diameter (appraox. 25% larger than the initial 3
mOne Metric Tonneo 4 mm. joint) overlaid with bond breaking tape as per
detailed drawing. Item includes cleaning the joints with water jet / air
compressor and allowing joint to become thoroughly dry before sealent is
applied and applying primer. (A) Contraction and longitudinal joints (15 mm.
deep x 8 mm.wide)
Rate as per item no.5.18, sr.no.186 Pg.no.44 State Schedule Rates for year 2022-23
Rmt
311.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -3.11
Total 307.89
Add Labour labour cess 1% 3.11
Rate per Rmt 311.00
RMT Say 311.00
32 Providing & fixing in position premoulded asphalt filler 12mm thick
conforming to I.S.1838 of 1983 for placing of the expansion joint, around
manholes & water entrances, etc. put to the required depth & 25 mm below the
camber, etc. complete as directed.
MCGM USOR Itm No- R2-RW-10-13 sqm 352.00
DEDUCTED GST @ 12% 37.71
Rate SQM Rmt 314.29
Say 314.00
33 Prime coat - Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including cleaning of road surface and
spraying, primer at the rate of 0.60 kg/sqm using mechanical means.
Rate as per item no.3.29, sr.no.139 Pg.no.30 State Schedule Rates for year 2022-23
Sqm.
33.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.33
Total 32.67
Add cost of transport of Bitumen
for 90 km lead Sqm. 0.0006 204.0 0.12
Difference of Bitumen Cost.= 61680-52764=8916 /MT 0.0006 8916.0 5.35
Add Labour labour cess 1% 0.33
Rate per Sqm 38.47
SQM Say 38.00
34 Providing and applying tack coat on the prepared surface heating by fames in
Boiler and spraying bitumen set footed in bitumen boller on B.T. surface 2.5
kg/10 sqm.(VG-30 bulk bitumen rates are considered to arrive at rates)
Rate as per item no.3.30, sr.no.140 Pg.no.30 State Schedule Rates for year 2022-23
Sqm.
18.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.18
Total 17.82
Add cost of transport of Bitumen
for 90 km lead Sqm. 0.0025 204.00 0.51
Difference of Bitumen Cost.= 61680-52764 = 8916 /MT 0.0025 8916.00 22.29
Add Labour labour cess 1% 0.18
Rate per Sqm 40.80
SQM Say 41.00
35 BITUMINOUS MACADAM: Proving and laying bituminous macadam using
crushed aggregates of Grading 1, premixed with bituminous binder,
transported to site with VTS , laid over a previously prepared surface, finished
to the required grade, level, alignment, and rolling to achieve the desired
compaction for 80/100 mm compacted thickness with 3.3 % using specified
grade of Bitumen. -- USING Batch mix type hot mix plant with SCADA, Sensor
Paver, vibratory roller.(VG-30 bulk bitumen rates are considered to arrive at
rates)
Rate as per item no.3.40, sr.no.154 Pg.no.33 State Schedule Rates for year 2022-23
Cum
7644.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -76.44
Total 7567.56
Add cost of transport of Bitumen 3.30%
for 90 km lead CUM 0.06105 204.00 12.45
Difference of Bitumen Cost.= 61680-52764 = 8916 /MT 0.06105 8916 544.32
Add Lead for Crush Aggregate 1.48 Cum 1.48 408.00 603.84
Add Labour labour cess 1% 76.44
Rate per Cum Total 8805.00
Cum Say 8805.00
36 DENSE BITUMINOUS MACADAM: Proving and laying dense bituminous
macadam using crushed aggregates of Grading 1, premixed with bituminous
binder of specified grade of Bitumen @ 4.50 per cent by weight of total mix and
filler, transported to site with VTS , laid over a previously prepared surface,
finished to the required grade, level, alignment, and rolling to achieve the
desired density for 76-100 mm compacted thickness .USING Batch mix type hot
mix plant with SCADA, Sensor Paver, Vibratory roller with Stone Dust filler.
(VG-30 bulk bitumen rates are considered to arrive at rates)
Rate as per item no.3.44, sr.no.156 Pg.no.34 State Schedule Rates for year 2022-23
Cum
9664.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -96.64
Total 9567.36
Add cost of transport of Bitumen 4.50%
for 90 km lead CUM 0.0832 204.00 16.97
Difference of Bitumen Cost.= 61680-52764=8916 /MT 0.0832 8916 741.81
Add Lead for Crush Aggregate 1.53 Cum (.61+.459+.459) 1.53 408 624.24
Add Labour labour cess 1% 96.64
Rate per Cum Total 11047.00
Cum Say 11047.00
37 BITUMINOUS CONCRETE:- Providing and laying bituminous concrete using
crushed aggregates of grading 1, premixed with bituminous binder @ 5.20 per
cent by weight of total mix and filler, transported to site with VTS , laid over a
previously prepared surface, finished to the required grade, level, alignment,
and rolling to achieve the desired compaction for 50 mm compacted thickness
with specified grade of Bitumen,Excluding prime / tack coat. For Bitumen of
specified grade -- USING Batch mix type hot mix plant with SCADA, Sensor
Paver, Vibratory roller with Stone Dust filler. (VG-30 bulk bitumen rates are
considered to arrive at rates)
Rate as per item no.3.48, sr.no.158 Pg.no.34 State Schedule Rates for year 2022-23
10599.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -105.99
Total 10493.01
Add cost of transport of Bitumen 5.20%
for 90 km lead CUM 0.102 204.00 20.81
Difference of Bitumen Cost.= 61680-52764=8916 /MT 0.102 8916 909.43
Add Lead for Crush Aggregate 1.48 Cum 1.57 408.00 640.56
Add Labour labour cess 1% 104.93
Rate per Cum 12169.00
Cum Say 12169.00
38 Providing & fixing in the carriageway 100 mm thick interlocking concrete
unishape pavers( monolithic- single layer precast concrete blocks) of grey
cement colouredhaving average crushing strength not less than 50N/mm² as per
technical specificationand IS CODE 15658:2006, placed on average compacted
thickness 25 mm well graded sand cushioning uniformly compacted with proper
capacity mechanical compactor with required level, grade and camber etc.
complete as specified and as directed by the Engineer.
Rate from MGCM 2018, Item No. R2-RW-3-19 Sqm 1054.00
DEDUCTED GST @12% 112.93
Rate per Nos 941.07
SQM Say 941.00
39 Providing Heavy Duty Fibre Glass Reinforced Plastic Temporary Barricade of
1.75 m hight, with base width of 430 mm as a provision to accept water
ballasting of 101 Itrs-110 Ltrs approx. and arrangement for traffic diversion
such as traffic signals during construction at site, for day and night as per
requirement. The raw material shall be UV stabilized Linear Low Density
Polyethylene and should meet the requirements stipulated in standard IS:
10146-1982, IS:10141-1982 and should also comply to FDA:CFR Title
21.177.1520. Olefin Polymers , with specific FRP Grade 300-104 reinforced
-----------------and 2 nos on Extension top for holding light brackets / Rod for
cloth holding. The plastic barricades has a strong vertical rib of 1740 mm length
at the rear centre & 72 No's ofa) For 725 mm height (LType Jersey
Barrier ) ,Empty Weight:6.67 Kilogram/ Rgm,Weight Full : 35.89Kilogram/
Rgm approx. (After Water / Sand Filling)
Rate as per item no.50.46, sr.no.1785 Pg.no.343 State Schedule Rates for year
2022-23 1846.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -18.46
Total 1827.54
Add Labour labour cess 1% 18.46
Rate per Sqm 1846.00
SQM Say 1846.00
Section-IV - Storm Water Drain
40 Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
including shoring and strutting, dewatering as necessary and disposing off
excavated stuff as directed etc. complete. ( By Mechanical Means )

Upto 1.50 m lift Normal Rate


Rate as per item no.12.03, sr.no.407 Pg. no.84 State Schedule Rates for year 2022-23
Cum
90.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -0.90
Total 89.10
Add labour cess 1% 0.90
90.00
Rate per Cum. Cum 90.00
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum

41 including shoring and strutting, dewatering as necessary and disposing off

excavated stuff as directed etc. complete. ( By /manaual Means )


Upto 1.50m lift Normal Rate
Rate as per item no.12.02, sr.no.406 Pg. no.84 State Schedule Rates for year 2022-23
Cum
239.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) ` -2.39
Total 236.61
Add labour cess 1% 2.39
Rate per Cum 239.00
Cum Say 239.00
42 Excavation for foundation in hard murum and boulders including shoring and
strutting, dewatering as necessary and disposing off excavated stuff as directed
etc. complete.

Upto 1.50m lift Normal Rate


Rate as per item no.12.06, sr.no.409 Pg. no.84 State Schedule Rates for year 2022-23
Cum
286.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) ` -2.86
Total 283.14
Add 5% for Municipal Corporation Areas 14.16
Add labour cess 1% 2.86
Rate per Cum 300.16
Cum Say 300.00
43 Excavation for foundation in soft rock including shoring and strutting,
dewatering as necessary and disposing off excavated stuff as directed etc.
complete.
Upto 1.50m lift Normal Rate
Rate as per item no.12.08, sr.no.410 Pg. no.84 State Schedule Rates for year 2022-23
Cum
557.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -5.57
Total 551.43
Add labour cess 1% 5.57
Rate per Cum 557.00
Cum Say 557.00
44 Excavation for foundation in hard rock by chiselling and wedging or line
drilling including shoring and strutting, dewatering as necessary and disposing
off excavated stuff as directed etc. complete
Upto 1.50m lift Normal Rate
Rate as per item no.12.11, sr.no.413 Pg. no.85 State Schedule Rates for year 2022-23
Cum 1932.00

Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -19.32


Total 1912.68
Add labour cess 1% 19.32
Rate per Cum 1932.00
Cum Say 1932.00
45 Providing rubble filling of trap/ granite/ quartzite gneiss stones for foundations

including filling voids with sand/grit and compaction etc complete


Rate as per item no.11.01, sr.no.376 Pg. no.81 State Schedule Rates for year 2022-23
Cum 1701.00

Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -17.01


Total 1683.99
Add lead chrges for 14 km lead . 1.2 499 598.80
Add Labour cess 1% 17.01
Rate per Cum 2299.80
Cum Say 2300.00
46 Providing and laying Cast in situ/Ready Mix cement concrete in M15 of trap/
granite/quartzite/gneiss metal for foundation / steps including steel centering,
formwork, laying/pumping, compacting, roughening them if special finish is to
be provided, finishing uneven and honeycombed surface and curing etc.
complete. The Cement Mortar 1:3 plaster is considered for rendering uneven
and honeycombed surface, only. Newly laid concrete shall be covered by gunny
bag, plastic, tarpaulin etc. (Wooden centering will not be allowed.),with fully
automatic micro processor based PLC with SCADA enabled reversible Drum
Type mixer/concrete Batch mix plant (Pan mixer) etc. complete. With fine
aggregate (Crushed sand VSI Grade
Rate as per item no.24.04, sr.no.828 Pg. no.175 State Schedule Rates for year 2022-
Cum
23 1 6359.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -63.59
Total 6295.41
Add lead for cement-45 km Cum 0.33 703.00 231.99
Add Metal lead charges for 14 km Cum 0.85 408.00 346.80
Add Sand lead charges for 14 km Cum 0.45 408.00 183.60
Add back Labour labour aminities & cess 1% 63.59
Rate per Cum 7121.39
Cum Say 7121.00
47 Providing and laying Cast in situ/Ready Mix cement concrete in M20 of trap/
granite/quartzite/gneiss metal for bed blocks, foundation blocks and such
other items including bailing out water, Steel centering, formwork, laying/
pumping, compacting, roughening them if special finish is to be provided,
finishing uneven and honeycombed surface and curing etc. complete. The
Cement Mortar 1:3 plaster is considered for rendering uneven and
honeycombed surface only. Newly laid concrete shall be covered by gunny bag,
plastic, tarpaulin etc. (Wooden centering will not be allowed.), with fully
automatic micro processor based PLC with SCADA enabled reversible Drum
Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete. With fine
aggregate (Crushed sand VSI Grade)
Rate as per item no.24.10, sr.no.831 Pg. no.176 State Schedule Rates for year 2022-
Cum
23 6721.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -67.21
Total 6653.79
Add lead for cement-45 km cum 0.41 703.0 288.23
Add Metal lead charges for 14 km Cum 0.9 408.0 367.20
Add Sand lead charges for 14 km Cum 0.425 408.0 173.40
Add back Labour labour aminities & cess 1% 66.54
Rate per Cum 7549.16
Cum Say 7549.00
48 Providing and laying Cast in situ/Ready Mix cement concrete in M-20 of trap/
granite/ quartzite/ gneiss metal for R.C.C. pardi of required thickness including
steel centering, formwork, cover blocks, laying/pumping, compacting , curing ,
finishing and rougheningthem if special finish is to be provided and curing
complete.(Excluding reinforcement and structural steel).with fully automatic
micro processor based PLC with SCADA enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate
(Crushed sand VSI Grade
Rate as per item no.26.17, sr.no.860 Pg. no.185 State Schedule Rates for year 2022-
Cum
23 15567.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -155.67
Total 15411.33
Add lead for cement-45 km cum 0.41 703.0 288.23
Add Metal lead charges for 14 km Cum 0.9 408.0 367.20
Add Sand lead charges for 14 km Cum 0.425 408.0 173.40
Add back Labour labour aminities & cess 1% 155.67
Rate per Cum 16395.83
Cum Say 16396.00
49 Providing and laying Cast in situ/Ready Mix cement concrete M-25 of trap/
granite /quartzite/ gneiss metal for R.C.C. slabs and landings as per detailed
designs and drawings including steel centering, formwork, cover blocks,
laying/pumping, compaction finishing the formed surfaces with cement mortar
1:3 of sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing etc. complete,
(Excluding reinforcement and structural steel).with fully automatic micro
processor based PLC with SCADA enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate
(Crushed sand VSI Grade).

Rate as per SSR 2022-23 item. No.14.17 Cum 12617.00


Deduct labour Cess @ 1% ( SSR 20-21 pg no 3) -126.17
Total 12490.83
Add lead for cement-45 km cum 0.435 703.0 305.81
Add Metal lead charges for 14 km Cum 0.851 408.0 347.21
Add Sand lead charges for 14 km Cum 0.425 408.0 173.40
Add back Labour labour aminities & cess 1% 124.91
Rate per Cum 13442.15
Cum Say 13442.00
50 Providing and fixing in position TMT - FE - 500 bar reinforcement of various
diameters for R.C.C. footings, foundations, slabs, beams columns, canopies,
staircase, newels, chajjas, lintels pardis, copings, fins, arches etc. as per detailed
designs, drawings and schedules. including cutting, bending, hooking the bars,
binding with wires or tack welding and supporting as required complete.
Rate as per item no.26.33, sr.no.871 Pg. no.188 State Schedule Rates for year 2022-
MT
23 1 89703.00
Deduct labour Cess @ 1% ( SSR 22-23 -IV-b pg no 2) -897.03
Total 88805.97
Add Lead Charges 45 Km. MT 1 703 703.00
Add back Labour labour aminities & cess 1% 897.03
Rate per MT 90406.00
MT Say 90406.00
51 Supplying & Fixing 0.9 m x 0.6 m rectangular SFRC frame and cover as per
drawing fixed complete to manhole as specified and directed
Rate as per MCGM SOR-2018 item. No.R2-SE-10-12 7875.00
DEDUCTED GST @12% 843.75
Total 7031.25
Rate per Nos 7031.25
Nos. Say 7031.00
52 Providing and fixing of cement concrete Kerb Stone of various grades of size:
500mm width x 325 height x 165mm thick (Half Batter, Bull Nose/ Full Batter)
manufactured in wet press vacuum dewatering technology plant / equivalant
with face pimple finish for high visibility with excellent quality and finish and
edges perfect and sharp. Grade – M-25 including excavation in any soil except
rock, laying a leveling course of M 15 grade RMC 100mm thick to required
slope (inclusive of form work), jointing in C.M. 1:2 proportion flush to concrete
surface, painting exposed surface with one coat of primer and two coats of 1st
grade road marking paint in the yellow/ white/ black or any shade as directed.
(Kerbstones shall be procured from MCGM registered agencies).
MCGM USOR-2018 R2-RW-10-50 Rmt 1116.00
DECUCTED GST @12% 119.57
Rate per MT 996.43
RMT Say 996.00
53 Providing & fixing in the foothpath Concrete Paver blocks 200 X 200 X 80 mm
thick or any approved size in grey or any specified colour with shot blasted
texture or any aproved texture on top surface of approved pattern/shape and
colour having average crushing strength not less than 50N/mm² as per technical
specification sand IS CODE 15658:2006 manufactured in double layer precast
concrete Paverblocks 12to15 mm thick top layer and consisting of cubical shape
Quartz stone aggregate 8mm seve 100% passing and retained on 4.75mm
sizesieve, silicasand. The bottom layer should be 65 to 68 mm thick in grey
cement having 12 mm sieve 100% passing aggregates as per technical
specifications, rested on average compacted thickness of 25mm well graded
sand cushioning uniformly compacted with proper capacity mechanical
compactor with required level, grade and camber etc. complete as specified and
as directed by the Engineer.
MCGM USOR-2018 Itm No- R2-RW-3-29 Sqm 1717.00
DEDUCTED GST @12% 183.96
Rate per Sqm 1533.04
SQM Say 1533.00
Section-V- CD Works and Culvert, Bridges

Excavation for foundation in earth, soils of all types, sand, gravel, soft murum
including shoring and strutting, dewatering as necessary and disposing off
54 excavated stuff as directed etc. complete. ( By Mechanical Means )

SSR /2022-23/Item no. 12.03 Sr.no.407 Page no.84 Cum 90.00


Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -0.90
Total 89.10
Add 5% for Municipal Corporation Areas 4.46
Add back Labour labour aminities & cess 1% 0.89
Rate per Cum 94.45
CUM Say 94.00
55
Excavation for foundation in soft rock including shoring and strutting,
dewatering as necessary and disposing off excavated stuff as directed etc.
complete.
SSR /2022-23/Item no. 12.08 Sr.no.410.Page no.84 Cum 557.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -5.57
Total 551.43
Add back Labour labour aminities & cess 1% 5.51
Rate per Cum 556.94
Cum Say 557.00
56 Excavation for foundation in hard rock by chiselling and wedging or line
drilling including shoring and strutting, dewatering as necessary and disposing
off excavated stuff as directed etc. complete.
SSR /2022-23/Item no. 12.11 Sr.no.413 Page No.85 Cum 1932.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -19.32
Total 1912.68
Add back Labour labour aminities & cess 1% 19.13
Rate per Cum 1931.81
Cum Say 1932.00
57 Dewatering on BHP basis by using water pump including diversion of stream,
providing cofferdams, earthern bunds etc. as may be necessary for foundation
and other parts of the the works and pumping out water during and after
excavation as may be required by using 5.0 to 9.0 BHP pump etc. complete.
(prior approval of Superintending Engineer will be necessary)

SSR /2022-2023/Item no. 12.23 Sr.no.417 Page No.86 Hour 201.00


Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -2.01
Total 198.99
Add back Labour labour aminities & cess 1% 1.99
Rate per Cum 200.98
Hour Say 201.00
58 Providing rubble filling of trap/ granite/ quartz it egneiss stones for foundations

includingh and packing filling gravel/sand in the voids etc. complete.


Rate as per SSR 2022-23 item. No.11.01 Sr.no.81 Cum 1701.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -17.01
Total 1683.99
Add lead chrges for 14 km lead and 0.20 for loose qty. Cum 1.2 499.00 598.80
Add back Labour labour aminities & cess 1% 16.84
Rate per Cum 2299.63
Cum Say 2300.00
59 Providing and laying in situ cement concrete M15 proportion of trap / granite /
quartzite / gneiss metal for foundation and bedding including necessary
formwork, scaffolding, bailing out water,compacting, curing etc. complete as
directed by Engineer in charge.
Rate as per SSR 2022-23 item. No.17.38 Cum 1 7519.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -75.19
Total 7443.81
Add lead for cement-60 km 0.33 703 231.99
Add Metal lead charges for 16 km 0.85 408 346.80
Add Sand lead charges for 16 km 0.45 408 183.60
Add 5% for Municipal Corporation Areas 372.19
Add back Labour labour aminities & cess 1% 74.44
Rate per Cum 8652.83
Cum Say 8653.00
60
Providing and casting in situ / ready mix PCC M20 grade of trap metal for
coping to head walls / parapet including centering, form work, compaction and
curing etc. complete. (with reversible drum type mixer/ concrete batch mix
plant (pan mixer) with SCADA with fine agreegates of required specifications
(Natural sand / VSI sand finely washed etc
Rate as per SSR 2022-23 item. No.11.31 Sr.No.-405 Page No.83 Cum 9258.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -92.58
Total 9165.42
Add lead for cement-45 km Cum 0.41 703 288.23
Add Metal lead charges for 14 km 0.90 408 367.20
Add Sand lead charges for 14 km Cum 0.425 408 173.40
Add back Labour labour aminities & cess 1% 91.65
Rate per Cum 10085.90
Cum Say 10086.00
61
Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 1200 Rmt
mm diameter in proper line, level and slope etc. complete
Rate as per SSR 2022-23 item. No.11.18 Sr.no.394 Page no.82 1 11790.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -117.90
Total 11672.10
add for lead of 25 Km 517.00
Add back Labour labour aminities & cess 1% 116.72
Rate per Rmt 12305.82
RMT Say 12306.00
62 Providing and laying cement concrete pipe of IS 458:2003 NP-3 class of 900 mm
diameter in proper line, level and slope etc. complete
Rate as per SSR 2022-23 item. No.11.16 Sr.no.392 Page No.82
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) 1 8272.00
Total -82.72
add for lead of 25 Km 310.00
Add back Labour labour aminities & cess 1% 136.00
Rate per Rmt 8635.28
Rate per Rmt RMT Say 8635.00
63 Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 600 mm
diameter in proper line, level and slope including providing and fixing collars in
cement mortar 1:2 and curing etc. complete.
Rate as per SSR 2022-23 item. No.11.09 Sr.no.384 Page No.81
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) 1 2733.00
Total -27.33
add for lead of 25 Km 163.00
Add back Labour labour aminities & cess 1% 73.00
0.00
2941.67
Rate per Rmt RMT Say 2942.00
64 Providing and laying 300mm dia NP2 Class R.C.C. hume pipes with Collar
joints conforming to IS 458:2003 and laid on approved bedding as per IS
783:1985 (reaff. 2010) including jointing the pipes and filleting with hemp and
stiff mix of cement mortar 1:2, including testing of pipes at contractors costs (in
presence of munipal staff) as per IS 3597 etc. complete as specified & as
directed by Engineer in Charge. (excluding necessary earthwork & bedding ).
MCGM USOR-2018 Itm No- R2-SWD-74 Rmt 1180.00
DEDUCTED GST @12% 126.43
add for lead of 35 Km 52.00
Rate per Rmt RMT 1105.57
65 Providing and laying in situ / ready mix M-25 controlled reinforced cement
concrete of trap metal for raft slab including "V" haunches, formwork,
scaffolding, compaction by vibrating, finishing curing etc. complete. concrete
batch mix plant / pan mixer with fine agreegates of required specifications
(Natural sand / VSI sand finely washed etc ) etc. complete. (excluding
reinforcement). a) RCC Grade with reversible drum type mixer/ concrete batch
mix plant (pan mixer) .
Rate as per SSR 2022-23 item. No.17.33 Sr.no.621 Pg.131 Cum 6241.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) -62.41
Total 6178.59
Add lead for cement-45 km 0.41 703 288.23
Add Metal lead charges for 14 km 0.9 408 367.20
Add Sand lead charges for 14 km 0.45 408 183.60
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 61.79
Rate per Cum 7079.41
Rate per Cum CUM Say 7079.00
66 Providing and laying in situ / ready mix M-25 cement concrete of trap
/granite/quartzite/ gneiss metal for cast in citu R.C.C. solid piers, column Wall
etc . including provision of V shaped false joints to form suitable panels on the
faces to approve design with compacting by vibrating and curing complete.
Including plywood/steel formwork, centering ( excluding dewatering by means
of pump) and including bailling out water and including CM 1:3 curing
complete.
a) Height upto 5 M. (With Concrete Mixer)
i) Height up to 5 m, normal rate.
ii) Height 5 to 7.50 m, add 5 percent extra over basic rate.
iii) Height 7.50 to 10 m, 7.50 percent extra.
iv) Over 10 m Height, add 10 percent extra for every 2.50m rise with fine
agreegates of required specifications (Natural sand / VSI sand finely washed
etc )

Rate as per SSR 2022-23item. No.17.48 Sr.no.-636 Pg.no-137 Cum 8246.00


Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -82.46
Total 8163.54
Add lead for cement-45 km cum 0.41 703 288.23
Add Metal lead charges for 14 km Cum 0.9 408 367.20
Add Sand lead charges for 14 km Cum 0.45 408 183.60
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 81.64
9084.21
Rate per Cum Say 9084.00
67 Providing and laying in situ / ready mix M-30 controlled cement concrete of
trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc.
including ramming, vibrating, curing, formwork, centering and finishing in
cement plaster excluding reinforcement etc. complete. (with fully automatic
micro processor based PLC with SCADA enabled concrete batch mix plant /
pan mixer and fine agreegates of required specifications ( VSI sand finely
washed etc ) i) Height up to 5 m, normal rate. ii) Height 5 to 7.50 m, add 5
percent extra over basic rate. iii) Height 7.50 to 10 m, 7.50 percent extra. iv)
Over 10 m Height, add 10 percent extra for every 2.50m rise

Rate as per SSR 2022-23 item. No.14.17 Sr.no.-465 Pg.no.94 Cum 11122.00
Deduct labour Cess @ 1% ( SSR 22-23pg no 2) -111.22
Total 11010.78
Add lead for cement-45 km cum 0.45 703 316.35
Add Metal lead charges for 14 km Cum 0.86 408 350.88
Add Sand lead charges for 14 km Cum 0.43 408 175.44
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 110.11
11963.56
Rate per Cum CUM Say 11964.00
68 Providing & laying weep holes of 100 mm dia. AC /PVC pipes as per drawing
for Abutment, returns, return wall, etc. complete.
Rate as per SSR 2022-23 item. No.17.37 Sr.no.-625 Pg.no.-132 Rmt 533.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -5.33
Total 527.67
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 5.28
532.95
Rate per Rmt RMT Say 533.00
Section-VI - Road furniture
69 Providing and fixing Caoutinary/Warning sign board in shape of equilateral
triangle of 90 cm sides made out sheet bonded with white retro reflective
sheeting of Class C (Type XI Microprismatic grade sheeting) having pressure
sensitive/heatactivated adhesive retoreflective specified background, border and
back side retoreflctive symbols, letters,numerals, arrow as per IRC:67-2012
Table No 8.3 Supported with back support frame 25mmx25mmx3mm, duly
painted on back side with grey stove enamel paint and supported on one no. of
M.S.angle iron post of size 65mmX65mmX6mm, 3.45 m long, duly painted with
with flat oil paint having alternate black and white bands of 25 cm width
including G.I. fixtures etc; fixing the boards in M25 grade concrete block ofsize
60cmX60cmX75 cm including transportation etc; complete. Class C (TypeX I
Microprismatic grade sheeting) shall have10 years written warranty from the
manufacturer and authorised distributor /convertor issued for field
performance including the screen printed are as and cut-out sheeting and cut-
out durable transparent overlay film and this warranty certificate in original
shouldbe submitted to the Engineer incharge by the contractor/supplier.

Rate as per SSR 2022-23 item. No.6.30e Sr.no.260 Pg.55 Nos 6289.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) -62.89
Total 6226.11
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 62.26
6288.37
Rate per Nos Nos. Say 6288.00
70 Providing and fixing Mandatory/Regulatory sign boards in circular shape of
600 mm dia made out of 3mm aluminum SHEET composite material bonded
with white retro reflective sheeting of Class C ( Type XI Micro prismatic grade
sheeting) having pressure sensitive/heat activated adhesive retoreflective
specified back ground, border and back side retoreflctive symbols, letters,
numerals, arrow as per IRC:67-2012 Table No 8.3 Supported with back support
frame 25mm x 25mm x 3mm, duly painted on back side with grey stove enamel
paint and supported on one no. of M. S. angle iron post of size 65 mm X 65 mm
X 6 mm, 3.45 m long, duly painted with with flat oil paint having alternate
black and white bands of 25 cm width including G.I. fixtures etc; fixing the
boards in M25 grade concrete block of size 60cm X 60cm X 75cm including
transportation etc; complete. Class C ( Type XI Micro prismatic grade sheeting)
shall have 10 years written warranty from the manufacturer and authorised
distributor/convertor issued for field performance including the screen printed
areas and cut-out sheeting and cut-out durable transparent overlay film and
this warranty certificate in original should be submitted to the Engineer in
charge by the contractor/supplier.

600 mm dia made out of 3mm aluminum composite material


Rate as per SSR 2022-23 item. No.6.28b Sr.no.-241 Pg.no.-53 Nos 5396.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -53.96
Total 5342.04
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 53.42
Rate per Nos 5395.46
Nos Say 5395.00
71 Providing and fixing of retro reflectorised informatory sign board Sqm
rectangular/Square in shape having area greater than 0.9 square meter
made out of 2mm aluminum sheet bonded with white retroreflective
sheeting of Class B( Type IV High intensity micro prismatic grade
sheeting HIP ) having pressure sensitive/heat activated adhesive
retoreflective specified background, border and back side retoreflctive
symbols, letters, numerals, arrow as per IRC:672012 Table No 8.3,
supported with back support frame 25mmx25mmx3mm, duly painted on
back side with two coats of grey stove enamel paint and supported on two
no. mild steelangleironpost75 mm x 75 mm x 6 mm, 3.5 mt long firmly
fixed to the ground by means of properly designed foundation with M25
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing The angle iron post shall be duly painted with
one coat of epoxy primer and two coats of epoxy finish paint having
alternate black and white bands of 25 cm width including GI fixures and
transportation etc. complete. The nut bolts of board with angle iron
post/supporting structure after fixing at site has to be electrically welded.
Class B (Type IV High intensity micro-prismatic grade sheeting- HIP)
sheeting shall have 7 years written warranty from the manufacturer and
authorized distributor/convertor issued for field performance including
the screen printed areas and cut-out sheeting and cut-out durable
transparent overlay film and this warranty certificate in original should
be submitted to the Engineer in charge by the contractor/supplier.

Rate as per SSR 2022-23 item. No.6.34a Sr.no.-276 Pg.no.-58 12364.00


Deduct labour Cess @ 1% ( SSR 22-23pg no 2) -123.64
Total 12240.36
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 122.40
Rate per Sqm 12362.76
Rate per Sqm SQM Say 12363.00
72 Providing and fixing board displaying information, such as 'Name of work,
Tender cost, Name of Contractor, Work completion and liability period etc',
having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm)
thick mild steel sheet painted with one coat of Zinc chromate stoving primer
and two coats of enamel paint on front side and grey stove enamel on back side
and border / messages / symbols etc. with approved colour shade paint
complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced
M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle
iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate
black and white bands of 25 cm width including all fixtures etc.and fixing the
boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including,
excavation, refilling, transportation, and labour etc complete. Spec. No. As
directed by Engineer in Charge
Rate as per SSR 2022-23 item. No.6.36 Sr.no.-284 Pg.no.-60 9963.00
Deduct labour Cess @ 1% ( SSR 22-23pg no 2) -99.63
Total 9863.37
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 98.63
Rate per No 9962.00
Rate per No Nos Say 9962.00
73 Providing and applying hot applied thormoplastic compound 2.5 mm thick
including reflectorising glass beads @250 gms per sqm area thickness of 2.5 mm
. The finished surface to be level,uniform and free from streaks and holes
(white/yellow)
Rate as per SSR 2022-23 item. No.6.12a Sr.no.-215 Pg.no.-48 Sqm 666.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -6.66
Total 659.34
Add 5% for Municipal Corporation Areas 32.97
Add back Labour labour aminities & cess 1% 6.59
Rate per Sqm 698.90
Say 699.00
74 Supplying and Fixing of Molded Shank Raised Pavement Markers / Cat's Eye
made of polycarbonate and ABS moulded body and reflective panels with micro
prismatic lens capable of providing total internal reflection of the light entering
the lens face and shall support a load of 16000 kg tested in accordance to ASTM
D 4280 Type H and complying to Specifications of Category A of MORTH
Circular No RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and
length shall not exceed 50 mm, 100 mm and 102 +/- 2 mm and with minimum
reflective area of 13 Sqcm on each side and the slope to the base shall be 35 +/- 5
degree. The strength of detachment of the integrated cylindrical shanks, (of
diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from
the body is to be a minimum value of 500 Kg. Fixing will be by drilling holes on
the road for the shanks to go inside, without nails and using epoxy resin based
adhesive as per manufacturer's recommendation and complete as directed by
the engineer.The contractor shall submit a two year warranty for satisfactory
field performance including stipulated retro-reflectance of the reflecting panel,
to the Engineer.

Rate as per SSR 2022-23 item. No.6.09 Sr.no.212 Pg.no.47 Nos. 1 366 366.00
Deduct labour Cess @ 1% ( SSR 22-23 pg no 2) -3.66
Total 362.34
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 3.62
Rate per Nos 365.96
Nos say 366.00
Section-VII Ancillary Work
75 Providing Fixing and Maintaining M.S. fabricated traffic barricating on either
side of the carriageway/portion of the carriage way closed to trafficetc.
Complete as per drawing and directed by Engineer. Fixing and maintaining
1800x1800 mm panel.
Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19 1766.79
Increases 15% due to above rate 2018-2019 265.02
Total 2031.81
Rmt Say 2032.00
76 Shifting ,Fixing & Maintaining M.S. fabricated traffic barricating on sides of
the carriageway/portion of the carriage way closed to trafficetc. Complete as
per drawing and directed by Engineer.Labour for shifting, Fixing and
maintaining 1.8x1.8m panel.
Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19 776.79
Increases 15% due to above rate 2018-2019 116.52
Total 893.31
Rmt Say 893.00
77
Providing traffic wardens for regulation of traffic during construction as per
the requirement of traffic police and as directed by the engineers
Rate Taken from Bhivandi Work Tender.No: ED/OARDS/Bhiwandi/19 453.21
Increases 15% due to above rate 2018-2019 67.98
Total 521.19
Nos Per day Say 521.00
78
Providing and applying three coats of water proof cement paint of approved
manufacture and of approved colour to new plastered surfaces including
scaffolding if necessary, cleaning and preparing the surface, watering for two
days etc. complete
Rate as per SSR 2022-23 item. No.35.15 Sr.no.-1085 Pg.no.-224
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 104.00
Total 104.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 1.04
Rate per NO 105.04
Nos Say 105.00
Section-VIII - Water Supply and Sanitary Fitting

79 Providing and laying cast iron pipes of B class of 80mm diameter with sockets
and spigot ends/ flanges and cast centrifugally / vertically including specials,
laying pipes and back filling the trench complete including excavation.

Rate as per SSR 2022-23 item. No.41.01 Sr.no.-1307 Pg.no.-332


Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 1317.00
Total 1317.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 13.17
Rate per Rmt 1330.17
RMT Say 1330.00
80

Providing and fixing on walls/ ceiling/ floors, 32 mm dia. heavy grade having
embossed as ISI Mark galvanised iron pipes weight of 3.89 Kilogram/meter
with necessary fittings . remaking good the demolished portion and applying
primer of anti-corrosive oil paint 2 coats Including necessary scaffolding and
removing existing pipe line if necessary and conveying and stacking the same in
PWD chowky or as directed etc. complete.
Rate as per SSR 2022-23 item. No.41.13 Sr.no.-1319 Pg.no.-333
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 696.00
Total 696.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 6.96
Rate per Rmt 702.96
RMT Say 703.00
81
Providing and laying in trenches 20 mm dia. medium grade having embossed as
ISI Mark galvanised iron pipes ?of 1.63 Kilogram/meter necessary fitting
remaking good the demolished portion with filling trenches and with primer of
anti-corrosive oil paint, 2 coats Including removing existing pipe line if
necessary and conveying and stacking the same in PWD chowky or as directed
etc. complete.
Rate as per SSR 2022-23 item. No.41.19 Sr.no.-1325 Pg.no.-334
Deduct labour Cess @ 1% ( SSR 22-23 pg no 3) 487.00
Total 487.00
Add 5% for Municipal Corporation Areas 0.00
Add back Labour labour aminities & cess 1% 4.87
Rate per Rmt 491.87
RMT Say 492.00

PMC
DEPUTY ENGINEER EXECUTIVE ENGINEER
MMRDA MMRDA
Name of work : Construction of Concrete roads 1) SH-76 Angaon Junction to Pilanze Bk ,
Pilanze Kh to Bedarpada road situated in Bhiwandi Taluka, District Thane under OARDS .

Name of Client: Mumbai Metropolitan Region Development Authority


Name of Consultant : Ekansh Concepts Limited, Mumbai.
RECAPITULATION SHEET
Details Amount
Section - I Site Clearence & Dismantling 436,852.35
Section -II Earth Work 12,899,205.83
Section -III Road Pavement 34,278,620.63
Section-IV - Storm Water Drain 7,434,121.95
Section-V- CD WORKS & Culverts 5,537,441.19
Section -VI Road Furniture 872,403.00
Section-VII Ancillary Work 5,016,516.00
Section-VIII Water Supply and Sanitary Fitting 324,675.00
Work Portion 66,799,835.95
Add For GST 18% 12,023,970.47
Work Portion ( with GST 18% ) -A 78,823,806.42
ADD - Provisional Cost
Utility Shiffting.- 100,000.00
Royalty 1% 667,998.36
Material Tesing Charges .3% 200,399.51
ADD - Provisional Cost= B 968,397.87
Total Rs. A +B 79,792,204.28

Consultant DEPUTY ENGINEER EXECUTIVE ENGINEER