Professional Documents
Culture Documents
LNG Shutdown Checksheet
LNG Shutdown Checksheet
Scope:
This inspection program describes both external visual inspection and thickness measurement
process for piping, tubing, valves (other than control valve), and fittings in a turnaround planned
shutdown maintenance for LNG Trains.
Purpose:
The primary purpose of this inspection program is to observe, report and specify needed repairs
or replacement to avoid leaks leading to process safety incident, and hazardous to exposed
personnel and or environmental consequences. It establishes adequate inspection for
maintaining piping and its components in a safe, reliable condition.
References:
API 570 – Inspection, Repair, Alteration of In-service Piping Systems
API RP 571 – Damage Mechanisms Affecting Fixed Equipment in the Refining Industry
API RP 583 – Corrosion Under Insulation and Fireproofing
ASME B16.5 – Pipe Flanges and Flanged Fittings
ASME B16.34 – Valves: Flanged, Threaded and Welding End
ASME PCC-1: Guidelines for Pressure Boundary Bolted Flange Joint Assembly
Inspection Procedures:
External Visual Inspection and thickness gauging: Carry out external visual inspection on all
piping to check for signs of paint damage, external corrosion, bulging, scaling, localized
buckling, metal deterioration, leakage and misalignment as well as external condition of piping
and pipe supports. Tick appropriately on below check sheet.
Check Sheet on inspection at shutdown during turnaround maintenance
Train #: Date:
System #:
Line #: Drawing #:
YES NO
or
DONE
Piping
1 Is piping dislodged from one or more supports so that its weight is not
being properly distributed on the remaining hangers, beam or saddles
14 Visually examine for spring support integrity and proper operation. For spring
supports, check spring can, spring, locking device, hanger accessories (rods
and support clamps), piping under support clamps and supporting structural
steel for any evidence of corrosion or mechanical overload.
15 Spring hanger loads should be checked under both cold and hot conditions,
and the readings obtained should be checked against the original cold and hot
readings
16 Check all support points on lines that sweats for deterioration due to corrosion
17 Check all bolting on flanges especially those below 3 and 9 o’clock for signs of
corrosion and replace accordingly
18 Check insulation integrity on high temperature lines and replace burnt
insulation
19 High temperature lines should be checked of bulging due to temperature and
corrected
20 Check pipe wall thickness and corrosion damage at different spots in Amine
Piping System, using A-Scan with numeric thickness readout UT machine.
Compare original data with report for rejection or acceptance
Flanges
21 The gasket seating faces of flanged joints that have been opened should be
visually inspected for corrosion and defects such as scratches, cuts, and
gouges that might cause leakage
Valves
22 The seating surfaces of Gate valve should be visually inspected for defects that
might cause leakage.
The wedge guides/body, stem and threads on the stem and in the bonnet
should be inspected for corrosion and erosion
23 The connection in Gate Valve between the stem and the wedge should be
inspected to ensure that the wedge will not detach from the stem during
operation
24 Swing-check valves can be inspected by removing the cover or cap. The disc
should be checked for free rotation, and the nut holding either to the arm
should be checked for security and the presence of a locking pin, lock washer,
or tack weld.
25 The arm of opened check valve should be free to swing, and the anchor pin or
shaft should be inspected for wear
26 The seating surfaces on both the disc and the valve body can be checked for
deterioration by feeling them with the fingers
27 Confirm that the Check Valve is extremely important that the cover is installed
in the proper orientation for the wedge to operate
properly