MEP SCHEDULE MEI JUNI JULI

Task Name Duration Start Finish 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31


Pre Construction 5 days Sat 18/05/24 Thu 23/05/24
Construction Stage 31 days Fri 24/05/24 Fri 05/07/24
Demolition 7 days Fri 24/05/24 Mon 03/06/24
Electrical Installation 28 days Mon 27/05/24 Wed 03/07/24
IT Installation 26 days Mon 03/06/24 Mon 08/07/24
HVAC/ Mechanical Work 26 days Mon 27/05/24 Sun 30/06/24
Fire Fighting System 14 days Mon 03/06/24 Thu 20/06/24
Completion Stage 18 days Mon 17/06/24 Wed 10/07/24
Commisioning Test 8 days Sat 13/07/24 Tue 23/07/24
Defect and Handover 6 days Mon 22/07/24 Mon 29/07/24