Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

NOTES

GENERAL

1.)TO PROVIDE LOAD SUPPORT AND DISTRIBUTION


OF LOAD TO ALL DEGSINATED LOAD BEARING
COMPONENT DESIGNS.
2.) REPORT ANY UNFORESEEN CONDITIONS TO THE
GENERAL CONTRACTOR AND CONSULTANT
BEFORE PROCEEDING.
3.) ALL DIMENSIONS ARE IN MILIMETERS
4.) GIVE TOP OF SLAB, A TROWEL FINISH. THE SLAB
MUST BE RECTANGULAR HENCE IN SHORT
DISTANCE EXISTS THE MAIN BARS WHILE IN THE
LONGEST DISTANCE MUST BE THE DISTRIBUTION
BARS.

N REINFORCING STEEL

1.) ALL REINFORCING STEEL TO BE HIGH YIELD


STEEL.
2.)ALL REINFORCING IS TO BE DETAILED IN
ACCORDANCE WITH BS 4466 DETAILING MANUAL
EXCEPT AS OTHERWISE NOTED.
3.) CONCRETE COVER TO STEEL TO BE AS FOLLOWS

A B C D UNLESS OTHERWISE: 50
4.) LAPPING NOT TO BE DONE ON THE BEAMS IN
THE SLAB.
5.) ALL REINFORCING TO HELD IN PLACE, AND TIED

5500 5500 5500 BY THE USE OF PROPER ACCESSORIES, SUCH AS


HI-CHAIRS, SPACERS, ETC. TO BE SUPPLIED BY THE
REINFORCING STEEL FABRICATOR.

200 100 6.)SLAB REINFORCEMENT USED TO RESIST


PRINCIPAL OR TEMPERATURE STRESSES SHALL BE

200 SECURELY TIED.

100
B CAST-IN-PLACE CONCRETE

1.) CONCRETE SHOULD HAVE COMPRESSIVE


STRENGTH AT THE END OF 28 DAYS BY STANDARD

1 56Y16-01-300c/c B1
CYLINDER TEST AS FOLLOWS:

400
5500
2.) ALL CONCRETE IS TO BE CAST CONTINUOUSLY
BETWEEN PREDETERMINED CONSTRUCTION AND
CONTROL JOINTS.
3.) JOINTS TO BE FILLED WITH APPROVED

A A 84Y12-04-200c/c B2
JOINT/CRACK FILLER.
4.) BONDING AGENT - SHALL BE A PROPRIETARY
PRODUCT WHICH IS NO WATER SOLUBLE AND
ENSURE FULL BOND BETWEEN HARDENED AND

2 FRESH CONCRETE.

BACKFILLING GRADE BEAM ON BOTH SIDES

1.) GRADE BEAMS ARE NOT DESIGNED TO CARRY

5500
CANTILEVER LOADS, AND ARE TO BE BACKFILLED
SIMULTANEOUSLY INSIDE AND OUT, USING A

38Y10-02-300 NON-EXPANDING AND NON-ORGANIC TYPE OF


SOIL INLIFTS NOT EXCEEDING 8" (200 mm)
COMPACTED TO MINIMUM 98% STANDARD

112Y10-03-300c/c PROCTOR MAX. DRY DENSITY.

SLAB ON GRADE

3 1.) REMOVE ALL ORGANIC AND DELETERIOUS


MATERIAL.

B 2.) PROOFROLL SUBGRADE TO DELINEATE ANY


SOFT AREAS. ANY SOFT AREAS TO BE EXCAVATED
AND RECOMPACTED.
3.) CAST SLAB ON 0.15 mm POLYETHYLENE VAPOR
BARRIER.
4.) SAW CUT SLAB AS LOCATED ON DRAWINGS TO
DEPTH OF 200mm WITHIN 24 HOURS OF CASTING
CAULK WITH JOINT SEALANT.
5.) DO NOT CAST SLAB ON DESICCATED, FROZEN
OR WET SOIL OR BASE.
6.) DO NOT ALLOW SOIL BENEATH THE SLAB TO
FREEZE AFTER CASTING SLAB.

STRUCTURAL STEEL NOTES

1 2 3 1.) ALL STRUCTURAL STEEL MATERIALS,


FABRICATION, ERECTION, INSPECTION, AND

A B C D TESTING SHALL CONFIRM TO THE STANDARDS.


2.) THERE SHALL BE NO CUTTING OF THE
STRUCTURAL STEEL MEMBERS FOR THE WORK OF
OTHER TRADES WITHOUT PRIOR APPROVAL OF
THE STRUCTURAL CONSULTANT.
3.) PROVIDE ADEQUATE TEMPORARY BRACING OF
THE STRUCTURE TO RESIST LOADS AND ERECTION
STRESSES DURING CONSTRUCTION. DESIGN OF
TEMPORARY BRACING IS THE STRUCTURAL STEEL
CONTRACTOR'S RESPONSIBILITY.
14.) SUBMIT CHECKED SHOP AND ERECTION
DRAWINGS FOR ALL STEEL WORK TO THE
STRUCTURAL CONSULTANT FOR REVIEW PRIOR TO
FABRICATION.
15.) SHOP DRAWINGS FOR CONNECTIONS AND

5500 5500 5500 COMPONENTS DESIGNED BY THE FABRICATOR


SHALL BE SEALED BY A PROFESSIONAL ENGINEER
REGISTERED IN THE PROVINCE HAVING
JURISDICTION WHOM SHALL BE RESPONSIBLE FOR

38Y10-02-300 THE DESIGN AND NECESSARY INSPECTIONS


DURING FABRICATION & INSPECTION TO ENSURE
THAT THE WORK IN BUILT IN ACCORDANCE WITH
THE DESIGN.

112Y10-03-300 c/c 56Y16-01-300c/cB1


NAME: WIZA LWENJE.

84Y16-01-200c/c T1 STUDENTNUMBER:
202102612.
SECTION B-B SECTION A-A
CHECKED BY :
Ms SHABA
SCALE: DATE :
1:4000 23/05/2023

You might also like