Aktifita Predecessor Estimasi Waktu (Bulan)

No
s s a m b
1 A 15 17 20
2 B A 10 12 16
3 C A 14 18 23
4 D A 11 14 19
5 E B 17 19 21
6 F B,C,D 9 16 20
7 G D 10 13 17
8 H E,F,G 14 17 20
9 I H 17 20 25

a. Network Planning

b. Jalur Kegiatan (warna merah)


c. Expected time

Aktifita Predecessor Estimasi Waktu (Bulan)


No mean variansi
s s a m b
1 A 15 17 20 17,17 0,69
2 B A 10 12 16 12,33 1,00
3 C A 14 18 23 18,17 2,25
4 D A 11 14 19 14,33 1,78
5 E B 17 19 21 19,00 0,44
6 F B,C,D 9 16 20 15,50 3,36
7 G D 10 13 17 13,17 1,36
8 H E,F,G 14 17 20 17,00 1,00
9 I H 17 20 25 20,33 1,78

Maka : Expected time 70 bulan


d. Jalur kritis : A-B-E-H-I

e. Variance
Rumus = (a-b/6)^2

Aktifita Predecessor Estimasi Waktu (Bulan)


No mean variansi
s s a m b
1 A 15 17 20 17,17 0,69
2 B A 10 12 16 12,33 1,00
3 C A 14 18 23 18,17 2,25
4 D A 11 14 19 14,33 1,78
5 E B 17 19 21 19,00 0,44
6 F B,C,D 9 16 20 15,50 3,36
7 G D 10 13 17 13,17 1,36
8 H E,F,G 14 17 20 17,00 1,00
9 I H 17 20 25 20,33 1,78

f. Standar deviasi
S = √ varians

Aktifita Predecessor Estimasi Waktu (Bulan)


No mean variansi
s s a m b
1 A 15 17 20 17,17 0,69
2 B A 10 12 16 12,33 1,00
3 C A 14 18 23 18,17 2,25
4 D A 11 14 19 14,33 1,78
5 E B 17 19 21 19,00 0,44
6 F B,C,D 9 16 20 15,50 3,36
7 G D 10 13 17 13,17 1,36
8 H E,F,G 14 17 20 17,00 1,00
9 I H 17 20 25 20,33 1,78
jumlah 13,67
STD 3,70