Annex “C”

(Barangay Address)
Monthly Monitoring Report
On Barangay Road Clearing Operations (BaRCO)
(Latest DILG Memorandum Circular No. 2022-085 dated June 20, 2022, DILG MC No. 2023-017 dated January 25, 2023 and DILG MC No. 2024-053 dated April 16, 2024)
For the Month of April CY 2024

Conducted Road Clearing Remarks (should include


Operations Inventory of Barangay Roads, Streets, Alleys details on the conduct of
[Check appropriate column] & Turned Over Road/s Road Length (in km) Date of Clearing Action Taken BaRCO from the 20th day to
YES NO [Location/Street name/Address] (d) Operation (f) the last day of the previous
(a) (b) (c) (e) month; type of MOV/s,
other information/details)
(g)
/ 1. P Hernando St. .3 km April 15, 2024 Removal of overgrown trees Completed/removed
2. FR Castro St. .35 km April 15, 2024 Removal of sacks of cement/rocks Completed/removed
3. C Peralta St. .5 km April 15, 2024 Removal/pruning of dead mango tree Completed/removed

Total 1.15 km

Prepared by: I hereby CERTIFY and DECLARE that the above information
and activities are true and accurate to the best of my knowledge.
GENESIS S. REMULAR
Barangay Secretary
JOHN ALDRICK S. PERALTA
Punong Barangay

“Kalinisan at Kaayusan sa Bagong Pilipinas”

Page 1 of 1