Gantt Chart
Gantt Chart
Year
Month
ID Task Name Start Date End Date Duration Jan'24 Feb'24 Mar'24 Apr'24 May'24
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3
1 CAP MAKING PLANT-INTRODUCTION
2 VINAYAK INDUSTRIES WAY OF WORKING 01-01-2024 31-01-2024 4 week
3 SIDDHI PACKAGING WAY OF WORKING
4 APPLICATION OF 5S IN BOTH PLANTS 01-02-2024 21-02-2024 3 week
5 RAW MATERIAL HANDELING 22-02-2024 14-03-2024 3 week
6 STUDY OF POWER CONSUMPTION BY ALL THE MOTORS IN FACTORY 15-03-2024 29-03-2024 2 week
7 STUDY OF DEFECTS IN ALUMINIUM CAPS 30-03-2024 13-04-2024 2 week
8 STUDY OF BLOW MOULDING 14-04-2024 29-04-2024 2 week
9 QUALITY CONTROL OF CAPS AND POLY BAGS 30-04-2024 14-05-2024 2 week
10 COST ESTIMATION 15-05-2024 22-05-2024 1 week