BP West Nile Delta Gas Development Project: Inspection and Test Plan For Cable Pulling

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

BP West Nile Delta

Gas Development Project


Security Classification:
WND Project Internal

Inspection and Test Plan for Cable Pulling

REASON
REV DATE BY CHK Appr
FOR ISSUE

C01 23-Jan-2018 Issued for Approval AA AS CN


B01 17-Jan-2018 Issued for implementation MM AS CN
A01 1-Nov-2017 Issued for Review MM AS CN

Sub Contract No Originator Document


Agreement No: Document Number Rev
Number
26008-RRO-HC2-E00Z-
GPO-WND-EPCC-15-031
00001
N/A EG001-QA-PLN-11Z-9008 CA01

WND Project Internal (Bechtel Confidential)


©2014/15/16 BP EXPLORATION (DELTA) LTD (“BP”). THIS DOCUMENT, PREPARED UNDER CONTRACT GPO-WND-EPCC-15-031 (THE “CONTRACT”) BETWEEN BECHTEL OVERSEAS CORPORATION (“BECHTEL”) AND BP, CONTAINS INFORMATION CONFIDENTIAL AND/OR
PROPRIETARY TO BP THAT IS NOT TO BE USED, DISCLOSED, OR REPRODUCED IN ANY FORM BY ANY PERSON OR ENTITY OTHER THAN BP WITHOUT BP’S PRIOR WRITTEN PERMISSION. ALL RIGHTS RESERVED. NOTICE: THESE MATERIALS ARE THE WORK PRODUCT OF
BECHTEL. BECHTEL ACCEPTS NO LIABILITY FOR ANY RELIANCE BY ANY PERSON OTHER THAN ITS CLIENT, BP, ON THE CONTENT OF THIS WORK PRODUCT. BP HAS EXPRESSLY AUTHORIZED BECHTEL TO ISSUE THIS DISCLAIMER.

ELECTRONIC DOCUMENTS ARE CONTROLLED. ANY PRINTED COPY WILL BE UNCONTROLLED AND MAY BECOME OUTDATED
BP West Nile Delta
Gas Development Project
Security Classification:
WND Project Internal

REASON
REV DATE BY CHK Appr
FOR ISSUE

C01 23-Jan-2018 Issued for Approval AA AS CN


B01 17-Jan-2018 Issued for implementation MM AS CN
A01 1-Nov-2017 Issued for Review MM AS CN

Sub Contract No Originator Document


Agreement No: Document Number Rev
Number
26008-RRO-HC2-E00Z-
GPO-WND-EPCC-15-031
00001
N/A EG001-QA-PLN-11Z-9008 CA01

WND Project Internal (Bechtel Confidential)


©2014/15/16 BP EXPLORATION (DELTA) LTD (“BP”). THIS DOCUMENT, PREPARED UNDER CONTRACT GPO-WND-EPCC-15-031 (THE “CONTRACT”) BETWEEN BECHTEL OVERSEAS CORPORATION (“BECHTEL”) AND BP, CONTAINS INFORMATION CONFIDENTIAL AND/OR
PROPRIETARY TO BP THAT IS NOT TO BE USED, DISCLOSED, OR REPRODUCED IN ANY FORM BY ANY PERSON OR ENTITY OTHER THAN BP WITHOUT BP’S PRIOR WRITTEN PERMISSION. ALL RIGHTS RESERVED. NOTICE: THESE MATERIALS ARE THE WORK PRODUCT OF
BECHTEL. BECHTEL ACCEPTS NO LIABILITY FOR ANY RELIANCE BY ANY PERSON OTHER THAN ITS CLIENT, BP, ON THE CONTENT OF THIS WORK PRODUCT. BP HAS EXPRESSLY AUTHORIZED BECHTEL TO ISSUE THIS DISCLAIMER.

ELECTRONIC DOCUMENTS ARE CONTROLLED. ANY PRINTED COPY WILL BE UNCONTROLLED AND MAY BECOME OUTDATED
Inspection and Test Plan for Cable Pulling

Table of Contents
1. Scope...............................................................................................................................................................4
2. Inspection and Test Requirements...................................................................................................................4
3. Inspection and Test Records............................................................................................................................4
4. Inspection and Testing Personnel....................................................................................................................4
5. Measuring and Equipment for Cable Pulling..................................................................................................4
6. Appendices:.....................................................................................................................................................4
6.1 Appendix 1 Inspection and Test Requirements (1 Page)........................................................................4
7. Attachment......................................................................................................................................................6
7.1 Attachment 1 Inspection Test Report (PTR) (1 Page).......................................................................67.1
Attachment 1 Inspection Test Report (ITR) (1 Page).............................................................................6

Document No. EG001-QA-PLN-11Z-9008 Page 2 of 10Page 2 of 7108 Rev: CA01


© BP Exploration (Delta) Ltd. WND Project Internal (Bechtel Confidential)
Inspection and Test Plan for Cable Pulling

Revision History

Revision Amender
Amendment Date Amendment
Number Initials
25-Oct-2017 A01 ASMM Issued for Review
17-Jan-2018 B01 ASMM Issued for implementation
23-Jan-2018 C01 AA Issued for Approval

All previous issues are hereby superseded and are to be destroyed.


NOTES:
Revisions after Rev. A01 are denoted as follows:
By a vertical line in the right-hand margin adjacent to the revised text.
OR
By a triangle symbol for graphics, the revision number being denoted within the symbol positioned
adjacent to the revision.

Related Documents and References

Document
Document Name Description of Content
Number
EG001-EN-SOW- Score of Work Scope of Work
11E-0004
EG-0001-EL- Electrical Specification Electrical Specification
SPE-11E-0016
EG001-EL-MET- Method of Statement Method of Statement for Cable pulling
11Z-9008

Holds

Hold Number Section Description

Document No. EG001-QA-PLN-11Z-9008 Page 3 of 10Page 3 of 7108 Rev: CA01


© BP Exploration (Delta) Ltd. WND Project Internal (Bechtel Confidential)
Inspection and Test Plan for Cable Pulling

1. Scope
Inspection and Test Plans (ITP) are documents that shall be issued by the CGE in accordance with the
Subcontract requirements (Subcontract Exhibits). Contractor will work with the CGE to develop the ITP’s for
their scope of work. This document provides this procedure covers the minimum requirements inspection and
testing related to Cable Pulling. Job Hazard Analysis for Cable Pulling installations covers the ES&H risks and
mitigation for this scope of work. Means and methods are covered by the associated execution plan(s).
Examples ITP for the Site Preparation work and explain how the ITP’s are developed by the CGE.
Definition Description of Definition
CONTRACTOR Bechtel
SUBCONTRACTOR Carlo Gavazzi Egypt (CGE)
RFE Responsible Field Engineer
JHA Job Hazard Analysis
MWR Material Withdrawal Request
ITP Inspection and Test Plan
ITR Inspection and Test Record
MTE Measuring and Test Equipment
ES&H Environmental, safety and Health

2. Inspection and Test Requirements


Inspection and Test Requirements are outlined in Appendix 1.

3. Inspection and Test Records


Example Inspection and Test Record forms are provided in Appendix 2. ITR formatting and information fields
shall match the approved example.

4. Inspection and Testing Personnel


All inspection and tests must be performed by personnel deemed competent through experience, education,
training, and/or certification as required.

5. Measuring and Equipment for Cable Pulling


The following measuring and test equipment is required for this ITP. The equipment must be kept calibrated:
- Megger
- Digital Mutimeter
- Electrician toolbox
- Tension measuring device

Document No. EG001-QA-PLN-11Z-9008 Page 4 of 10Page 4 of 7108 Rev: CA01


© BP Exploration (Delta) Ltd. WND Project Internal (Bechtel Confidential)
Inspection and Test Plan for Cable Pulling

[6.] Appendices:
5.1[6.1] Appendix 1 Inspection and Test Requirements (1 Page)

6.1 Appendix 1 Inspection and Test Requirements (1 Page).

Document No. EG001-QA-PLN-11Z-9008 Page 5 of 10Page 5 of 7108 Rev: CA01


© BP Exploration (Delta) Ltd. WND Project Internal (Bechtel Confidential)
Inspection and Test Plan for Cable Pulling

[6.2] Appendix 1 Inspection and Test Requirements (1 Page)

Document No. EG001-QA-PLN-11Z-9008 Page 6 of 10Page 6 of 7108 Rev: CA01


© BP Exploration (Delta) Ltd. WND Project Internal (Bechtel Confidential)
Inspection and Test Plan for Cable Pulling

Appendix 1 – Cable pulling ITP

Demonstrated
Inspection/Test Inspection/Test Reference Reference Method of Method of Method of System System
Evidence
Requirements Requirements Documentation Documentation verification verification verification Turnover Turnover
Report/checklist

Test or System
Activity Acceptance Subcontracto
ITP Number
Activity Description Inspection Stage/Frequency Cod/Spec/Ect
Criteria r
Bechtel Insp. Client Rep. Reference Reference Client
Performed Number
EG001-EN-
Check Drums,
SOW-11E -0004 Engineering inspection
Cable Pulling 1 Cables Receiving type ,size of Before installation
EG001-EL-SPE-
Pass/Fail N/A I S
Report
cables
11E-0016
EG001-EN-
Check Drums,
SOW-11E -0004 Cables Withdraw
Cable Pulling 2 Cables Withdraw type ,size of Before installation
EG001-EL-SPE-
Pass/Fail I H S
request
cables
11E-0016
EG001-EN-
Check
Check continuity SOW-11E -0004
Cable Pulling 3 continuity/insulation
on the drum
Before installation
EG001-EL-SPE-
Pass/Fail I HS S HI-POT
test on the drum
11E-0016

Cable route
Check drawing
Cable Pulling 4 identification with
route
Before installation Set route card Pass/Fail I H S Drawing
drawing route
Laying the cable EG001-EN-
from the drum and SOW-11E -0004 EG001-EL-MET-11Z-
Cable Pulling 5 running it on the
Visual inspection Continuous
EG001-EL-SPE-
Pass/Fail I H S
9008
cable tray 11E-0016

Test and Before/During EG001-EL-SPE-


Cable Pulling 6 Pulling Tension
inspection Installation 11E-0016
Pass/Fail H H S Set route CARD

After installation
Cable Pulling 7 Report Progress Inspection
complete
I H S Set route data base

I = Inspection, H = Hold Point, S = Surveillance, R =Responsible

Document No. EG001-QA-PLN-11Z-9008 Page 5 of 10Page 67 of 108 Rev: CA01


© BP Exploration (Delta) Ltd. WND Project Internal (Bechtel Confidential)
Inspection and Test Plan for Cable Pulling

6.[7.] Attachment
6.1 Attachment 1 Inspection Test Report (IPTR) (1 Page).

Document No. EG001-QA-PLN-11Z-9008 Page 6 of 10Page 6 7 of 108 Rev: CA01


© BP Exploration (Delta) Ltd. WND Project Internal (Bechtel Confidential)