ThuyHienxGiaBao - PM Lab Report
ThuyHienxGiaBao - PM Lab Report
ThuyHienxGiaBao - PM Lab Report
--------------- ---------------
LAB
1
• Develop CRM usage instructions and CRM operating procedures
• Run a test of the Automation Email Marketing system
• Evaluate results and deploy mass email marketing
TRAN NGUYEN PC CRM
• CRM service consultancy
• Collect the requirements for the CRM platform
• Testing and validating the system
MANH TUONG MEDIA
• Designing website layout
Double click on the task name to see “Task information” -> Advanced -> In “Task type”,
choose “Fixed duration” -> Click OK
2
c) The SEMTEK AND BIZLEADER has the latest end date.
So we will have all other project end date will be before the end of SEMTEK AND
BIZLEADER. Set the predecessors of task “Evaluate results and deploy mass email
marketing” which is the last task of this project to have Finish to Finish relationship: 1FF
(with Giaiphapcucuon.com), 11FF (with DR.Reju), 41FF (with TRAN NGUYEN PC CRM)
and 49FF (MANH TUONG MEDIA WEBSITE):
3
Go to File -> Options -> Advanced -> Tick in the box of “Multiple critical paths” to show
all the critical paths in a multiproject project.
Go to Gantt Chart Format -> Bar Style -> Tick in the box of “Critical Tasks”
4
Step 2: Identify the activities that are on the Gantt Line
Resource
WBS Task Name Duration Start Finish Predecessors
Names
Wed Tue
1 Giaiphapcuacuon.com 15 days
7/5/23 7/25/23
Wed
1.2 Google Analytics 3 days Fri 7/7/23 Technical 3
7/5/23
Marketing
Mon Mon
1.3 Making up content 1 day 2,3 1,Marketing
7/10/23 7/10/23
3
Tue Thu
1.4 Banner Designing 3 days 3,4 Marketing 4
7/11/23 7/13/23
Mon Fri
1.6 Facebook content 5 days 2,3,5 Marketing 2
7/17/23 7/21/23
Tue Thu
1.9 Adding new functions 3 days 8 Technical 3
7/18/23 7/20/23
Mon Tue
2 DR REJU 47 days
7/10/23 9/12/23
5
8/15/23 8/17/23
Technical
Customer Information Fri Mon
2.9 2 days 18,19 1 ,Technical
Buidling 8/25/23 9/4/23
3
Mon Wed
2.11 Testing Website 3 days Project 1
8/21/23 8/23/23
Marketing
1,Marketing
Build and perfect the Tue Mon
3.1 10 days 2,Marketing
brand identity 9/12/23 9/25/23
3,Marketing
5
Marketing
Develop sales content Mon Fri
3.6 9 days 26,27,28 2,Sale 2,Sale
scripts for products 10/16/23 11/3/23
3
Marketing
2,Marketing
Evaluate results and
Thu Tue 3,Project
3.8 deploy mass email 14 days 30
11/30/23 12/19/23 2,Sale 1,Sale
marketing
2,Technical 1
,Technical 3
Technical
Build 15 demo landing Fri Fri
3.9 15 days 1 ,Technical
pages 10/13/23 11/3/23
2,Technical 3
6
1,Marketing
2,Marketing
recruitment plan 10/24/23 10/30/23
3,Sale 1,Sale
2,Sale 3
Marketing
1,Marketing
Develop a Marketing Tue Mon 2,Marketing
3.14 10 days 27,30,35,36
plan 10/31/23 11/13/23 3,Project
1,Sale 1,Sale
2
Marketing
1,Marketing
2,Marketing
Tue Thu
3.15 Build a business plan 12 days 27,30,35,36 3,Project
11/14/23 11/30/23
2,Sale 1,Sale
2,Sale
3,Technical 3
Develop an income
Mon Project
3.16 regime for business 5 days Fri 7/7/23
7/3/23 1,Sale 1
collaborators
Develop work
Mon Tue
3.17 instruction procedures for 15 days Technical 1
8/21/23 9/19/23
each position in charge
Collect the
Fri Tue Technical
4.3 requirements for the CRM 3 days 42
8/25/23 8/29/23 2,Technical 3
platform
Tue Tue
4.5 Set up authority 1 day 45 Technical 3
9/26/23 9/26/23
7
2,Technical 3
Marketing
Designing website Tue Wed 3,Marketing
5.5 7 days 51,53
layout 8/1/23 8/9/23 4,Marketing
5
Technical
Adding sub-function on Thu Fri
5.6 7 days 54 1 ,Technical
the website 8/10/23 8/18/23
3
Tue Wed
5.8 Keywords Analytics 2 days 56,53 Technical 1
8/15/23 8/16/23
Project
Testing and Validating Fri Fri
5.10 1 day 57,56 1,Technical 1
the website 8/18/23 8/18/23
,Technical 2
1.3. Set the working conditions such as not working on Saturday and Sunday,
holidays,
Go to Project -> Properties -> Change Working Times -> For calendar -> Choose
Standard (Project Calendar).
Exception -> Input the name of the days that the workers not working on in “Names” and
the duration of not working from “Start” to “Finish” -> Click OK.
8
9
PROJECT LAB 2
Eliminate the overallocated task. Given the solution for solving the overallocated task
Problem statement: Most of Resources are overallocated in many days as below (except
Project 1). Exerting excessive effort by working overtime and pushing resources beyond their
limits can have harmful effects on both their physical and mental well-being. In simpler
terms, it can cause harm to their bodies and minds.
However, the manager also want to optimize these prices and project duration. Hence,
optimal function is created to determine these criterion:
COST
Min Z = Duration * 10 + 6 (Million VND)
10
To minimize this function, we use the Team Planner to efficiently manage tasks and ensure
that resources are appropriately assigned, also increase the resources to a certain level that
meet our criteria.
First of all, baseline should be set to keep track our proccess. To do this, click Project -> Set
Baseline -> Click OK. Then, we go straight to Team Planner funciton: Task -> Built In ->
Team Planner.
10
The gray-colored tasks represent initial tasks that can be easily rearranged. In contrast, the
blue colored tasks have predecessor tasks and require careful planning. Our goal in this
arrangement is to prioritize tasks that are time-consuming and resource-intensive. By
addressing these tasks first, we ensure that all resources can work concurrently, leading to
optimal durations for the remaining tasks. Hence, following task in SEMTEK AND
BIZLEADER should be arranged first: Build and perfect the brand identity, Run a test of the
Automation Email Marketing system, Evaluate results and deploy mass email
marketingBuild content scripts for Automation Email Marketing for course products,
Develop a Marketing plan, Build a business plan. Moreover, these tasks should work at the
same time by all resources as minimize the task duration and money.
11
From the Team Planner, we can “drag and drop” these box to optimize scheduling, also add
more resources to solve the overload task which hard to change or create too long duration.
Next, re-arranging other tasks, some tasks should be split as we don’t want to overload some
resources, these task spilted are: Develop an income regime for business collaborators,
Develop a monthly recruitment plan, Email Marketing.
- Step 1: Set up optimal function. Put more priority on SEMTEK AND BIZLEADER
tasks, especially some tasks are long durration and must account for many resources.
- Step 2: Re-arrange, add more resources or split tasks (if possible) using Team
Planner.
- Step 3: Check with the baseline and optimal function value. If these are still
overloading, note optimal value and back to step 2.
Result: After re-arrangement, all resources have no problem with working scheduling, also
the we’ve tried many option to optimize our time and money base on optimal function we’ve
mentioned above.
12
Min Z = 62*10 + 852.9 = 1472.9 (million VND).
Meanwhile, the baseline is: Z* = 49*10 + 505.8 = 995.8. This suggests that to prevent
overloading, we can consider increasing our project budget up to 48%. However, it’s
essential for the manager to propose solutions that enhance resource efficiency to improve the
success rate of projects.
13
14
PROJECT LAB 3
After 1.4.2024, we have a reduction in staff as the table below. Please reallocate workers
and calculate the unexpected value (time, cost)
Step 1: Update the project’s progress to be all done to the date 1.4.2024:
Go to Project -> Status -> Update Project -> Set “Mon 4/1/24” for Update work as
complete through.
Go to Resource -> Leveling options -> Change the Leveling range to Level from “Tue
4/2/2024” to a far day -> Press OK
15
Step 3: Check the statistics after making changes
The baseline is the initial project (the scenario without reduction in resources), it would have
taken us 65 days and about 876.720.000 VND to finish the project.
The current is the scenario where the resource reduction happened, although the cost
decreases significantly but the duration increased to 104 days.
16