Daily Maintenance 18-02

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

Preventing Maintenance at 132/220/400K

Time
Sr.No Name of Sub-Station Name of element / Bay Date
From

1 300 Ah Battery bank 2/16/2021 12:00

2 100 MVA T-3 2/17/2021 12:15

3 66 kv Sanjeev bhatia 2/18/2021 10:10

20 MVA T-4 and


4 2/18/2021 11:10
11 KV Incomer No. 4

20 MVA T-6 and


5 2/18/2021 12:40
11 KV Incomer No. 5

6 20 mva 66/ 11 kv T-2 2/17/2021 11.05


Maintenance at 132/220/400KV Substations for the period of to .
Time
PTW No. Detail of work done
To

Battery installation, wiring from battery bank to


2
charger, charger to DCDB done

100 MVA P/T/F T3, fresh oil top up through


13:45 3
main conservator tank (1 drum)

66 kv Breaker protection testing ,c and r panel


42 cleaning, Marshelling boxes cleaning Breaker
11:10
and isolator Lubrication and changed the
jumper between CT & line isolator of Y phase

20 mva p/t/f protection testing,c and r panel


cleaning, Cleaning of CT and T/F bush discs,
12:35 43 Marshelling boxes cleaning , Breaker
Lubrication. All 11 kv breakers cleaning,
lubrication . terminals contact tightning .

20 mva p/t/f protection testing,c and r panel


cleaning, Cleaning of CT and T/F bush discs,
44 Marshelling boxes cleaning , NTC Repaire
14:30
work, Breaker Lubrication. All 11 kv breakers
cleaning, lubrication . terminals contact
tightning .

Cleaning of T/F Bushing hv & lv side, cleaning


of T/F body, CT and T/F clamp, Jumper
16.05 1
Tightning work. 11 kv incomer trolley cleaning
& lubrication.
to .

Name & Designation of officer/official who Remarks


supervised maintenance work (If any)

Battery Bank permit is in


progress, batteries are kept on
boost charging mode