SCHEDULE OF QUANTITY

NAME OF WORK:- Prov. LWSS to group of villages Tokki Chhanni Beli in Tehsil Indora Distt. Kangra (H.P.)
SUB HEAD:- S/E of Submersible pumping machinery with allied accessories from Proposed T/Well to OSHR at point-1 )

S.NO. DESCRIPTION SPECIFICATIOS QUANTITY RATE


(To be specified by tenderer) In Figures
1 Supply of submersible pumping set of KSB/Calama/SU/Johnston/Crompton/BS make conforming to BIS; 2 sets of 3375
8034-1979/5659-1979 ( latest) suitable for lifting clear water fitted with bronze impellers or suitable alloy directly 10 HP Each
coupled to squirrell cage electric induction motor of same make as that of pump conforming to BIS;9283-19a) Pump:-
(latest with uptodate ammendments) and totally water proof for submersible duty, isolated from the
pump by intermediate casing with double mechanical seal in oil chamber, grease packed lubricated b) Motor
bearings & provided with stainless steel thrust bearing plate to with stand non-vertical loads with
minimum wear & tear.It should also be fitted with a device to take up expansion of water with the
heating of motor including water level guard,errection clamps,cable clips & depth gauge etc.
The pump shall be suitable for operation on data given below:-
i) Location of site The site is located at a distance of __2__ KMs from
_Kandrori Railway station by road and _100_ Metres by head load
ii) The altitude of place in which Altitude of place is _450_ m above MSL
the motor is intended to work
iii) Type of current AC three phase supply with frequency 50 cycles per second
iv) Rated Voltage 415V ± 10%
v) Charactrstics of water a) Temperature _20_ °C d) pH _7.5_
b) Turbidity _Upto 10 NTU e) Total solids __ Mg/litre
c) Hardness ___ Mg/Litre(as CaCO3) f) Others :
d) Alkalinity ___ Mg/Litre(as CaCO 3)
vi) Depth of well assembly __23__ mts.
vii) L.W.L. in well _ 77.00_mts.
viii) Max. draw down __ 2.60 _ mts.
ix) Centre line Level of Pump _ 77.00 mts.
x) Discharge Level of highest point _123.00_mts.
xi) Nos of pumps reqd. _2_ pumps (One to work at a time independently)
xii) Capacity _6.63_ lps for each pump
xiii) Total head in Mts. _ 12.75mts
xiv) Length of R/Main __15_mts
xv) Dia of R/Main __80_ mm
xv) Pumping hours per day 8 hours
xvi) Limits of pump operation (-) 25% to (+) 10% of Total head