C&I SHUT DOWN ACTIVITIES (April 2024)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

APRIL 2024 SHUT DOWN ACTIVITIES (MS - C & I)

SCHEDULE TOTAL WORK


ITEM ACTIVITY MANPOWER DURATION REMARKS
DAY 1 DAY 2 DAY 3 DAY 4 DAY 5 DAY 6 DAY 7 DAY 8 DAY 9 DAY 10 DAY 11 DAY 12 DAY 13 DAY 14 DAY 15 DAY 16 DAY 17 DAY 18
Turbine Overhauling Activities
P 0 hr.
1 Removal of all Turbine Instruments A 0 hr.
P 0 hr.
2 Reinstallation of all removed instruments A 0 hr.
P 0 hr.
3 Vibration voltage gap setting A 0 hr.
Projects and Rectifications
P 0 hr.
1 Stroke setting for Start-up Vent A 0 hr.
P 0 hr.
2 Replacement of Ejector/Gland Sealing Steam PRDS TCV A 0 hr.
P 0 hr.
3 Installation and cable laying for WTP signal isolators A 0 hr.
P 0 hr.
4 Creation of export power display in DCS (coordination w/ MS-Electrical) A 0 hr.
P 0 hr.
5 Channel transfer of all signal spikes in DCS A 0 hr.
P 0 hr.
6 Calibration of gland sealing pressure gauges A 0 hr.
P 0 hr.
7 Checking of probe length of all temperature elements A 0 hr.
P 0 hr.
8 Arresting of leaks on hydrastep (Levelstate) A 0 hr.
Routine Activities
P 0 hr.
1 Cleaning and tightening of terminals of DCS I/O Panels A 0 hr.
P 0 hr.
2 Cleaning and tightening of terminals of Turbine Control Panel (TCP) A 0 hr.
P 0 hr.
3 Cleaning and tightening of terminals of Turbine Gauge Panel (TGP) A 0 hr.
P 0 hr.
4 Cleaning and tightening of terminals of all Instrument Junction Boxes A 0 hr.
P 0 hr.
5 Trial of MSSV and TSSV Main and Bypass MOVs A 0 hr.
P 0 hr.
6 Gap Voltage checking on STG Vibration Monitors A 0 hr.
P 0 hr.
7 Cleaning of DCS Operating and Eng'g Consoles and System Units A 0 hr.
P 0 hr.
8 Air Dryer Maintenance A 0 hr.
Stroke Checking and Correction of Control Valves & Dampers
P 0 hr.
1 ID Fan Damper 11-PY-100A A 0 hr.
P 0 hr.
2 SA Fan Damper 11-FY-106A A 0 hr.
P 0 hr.
3 FD Fan Damper 11-FY-107A A 0 hr.
P 0 hr.
4 CBD Tank Level CV 11-LCV-205 A 0 hr.
P 0 hr.
5 Feed Water 100% FCV 11-FCV-1120A A 0 hr.
P 0 hr.
6 Feed Water 30% FCV 11-LCV-1120B A 0 hr.
P 0 hr.
7 Attemperator Water CV 11-TCV-606 A 0 hr.
P 0 hr.
8 Soot Blowing Pressure CV 11-PCV-609 A 0 hr.
P 0 hr.
9 Start Up Vent CV 11-HCV-1132 A 0 hr.
P 0 hr.
10 Deaerator Pressure CV 11-PCV-102 A 0 hr.
P 0 hr.
11 Deaerator Level CV 11-LCV-101 A 0 hr.
P 0 hr.
12 Ejector/Gland Sealing Steam PRDS PCV 40-PCV-161 A 0 hr.
P 0 hr.
13 Deaerator Pegging Steam PRDS PCV 40-PCV-162 A 0 hr.
P 0 hr.
14 Process Bypass Steam PRDS PCV 40-PCV-163 A 0 hr.
P 0 hr.
15 Ejector/Gland Sealing Steam PRDS TCV 40-TCV-161 A 0 hr.
P 0 hr.
16 Deaerator Pegging Steam PRDS TCV 40-TCV-163 A 0 hr.
P 0 hr.
17 Process Steam PRDS TCV 40-TCV-164 A 0 hr.
P 0 hr.
18 Deaerator Overflow Shutoff 11-UV-103 A 0 hr.
P 0 hr.
19 Hot Well Recirculation CV 21-LCV-300 A 0 hr.
P 0 hr.
20 Hot Well Level CV 21-LCV-301 A 0 hr.
P 0 hr.
21 Service Air SOV 40-UV-201 A 0 hr.
MME CALIBRATION
January 2024 Cancelled Calibration Activities
P 0 hr.
1 Calibration: DMF Inlet Flow Tx. 60-FT-251
1
APRIL 2024 SHUT DOWN ACTIVITIES (MS - C & I)
SCHEDULE TOTAL WORK
ITEM ACTIVITY MANPOWER DURATION REMARKS
DAY 1 DAY 2 DAY 3 DAY 4 DAY 5 DAY 6 DAY 7 DAY 8 DAY 9 DAY 10 DAY 11 DAY 12 DAY 13 DAY 14 DAY 15 DAY 16 DAY 17 DAY 18
1 Calibration: DMF Inlet Flow Tx. 60-FT-251 A 0 hr.
P 0 hr.
2 Calibration: FG @ PSH Outlet PT 11-PT-102A A 0 hr.
P 0 hr.
3 Calibration: FG @ ESP Inlet PT 11-PT-105 A 0 hr.
P 0 hr.
4 Calibration: RO Outlet Flow Tx. 60-FT-281 A 0 hr.
P 0 hr.
5 Calibration: FG @ APH Inlet PT 11-PT-104A A 0 hr.
P 0 hr.
6 Calibration: SA Fan to Pn. Spreader PG 11-PG-217 A 0 hr.
P 0 hr.
7 Calibration: FD Fan Disch. Air PT 11-PT-200 A 0 hr.
P 0 hr.
8 Calibration: SA Fan to TG Cooling Air PG 11-PG-216 A 0 hr.
P 0 hr.
9 Calibration: FD Fan Air @ APH O/L PT 11-PT-203 A 0 hr.
P 0 hr.
10 Calibration: SA Fan Air Flow Tx. 11-FT-201 A 0 hr.
P 0 hr.
11 Calibration: DMW Storage Tank #1 LT 40-LT-103A A 0 hr.
P 0 hr.
12 Calibration: DMW Storage Tank #2 LT 40-LT-103B A 0 hr.
P 0 hr.
13 Calibration: Belt Weigher # 1 70-BWS-1 A 0 hr.
P 0 hr.
14 Calibration: Belt Weigher # 2 70-BWS-2 A 0 hr.
P 0 hr.
15 Calibration: ESP #1 Dome Seal PS 30-PSI-131 A 0 hr.
P 0 hr.
16 Calibration: Boiler Instrument Air PT 11-PT-110 A 0 hr.
P 0 hr.
17 Calibration: Soot Blower Steam O/L PT 11-PT-609 A 0 hr.
P 0 hr.
18 Calibration: FW @ ECO Inlet PT 11-PT-501 A 0 hr.
P 0 hr.
19 Calibration: CT Make-up Pump Disch. PT 40-PT-104 A 0 hr.
P 0 hr.
20 Calibration: Inst. Air Receiver Tank PT 40-PT-107 A 0 hr.
P 0 hr.
21 Calibration: CBD Tank Level Tx. 11-LT-205 A 0 hr.
P 0 hr.
22 Calibration: ESP #2 Dome Seal PS 30-PSI-141 A 0 hr.
P 0 hr.
23 Calibration: ESP #2 Vessel PS (High) 30-PSH-141 A 0 hr.
P 0 hr.
24 Calibration: ESP #2 Vessel PS (Low) 30-PSL-141 A 0 hr.
P 0 hr.
25 Calibration: Deaerator Pressure Tx. 11-PT-102 A 0 hr.
P 0 hr.
26 Calibration: FG @ Boiler Bank Outlet PT 11-PT-103 A 0 hr.

Prepared by: Checked & Approved by:

ALI NASEEF D. CALUDTIAG HADZARIE C. MASMODI


C & I Maintenance Supervisor Station Manager

You might also like