Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Monthly Progress Report JANUARY 2024 DHQ-MJY GHAT SECTION

1.0 Earthwork in cutting in cum – 5,000cum


1.0 Tree counting in nos. - 2170 nos.
2.0 Safety fencing 820 meter - 0.820 K.m
3.0 Establishment of GPS POINTS ALONG STRETCH
4.0 Fixing of TBM along stretch.
5.0 Initial survey ,chainage marking
6.0 Camp erection, Crusher erection, Batching plant set up

Monthly Progress Report FEBRUARY 2024 DHQ-MJY GHAT SECTION

1.0 Earthwork in cutting in cum – 47000 cum


2.0 Tree cutting in nos. - 580nos.
3.0 Safety fencing 920 meter - 0.920 K.m

Monthly Progress Report MARCH 2024 DHQ-MJY GHAT SECTION

1.0 Earthwork in cutting in cum – 1,95,500 cum


2.0 Tree cutting in nos. - 580nos.
3.0 Safety fencing 750 meter - 0.750K.m
4.0 BR. NO- no 841 /1 ,841/2 & 840/1 excavation = 120 cum
5.0 Fixing of hume pipe at Br. No 841/1 .
6.0 Boulder filling at Br. No 841/1 15 cum.
7.0 Pcc = 10 cum at Br. No 841/1 .

You might also like