Project Name : Malibu Village

Project ID :-
City : Tangerang
Homepass Plan : - HP

May-23 Jun-23 Jul-23


No Item Duration Start Finish
Week-1 Week-2 Week-3 Week-4 Week-1 Week-2 Week-3 Week-4 Week-5 Week-1 Week-2 Week-3 Week-4
1 SURVEY ON SITE SEBELUM KOM 1 Day 5-May-23 5-May-23
2 KICK OFF MEETING (KOM) 1 Day 6-May-23 6-May-23
3 PERSIAPAN MATERIAL 6 Days 8-May-23 13-May-23
4 IZIN KAWASAN 6 Days 8-May-23 13-May-23
5 SURVEY ON SITE & MARKING 1 Day 8-May-23 8-May-23
6 GALIAN,GELAR SUBDUCT & PERAPIHAN
JL.ACERO
JL.BAILARD 4 Days 10-May-23 13-May-23
JL.CAVALERI
JL.DRESER
JL.FILARE
5 Days 15-May-23 20-May-23
JL.GAYTON
JL.HORIZON
JL.INGLESIDE
JL.LUNITA
6 Days 22-May-23 27-May-23
JL.AVENIDA
JL.BONSAL
JL.CLIFSIDE
JL.DELAPLANE
5 Days 29-May-23 3-Jun-23
JL.FERNHIL
JL.GORGE
JL.HARVESTER
JL.INLAND
6 Days 5-Jun-23 10-Jun-23
JL.LECHUZA
JL.MESA
JL.PENA
6 Days 12-Jun-23 17-Jun-23
JL.SERA

JL.ANACAPA
JL.BADEN
6 Days 19-Jun-23 24-Jun-23
JL.CALPIN
JL.DECKER
JL.FAIRSIDE
JL.GALAHAD
5 Days 26-Jun-23 1-Jul-23
JL.HAREL
JL.LATIGO
JL.MARVISTA
JL.NN
6 Days 3-Jul-23 8-Jul-23
JL.RAMBLA
JL.NN
7 PEMBUATAN HANDHOLE 60x60x60 3 Days 10-Jul-23 12-Jul-23
8 PULLING CABLE 3 Days 13-Jul-23 15-Jul-23
PEMBUATAN PONDASI DAN
9 2 Days 17-Jul-23 18-Jul-23 `
PEMASANGAN PEDESTAL
10 SPLICING,INTEGRASI and OPM 3 Days 20-Jul-23 22-Jul-23
11 PERAPIHAN PEMADATAN 2 Days 24-Jul-23 25-Jul-23
12 FINISHING BEKAS PEKERJAAN 2 Days 26-Jul-23 27-Jul-23
13 TEST COMMISIONING 1 Days 28-Jul-23 28-Jul-23
14 ATP 2 Days 28-Jul-23 29-Jul-23