Project ID :-
City : Tangerang
Homepass Plan : - HP
JL.ANACAPA
JL.BADEN
6 Days 19-Jun-23 24-Jun-23
JL.CALPIN
JL.DECKER
JL.FAIRSIDE
JL.GALAHAD
5 Days 26-Jun-23 1-Jul-23
JL.HAREL
JL.LATIGO
JL.MARVISTA
JL.NN
6 Days 3-Jul-23 8-Jul-23
JL.RAMBLA
JL.NN
7 PEMBUATAN HANDHOLE 60x60x60 3 Days 10-Jul-23 12-Jul-23
8 PULLING CABLE 3 Days 13-Jul-23 15-Jul-23
PEMBUATAN PONDASI DAN
9 2 Days 17-Jul-23 18-Jul-23 `
PEMASANGAN PEDESTAL
10 SPLICING,INTEGRASI and OPM 3 Days 20-Jul-23 22-Jul-23
11 PERAPIHAN PEMADATAN 2 Days 24-Jul-23 25-Jul-23
12 FINISHING BEKAS PEKERJAAN 2 Days 26-Jul-23 27-Jul-23
13 TEST COMMISIONING 1 Days 28-Jul-23 28-Jul-23
14 ATP 2 Days 28-Jul-23 29-Jul-23