Professional Documents
Culture Documents
Circuit Breaker Selective Coordination Common Questions and Misconceptions
Circuit Breaker Selective Coordination Common Questions and Misconceptions
Slide 2
—
Key National Electrical Code Requirements
—
Definitions per the NEC
Art. 100 NEC: “Coordination, Selective. Localization of an overcurrent condition to restrict
outages to the circuit or equipment affected, accomplished by the selection and installation
of overcurrent protective devices and their ratings or settings for the full range of available
overcurrents, from overload to the maximum available fault current, and for the full range of
overcurrent protective device opening times associated with those overcurrents.”
NOT AFFECTED
Fault
Art 517.31(G): Overcurrent protective devices serving the essential electrical system shall be
coordinated for the period of time that a fault’s duration extends beyond 0.1 seconds
Slide 4
—
Example of Systems Requiring Selective Coordination
• all emergency (700), legally required standby (701), or critical operations power systems
(708) are coordinated for the entire range of available fault current per articles 700.32,
701.32, and 708.54
• essential systems under 517.31 (healthcare) can be coordinated to 0.1 seconds if the 2014
NEC or later is in effect
• all elevators (and associated Art 620 equipment) are coordinated to the entire range of
available fault current
Slide 5
—
Common Questions and Misconceptions:
Selective Coordination of Circuit Breakers
—
Slide 7
— 1000.00
Coordination by Region
11 Fault A Fault B
Separation between the time-current
100.00
2 2
Overlap between circuit breaker TCC’s in
this part of the curve requires special 1.00
consideration if selective coordination is
to be achieved throughout the range of 33
available fault current
0.10 44
Selective coordination (“0.01 second”)
Seconds
requires all parts of the curve to coordinate
(overload + short circuit region = non- 0.01
instantaneous + instantaneous coordination) 100 Amperes
1,000 10,000 100,000
Slide 8
—
Circuit Breaker Coordination Tables
Slide 9
—
Example Table from ABB DET-760G Guide to Instantaneous Selectivity
Sensor Options
Upstream Breakers
Downstream Breakers
Coordination in this particular table does not rely on any circuit breaker or trip unit option. The condition for using these values is the
upstream breaker must be set to its maximum instantaneous pick-up.
Slide 10
—
Common Questions and Misconceptions:
Specification of Selective Coordination
—
Slide 12
—
Selectivity Triage
Slide 13
—
The Bottom Line - Selectivity WWW = What, Where, and Why
For any design, the plans and specs must make clear:
Slide 14
—
Slide 15
—
Power System Study Specification and Coordination
Slide 16
—
Standard Power Systems Analysis (Study) Specification Statements
Standard language in the Protective Device Coordination Study section may
not be complete for some situations or may cause confusion if not edited
“Provide adequate time margins between device characteristics such that selective
operation is provided, while providing proper protection”
or
“Graphically illustrate that adequate time separation exists between devices in
series,…”
Slide 17
—
Example Specification
Slide 18
—
Example Drawing Notes
“Selectively coordinate the emergency branch per 2020 NEC Article 700.32”
“Provide selectively coordinated overcurrent protective devices for the branches of power
indicated (all OCPD from the source breakers to the last OCPD fed from ATS-LS and ATS-LRS),
so that only the closest upstream OCPD of an overcurrent opens (coordinate to 0.01 seconds)”
[this note number was applied on the drawing to the generator CB, and each panel associated
with the LS and LRS systems, as well as the normal switchboard MCB and feeders to the ATS’s]
“Manufacturer shall select appropriate breaker types to provide selective coordination for all
supply side/up-stream devices connected to systems containing normal and generator
powered circuits. Coordination shall be demonstrated by manufacturers published
coordination tables and data.
Requirements and Assumptions
1. Coordination shall comply with NEC articles 700.32 and 701.32
2. Unlimited short circuit current on primary”
Slide 19
—
Common Questions and Misconceptions:
Coordination Across a Transformer
—
Slide 21
—
Selective Coordination Across a Transformer
A
For a system requiring selective coordination, protective devices 480V
across a transformer must be coordinated the same as devices
at the same voltage. 208V
B
In the diagram to the right:
Slide 22
—
The Role of the Transformer in Coordination
Example: If a fault on the 208V side of a 45 kVA transformer is 2900A (at 208V ), the resulting
fault current on the 480V side is 2900/2.31 = 1255A (at 480V)
The 480V devices see a substantially reduced amperage for faults on the 208V side relative to
faults on the 480V.
Slide 23
—
Typical Coordination Layout Across A
a Transformer
B
C
CB C: 208V Electronic Trip Main
Slide 24
—
Common Questions and Misconceptions:
Coordination with Ground Fault Protection
—
Slide 26
—
Typical Low Voltage Overcurrent Protection Combinations
3. Upstream Phase and Ground Fault – Downstream Phase and Ground Fault
Situations 2 and 3 are evaluated for selectivity similarly to what we have already discussed for situation 1.
The key difference is where GF protection is involved, the combined phase + GF curve of the device must be
used to evaluate coordination.
Phase coordination in the instantaneous region is still evaluated using coordination tables.
Slide 27
—
Main Breaker over Feeder
No Ground Fault Protection on Either Breaker
Slide 28
—
Ground Fault Protection Added to Main
No Ground Fault Protection on Feeder
GF Curve
PU = 0.4 = 400A
These two breakers are NOT selectively coordinated.
Slide 29
—
Ground Fault Protection on Main Adjusted
No Ground Fault Protection on Feeder
GF Curve
PU = 0.6 = 1200A
These two breakers are selectively coordinated. I2T slope added
Slide 30
—
Ground Fault Protection on Main with Additional Adjustments
No Ground Fault Protection on Feeder
GF Curve
PU = 0.6 = 1200A
These two breakers are selectively coordinated. Selective GF Delay
Slide 31
—
Common Questions and Misconceptions:
Selective Coordination Ratios for Circuit Breakers
—
Instead of using vendor coordination tables, why can’t I just use a rule
of thumb for ratios of the circuit breakers that will selectively
coordinate?
Slide 33
—
Issues with using Circuit Breaker Ratios
- Thermal mag to Thermal mag vs Etrip to Thermal mag vs Etrip to Etrip will all be different
- In general, too many ratios to know – not easier and less reliable than using TCC analysis and
coordination tables
What ratios are we talking about? (in breakers, the same amperage may be set on multiple frames)
For circuit breaker selective coordination (entire range of available fault current), both frame
size and amperage separation are important.
Slide 34
—
Basic Template for MCCB Frame Selection
Instantaneous Region Coordination At the Same Voltage (not across a transformer)
Example based on ABB DET-760 (applicable to ABB Molded Case Circuit Breakers)
800/1000/1200 AF 800/1000/1200 AF
400/600 AF 400/600 AF
250 AF
125 AF 250 AF
100 AF
Thermal-Magnetic Branch up to 60A (1) Thermal-Magnetic Branch Branch > 125A to 250A
up to 125A (1)
Based on the above, a simple rule is: at least one frame size difference is needed between upstream and downstream CB’s.
Slide 35
—
Amperages and Selective Coordination
Slide 36
—
Summary
Slide 37
—
Q&A
Thank you for joining us!
Slide 38