Professional Documents
Culture Documents
Pits Resistance Report
Pits Resistance Report
Pits Resistance Report
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 1 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 2 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Motorized Butterfly valve and flow meters chambers earthing & datasheets and Specifications) will submit separate
equipotential bonding layout, shop drawing and details. transmittals.
The contractor to add the earthing calculation for sizing number for Added in section 4.
JA
reference in section 4.
7. GRP/PMC Comments Rev00 Contractor’s Reply
JA Contractor to add complete material list either in the section10.2 or 12. Added and Confirmed In section 12.
8. GRP/PMC Comments Rev00 Contractor’s Reply
JA Contractor to add the detail of QA/QC Manager in section 6.16 Updated.
9. GRP/PMC Comments Rev00 Contractor’s Reply
The contractor to add the Construction Manager signature on page# 28 in the
JA Updated.
Risk Assessment
10. GRP/PMC Comments Rev00 Contractor’s Reply
The soil resistivity report Added in section 8.2.19 and It will
JA Contractor to attach the soil resistivity report in the method statement for testing.
be sent separately.
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 3 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 4 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
6- Contractor to confirm is there separate earthing pit for shelter and chamber?
If yes, describe the installation and testing method.
14. GRP/PMC Comments Rev00 Contractor’s Reply
Please correct below document numbers.
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 5 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 6 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Contractor shall ensure, prior to conduct testing of Grounding & Bonding shall
Noted and Confirmed.
OP furnish all approved drawings shall be made available upon request prior to
commence the activity. Please confirm.
17. GRP/PMC Comments Rev00 Contractor’s Reply
Contractor shall provide separate Site Acceptance Test Procedure for Noted and Confirmed.
OP
Grounding and Bonding Testing subject for review and acceptance.
18. GRP/PMC Comments Rev00 Contractor’s Reply
Contractor shall conform that the Grounding and Bonding system installation is
Noted and Confirmed.
OP meeting the requirements of ANSI/NFPA 70 (NEC), NETA, IEEE 81 clause 8.3
and ANSI C2 or as specified in the Construction Project Specification.
19. GRP/PMC Comments Rev00 Contractor’s Reply
Contractor shall perform Continuity check of each grounding conductor with the Noted and Confirmed.
OP
structure / equipment to ensure connection.
20. GRP/PMC Comments Rev00 Contractor’s Reply
Upon completion of Grounding Bonding Testing the Contractor shall submit 5
Noted and Confirmed.
OP certified copies of Test reports not later than 10 days subject for review and
approval by the Royal Commission.
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 7 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 8 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
Prior to commence Earth/Grounding Test, the electrode shall be free from Noted and Confirmed.
OP
nonconductive coatings such as paint or enamel. Per [NEC 250.53(A)(1)]
26. GRP/PMC Comments Rev00 Contractor’s Reply
Contractor to conduct Earth Testing to provide Test reports subject for review Noted and Confirmed.
OP
and approval from the Client.
27. GRP/PMC Comments Rev00 Contractor’s Reply
Noted and Confirmed.
OP Wire shall be tested in accordance with specified UL Standards 44 type XHHW.
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 9 of 10
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-MST- C = Approved with comments & F = No action
00 C 06/05/2024
00005 resubmit
The Contractor is to confirm that they will submit separate transmittals as follows:
• ITP, Quality Control Plan Noted and confirmed
• Shop drawings (All vendor drawings and products datasheets and
Specifications)
• PQ for all Lists of Manufacturers (Manufacturer’s catalogues include
installation instructions for grounding conductors, grounding rods and
accessories.
• Material Submittals before commencement of the installation works
• Factory Test Reports.
• Samples of grounding conductors, grounding rods and accessories for Noted and confirmed
review and approval by PMC.
• Calculations for sizing of grounding conductors, material and grounding rods.
• Soil Resistivity measurements.
• Design of Grounding System.
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 10 of 10