Professional Documents
Culture Documents
Anyango Agnes
Anyango Agnes
MEASUREMENT
200 20700mm
200mm
8200mm
A
B
200mm
A B
200mm 200
SECTION A-A
DPC 1
1.REINFORCEMENT
a.column
mainbars
H-2.70
Add joints& overlaps
Say 300mm
0.30
3.0
Reinforcement column
Main bars200mm thick
b.stirrups/rings
L-1.00
2
Owning Cost
Annual Depreciation=10000000-4000000/10=600000
600000 . 00
Running Cost
3
Fuel Consumption 5x125 625
Operator 110
Oil 50
Total running Cost 785 785 .00
PRELIMINARY ITEM
Build up unit rate for foreman
DATA
Salary 8400 per week
Medical allowances Ksh 400
House allowance Ksh 400 per week
Commuting allowance Ksh 350 per week
NSSF Ksh 50 per week
Duration 18 weeks
4
Total cost per week
8400+400+400+350+50=9600 9600 00
Total Cost=216000
SOLUTION
Total allowances + Basic salaries
8000+2000+1200+1000+1000+1000=14200
Ksh 14200 per month 14200 00
5
Total cost for the 6 months
6x14200=85200 85200 00
Operator skilled
Assume 1x110x8=Ksh 880
Assume 3 unskilled 60x3x8=Ksh 1440
6
PLUNKING AND STRUTING
Build up unit ratio for plunking and struting
DATA
Cost of sawn softwood 100x100mm@150 per metre
Cost of sawn softwood 200x50@ 250 per metre
Cost of sawn softwood 200x40 @ 200 per metre
Skilled labour Ksh 900 per day
Unskilled labour Ksh 450 per day
Length 26.6m
Duration 5 days
26.60x1000=26600mm
26600/100=266
Cost=266x250=66500
Ksh. 66500 66500 00
(200x40)
Struts (100x100)
No of struts +1
=13+1x2=26
Cost 26x150=Ksh 3900
7
Ordinary Nails
Assume 10 kg @ 150 per kg
10x150= Ksh 1500
Total cost=65500+53200+3900+1500
=124100
Allow 5% wastage
105/100x124100=130305 130305 00
LABOUR
Assume 3 skilled=3x9x5= Ksh 13500
Assume 6 unskilled=450x6x5= Ksh 13500
27000
Total cost for plunking and struting
130305+27000=157305
Allow 25% profit
125/100x157305=196631.25 196631 25
196631.25/26.6metres
Struting for m run
=7392.15 7392 15
FORMWORK
Build up unit for formwork
DATA
Cost of 200x25mm sawn Ksh 150 per m
Cost of ordinary nails Ksh 140 per kg
Cost of 100m of 20m Ksh 120 per post
Cost of wedges Ksh 10 per wedge
8
Mould oil Ksh 30 per litre
Skilled labour Ksh 900 per day
Unskilled labour Ksh 450 per day
Length 26.6m
SOLUTION
Materials 200x25mm
2x26.6=53.2
Cost 53.2x150=Ksh 7980 7980 00
Strut (50x50)
=45 struts
Ordinary nails
Labour assume
5 skilled 5x900=Ksh 4500
10 unskilled 10x450=4500
9
Cost of cement 900 per 50 kg
Cost of ballast 1700 per tonne
Cost of sand 1500 per tonne
Density of cement 1440 kg/m3
Density of sand 1600 kg/m3
Density of ballast 1700 kg/m3
200l/mixer
MATERIAL
CEMENT
=3702.86 3702 82
SAND
=514.29 514 29
BALAST
10
=1651.42 1651 42
TOTAL COST
3702.86+514.29+1651.42=5868.57
PLANT
Owning cost
Annual depreciation=2000000-
800000/5=
=240000 240000 00
Repair and maintainance-70000 70000 00
Interest on investment
15/100x2000000x60/100=180000 180000 00
Total Owning
Cost=240000+70000+180000
=490000 490000 00
Running cost
540 per hour 540
11
=5 Buckets
200/1000x5 = 1m3/hr
Transportation
Assume 10m distance
To and fro=10x2=20m
Wheel barrow-45L
Time taken to transport -8 mins
No of wheelbarrows=5 wheelbarrows
1-0.05m3
5-?
=0.25m3
8 mins-0.25m3
?-1m3
=32 mins
Cost=5x60x32/60=160m3
12
LAYING COST
Assume 4 skilled 4x110= 440/=
Assume 4 unskilled 4x60= 240
680 680 00
TOTAL COST=540+288+680=1508
DATA
Labour Constant
Cutting Ksh. 15 per hour
Fixing Ksh 50 per hour
Bending Ksh 40 per hour
13
TOTAL COST
120000+10000+50000= Ksh 135000 135000 00
Allow 5% wastage and bends
105/100x135000 =141750 141750 00
LABOUR
90(190+50)=21600
DATA
Cost of BRC SIZE 50x2=100m2-
18400 per role
Skilled labour 110 per hour
Unskilled labour 60 per hour
SOLUTION
2X50 =100m2 18400
356.56 -?
=64871.04 64871 64
14