Net-metering process: This is only based on personal Experience.

We will constantly be updating the


instructions.

☑️INITIAL INFORMATION NEEDED FOR FILLING UP THE APPLICATION (10kWp sample)

1) Serial no. of the inverter: 110230011490303A

2) Watts capacity, and brand of solar panel: AE Solar 550W

3) No.of solar panel conected: 19pcs

4) Meralco bill (client):

5) Valid id (client):

☑️MAKE OR HAVE A RISER DIAGRAM SIGN AND SEAL BY PEE

☑️GO TO MERALCO WEBSITE, DOWNLOAD AND FILL OUT THE APPLICATION

☑️READY AND COMPLETE THE FOLLOWING TO GET CEI FROM CITY HALL

1. Title (complete page)

2. Occupancy Permit

3. Amilyar
4. Tax declaration (land and bldg.)

5. Brgy. Clearance for electrical permit purposes

☑️SUMBIT ALL THE DOCUMENTS NEEDED

☑️SUBMIT THE APPLICATION TO MERALCO OFFICE ON YOUR AREA, ASK FOR ESPECIAL
INSTRUCTIONS FOR IF THERE ARE ANY.

☑️WAIT FOR YOUR APPLICATION TO GET APPROVED, AND WAIT YOUR METER BASE TOGETHER
WITH THE YELLOW CARD.

☑️PROPERLY INSTALL THE REC METER BASE, AND INFORM THE MERALCO AFTER.

☑️IF APPROVED MERALCO WILL INSTALL THE BI-DIRECTIONAL METER, WAIT FOR THE SCHEDULE
OF THE INSPECTION AND COMMISIONING.