Professional Documents
Culture Documents
Cowsill & Watts-2012-Treatment of A Deep Uncompacted Fill
Cowsill & Watts-2012-Treatment of A Deep Uncompacted Fill
rcha
n
m
24.4
rge
Magnet
settlement gauge
m
0 (MSG) MSG7 11.0
m
0m
100
Injection well
m
200 MSG8
10 m m
-5 m
300
400 8.2m
500
600 Percolation well
5mm
700
Settlement pin
1 5 mm
800
20mm
900
Standpipe
peizometer m
25m
Cres
trial
t of s d (1)
mou
Figure 4: Magnitude and distribution of trial mound settlement MSG2
urch
n
arge
measured were substantially levels and ground levels were
understating volumetric strains. monitored during the injection and
Some validation was necessary to the MSGs were monitored before, Figure 5: Layout of percolation and injection wells under the
determine at what point beneath the during and after injection. western flank of the trial mound showing movements induced during
mound sufficient compaction had Movement was observed in both water percolation
taken place to prevent collapse MSGs 7 and 8 but the movement
compression. This was achieved by only commenced when the injection
wetting the fill after the mound was took place around MSG8 further
Toe
trial
removed. Initially a rectangular box down the shoulder. This movement
of su MSG6
mou
of percolation wells was drilled appeared to drag the ground down rcha
between the line of the toe and the at positions under higher points of
nd (1
rge
crest on the west side of the trial the former trial mound. MSG8 was
)
105m
0m m
mound. Standpipe piezometers suspected that this must have been
were installed to monitor the substantial. mm
80
10mm
m
anticipated saturation front. Surface It was possible, however, to
2 0mm
m
70 m
mm
m
0m
m 40m
5
settlement pins were placed estimate the position of a line of 0m
30
6
throughout the area and water was zero movement above which heave
Cres
introduced into the wells. was observed and below which
trial
t of s
Due to the high permeability of significant collapse movement was
mou
the ground water ran away to the detected. Figure 6 illustrates total
urch
MSG2
nd (1
base of the wells and the effects in surface movements induced after
arge
the piezometers were minimal. water injection at the location of the
Whilst it seemed likely that shoulder of the former trial mound. )
considerable wetting was taking As in the trial, no collapse was Figure 6: Total vertical ground movement following percolation and
place very little saturation could be observed due to water percolation water injection
proved. Responses were improved and injection below approximately
to some degree by introducing pfa 25m below the ground surface. Mound as-built
down the wells with a view to The final conclusion from all the crest line
blocking any major seepage paths attempts at saturation was that the Mound as-built Trial
12m contour mound 1
and localising the saturation. Figure mound had effectively eliminated
5 shows the layout of wells, inundation collapse potential in Proposed mound Mound
settlement points, additional MSG’s areas above its 12m contour. It was toe line 7
Mound Mound
and movements induced through not possible to assess the possible Historic mound 4 6
12m contour
percolation. added benefits of two mounds
Up to around 25mm surface overlapping or located close together 12m contour
taken for historic
settlements were noted toward the as only one trial mound could be mound position
Mound
toe of the former mound and a constructed. 5B
Mound
Mound 5A
small amount of heave was
8
measured under the mound in this Surcharge design
period but evidence of saturation Based on the results of the trial Mound Mound Mound
10A 11B 3
proved elusive. mound and wetting experiments a
With the aim of proving remediation scheme was designed Mound
9
saturation it was then decided to use moving a 15m high mound around
Mound
water injection using a series of the site, with the footprint Mound 2
Mound
eight wells and associated MSG7 overlapping the adjacent mound 10B 11A
and MSG8 plus standpipe position such that the 12m contour
piezometers to record the effects. of each mound coincided. A similar Validation mound
Between 5m3 and 6m3 of water was overlap was designed against the (50x50x1.8m high plateau)
injected at 6m depth intervals during former landscape mound. The
drilling of the injection wells. Water landscape mound had been Figure 7: Plan of surcharge mounds