METHOD STATEMENT TPHL/QMS Document No.

10

FOR FIXING OF WALL & Rev: 0 Working status :


COLUMN FORMWORK
WORK Page 1 / 6 Date : 02.11.2023

TRIDENT HILLS PRIVATE LIMITED

PROJECT NAME:- WINDSONG RESIDENCES, PANCHKULA

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 1
METHOD STATEMENT TPHL/QMS Document No. 10

FOR FIXING OF WALL & Rev: 0 Working status :


COLUMN FORMWORK
WORK Page 2 / 6 Date : 02.11.2023

CONTENTS

1. Objective and scope

2. Tools and Equipments

3. Materials required

4. Engineering works

5. Responsibility

6. Health & Safety

6.1 Hazards

6.2 General Control Measures

6.3 Recovery Measures

7. Sequence of Work

7.1 Preparation of Formwork

7.2 Fixing of Formwork

7.3 Miscellaneous

8. Documentation

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 2
METHOD STATEMENT TPHL/QMS Document No. 10

FOR FIXING OF WALL & Rev: 0 Working status :


COLUMN FORMWORK
WORK Page 3 / 6 Date : 02.11.2023

1. Objective and scope:


This method statement describes work procedure for Wall & Column formwork in a building as specified
in the tender document/drawing. It shall be done by experienced workers as per the relevant
standards/drawings and to the full satisfaction of the Engineer-in-charge.

2. Tools and Equipments:


All tools and tackles required for the complete execution and completion of the work shall be arranged
well in advance. The list of tools to be required for the work as followings: -
2.1 Personnel Protective Equipments
2.2 Plumb bob
2.3 Measuring tape
2.4 Hand saw
2.5 Wood cutting machine
2.6 Framing square
2.7 Wood chisel
2.8 Screw driver set
2.9 Wood boring machine with bit
2.10 Spirit Level
2.11 Adjustable wrench
2.12 Thread or Line Dori
2.13 Hammer
2.14 Waler

3. Materials required:
3.1 Nails
3.2 Marker pen
3.3 Timber Log
3.4 Film faced Plywood sheets
3.5 Scaffolding standard and Ledger
3.6 Scaffolding Joint Pin
3.7 Adjustable base jack
3.8 Wooden Runner
3.9 Scaffolding Coupler
3.10 Scaffolding Clamp
3.11 Scaffolding Prop jack
3.12 Scaffolding Pipe
3.13 U shape jack
3.14 Wing nut
3.15 Tie rods
3.16 Steel decking

4. Engineering works:
As receipt of drawings the Engineer-in-charge shall review the received drawings and discuss with their
senior for any technical doubts and clarifications.

5. Responsibility:

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 3
METHOD STATEMENT TPHL/QMS Document No. 10

FOR FIXING OF WALL & Rev: 0 Working status :


COLUMN FORMWORK
WORK Page 4 / 6 Date : 02.11.2023

5.1 The Engineer-in-charge will be responsible for implementing everything in this method
statement.
5.2 Safety officer will ensure that all safety procedures and measures are implemented in relation to
the type of work being done according to the project’s HSE plan.
5.3 QA/QC representative will be responsible for the implementation of QA/QC works as spelled out
in the Quality Management Plan.

6. Health & Safety


6.1 Hazards
6.1.1 Hot Sunrays
6.1.2 Hot Weather
6.1.3 Fall of heavy objects
6.1.4 Fall of persons from height
6.1.5 Dust
6.1.6 Noise during the works
6.1.7 Defective tools - chisel, hammer, nail extractor etc.
6.1.8 Defective hand tools, improper use of tools
6.1.9 Heat stress
6.1.10 Germicide and Insecticide
6.1.11 Food contamination
6.1.12 Water contamination
6.1.13 Skin contact/clothing contact
6.1.14 Eye contact

6.2 General Control Measures:


6.2.1 Tool Box Meeting
6.2.2 Use of proper PPE
6.2.3 Follow Procedures
6.2.4 Keep adequate warning signs and barricading in appropriate location.
6.2.5 Use skilled personnel
6.2.6 Deploy right person for the right job with valid licenses wherever required.
6.2.7 Impart proper Job Specific Training
6.2.8 Use proper Tools & Tackles
6.2.9 First Aider
6.2.10 Drinking Water
6.2.11 Deploy well maintained Lifting and Shifting Equipment
6.2.12 Underneath area shall be barricaded
6.2.13 Use of full body harness & 100 % tie off shall be ensured
6.2.14 Proper scaffolding shall be made & green tag shall be provided
6.2.15 No over load shall be allowed on working platform
6.2.16 Proper House Keeping
6.2.17 Start the work only after ensuring that it is safe in all respects
6.2.18 Stop work when it is not safe
6.2.19 Identify Assembly Point
6.2.20 Emergency contact will be annexed in project safety plan

6.3 Recovery Measures:

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 4
METHOD STATEMENT TPHL/QMS Document No. 10

FOR FIXING OF WALL & Rev: 0 Working status :


COLUMN FORMWORK
WORK Page 5 / 6 Date : 02.11.2023

6.3.1 In case any undesired event or incident does happen at the work site or residential camp, in spite
of the essential HSE protection systems and procedures are in place, the same shall be handled in
such a way as to reduce the severity of human injury or damages and to regain control within the
least possible time.
6.3.2 In incidents of major nature such as those resulting in fatalities, severe human injuries, fire and
explosion and natural calamities like rain, wind, sand storm etc.
6.3.3 Work will be stopped immediately and appropriate emergency response procedures adopted as
per procedures of company.
6.3.4 The matter will be communicated to key personnel by the easiest available means, seeking
assistance and advice.
6.3.5 Further work will be started only on getting clearance from senior management.
6.3.6 Tool box meeting will be conducted of all employees to explain the HSE part of the incident, the
immediate and the corrective/control measures that are essential to prevent further occurrences of
similar incidents.
6.3.7 Detailed investigation will be made into the incident, other than natural calamities, and the
learning points disseminated to the work force.
6.3.8 In less serious cases, first aid or clinical aid shall be extended to injured victims if any and the
matter intimated to all concerned. Adequate first aid boxes shall be in place and trained first
aiders provided at site.

7. Sequence of work:
8.1 Preparation of Formwork:
8.1.1 The Engineer-in-charge will ensure layout work shall be completed as per drawings and to be
checked by him.
8.1.2 Carpenter shall make formwork of plywood (18mm thickness) as per shape, size and dimensions
as per drawing and according to design load.
8.1.3 Site Engineer shall check the formwork made by carpenter before fixing as per drawings.
8.1.4 Site Engineer shall check for cleaned and smoth surface before shuttering oil
8.1.5 Site Engineer shall check shuttring oil applied as per specification

8.2 Fixing of Formwork:


8.2.1 Surveyor shall mark the layout for column according to drawing.

8.2.2 Welding workman shall fix the KANDA/SPACER as per layout done by surveyor to give require
rigid support to formwork and to maintain eccentricity of column formwork.
8.2.3 Site engineer shall check the layout and shall proceed for fixing of formwork through RFI.
8.2.4 Carpenter shall fix the formwork at location after inspection of the Engineer-in-charge.
8.2.5 Carpenter shall fix the formwork at location as per layout marked by the surveyor at site.
8.2.6 Position of proper supports in formwork like tie rod/walers etc. shall be checked by site engineer.
8.2.7 The Engineer-in-charge shall check the level, line, verticality, size and shape as per drawing
before proceeding for concreting work start.

8.3 Miscellaneous:
The completed works shall be inspected and any left out items, minor defects if any, will be rectified
immediately.

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 5
METHOD STATEMENT TPHL/QMS Document No. 10

FOR FIXING OF WALL & Rev: 0 Working status :


COLUMN FORMWORK
WORK Page 6 / 6 Date : 02.11.2023

8. Documentation: RFI and checklist shall be maintained by the site Engineer for the work.

Prepared by : Karambir Singh Reviewed by: Approved by :

Page | 6