Method Statement For Fixing of Wall & Column Formwork
Method Statement For Fixing of Wall & Column Formwork
10
Page | 1
METHOD STATEMENT TPHL/QMS Document No. 10
CONTENTS
3. Materials required
4. Engineering works
5. Responsibility
6.1 Hazards
7. Sequence of Work
7.3 Miscellaneous
8. Documentation
Page | 2
METHOD STATEMENT TPHL/QMS Document No. 10
3. Materials required:
3.1 Nails
3.2 Marker pen
3.3 Timber Log
3.4 Film faced Plywood sheets
3.5 Scaffolding standard and Ledger
3.6 Scaffolding Joint Pin
3.7 Adjustable base jack
3.8 Wooden Runner
3.9 Scaffolding Coupler
3.10 Scaffolding Clamp
3.11 Scaffolding Prop jack
3.12 Scaffolding Pipe
3.13 U shape jack
3.14 Wing nut
3.15 Tie rods
3.16 Steel decking
4. Engineering works:
As receipt of drawings the Engineer-in-charge shall review the received drawings and discuss with their
senior for any technical doubts and clarifications.
5. Responsibility:
Page | 3
METHOD STATEMENT TPHL/QMS Document No. 10
5.1 The Engineer-in-charge will be responsible for implementing everything in this method
statement.
5.2 Safety officer will ensure that all safety procedures and measures are implemented in relation to
the type of work being done according to the project’s HSE plan.
5.3 QA/QC representative will be responsible for the implementation of QA/QC works as spelled out
in the Quality Management Plan.
Page | 4
METHOD STATEMENT TPHL/QMS Document No. 10
6.3.1 In case any undesired event or incident does happen at the work site or residential camp, in spite
of the essential HSE protection systems and procedures are in place, the same shall be handled in
such a way as to reduce the severity of human injury or damages and to regain control within the
least possible time.
6.3.2 In incidents of major nature such as those resulting in fatalities, severe human injuries, fire and
explosion and natural calamities like rain, wind, sand storm etc.
6.3.3 Work will be stopped immediately and appropriate emergency response procedures adopted as
per procedures of company.
6.3.4 The matter will be communicated to key personnel by the easiest available means, seeking
assistance and advice.
6.3.5 Further work will be started only on getting clearance from senior management.
6.3.6 Tool box meeting will be conducted of all employees to explain the HSE part of the incident, the
immediate and the corrective/control measures that are essential to prevent further occurrences of
similar incidents.
6.3.7 Detailed investigation will be made into the incident, other than natural calamities, and the
learning points disseminated to the work force.
6.3.8 In less serious cases, first aid or clinical aid shall be extended to injured victims if any and the
matter intimated to all concerned. Adequate first aid boxes shall be in place and trained first
aiders provided at site.
7. Sequence of work:
8.1 Preparation of Formwork:
8.1.1 The Engineer-in-charge will ensure layout work shall be completed as per drawings and to be
checked by him.
8.1.2 Carpenter shall make formwork of plywood (18mm thickness) as per shape, size and dimensions
as per drawing and according to design load.
8.1.3 Site Engineer shall check the formwork made by carpenter before fixing as per drawings.
8.1.4 Site Engineer shall check for cleaned and smoth surface before shuttering oil
8.1.5 Site Engineer shall check shuttring oil applied as per specification
8.2.2 Welding workman shall fix the KANDA/SPACER as per layout done by surveyor to give require
rigid support to formwork and to maintain eccentricity of column formwork.
8.2.3 Site engineer shall check the layout and shall proceed for fixing of formwork through RFI.
8.2.4 Carpenter shall fix the formwork at location after inspection of the Engineer-in-charge.
8.2.5 Carpenter shall fix the formwork at location as per layout marked by the surveyor at site.
8.2.6 Position of proper supports in formwork like tie rod/walers etc. shall be checked by site engineer.
8.2.7 The Engineer-in-charge shall check the level, line, verticality, size and shape as per drawing
before proceeding for concreting work start.
8.3 Miscellaneous:
The completed works shall be inspected and any left out items, minor defects if any, will be rectified
immediately.
Page | 5
METHOD STATEMENT TPHL/QMS Document No. 10
8. Documentation: RFI and checklist shall be maintained by the site Engineer for the work.
Page | 6