Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 28

CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS

WET TRADES
SUBSTRUCTURE

Concrete

Grade 10-20 m3 0

sand 0

cement 0

stone 0

Grade 20-20 m3 0

sand 0

cement 0

stone 0

Grade 25-20 m3 0

sand 0

cement 0

stone 0

Grade 30-20 m3 0

sand 0

cement 0

stone 0

Grade 30-40 m3 0

sand 0

cement 0

stone 0

Grade 40-20 m3 0

sand 0

cement 0

stone 0

Polythene sheeting
m2 0

m 0

Mesh fabric reinforcement Ref S193


m2 0

sheets 0

Hardcore
m3 0
Sand blinding
m3 0

Termite treatment
m2 0

litres 0

Half brick wall Face brick wall


m2 0 m2 0

commons 0 facings 0
pit sand 0 pit sand 0
cement 0 cement 0
One brick wall
m2 0

commons 0
pit sand 0
cement 0

Piers
m3 0
commons 0
pit sand 0
cement 0

Brick-on-edge
m2
bricks 0
pit sand 0
cement 0

Damp proof course for half brick wall


m 0 m2 0
roll 0 roll 0

Damp proof course for one brick wall


m 0 m2 0
roll 0 roll 0

Ref C1 for half brick wall


m 0
roll 0

Ref C2 for one brick wall


m 0
roll 0

Steel bar reinforcement


m3 0
kg 0

10mm Expansion joint. 3 ply bituminous felt sheeting


m2 0 m2 0
sheets 0 sheets

Thioflex sealant.
m 0
tubes 0

Woodfloat plaster
m2 0
pit sand 0
cement 0
undercoat 0
EPVA 0
SUPERSTRUCTURE

Concrete

Grade 10-20 m3 0

sand 0

cement 0

stone 0

Grade 20-20 m3 0

sand 0

cement 0

stone 0

Grade 25-20 m3 0

sand 0

cement 0

stone 0

Grade 30-20 m3 0

sand 0

cement 0

stone 0

Grade 30-40 m3 0

sand 0

cement 0

stone 0

Grade 40-20 m3 0

sand 0

cement 0

stone 0

Screeds
m2 0
river sand 0
cement 0

Half brick wall Face brick wall


m2 0 m2 0

commons 0 facings 0
pit sand 0 pit sand 0
cement 0 cement 0
One brick wall
m2 0

commons 0
pit sand 0
cement 0

Piers
m3 1
commons 481
pit sand 0
cement 2

Brick-on-edge
m2 0
bricks 0
pit sand 0
cement 0

150 mm Block wall


m2 0
blocks 0
pit sand 0
cement 0

Damp proof course for half brick wall


m 0
roll 0

Damp proof course for one brick wall


m 0
roll 0

Ref C1 for half brick wall


m 0
roll 0

Ref C2 for one brick wall


m 0
roll 0

Mesh fabric reinforcement Ref S311


m2 0

sheets 0

Steel bar reinforcement


m3 0
kg 0

150 x 150 mm White glazed wall tiles 0


m2 0
tiles 0
tylon 0 5kg
tile addhesive 0 20kg

Render and set to walls Redecoration to existing int. walls


m2 0 m2 0
pit sand 0 pit sand 0
cement 0 cement 0
rhinoset 0 rhinoset 0
undercoat 0 undercoat 0
IPVA 0 IPVA 0

Woodfloat plaster Redecoration to existing int. walls


m2 0 m2 0
pit sand 0 pit sand 0
cement 0 cement 0
undercoat 0 undercoat 0
EPVA 0 EPVA 0

Plasterboard ceilings Plasterboard ceilings redecor


m2 0 m2 0
Rhinobond 0 Rhinobond 0
plasterboard sheets 2400x1200 mm 0 plasterboard sheets 2100x1200 0
ceiling white 0 ceiling white 0
clout nails 0 clout nails 0
brandering 0 brandering 0
covebond 0

Cill ( quarry tiles)


m 0
no. 0
pit sand 0
cement 0

300 x 300 Vinyl tiles


m2 0
tiles 0
tylon 0
tile adhesi 0

150 x 150 Quarry floor tiles


m2 0
tiles 0

Wall plate
m 0
galvanised hoop iron ties 0
carbolineum 0

Painting to metal
m2 0
undercoat 0
metal primer 0
high gloss 0

Painting to wood
m2 0
undercoat 0
wood primer 0
high gloss 0

ROOF COVERINGS

Concrete roof tiles


m2 0
no. 0
Roof nails
m2 0
kg 0

Battens m2 0
m 0

Skirting
m 0

varnish 0

Pelmets
m 0

varnish 0
0
SCHEDULE OF MATERIAL QUALIFICATIONS

NOTE

1) This material schedule was prepared to the highest level of accuracy that was obtainable in terms
of information supplied and the contribution supplied by the Architect and all the interested parties
to the structure.

2) It should be noted with concern that material schedule accuracy depends on the information
supplied and cooperation of the interested parties.

3) This schedule of material remains correct if there are no changes made to the structure and the
material waste is maintained within the allowable range.

4) This schedule was prepared allowing a reasonable waste of between 5% and 10% depending with
the material type and quality.

5) Provisional quantities are to be remeasured on site to determine the correct material quantity but
if no changes to the specifications they are suppose to tally with the degree of + - 5%
CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS

SUBSTRUCTURE

1 Grade 10-20 m3 1

sand 0.79 m3
cement 4.46 Bag
stone 0.85 m3

2 Grade 15-20 m3 1

sand 0.84 m3
cement 6.09 Bag
stone 0.84 m3

3 Grade 20-20 m3 0

sand - m3
cement - Bag
stone - m3

4 Grade 25-20 m3 1

sand 0.71 m3
cement 5.99 Bag
stone 0.88 m3

4 Grade 30-20 m3 48.4

sand 34.05 m3
cement 429.43 Bag
stone 43.71 m3

5 Grade 30-40 m3 1

sand 0.71 m3
cement 6.51 Bag
stone 0.90 m3

6 Grade 40-20 m3 0

sand - m3
cement - Bag
stone - m3

7 Polythene sheeting m2 20 m2 392

m 13.33 m Roll 1.5*20m 13.07

8 Mesh fabric reinforcement Ref S193 m2 17

sheets 1.18 no.

9 Hardcore m3 0 m3

10 Sand blinding m2 20 m3
50mm blinding
m3 1.00 m3

11 Termite treatment m2 5

litres 0.54 ltrs


12 Half brick wall m2 39.42 Face brick wall m2 40

commons 2,276.51 no facings 2,226.00


pit sand 0.98 m3 pit sand 0.99
cement 5.38 Bag cement 5.46

13 One brick wall m2 195.84

commons 22,619.52 no
pit sand 12.32 m3
cement 68.13 Bag

14 Piers m3 0
commons - no
pit sand - m3
cement - Bag

15 Brick-on-edge m2 0
bricks - no
pit sand - m3
cement - Bag

16 Damp proof course for half brick wall m 0 16 a) m2 0


roll - no. roll -

17 Damp proof course for one brick wall


m 0 17 a) m2 5.00
roll - no. roll 1.09

18 Ref C1 for half brick wall m 219


roll 10.95 no.

19 Ref C2 for one brick wall m 1088


roll 54.40 no.

20 Steel bar reinforcement m3 0


kg - kgs

21 10mm Expansion joint. 3 ply bituminous felt sheeting


m2 1 m2 0
sheets 0.35 no. sheets -

22 Thioflex sealant. m 1
tubes 0.17 no.

23 Woodfloat plaster m2 0
pit sand - m3
cement - Bag
undercoat - ltr
Ext PVA -
CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS

SUPERSTRUCTURE

1 Grade 10-20 m3 1.6

sand 1.26 m3
cement 7.14 bag
stone 1.3608 m3

2 Grade 20-20 m3 1

sand 0.777 m3
cement 7.35 bag
stone 0.8085 m3

3 Grade 25-20 m3

sand 0 m3
cement 0 bag
stone 0 m3

4 Grade 30-20 m3 1

sand 0.7035 m3
cement 6.7725 bag
stone 0.903 m3

5 Grade 30-40 m3 0

sand 0 m3
cement 0 bag
stone 0 m3

6 Grade 40-20 m3 0

sand 0 m3
cement 0 bag
stone 0 m3

7 Screeds m2 468.63
river sand 21.65071 m3
cement 207.8468 bag

8 Half brick wall m2 1 Face brick wall m2 254.1

commons 54.6 no. facings 14140.665


pit sand 0.02478 m3 pit sand 6.296598
cement 0.168 bag cement 34.71133

9 One brick wall m2 1

commons 115.5 no.


pit sand 0.062895 m3
cement 0.347865 bag

10 Piers m3 0
commons 0 no.
pit sand 0 m3
cement 0 bag

11 Brick-on-edge m2 0
bricks 0 no.
pit sand 0 m3
cement 0 bag

12 150 mm Block wall m2 410


blocks 4249.035 no.
pit sand 12.915 m3
cement 90.405 bag

13 Damp proof course for half brick wall m 43.8


roll 1.990909 no.

14 Damp proof course for one brick wall m 217.6


roll 9.890909 no.

15 Ref C1 for half brick wall m 394.2


roll 19.71 no.

16 Ref C2 for one brick wall m 1958.4


roll 97.92 no.

17 Mesh fabric reinforcement Ref S311 m2 0

sheets 0 no.

18 Steel bar reinforcement m3 0


kg 0 kgs
CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS

FINISHIES

1 Render and set to walls m2 2511


pit sand 63 m3
cement 456 Bag
rhinoset 132 25kgs
undercoat 244 ltr
Int PVA 732 ltr

2 Woodfloat plaster m2 1760


pit sand 41 m3
cement 390 Bag
undercoat 171 ltr
Ext PVA 513 ltr

3 Plasterboard ceilings m2 468.63


Rhinobond 98 25kgs
Plasterboard 163 (2400 x 1200)m2
ceiling white 95 ltr
clout nails 4921 no
brandering 2343 m
covebond 25 25kgs

4 Cill ( quarry tiles) m 0


Tiles 0 no.
pit sand 0 m3
cement 0 bag

5 300 x 300 Vinyl tiles m2 0


tiles 0 no.
tylon 0 5kg
tile adhesive 0 20kg

6 150 x 150 Quarry floor tiles m2 0


tiles 0 no.
pit sand 0 m3
cement 0 bag

7 150 x 150 mm White glazed wall tiles m2 0


tiles 0 no.
tylon 0 5kg
tile adhesive 0 20kg

8 Painting to metal m2 0
undercoat 0 ltr
metal primer 0 ltr
high gloss 0 ltr

9 Painting to wood m2 0
undercoat 0 ltr
wood primer 0 ltr
high gloss 0 ltr
CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS

ROOF COVERINGS

1 Concrete roof tiles m2 501.7


no. 7375

2 Roof nails m2 501.7


kg 50

3 Battens m2 501.7
m 1605

4 Skirting m 0

varnish 0 ltr

5 Pelmets m 0

varnish 0 ltr

6 Wall plate m 152


GI hoop iron ties 213
carbolineum 16
ADDITIONAL ESTIMATING DATA

A. WHEEL & TIP BY HAND BARROW

a) Hauling not exceeding 20m 1 lab 180wb/day


b) Ditto 50m 1 lab 70wb/day
c) Ditto 100m 1 lab 36wb/day

B. COMPACTION ( avarage 150mm thick )

a) Plate compactor 1 lab 50m2/day


b) Bomag pedastrian roller 1 lab 75m2/day
c) hand ramming 1 lab 35m2/day

C. TIMBERING & SHORING TRENCHES

a) Both sides to trenches not exceeding 2m deep 1 lab 12m/day


b) Ditto 3m deep 8m/day
c) Ditto 4m deep 5m/day
d) Ditto 6m deep 2.5m/day

D. STEEL FIXING

a) Beams,floors,roofs & walls 1 lab 1ton/day


b) Braces column slopes 1 lab 0.5ton/day
c) Hoisting not exceeding 3m from ground 1 lab 4ton/day
d) Ditto 9m 1 lab 2.5ton/day
e) Ditto 15m 1 lab 2ton/day
f) Ditto 20m 1 lab 1.5ton/day

E. WALL & FLOOR TILING

Labour - Gang based on 1 Carpenter / Plumber and 2 Assistants

a) Ceramic wall tiles gang 6m2/day


b) Quarry wall & floor tiles gang 10m2/day
c) Sloping wall tiles gang 3m2/day
d) Vinyl tiles in boxes gang 10m2/day
e) Ditto in sheets gang 20m2/day
f) Carperting laying gang 100/day
g) Cladding gang 100/day
h) Concrete roofing tiles gang 100/day

F. PLUMBING

a) Sanitary fittings gang 3no/day


b) Pipe & accessories - water gang 30m/day
c) Pipe & accessories - sewer gang 59m/day
d) Accessories gang
e) Gutters & down pipes gang 14m/day
ADDITIONAL ESTIMATING DATA

A. CONCRETE

a) Mixing by hand 8hrs/m3

B. Panda

a) 600 x 600 x 50mm Pcc paving blocks 1 Pallet = 405 No.


b) 80mm Pcc interlocking pavers 1 Pallet = 500 bricks
Ditto above transportted by Superlink 1 load = 26 Pallets
226,266.00
266,993.88
40,727.88
ESTIMATING DATA

GROUND WORKS
A. SITE CLEARANCE

1,Clear site of all vegetation 1 Lab 20m2/day

B. EXCAVATIONS

1, Normal pickable ground


a) Trenches etc not exceeding 1m deep 1 Lab 2m3/day
Ditto 1-2m deep 1 Lab 1.5m3/day
Ditto 2-3m deep 1 Lab 1m3/day

b) Bases etc not exceeding 1m deep 1 Lab 1.75m3/day


Ditto 1-2m deep 1 Lab 1.20m3/day
Ditto 2-3m deep 1 Lab 0.75m3/day

c) Reduce levels n.e. 1m deep 1 Lab 2.20m3/day

2, Hard pickable ground


As above, but +250% 1 Lab

3, Rock excavation
As above, but +1200% 1 Lab

C. DISPOSALS

a) Backfilling to trenches and bases 1 Lab 2.5m3/day


b) Loose fill under floor 1 Lab 3.0m3/day
c) Ram fill under floors 1 Lab 2.0m3/day
d) Compacting 1 Lab 35m2/day
e) Load for disposal 1 Lab 1.5m3/day

BRICKWORK AND BLOCKWORK


NB
Adjustments must be made for high standard requirements
All data based on gang of 1 Bricklayer + 2 Assistants
Scaffolding not included

BRICKWORK

Common brickwork:
In foundations,
Half brick thick 375/day
One brick thick 400/day
One and half brick thick 425/day

In superstructure up to 2 storeys,
Half brick thick 350/day
One brick thick 380/day
One and half brick thick 400/day
ESTIMATING DATA

BRICKWORK AND BLOCKWORK


Facing brickwork:
In foundations,
Half brick thick 325/day
One brick thick 340/day

In superstructure up to 2 storeys,
Half brick thick 300/day
One brick thick 325/day

Composite brickwork ( faced on side )


In foundations,
One brick thick 350/day

In superstructure up to 2 storeys,
One brick thick 330/day
Mortar
Mixing by hand 8hrs/m3 1.125

BLOCKWORK
115mm blockwork:
In foundations 180/day
In superstructure 150/day

230mm blockwork:
In foundations 150/day
In superstructure 120/day
SUNDRIES
Beam filling 3m/hr/skin
Rough cutting 2.5hrs/m2
Cutting pipe chases 1.5hrs/m
Copings 0.75hrs/m
Fair cuttings 1hr/m
Cut small holes 1hr/skin
Cut large holes 2hrs/skin
Fix door and window frames 0.8hrs/m2
Unload and stack 3 lab hrs/1000
Painting around frames 3hrs/m

MORTAR MIX (per m3)


Mix Cement (50kg) Pit Sand (m3)
3;1 10.6 1.3
4;1 8.9 1.4
5;1 7.5 1.5
6;1 6.5 1.6
7;1 6.2 1.7
8;1 5.4 1.7
Note: Pit sand - Allow 15% bulk factor
ESTIMATING DATA

BRICKWORK

1.Mortar required per m2 of walling:


a. 75mm brick on edge 0.02m3
b. Half brickwall 0.028m3
c. One brickwall 0.04m3
d. One and half brickwall 0.096m3
e. 230 x 230mm clay block wall 0.018m3
f. 230 x 150mm ditto 0.023m3

2.Brick per m2 of walling (exclude waste) Commons Facings


a. 75mm brick on edge 35 *
b. Half brickwall 52 *
c. One brickwall 104 *
Based on one brickwall
d. English bond 26 78
e. English garden wall bond 39 65
f. Colonial bond 42 62
g. Flemish bond 39 65
h. Mass brickwork per m3 455 *

3.MORTAR TO BLOCKWORK (per m2 of walling)


a. Nominal 600 x 300mm - 108mm walls 0.017m3
b. Nominal 450 x 230mm - 108mm walls 0.023m3
- 150mm walls 0.031m3
- 230mm walls 0.054m3

Hoop irons 24 ggr = 0.6mm = 6.20kg/m3

CEMENT MORTAR

MIX Materials per m3


Cement Lime-25kg Sand m3
1;1 22.4 0.91
1;2 10.48 1.25
1;3 10.6 1.38
1;4 8.9 1.5
1;5 7.8 1.63
1;6 6.4 1.69
1;7 5.9 1.75
1;8 5.3 1.81
1;2;9 3.6 1.38
1;2;12 3 1.5

MATERIAL CONCRETE GRADE


10 15 20 25 30
Cement 5 6 7 9.26 10.29
River sand 0.8 0.8 0.74 0.7 0.65
19mm Ag 0.8 0.8 0.77 0.78 0.78

Brick reinforcement per four courses = 2.94m/m2

ESTIMATING DATA

CONCRETING
Labour

A. Mixing concrete Hourly output Lab output/hour


7/5 mixer 1.75m3 3/1.7
10/7 mixer 3.15m3 3/1.1
14/10 mixer 3.85m3 3/0.8
21/14 mixer 5.25m3 5/0.9

B. Transport and Place concrete


Mass filling 2hrs/m3
Foundations,bases,ground beams 4hrs/m3
Slabs 6hrs/m3
Blinding 12hrs/m3
Columns below ground 8hrs/m3
Columns not exceeding 4m high 12hrs/m3
Beams not exceeding 4m high 10hrs/m3
Suspended slabs ditto 10hrs/m3
Walls 8hrs/m3
Isolated small areas 12hrs/m3

Hours to be adjusted accordingly for high level work

Curb concrete 12m2/hr


Powerfloat finish 2m2/hr
Steel trowelled 2m2/hr
Fix expansion joints 150mm wide 5m/hr
Expansion joint filler m3/hr
Fix mesh reinforcing 5m2/hr

FORMWORK

Labour - Shuttering gang based on 1 Carpenter and 2 Assistants

Hard work and strip formwork to: Gang hours


Beams 0.85/m2
Walls 0.75/m2
Columns 1.15/m2
Soffits 0.80/m2
Narrow widths to edges 2.15/m2
PLASTERWORK

Single coat work (walls) - wood float 1+2 16m2/day


In narrow widths - ditto 1+2 10m2/day
Single coat work (walls) - steel float 1+2 14m2/day
In narrow widths - ditto 1+2 8m2/day
Single coat soffits - wood float 1+2 12m2/day
Ditto - steel float 1+2 10m2/day
Two coat work:
1st coat 1+2 16m2/day
Skim coat 1+2 23m2/day

ESTIMATING DATA

PLASTERWORK

Floor screeds 1+2 20m2/day


Narrow widths 1+2 16m2/day

Precast paving slabs 1+3 1m2/hr


Wall tiling 1+1 1m2/hr
Narrow widths 1+1 0.5m2/hr

GRANO

MIX MATERIALS PER M3


CEMENT SAND CHIPS
50kg M3 M3
1;3 11.4 * 1.1
1;1;1.05 14.5 0.59 0.7
1;1;2 12 0.49 0.77

Rhinosand 8m2/sack(25kg)
Rhinoset 20m2/sack
Rhino bond 6m2/sack
Cemwash 12m2/sack/coat
1m3 cment = 30bags
PAINTING
Paint to ceiling
Paint to walls 60m2/day
Paint to frames 50m2/day
Paint to timber 45m2/day
Paint to small pipes 25m/hr/coat
Paint to large pipes 10m/hr/coat
NB. Add 10% to labour figures for turps,brushes etc.

Paint covering capacities


All per 5 litres

PVA to boards 5 Litres 1 Litre

1st coat 30m2 6m2


2nd coat 40m2 8m2
3rd coat 50m2 10m2

PVA to plaster

1st coat 40m2 8m2


2nd & 3rd coat 50m2 10m2
PVA to blockwork:

1st coat 40m2 6m2


2nd coat 35m2 7m2
3rd coat 45m2 9m2

paint to 230 steel dr frame size 815x2032 =2.03m2


paint to 115 steel dr frame size 815x2032 =1.47m2
ESTIMATING DATA

PAINTING

xs Primer / Uct / Gloss ct etc 5 Litres 1 Litre


To steel work:

1st coat 45m2 9m2


Subsequent 50m2 10m2

To timber:
1st coat 35m2 7m2
2nd coat 40m2 8m2
Subsequent 50m2 10m2

REINFORCEMENT

DIAMETER ROUND PLAIN HIGH


MILD SQUARE YIELD
TWIST DEFORMED
(R) (X) (Y)
6mm 0.222 0 0.222
6.50mm 0.26 0.332 0
8mm 0.395 0.502 0.395
10mm 0.616 0.784 0.616
12mm 0.887 1.129 0.888
14mm 1.207 1.537 1.21
16mm 1.577 2.008 1.579
20mm 2.464 3.137 2.466
22mm 2.981 3.796 0
25mm 3.85 4.902 3.854
30mm 5.544 7.059 0
32mm 0 0 6.313
35mm 0 9.608 0
40mm 0 0 9.869

KGs PER RUNNING METRE

1.BASES 90kg/m3
2.COLUMNS 170kg/m3
3.WALLS 100kg/m3
4.SLABS 120kg/m3
5.BEAMS 150kg/m3
FABRIC REINFORCEMENT

Ref No S245 2.45kg/m2


Ref No S193 1.93kg/m2
Ref No S125 1.25kg/m2

Hoop irons 24 ggr = 0.6mm = 6.20 kg/m3

ESTIMATING DATA

BLOCK PRODUCTION DATA


1 Sack cement = 0.034m3
1 Barrow = 0.057m3 ( 2 cu ft )

Block Volumes

( A ) 450 x 220 x 168 hollow = 0.00666m3/block = 15kg


( B ) 450 x 220 x 103 solid = 0.01070m3/block = 30kg
( C ) 450 x 220 x 216 hollow = 0.00879m3/block = 27kg

Theoretical Mixes Mix 1:6 Mix 1:8 Mix 1:10 Mix 1: 12


Cement 0.034m3 0.034m3 0.034m3 0.034m3
Aggregate 0.204m3 0.272m3 0.340m3 0.408m3

Practical Equivalents
Cement 1 sack 1 sack 1 sack 1 sack
Aggregate 3.5barrws 4.5barrws 6 barrows 7 barrows
Dry Volume 0.234 0.291 0.376 0.433
Waste 5% 0.012 0.015 0.019 0.022
0.222 0.276 0.357 0.411

Mixed Volume 0.155m3 0.193m3 0.250m3 0.288m3

YIELDS Per SACK

Mix 1:6 Mix 1:8 Mix 1:10 Mix 1:12


A. 23 29 37 43
B. 14 18 23 27
C. 17 22 28 32

Mortar in filling 230mm hollow blocks 0.013m3/block = 0.124m3/m2


Mortar in filling 115mm hollow blocks 0.007m3/block = 0.067m3/m2

ROOFING

Sheets 1+4 6sheets/hr


Mitring 1+1 20sheets/hour
Fix barge and fascia board 1+2 5m/hr
Fix IBR roof sheeting 1+4 6m2/hr
Fix tiling battens 1+2 10m2/3hrs

CARPENTRY
Fix purlins 1+2 20m/hr
Fix rafters 1+2 14m/hr
Fix trusses ( 8m ) 1+4 4No/day
Fix sprockets 1+2 3m/hr
Fix joists 1+2 15m/hr
Fix hangers 1+2 3m/hr

ESTIMATING DATA

CARPENTRY

JOINERY
Fix brandering one way 1+2 3m2/hr
Fix ceilings 1+3 2m2/hr
Fix cover strip 1+2 20m/hr
Fix cornice 1+2 15m/hr
Fix skirting 1+2 10m/hr
Fix framing 1+1 6m/hr
Cut and fix blocked shelving 1+1 2hrs/sheet
Fix pre-cut shelving 1+1 6m/hr
Hang doors 1+2 1No /hr
Plugging 1+1 8plugs/hr
Screwing 1+1 20/hr

IRONMONGERY & SUNDRIES


Mortice lock 1+1 1hr/each
Indicator lock 1 0.75hrs/each
Shelf brackets Allow plugs and screws
Curtain track 1+1 2m/hr

Rhinoset coverage 14m2/25kg bag


Rhinobond coverage 6m2/25kg bag
Turnall Products
Endurites 0.875 wide
Traffold tiles 1.015 wide

Brickforce ( per 4 courses ) 2.94m/m2

ESTIMATING DATA
Wheelbarrow 0.057m3
Sack cement 0.034m3

Grout

a+b xcxdx1.7 kg/m2


axb

where a - length of tile


b - width of tile
c - thickness of tile
d - average joint width
one side two sides
single Normal door 0.813*2032mm 1.652016 3.304032
1
Retaining wall Rand
One load of loffelstein L300 coulor grey 24 packs ( 864 blocks - 90.95m2 ) 39.5

Tylone 4m2 per 20kgs


Glue to carpet 1ltr per 1m2
2.00
Bwp
19.75 Nett price
6.94 Trans
26.69
13.35 Other related charges
40.04

You might also like