WET TRADES
SUBSTRUCTURE
Concrete
Grade 10-20 m3 0
sand 0
cement 0
stone 0
Grade 20-20 m3 0
sand 0
cement 0
stone 0
Grade 25-20 m3 0
sand 0
cement 0
stone 0
Grade 30-20 m3 0
sand 0
cement 0
stone 0
Grade 30-40 m3 0
sand 0
cement 0
stone 0
Grade 40-20 m3 0
sand 0
cement 0
stone 0
Polythene sheeting
m2 0
m 0
sheets 0
Hardcore
m3 0
Sand blinding
m3 0
Termite treatment
m2 0
litres 0
commons 0 facings 0
pit sand 0 pit sand 0
cement 0 cement 0
One brick wall
m2 0
commons 0
pit sand 0
cement 0
Piers
m3 0
commons 0
pit sand 0
cement 0
Brick-on-edge
m2
bricks 0
pit sand 0
cement 0
Thioflex sealant.
m 0
tubes 0
Woodfloat plaster
m2 0
pit sand 0
cement 0
undercoat 0
EPVA 0
SUPERSTRUCTURE
Concrete
Grade 10-20 m3 0
sand 0
cement 0
stone 0
Grade 20-20 m3 0
sand 0
cement 0
stone 0
Grade 25-20 m3 0
sand 0
cement 0
stone 0
Grade 30-20 m3 0
sand 0
cement 0
stone 0
Grade 30-40 m3 0
sand 0
cement 0
stone 0
Grade 40-20 m3 0
sand 0
cement 0
stone 0
Screeds
m2 0
river sand 0
cement 0
commons 0 facings 0
pit sand 0 pit sand 0
cement 0 cement 0
One brick wall
m2 0
commons 0
pit sand 0
cement 0
Piers
m3 1
commons 481
pit sand 0
cement 2
Brick-on-edge
m2 0
bricks 0
pit sand 0
cement 0
sheets 0
Wall plate
m 0
galvanised hoop iron ties 0
carbolineum 0
Painting to metal
m2 0
undercoat 0
metal primer 0
high gloss 0
Painting to wood
m2 0
undercoat 0
wood primer 0
high gloss 0
ROOF COVERINGS
Battens m2 0
m 0
Skirting
m 0
varnish 0
Pelmets
m 0
varnish 0
0
SCHEDULE OF MATERIAL QUALIFICATIONS
NOTE
1) This material schedule was prepared to the highest level of accuracy that was obtainable in terms
of information supplied and the contribution supplied by the Architect and all the interested parties
to the structure.
2) It should be noted with concern that material schedule accuracy depends on the information
supplied and cooperation of the interested parties.
3) This schedule of material remains correct if there are no changes made to the structure and the
material waste is maintained within the allowable range.
4) This schedule was prepared allowing a reasonable waste of between 5% and 10% depending with
the material type and quality.
5) Provisional quantities are to be remeasured on site to determine the correct material quantity but
if no changes to the specifications they are suppose to tally with the degree of + - 5%
CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS
SUBSTRUCTURE
1 Grade 10-20 m3 1
sand 0.79 m3
cement 4.46 Bag
stone 0.85 m3
2 Grade 15-20 m3 1
sand 0.84 m3
cement 6.09 Bag
stone 0.84 m3
3 Grade 20-20 m3 0
sand - m3
cement - Bag
stone - m3
4 Grade 25-20 m3 1
sand 0.71 m3
cement 5.99 Bag
stone 0.88 m3
sand 34.05 m3
cement 429.43 Bag
stone 43.71 m3
5 Grade 30-40 m3 1
sand 0.71 m3
cement 6.51 Bag
stone 0.90 m3
6 Grade 40-20 m3 0
sand - m3
cement - Bag
stone - m3
9 Hardcore m3 0 m3
10 Sand blinding m2 20 m3
50mm blinding
m3 1.00 m3
11 Termite treatment m2 5
commons 22,619.52 no
pit sand 12.32 m3
cement 68.13 Bag
14 Piers m3 0
commons - no
pit sand - m3
cement - Bag
15 Brick-on-edge m2 0
bricks - no
pit sand - m3
cement - Bag
22 Thioflex sealant. m 1
tubes 0.17 no.
23 Woodfloat plaster m2 0
pit sand - m3
cement - Bag
undercoat - ltr
Ext PVA -
CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS
SUPERSTRUCTURE
sand 1.26 m3
cement 7.14 bag
stone 1.3608 m3
2 Grade 20-20 m3 1
sand 0.777 m3
cement 7.35 bag
stone 0.8085 m3
3 Grade 25-20 m3
sand 0 m3
cement 0 bag
stone 0 m3
4 Grade 30-20 m3 1
sand 0.7035 m3
cement 6.7725 bag
stone 0.903 m3
5 Grade 30-40 m3 0
sand 0 m3
cement 0 bag
stone 0 m3
6 Grade 40-20 m3 0
sand 0 m3
cement 0 bag
stone 0 m3
7 Screeds m2 468.63
river sand 21.65071 m3
cement 207.8468 bag
10 Piers m3 0
commons 0 no.
pit sand 0 m3
cement 0 bag
11 Brick-on-edge m2 0
bricks 0 no.
pit sand 0 m3
cement 0 bag
sheets 0 no.
FINISHIES
8 Painting to metal m2 0
undercoat 0 ltr
metal primer 0 ltr
high gloss 0 ltr
9 Painting to wood m2 0
undercoat 0 ltr
wood primer 0 ltr
high gloss 0 ltr
CONVERSIONS FOR PREPARING SCHEDULE OF MATERIALS
ROOF COVERINGS
3 Battens m2 501.7
m 1605
4 Skirting m 0
varnish 0 ltr
5 Pelmets m 0
varnish 0 ltr
D. STEEL FIXING
F. PLUMBING
A. CONCRETE
B. Panda
GROUND WORKS
A. SITE CLEARANCE
B. EXCAVATIONS
3, Rock excavation
As above, but +1200% 1 Lab
C. DISPOSALS
BRICKWORK
Common brickwork:
In foundations,
Half brick thick 375/day
One brick thick 400/day
One and half brick thick 425/day
In superstructure up to 2 storeys,
Half brick thick 350/day
One brick thick 380/day
One and half brick thick 400/day
ESTIMATING DATA
In superstructure up to 2 storeys,
Half brick thick 300/day
One brick thick 325/day
In superstructure up to 2 storeys,
One brick thick 330/day
Mortar
Mixing by hand 8hrs/m3 1.125
BLOCKWORK
115mm blockwork:
In foundations 180/day
In superstructure 150/day
230mm blockwork:
In foundations 150/day
In superstructure 120/day
SUNDRIES
Beam filling 3m/hr/skin
Rough cutting 2.5hrs/m2
Cutting pipe chases 1.5hrs/m
Copings 0.75hrs/m
Fair cuttings 1hr/m
Cut small holes 1hr/skin
Cut large holes 2hrs/skin
Fix door and window frames 0.8hrs/m2
Unload and stack 3 lab hrs/1000
Painting around frames 3hrs/m
BRICKWORK
CEMENT MORTAR
ESTIMATING DATA
CONCRETING
Labour
FORMWORK
ESTIMATING DATA
PLASTERWORK
GRANO
Rhinosand 8m2/sack(25kg)
Rhinoset 20m2/sack
Rhino bond 6m2/sack
Cemwash 12m2/sack/coat
1m3 cment = 30bags
PAINTING
Paint to ceiling
Paint to walls 60m2/day
Paint to frames 50m2/day
Paint to timber 45m2/day
Paint to small pipes 25m/hr/coat
Paint to large pipes 10m/hr/coat
NB. Add 10% to labour figures for turps,brushes etc.
PVA to plaster
PAINTING
To timber:
1st coat 35m2 7m2
2nd coat 40m2 8m2
Subsequent 50m2 10m2
REINFORCEMENT
1.BASES 90kg/m3
2.COLUMNS 170kg/m3
3.WALLS 100kg/m3
4.SLABS 120kg/m3
5.BEAMS 150kg/m3
FABRIC REINFORCEMENT
ESTIMATING DATA
Block Volumes
Practical Equivalents
Cement 1 sack 1 sack 1 sack 1 sack
Aggregate 3.5barrws 4.5barrws 6 barrows 7 barrows
Dry Volume 0.234 0.291 0.376 0.433
Waste 5% 0.012 0.015 0.019 0.022
0.222 0.276 0.357 0.411
ROOFING
CARPENTRY
Fix purlins 1+2 20m/hr
Fix rafters 1+2 14m/hr
Fix trusses ( 8m ) 1+4 4No/day
Fix sprockets 1+2 3m/hr
Fix joists 1+2 15m/hr
Fix hangers 1+2 3m/hr
ESTIMATING DATA
CARPENTRY
JOINERY
Fix brandering one way 1+2 3m2/hr
Fix ceilings 1+3 2m2/hr
Fix cover strip 1+2 20m/hr
Fix cornice 1+2 15m/hr
Fix skirting 1+2 10m/hr
Fix framing 1+1 6m/hr
Cut and fix blocked shelving 1+1 2hrs/sheet
Fix pre-cut shelving 1+1 6m/hr
Hang doors 1+2 1No /hr
Plugging 1+1 8plugs/hr
Screwing 1+1 20/hr
ESTIMATING DATA
Wheelbarrow 0.057m3
Sack cement 0.034m3
Grout