Professional Documents
Culture Documents
Work Study and Labor Schemes Lecture 11 May 2023
Work Study and Labor Schemes Lecture 11 May 2023
Work Study
Work Study
𝑍 2 × 𝑃(1 − 𝑃)
𝑁=
𝐿2
Activity Sampling Procedure (1)
• List the operations and tasks to be studied:
• Working/Not working
Or
• In more details such as:
• Fixing Shutters (FS)
• Cleaning shutter panels (CL)
• Removing formwork (RF)
• Receiving instructions (RI)
• Idle (I)
Activity Sampling Procedure (2)
• Prepare a suitable observation sheet for recording the
information.
• Prepare a planned timetable of observation times at regular
intervals.
• Choose a suitable position for taking the observations.
• Record each activity that is in operation at the instant it is
observed.
• From the percentages of the activities observed, select the
activity or activities that show a disproportionate amount of
time being spent on them.
Activity Sampling Observation Sheet
Activity Sampling Equation
𝑍 2 × 𝑃(1 − 𝑃)
𝑁=
𝐿2
Where:
• N = No. of Required Observations
• Z = Confidence Level = 2 for 95% Confidence
• P = Percentage of activity observed
• L = Accuracy Level Required
Activity Sampling Example
Crane Operations were observed 400 times with the following
results:
Operation No of Observations
Crane Lifting 160
Crane Moving 80
Crane unloading 60
Crane Idle 100
1. Determine the percentage of time the crane was idle and the degree
of accuracy of the result (95% confidence level is required)
2. How many additional observations are required, If the degree of
accuracy is to be 2%.
Solution
Percentage Idle, P = 100/400 = 0.25
For 95% confidence level Z = 2
𝑍 2 ×𝑃(1−𝑃) 22 × 0.25(0.75)
𝐿= = = 0.0433 = 4.33%
𝑁 400
If L = 2%, then:
𝑍 2 ×𝑃(1−𝑃) 22 ×0.25(0.75)
𝑁= = = 1875
𝐿2 0.022
Therefore, the number of additional observations is 1875 – 400 = 1475
Work Study
Work Study
Task 2
Worker 1 Task 1
Task 4
Equipment 1 Task 3
Equipment 2 Task 5
Worker 2 Task 6
Crane Skip2 Skip1
Crane Dumper2
Skip Dumper
Dumper1 Mixer Loader
0.5
1
1.5
Load
2
Fill Mixer 2.5
Raise 3
3.5
Mix
4
4.5
Load
Fill Dumper 5
Fill Mixer 5.5
Raise 6
Travel 6.5
Mix
7
Attach Fill Skip Fill Skip 7.5
Fill Dumper 8
8.5
Return
9
9.5
10
10.5
11
11.5
12
Return
Return
12.5
13
19
Travel & Pour
19.5
20
20.5
21
Return
Return
21.5
22
Attach 22.5
23
23.5
24
24.5
Travel & Pour
25
Fill Skip 25.5
26
26.5
27
Return
27.5
28
Attach Fill Skip 28.5
29
29.5
30
Travel &
Travel &
Crane Skip2 Skip1
Crane Dumper2
Skip Dumper
Dumper1 Mixer Loader
0.5
1
1.5
Load
2
Fill Mixer 2.5
Raise 3
3.5
Mix
4
4.5
Fill Dumper 5
5.5
6
Load
Travel 6.5
Fill Mixer 7
Attach Fill Skip Fill Skip Raise 7.5
8
Mix
8.5
Return
9
Fill Dumper 9.5
10
10.5
11
Travel
11.5
Attach Fill Skip Fill Skip 12
Return
Return
12.5
13
13.5
14
14.5
15
Return
15.5
16
Attach Fill Skip 16.5
17
17.5
18
18.5
Travel & Pour
19
Travel & Pour
19.5
20
20.5
21
Return
Return
21.5
22
Attach 22.5
23
23.5
24
24.5
Travel & Pour
25
Fill Skip 25.5
26
26.5
27
Return
27.5
28
Attach Fill Skip 28.5
29
29.5
30
Travel &
Travel &
Crane Skip2 Skip1
Crane Dumper2
Skip Dumper
Dumper1 Mixer Loader
0.5
1
1.5
Load
2
Fill Mixer 2.5
Raise 3
3.5
Mix
4
4.5
Fill Dumper 5
5.5
6
Travel 6.5
7
Attach Fill Skip Fill Skip 7.5
Load
Cycle time
Fill Mixer 8.5
Return
Raise 9
9.5
10
Time to Pour 80 m3
10.5
Fill Dumper
12.5
13
14
= 2 days
Fill Mixer 14.5
Return
= 8 hours
Raise 15
= 40 m3Return 15.5
Mix
16
Attach Fill Skip 16.5
Fill Dumper
= 60/6 x 0.5 = 5 m3
17
17.5
= 6 min to pour 0.5Travel
18
Return
Return
Travel
18.5
m3 & Pour
19
Travel & Pour
20
Fill Mixer 20.5
Return
Raise 21
Return
Return
21.5
Mix
22
Attach 22.5
Fill Dumper 23
23.5
24
Return
Travel
24.5
Travel & Pour
25
Fill Skip Attach Fill Skip
Fill Skip 25.5
26
26.5
Return
27
Return
27.5
Travel & Pour
28
Attach Fill Skip 28.5
29
29.5
30
Retur
Travel &
Travel &
Utilization Factors
Equipment Active Time Idle Time Utilization (%)
Loader 3 3 50%
Mixer 3 3 50%
½ m3 Dumper 4.5 1.5 75%
½ m3 Skip 6 0 100%
Crane 6 0 100%
Calculating Costs
Equipment Price/day
½ m3 Batching Plant 1200
½ m3 Dumper 400
½ m3 Skip 100
Crane 4000
Compaction Equipment 120
Labourer 300
Load
2
Fill Mixer 2.5
Raise 3
3.5
Mix
4
4.5
Load
Fill Dumper 5
Fill Mixer 5.5
7
Fill Skip Fill Skip 7.5
Load
Travel Raise 9
9.5
Mix
10
Attach Fill Skip Fill Skip 10.5
Load
Fill Dumper 11
Fill Mixer 11.5
Return
Raise 12
Travel
12.5
Mix
13
Raise 15
Return
Return
Travel
15.5
Mix
16
Attach Fill Skip Fill Skip 16.5
Load
Fill Dumper 17
Fill Mixer 17.5
Return
Raise 18
Travel
18.5
Travel & Pour
Mix
19
Travel & Pour
Raise 21
Return
Return
Travel
21.5
Mix
22
Attach Fill Skip Fill Skip 22.5
Load
Fill Dumper 23
Fill Mixer 23.5
Return
24
Travel
24.5
Travel & Pour
Travel & Pour
Mix
25
Fill Skip Fill Skip
Fill Skip 25.5
Fill Dumper Fill Dumper 26
26.5
Return
27
Return
Return
Travel
27.5
28
Attach Fill Skip Fill Skip 28.5
29
29.5
Return
30
Travel &
Travel &
Utilization Factors for Improved Method
Equipment Active Time Idle Time Utilization (%)
Loader 6 0 100%
Mixer 6 0 100%
½ m3 Dumper (2 used) 4.5 1.5 75%
1 m3 Skip (2 used) 6.5 5.5 54%
Crane 6 0 100%
Calculating Costs for improved method
Equipment Price/day
Cycle time = 6 min to pour 1 m3
½ m3 Batching Plant 1200 Output per hour = 60/6 x 1 = 10 m3
½ m3 Dumper (2 used) 400 Hours worked per day = 8 hours
Output per day = 8 x 5 = 80 m3
1 m3 Skip (2 used) 150 Time to Pour 80 m3 = 1 day
Crane 4000
Compaction Equipment 120
Labourer 300
Daywork
Piecework
Direct Hours
Saved Bonus
Geared Hours
Saved Bonus
Group Schemes
Levels of Performance
Performance Description
Target Hours
20 LE/Hour 16 Hours
Hourly Pay @75P
(1) (2) (3) (4) (5) (6) (7)
Worked Hours Saved hours Basic Pay Bonus Pay Total Pay Pay/Hour
Perf (P) 720/60/(1) Target-(2) 20LE*(2) 20LE*(3) (4) + (5) (6)/(2)
120 10 6 200 120 320 32
100 12 4 240 80 320 26.67
75 16 0 320 0 320 20
50 24 0 480 0 480 20
Geared Hours-Saved Bonus Scheme
• Workers are paid a bonus for each hour saved from a
certain target
• In the geared scheme, the bonus payment for each hour
saved is a fraction of the hourly rate for each hour worked
• The target number of hours is set for a lower level of
performance than that of Direct Schemes
• This allows for new jobs or un-skilled workers
Geared Hours-Saved Bonus Scheme
• Using a 50-100 geared scheme
• Standard Performance is 100P
• Target hours are calculated at 50P
• The hours saved are calculated as follows:
Hours Saved = Actual Hours Worked - Target Hours (at 50P)
• Worker is paid for Actual hours saved plus a bonus for hours
saved depending on his performance
• The hourly bonus pay can range between 25% to 75% of the
basic pay
Geared Hours-Saved Bonus Scheme
33%
Example of
Geared Hours-Saved Bonus Scheme
• Quantity = 720 Bricks
• At 100P – Output = 60 Bricks/Hour
• Using a 50 -100 Geared Hours Saved Scheme
• Basic Hourly Pay = LE 18 / Hour worked
• Bonus Hourly Pay = LE 6 / Hour Saved (33% of Basic)
Solution (Geared Scheme) 1
• At 50P – Output = 0.5 x 60 = 30 Bricks/Hour
𝟕𝟐𝟎
• Target Hours at 50P = = 24 Hours
𝟑𝟎
• If the worker is working at 100P then he will need:
720
• Hours worked = = 12 Hours
60
• Hours Saved = 24 Hours – 12 Hours = 12 Hours
• Basic Pay = 12 x 18 = 216 LE
• Bonus Pay = 12 x 6 = 72 LE
• Total Pay = = 288 LE
• Equivalent Hourly Rate = 288/12 = 24 LE (=1.33 Basic)
Solution (Geared Scheme) 2
Quantity 720 Bricks
Output Rate
At 100P 60 Bricks/Hour
At 50P 30 Bricks/Hour
Target
Hourly Hours
18 LE/Hour 24 Hours
Pay @50P
Bonus
Pay 6 LE/Hour
(1) (2) (3) (4) (5) (6) (7)
Worked Saved Bonus
Basic Pay Total Pay Pay/Hour
Perf (P) Hours hours Pay
720/60/(1)
18
24LE*(2) (4) + (5) (6)/(2)
Target-(2) 6
8LE*(3)
120 10 14 180 84 264 26.40
100 12 12 216 72 288 24.00
75 16 8 288 48 336 21.00
50 24 0 432 0 432 18.00
Geared Scheme Graph
133%
75
Overtime Scheme
• Overtime helps accelerate the work
• But overtime results in reductions in productivity rates.
• In some cases, working overtime can result in quicker
completion of the tasks but higher costs
Overtime Example
• Quantity = 4000 m2
• Labor Productivity = 6 m2/man-hour
• Available crew = 8 Men
• Hourly rate = LE 15/man-hour (Regular Hours)
• Hourly rate = LE 25/man-hour (Overtime Hours)
• Regular Schedule = 40 hours per week (5 days x 8 hours/day)
• Overtime Schedule = 50 hours per week (5 days x 10 hours/day)
• Inefficiency due to Overtime = 13%
Overtime Example Solution (1)
Regular Schedule:
• Quantity = 4000 m2
• Labor Productivity = 6 m2/man-hour Labor Cost / m2 = 2.50 LE/m2
• Available 8 Workers
4000 𝑚2
• Time Required = 6 𝑚2
= 83.33 hours
8 𝑚𝑒𝑛 ×
𝑚𝑎𝑛−ℎ𝑜𝑢𝑟
• 2 Weeks (40 hours each) + 0 days + 3.33 hours
• Hourly rate = LE 15/man-hour (Regular Hours)
• Cost of Labor = 8 Men x 83.33 Hours x 15 LE = 10,000 LE
Overtime Example Solution (2)
Overtime Schedule:
• Quantity = 4000 m2
• Labor Productivity = 6 m2/man-hour x (1-0.13) = 5.22 m2/man-hour
• Available 8 Workers
4000 𝑚2 2 = 3.35 LE/m2
• Time Required = 5.22 𝑚2
= 95.79 hours Labor Cost / m
8 𝑚𝑒𝑛 ×
𝑚𝑎𝑛−ℎ𝑜𝑢𝑟
• 1 Week (50 hours) + 4 days (10 hours) + 5.79 hours
• Hourly rate = LE 15/man-hour (Regular Hours)
• Hourly rate = LE 25/man-hour (Overtime Hours)
• Cost of Labor (Regular) = 8 Men x 15 (40 + 4x8) = 8640 LE
• Cost of Labor (Overtime) = 8 Men x 25 (10 + 4 x 2 + 5.79) = 4758 LE
• Total Cost of Labor = 8640 + 4758 = 13,398 LE