ASHRAE Guideline 0-2013

(Supersedes ASHRAE Guideline 0-2005)


Includes ASHRAE addenda listed in Annex Q

The Commissioning
Process

See Annex Q for approval dates by the ASHRAE Standards Committee and the ASHRAE Board of Directors.

This guideline is under continuous maintenance by a Standing Guideline Project Committee (SGPC) for which the Standards Com-
mittee has established a documented program for regular publication of addenda or revisions, including procedures for timely, doc-
umented, consensus action on requests for change to any part of the guideline. The change submittal form, instructions, and
deadlines may be obtained in electronic form from the ASHRAE website (www.ashrae.org) or in paper form from the Manager of
Standards. The latest edition of an ASHRAE Standard or Guideline may be purchased from the ASHRAE website (www.ashrae.org)
or from ASHRAE Customer Service, 1791 Tullie Circle, NE, Atlanta, GA 30329-2305. E-mail: orders@ashrae.org. Fax: 678-539-
2129. Telephone: 404-636-8400 (worldwide), or toll free 1-800-527-4723 (for orders in US and Canada). For reprint permission,
go to www.ashrae.org/permissions.

© 2013 ASHRAE ISSN 1049-894X

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

ASHRAE Standing Guideline Project Committee 0


Cognizant TC: TC 9.1, Large Building Air-Conditioning Systems
SPLS Liaison: Janice C. Peterson
Timothy F. Corbett, Chair Walter D. Horn
Thomas R. Meyer, Vice-Chair Gerald J. Kettler
Michael Amstadt, Secretary Kevin K. Knueven
Thomas E. Cappellin Guopeng Liu
Charles E. Dorgan Larry S. Ross
Justin Foster Garner

ASHRAE STANDARDS COMMITTEE 2013–2014


William F. Walter, Chair David R. Conover Malcolm D. Knight
Richard L. Hall, Vice-Chair John F. Dunlap Rick A. Larson
Karim Amrane James W. Earley, Jr. Mark P. Modera
Joseph R. Anderson Steven J. Emmerich Cyrus H. Nasseri
James Dale Aswegan Julie M. Ferguson Janice C. Peterson
Charles S. Barnaby Krishnan Gowri Heather L. Platt
Steven F. Bruning Cecily M. Grzywacz Douglas T. Reindl
John A. Clark Rita M. Harrold Julia A. Keen, BOD ExO
Waller S. Clements Adam W. Hinge Thomas E. Werkema, Jr., CO
Debra H. Kennoy

Stephanie C. Reiniche, Manager of Standards

SPECIAL NOTE
This Guideline was developed under the auspices of ASHRAE. ASHRAE Guidelines are developed under a review process, identifying
a guideline for the design, testing, application, or evaluation of a specific product, concept, or practice. As a guideline it is not definitive but
encompasses areas where there may be a variety of approaches, none of which must be precisely correct. ASHRAE Guidelines are written
to assist professionals in the area of concern and expertise of ASHRAE’s Technical Committees and Task Groups.
ASHRAE Guidelines are prepared by project committees appointed specifically for the purpose of writing Guidelines. The project
committee chair and vice-chair must be members of ASHRAE; while other committee members may or may not be ASHRAE members, all
must be technically qualified in the subject area of the Guideline.
Development of ASHRAE Guidelines follows procedures similar to those for ASHRAE Standards except that (a) committee balance is
desired but not required, (b) an effort is made to achieve consensus but consensus is not required, (c) Guidelines are not appealable, and
(d) Guidelines are not submitted to ANSI for approval.
The Manager of Standards of ASHRAE should be contacted for:
a. interpretation of the contents of this Guideline,
b. participation in the next review of the Guideline,
c. offering constructive criticism for improving the Guideline, or
d. permission to reprint portions of the Guideline.

DISCLAIMER
ASHRAE uses its best efforts to promulgate Standards and Guidelines for the benefit of the public in light of available information and
accepted industry practices. However, ASHRAE does not guarantee, certify, or assure the safety or performance of any products, components,
or systems tested, installed, or operated in accordance with ASHRAE’s Standards or Guidelines or that any tests conducted under its
Standards or Guidelines will be nonhazardous or free from risk.

ASHRAE INDUSTRIAL ADVERTISING POLICY ON STANDARDS


ASHRAE Standards and Guidelines are established to assist industry and the public by offering a uniform method of testing for rating
purposes, by suggesting safe practices in designing and installing equipment, by providing proper definitions of this equipment, and by providing
other information that may serve to guide the industry. The creation of ASHRAE Standards and Guidelines is determined by the need for them,
and conformance to them is completely voluntary.
In referring to this Standard or Guideline and in marking of equipment and in advertising, no claim shall be made, either stated or implied,
that the product has been approved by ASHRAE. --`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

CONTENTS
ASHRAE Guideline 0-2013,
The Commissioning Process
SECTION PAGE
Foreword .....................................................................................................................................................................2
1 Purpose.............................................................................................................................................................2
2 Scope ................................................................................................................................................................2
3 Utilization...........................................................................................................................................................3
4 Definitions .........................................................................................................................................................3
5 Predesign Phase...............................................................................................................................................4
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

6 Design Phase....................................................................................................................................................8
7 Construction Phase.........................................................................................................................................12
8 Occupancy/Occupation Phase........................................................................................................................16
Informative Annex A: Guide for Developing Supplementary Technical Guidelines for the
Commissioning Process ....................................................................................................................19
Informative Annex B: Commissioning Process Flow Chart ...................................................................................22
Informative Annex C: Cost and Benefits of the Commissioning Process..............................................................24
Informative Annex D: Commissioning Process Documentation Matrix .................................................................25
Informative Annex E: Commissioning Process Request for Qualifications ...........................................................28
Informative Annex F: Roles and Responsibilities ..................................................................................................31
Informative Annex G: Commissioning Plan...........................................................................................................33
Informative Annex H: Acceptance Plan.................................................................................................................34
Informative Annex I: Owner’s Project Requirements Workshop Guidance ...........................................................36
Informative Annex J: Owner’s Project Requirements............................................................................................38
Informative Annex K: Basis of Design (BoD).........................................................................................................42
Informative Annex L: Specifications ......................................................................................................................43
Informative Annex M: Construction Checklists......................................................................................................49
Informative Annex N: Quality-Based Sampling Examples ....................................................................................54
Informative Annex O: Systems Manual .................................................................................................................57
Informative Annex P: Training Manual and Training Needs..................................................................................59
Informative Annex Q: Addenda Description Information .......................................................................................65

NOTE

Approved addenda, errata, or interpretations for this guideline can be downloaded free of charge from the ASHRAE
Web site at www.ashrae.org/technology.

© 2013 ASHRAE
1791 Tullie Circle NE · Atlanta, GA 30329 · www.ashrae.org · All rights reserved.
ASHRAE is a registered trademark of the American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
ANSI is a registered trademark of the American National Standards Institute.
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This foreword is not part of this standard. It is merely Clear, concise, complete, and correct documenting of the
informative and does not contain requirements necessary OPR allows for emphasis on commissioning as an integral
for conformance to the standard. It has not been pro- process for achieving the facilities owner's expectations. The
cessed according to the ANSI requirements for a standard goal of a Guideline 0 Commissioning Plan is a fully func-
and may contain material that has not been subject to tional, fine-tuned facility, including all facility elements and
public review or a consensus process. Unresolved objec- assemblies, complete documentation, and a trained operating
tors on informative material are not offered the right to and maintenance staff at the significant completion milestone.
appeal at ASHRAE or ANSI.) It provides a methodology for implementing the commission-
ing process to building elements and assemblies for new con-
FOREWORD struction, and major renovations to existing facilities at a
level compatible with Owner input.
The latest version of Guideline 0 continues in demonstrat- A Guideline 0 Commissioning Plan places emphasis on
ing best practice principles for applying the whole-building documentation that transfers the OPR to the design criteria
commissioning quality process in facility elements. Guideline and construction documents, and on continuity of information
0 outlines the process for achieving, validating, and document- from one party to the next, providing value and the opportu-
ing the performance of facility elements in meeting the defined nity to improve the work process. The Guideline 0 Commis-
objectives and criteria of the Owner. This quality process sioning Plan also provides for the facility operating and
extends through all phases of new or major renovation proj- maintenance personnel training using actual performance
ects, from predesign to owner occupancy and operation, with documentation demonstrating the design, installation, and
tasks during each phase to ensure verification of design, con- intent of the building elements and assemblies in meeting the
struction, and operator training meeting the Owner's Project OPR. Owners can use this process in validating their stated
Requirements (OPR). Guideline 0 describes the overall com- objectives and criteria from the significant completion mile-
missioning process in providing a uniform, integrated, and stone onward. Application of this facility performance docu-
consistent approach for commissioning facilities. mentation provides the Owner with the opportunity to
This edition of Guideline 0 recognizes and addresses continue the benefits of whole-building commissioning in
changes in project delivery systems resulting from the evolu- improving facility performance during the post occupancy
tion of whole-building commissioning into the life cycle and phase and beyond.
sustainable facilities measurement and verification pro- Annexes to this guideline have been included to assist in
cesses. Guideline 0 is a guide to methods in performing, further understanding the commissioning process. Based on
measuring, validating, and documenting information in the specific project experiences, annexes suggest ways to improve
design and building processes used in constructing new current practices. Annexes illustrate varying applications of
facilities and renovating existing facilities. These commis- commissioning processes for all projects, and can be viewed
sioning processes are applicable to all building elements as examples for how to develop documents and to define
used in the construction process. owner's needs, design criteria, basis of design, design con-
Guideline 0 applies to all project delivery phases in iden- cepts, verification and functional performance testing
tifying and applying the whole-building commissioning pro- requirements, documentation, and operator training.
cesses, activities, and requirements for all building elements The commissioning process, beginning at project incep-
and assemblies. This guideline provides the format that serves tion, is a valuable tool to the Owner in controlling the project
as the pattern for the Commissioning Plan for specific facility through each milestone. Structuring the phases of a typical
elements or assemblies. This common content organization project around the OPR gives the Owner the advantage of
focuses on specific information in achieving a closely coordi- continuously monitoring the progress and the cost of the proj-
nated set of documents used together in any combination ect on a real time basis. This includes predesign, design
accommodating specific OPRs. Varying OPRs and applicable development, construction documents, construction, and
levels of commissioning follow a uniform method. Guideline 0 postconstruction phases.
organization also provides for technical commissioning This update of Guideline 0 describes the total building
guidelines that avoid repeating general commissioning pro- commissioning process and the responsibilities of the Commis-
cesses, activities, and requirements, making them more con- sioning Authority and the Owner. Selecting and developing a
cise in focusing on their technical subjects. Commissioning Plan following Guideline 0 assures the Owner
Guideline 0 acknowledges the integration and interdepen- of whole-building commissioning meeting the OPR, and a sus-
dency of facility elements; i.e., a performance deficiency of tainable facility at the time of final acceptance of the work.
one element can result in less than optimal performance by
other elements. To achieve satisfactory performance of the 1. PURPOSE
facility and all of its elements, the entire facility should experi- 1.1 The purpose of this guideline is to describe the Commis-
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ence commissioning beginning at the inception of the project. sioning Process capable of verifying that a facility and its sys-
This update of Guideline 0 emphasizes the important role tems meet the Owner’s Project Requirements (OPR).
of the Owner in determining the level and focus of the Com-
missioning Plan. This begins with more emphasis on defining 2. SCOPE
and clearly documenting the OPR in a Commissioning Plan 2.1 The procedures, methods, and documentation require-
detailing the Owner’s objectives in the work. ments in this guideline describe each phase of the project

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

delivery and the associated Commissioning Processes from cable regulatory requirements, standards, and guidelines. The
predesign through occupancy and operation, without regard document includes both narrative descriptions and lists of
to specific elements, assemblies, or systems, and provide the individual items that support the design process.
following:
checklists: Verification checklists that are developed and used
a. Overview of Commissioning Process Activities during all phases of the commissioning process to verify that
the Owner’s Project Requirements are being achieved. This
b. Description of each phase’s processes
includes checklists for general verification, plus testing, train-
c. Requirements for acceptance of each phase
ing, and other specific requirements.
d. Requirements for documentation of each phase
e. Requirements for training of operation and maintenance commissioning (Cx): See Commissioning Process.
personnel Commissioning Authority (CxA): An entity identified by the
Owner who leads, plans, schedules, and coordinates the com-
2.2 These Commissioning Process guideline procedures
missioning team to implement the Commissioning Process.
include the Total-Building Commissioning Process (TBCxP)
as defined by National Institute of Building Sciences (NIBS) Commissioning Plan (Cx Plan): A document that outlines
in its Commissioning Process Guideline 0. the organization, schedule, allocation of resources, and docu-
mentation requirements of the Commissioning Process.
3. UTILIZATION
Commissioning Process (Cx Process): A quality-focused pro-
3.1 The application of this guideline depends on the Owner’s cess for enhancing the delivery of a project. The process
Project Requirements and how the project is designed, built, and focuses on verifying and documenting that the facility and all
operated. The process described in this guideline is written for a of its systems and assemblies are planned, designed, installed,
generic project and must be adapted to each project. tested, operated, and maintained to meet the Owner's Project
3.2 This guideline describes the Commissioning Process, and Requirements.
is supplemented by companion technical guidelines. A tech- Commissioning Process Activities (Cx Process Activities):
nical guideline describes the specific details to properly Components of the Commissioning Process.
implement the Commissioning Process relative to a specific
facility system or assembly. Annex A in this guideline pro- Commissioning Process Progress Report (Cx Process Prog-
vides the required format for developing technical guidelines ress Report): A document that details activities completed as
for the Commissioning Process. part of the Commissioning Process and significant findings
from those activities, which is continuously updated during
4. DEFINITIONS the course of a project. Usually incorporated into the Com-
missioning Plan as an ongoing appendix.
acceptance: A formal action, taken by a person with appro-
priate authority (which may or may not be contractually Commissioning Process Report (Cx Process Report): A docu-
defined) to declare that some aspect of the project meets ment that records the activities and results of the Commission-
defined requirements, thus permitting subsequent activities to ing Process. Usually developed from the final Commissioning
proceed. Plan with all of its attached annexes.
Basis of Design (BoD): A document that records the con- Commissioning Team (Cx Team): The individuals who
cepts, calculations, decisions, and product selections used to through coordinated actions are responsible for implement-
meet the Owner’s Project Requirements and to satisfy appli- ing the Commissioning Process.

FIGURE 1 Relationship between commissioning guidelines.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

3
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

construction checklist: A form used by the contractor to ver- similar product, assembly, or system; or a random sampling
ify that appropriate components are on-site, ready for installa- that has scientific statistical basis.1, 2, 3
tion, correctly installed, and functional. Also see checklists. recommissioning: An application of the Commissioning Pro-
construction documents: These include a wide range of doc- cess requirements to a project that has been delivered using
uments that vary from project to project and with the Owner’s the Commissioning Process. This may be a scheduled recom-
needs and with regulations, laws, and countries. Construction missioning developed as part of an Ongoing Commissioning
documents usually include the project manual (specifica- Process, or it may be triggered by use change, operations
tions), plans (drawings), and general terms and conditions of problems, or other needs.
the contract. retrocommissioning: The Commissioning Process applied to
contract documents: These include a wide range of docu- an existing facility that was not previously commissioned.
ments that vary from project to project and with the Owner’s This guideline does not specifically address retrocommission-
needs and with regulations, laws, and countries. Contract doc- ing. However, the same basic process should be followed
uments frequently include price agreements, construction from Predesign through Occupancy and Operations to opti-
management process, subcontractor agreements or require- mize the benefits of implementing the Commissioning Pro-
ments, requirements and procedures for submittals, changes, cess philosophy and practice.
and other construction requirements, timeline for completion, systems manual: A system-focused composite document that
and the construction documents. includes the operation manual, maintenance manual, and
coordination drawings: Drawings showing the work of all additional information of use to the Owner during the Occu-
trades to illustrate that equipment can be installed in the space pancy/Operations Phase.
allocated without compromising equipment function or test procedure: A written protocol that defines methods, per-
access for maintenance and replacement. These drawings sonnel, and expectations for tests conducted on components,
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

graphically illustrate and dimension manufacturers’ recom- equipment, assemblies, systems, and interfaces among sys-
mended maintenance clearances. tems.
issues and resolution log: A formal and ongoing record of training plan: A document that details the expectations,
problems or concerns—and their resolution—that have been schedule, budget, and deliverables of Commissioning Process
raised by members of the Commissioning Team during the Activities related to training of project operating and mainte-
course of the Commissioning Process. nance personnel, users, and occupants.
nominal group technique: A formal, structured brainstorm- verification: The process by which specific documents, com-
ing process used to obtain the maximum possible ranked ponents, equipment, assemblies, systems, and interfaces
input from a variety of viewpoints in a short period of time. among systems are confirmed to comply with the criteria
The typical approach is a workshop session where a question described in the Owner’s Project Requirements.
is presented; the attendees record their responses individually
on a piece of paper; the individual responses are recorded on a 5. PREDESIGN PHASE
flip chart without discussion in a round robin fashion, all of 5.1 Introduction
the responses are discussed; and then the participants rank 5.1.1 Predesign is a preparatory phase of the project delivery
their top five responses. process in which the OPR is developed and defined. Informa-
Ongoing Commissioning Process (OCx): A continuation of tion about the project is gathered, including program require-
the Commissioning Process well into the Occupancy/Opera- ments, community context, codes and regulations, site and
tions Phase to verify that a project continues to meet current climate, facility context and function, facility technology, sus-
and evolving Owner’s Project Requirements. Ongoing Com- tainability, cost, schedule, and the client’s (including owner,
missioning Process Activities occur throughout the life of the occupants, operators, and maintenance personnel) needs and
facility; some of these will be nearly continuous in implemen- capabilities.
tation, and others will be either scheduled or unscheduled (as 5.1.2 This phase is critical to the Cx Process because the
needed). documented OPR forms the foundation for the design, con-
Owner’s Project Requirements (OPR): A document that struction, and occupancy and operation of the facility and are
details the functional requirements of a project and the expec- the basis for the Cx Plan and schedule. Starting the Cx Pro-
tations of how it will be used and operated. These include cess during the Predesign Phase facilitates project communi-
project goals, measurable performance criteria, cost consider- cation by monitoring the OPR from Predesign through
ations, benchmarks, success criteria, and supporting informa- Design, Construction, and Occupancy and Operations and by
tion. (The term Project Intent is used by some owners for their verifying decisions in these phases with the written docu-
Commissioning Process Owner’s Project Requirements.) ments called the Owner's Project Requirements and the BoD.
5.1.3 Predesign-Phase Cx Process objectives include the
quality-based sampling: A process for evaluating a subset following:
(sample) of the total population. The sample is based on a
known or estimated probability distribution of expected val- a. Developing the OPR
ues; an assumed statistical distribution based on data from a b. Identifying a scope and budget for the Cx Process

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

c. Developing the initial Cx Plan include testing soils, surveying, or other requirements during
d. Acceptance of Predesign-Phase Cx Process Activities Predesign.
e. Review and use of lessons-learned information from pre- 5.2.1.6 Responsibilities of the Cx Team during the Prede-
vious projects sign Phase include the following:
5.2 Predesign-Phase Cx Process Activities a. Assist Owner in preparing requests for project services
5.2.1 Predesign-Phase Cx Process Responsibilities that outline the roles and responsibilities developed in the
Cx Plan.
5.2.1.1 During the Predesign Phase, a Cx Team is formed
b. Facilitate development and documentation of the OPR.
to oversee, implement, and accomplish the Cx Process Activ-
c. Develop scope and format for project systems manual and
ities detailed in this guideline. Responsibility for leadership
select/designate entity responsible for developing this
of the Cx Team should be defined and assigned at the begin-
manual. Add this entity to the Cx Team where appropri-
ning of the Predesign Phase. The term used for the person
ate.
with overall responsibility for the Cx Process is “Cx Author-
d. Develop scope and budget for project-specific Cx Process
ity (CxA).” The Cx Team members must be available for
Activities.
meetings, have the qualifications to contribute to the develop-
e. Verify that Cx Process Activities are clearly stated in all
ment of the Owner's Project Requirements, and have the
project scopes of work.
authority to make decisions binding on the firms/constituen-
f. Integrate the Cx Process Activities into the project sched-
cies they represent. Lines of authority and lines of communi-
ule.
cation in determining Cx Team members’ responsibilities
g. Build and maintain cohesiveness and cooperation among
shall be documented. The Cx Team composition must be
the project team.
based on the scope of the Cx Process services established for
h. Coordinate Owner’s representative’s participation as
the project.
defined in Section 5.2.1.2.
5.2.1.2 The Owner must assign (or contract for) appropri- i. Conduct and document Cx Team meetings.
ate representatives to participate on the Cx Team, both from j. Identify who will accomplish the Cx Process Activities.
within and external to their organization. Cx Team responsi- k. Review Predesign-Phase documents for compliance with
bilities should be consistent with the agreements between par- the OPR.
ties involved in the project, and such agreements must clearly l. Write the initial Cx Plan.
address Cx Process responsibilities. m. Develop the initial format to be used for Issues and Reso-
5.2.1.3 Essential team members during the Predesign lution Logs throughout, and for each phase of, the Cx Pro-
Phase include Owner’s representatives, the CxA, predesign cess.
and programming professionals, design professionals, and (if n. Track and document issues and deviations relating to the
known) the construction/program/project managers. The CxA OPR and document resolutions in the Issues and Resolu-
can assist the Owner in identifying and selecting these initial tion Log.
Cx Team members. Owner's representatives will include the o. Write and review Cx Process Progress Reports.
project manager, occupants or users, facility manager, and
operation and maintenance personnel. Including operation 5.2.2 Develop OPR
and maintenance personnel on the Cx Team will help ensure 5.2.2.1 The OPR forms the basis from which all design,
that important operation and maintenance issues are included construction, acceptance, and operational decisions are made.
in the Owner's Project Requirements. The Owner will gener- An effective Cx Process depends on a clear, concise, and
ally need to reconcile conflicting project requirements and comprehensive OPR document. It includes information to
provide feedback on decisions to the Cx Team. The design help the project team to properly plan, design, construct,
team members and CxA can assist the Owner in reconciling operate, and maintain systems and assemblies.
conflicting technical requirements. 5.2.2.2 The CxA facilitates the development of the OPR.
5.2.1.4 The Cx Team will evolve as a project progresses. Input will be gathered from all team members.
During successive phases, the active membership of the Cx 5.2.2.3 Each item of the OPR shall have defined perfor-
Team may shift to meet the unique requirements of each mance and acceptance criteria. Those that can be bench-
phase. Contractors and vendors, for example, may join the Cx marked should have the benchmark defined in specific terms
Team after they are under contract or after the start of con- and the means of measurement defined.
struction. 5.2.2.4 The OPR should include the following:
5.2.1.5 Predesign-Phase Cx Process Activities described a. Project schedule and budget.
in this section to be performed by the design team must be b. Cx Process scope and budget.
included in the scope of services described in the “Owner- c. Project documentation requirements, including format for
Design Professional Service Agreement.” These Cx Process submittals, training materials, reports, and the systems
Activities may be more than are normally required in their manual. Consideration should be given to use of elec-
scope of services. The scope of services in the “Owner- tronic format documents and records where appropriate.
Design Professional Service Agreement” should also include d. Owner directives.
the requirement to cooperate with the CxA during Predesign, e. Restrictions and limitations.
Design, and Construction phases of the project. This may f. User requirements.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

5
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

g. Occupancy requirements and schedules. reports and workshop outcomes, and other activities in the
h. Training requirements for Owner’s personnel. Predesign Phase.
i. Warranty requirements. 5.2.3 Identify the scope and budget for the Cx Process.
j. Benchmarking requirements. 5.2.3.1 The scope of the Cx Process will vary from one
k. Operation and maintenance criteria for the facility that project to another. The Cx Team develops the scope for the
reflect the Owner’s expectations and capabilities and the Cx Process. The experiences of the programming team, users,
realities of the facility type. designers, CxA, and the Owner with similar and previous
l. Equipment and system maintainability expectations, facilities and projects can aid in establishing a scope for the
including limitations of operating and maintenance per- Cx Process. Additional insight regarding the scope of the Cx
sonnel. Process can be obtained from code officials, regulations, pub-
m. Quality requirements for materials and construction. lished information on similar facilities, and information in the
n. Allowable tolerance in facility system operations. technical Cx Process guidelines.
o. Energy efficiency goals. 5.2.3.2 A well-defined scope permits the establishment of
p. Environmental and sustainability goals. an appropriate budget allocation for the Cx Process. The Cx
q. Community requirements. Process budget should be realistic, distributed by phase, activ-
r. Adaptability for future facility changes and expansion. ity, and entity (Owner, CxA, design professional, and contrac-
s. Systems integration requirements, especially across disci- tors), and not subject to reduction without an express change
plines. in the Cx Plan. Lack of a properly defined and maintained Cx
t. Health, hygiene, and indoor environment requirements. Process budget will adversely affect the Cx Process and the
u. Acoustical requirements. success of the facility in meeting the OPR.
v. Vibration requirements. 5.2.3.3 Typically the Owner will focus the Cx Process
w. Seismic requirements. efforts on selected systems or assemblies based on the budget,
x. Accessibility requirements. systems or assemblies where the Owner has experienced pre-
y. Security requirements. vious problems, on complex systems and assemblies, or on
z. Aesthetics requirements. the criticality of the system or assembly in providing for the
aa. Constructability requirements. OPR. The Cx Process can focus on the following:
ab. Communication requirements. a. Substructure: includes basement and foundations
ac. Applicable codes and standards. b. Shell: includes superstructure, roof, walls, fenestration,
(See Table J-1 in Annex J for an example matrix that can and exterior doors
assist in the development of the OPR.) c. Interiors: includes interior construction, wall, floor, and
5.2.2.5 Obtaining the information and criteria for the ceiling finishes, partitions, interior doors, stairways, hard-
OPR document requires input from all key facility users and ware, and fitting specialties
operators. The method used to obtain the information should d. Services: includes controls, HVAC&R systems, electrical
allow the different user groups and operators to interact. systems, fire and life safety systems and assemblies, secu-
Nominal group technique workshops, interviews, and surveys rity systems, communication systems, plumbing systems,
can be used to obtain this input, with decreasing levels of conveying systems, and specialty or technology systems
interaction attained, respectively, for each type. See Annex I e. Equipment and furnishings
for additional guidance. f. Sitework
5.2.2.6 The OPR becomes part of the systems manual g. Landscaping
documentation.
5.2.4 Develop the Cx Plan
5.2.2.7 The OPR is a document that evolves through each
project phase. As decisions are made during the Design, Con- 5.2.4.1 The Cx Plan identifies processes and procedures
struction, and Occupancy/Operations Phases, this document necessary for a successful Cx Process. The Cx Plan addresses
will be updated to reflect the current project requirements of the OPR and reflects the defined scope and budget for the Cx
the Owner. It is the primary tool for benchmarking success Process.
and quality at all phases of the project delivery and through- 5.2.4.2 The Cx Plan includes a schedule of Cx Process
out the life of the facility. Activities, individual responsibilities, documentation require-
5.2.2.8 Make reference to the Owner's Project Require- ments, communication and reporting protocols, and evalua-
ments in the bidding documents as “information available to tion procedures. Evaluation procedures include the review
bidders.” It must be noted in the contract documents that the and verification to the OPR of the design documents, contract
OPR is issued for information only and that this document documents, construction and test procedures.
shall not define, nor shall it be used to interpret, the require- 5.2.4.3 The Cx Plan is continually updated during the life
ments of the contract. of a project to reflect changes in planning, design, construc-
5.2.2.9 Use quality-based sampling for verification of tion, and occupancy and operations. During the Predesign
each activity or task to determine how well it meets or relates Phase, the Cx Plan focuses on the scope of the Cx Process
to the OPR in the Predesign Phase. This includes program- during the Design Phase. The Construction-Phase and Occu-
ming documents, defined scope-of-design services, special pancy/Operations Phases are included, but details are usually

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

added during the Design Phase for the Construction and g. Description of the observed design, installation, or perfor-
Occupancy/Operations Phases (see Sections 6.2.3 and 7.2.5). mance issue, including any information that may be help-
5.2.4.4 The Cx Plan contains the following information: ful in diagnosing or evaluating the issue
h. Recommended corrective action, if apparent
a. Overview of the Cx Process developed specifically for the
i. Identification of the Cx Team member responsible for res-
project.
olution of the issue, if apparent
b. Roles and responsibilities for the Cx Team throughout the
project and specifically during the Predesign and Design j. Expected date of correction
Phases. The roles shall differentiate the areas with which k. Name of the person documenting the issue
each of the members is involved, and the responsibilities 5.2.5.3 Information to be documented when an issue is
shall detail the specific tasks that are to be completed by resolved includes the following:
the individual members.
c. Documentation of general communication channels to be a. Date of completion of resolution.
used throughout the project. Design-Phase procedures b. Description of corrective action taken. Include description
should be clearly documented during the Predesign Phase. of diagnostic steps taken to determine the root cause of
d. Detailed description of Cx Process Activities and a sched- the issue and the value of resolving the Cx Process issue
ule of activities during the Predesign and Design Phases. for the owner, design team, contractor, or occupant.
The milestones should include the Cx Team meetings, c. Identification of changes to the OPR or BoD that require
OPR development, design review periods, and the com- action (if any).
pletion of the BoD and the commissioning specifications. d. Statement that the correction was completed and the sys-
e. General description of Cx Process Activities that will tem or assembly is ready for retest, if applicable.
occur during the Construction and Occupancy/Operations e. Name of the person who resolved the issue.
Phases. f. Name of person documenting the issue resolution.
f. Guidelines and format that will be used to develop the Cx
Process documentation that facilitates communication 5.2.6 Prepare Issues Report
among the Cx Team and all other parties involved in the 5.2.6.1 On a periodic basis, at least for each Cx Team
project. meeting, a report shall be generated for review of outstanding
g. Cx Process forms that will be used during the Predesign issues. The following information should be included:
and Design Phases to communicate and track critical Cx
Process information. a. Issue number
h. Project design document verification procedures. b. Short, descriptive title of the issue
i. The framework for procedures to follow whenever Cx c. Date of the identification of the issue
Process verification does not comply with the OPR. d. Name of the Cx Team member assigned responsibility for
j. Quality-based sampling procedures for verification of resolution
compliance with the OPR during all project phases. e. Expected date of correction
5.2.4.5 If properly developed, the Cx Plan forms the core 5.2.7 Prepare Cx Process Progress Reports
of the Final Cx Process Report. 5.2.7.1 Cx Process Progress Reports are periodic reports
5.2.5 Establish Issues and Resolution Log Procedures of the status of Cx Process Activities throughout the project
5.2.5.1 An Issues and Resolution Log contains detailed and become part of the Cx Process Report. Cx Process Prog-
descriptions of design, installation, or performance issues that ress Reports should cover the following information:

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
are at variance with the OPR. Issues are identified and tracked a. Cx Process Activities completed since the last report,
as they are encountered during the design, construction, and including the current status of Predesign project activities.
operation of a facility. It is recommended that an Issues and b. Description of changes to the Cx Process schedule (e.g.,
Resolution Log be maintained with the status of all current early completion of or delays in work and early or late
and resolved issues. The information outlined in 5.2.5.2 and delivery of items that impact the Cx Process Activities),
5.2.5.3 should be documented in the log as a minimum. Cx Plan, and design, along with their effect on the OPR
5.2.5.2 Information to be documented at the time an issue and BoD.
is identified includes the following: c. Include new and outstanding issues and list those that
a. Unique numeric or alphanumeric identifier by which the have been resolved since the last Cx Process Progress
Report, including a brief description of actions taken to
issue may be tracked
resolve the issues. Also include planned activities to
b. Short, descriptive title of the issue
resolve outstanding issues expeditiously.
c. Date and time of the identification of the issue
d. Cx Process Activities anticipated during the period before
d. Test number of the test being performed at the time of the
the next Progress Report.
observation, if applicable, for cross-reference
e. Identification of system, equipment, or assembly to which 5.2.7.2 The frequency of Cx Process Progress Reports
the issue applies depends on the amount of work being accomplished and
f. Location of the issue could vary from every two weeks to every six months. A gen-

7
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

eral guide to follow is one progress report for every four Cx 6.1.4 Use quality-based sampling for verification of each
Team meetings. activity or task determined to be related to the OPR in the
Design Phase.
5.3 Predesign-Phase Acceptance Requirements
6.1.5 If the Cx Process on a particular project starts at the
5.3.1 During the Predesign Phase, the Cx Process should
Design Phase, then the Cx Process Activities described for
include the formal acceptance by the Owner of the OPR and
the Predesign Phase must be completed before the following
the Cx Plan.
Design-Phase activities are begun.
5.4 Predesign-Phase Documentation 6.2 Design-Phase Cx Process Activities
5.4.1 The Cx Process scope and budget, OPR, Cx Plan, 6.2.1 Design-Phase Cx Process Responsibilities
Issues and Resolution Log and reports, and Cx Process Prog-
6.2.1.1 During the Design Phase, the Cx Team works to
ress Reports are the primary documentation requirements for
verify that the construction documents meet and properly
the Predesign-Phase Cx Process.
convey the OPR.
5.4.2 The information in the OPR and the Cx Plan is used 6.2.1.2 Essential team members during the Design Phase
throughout subsequent project phases (including Occupancy include the Owner’s representatives, the CxA, design profes-
and Operations). sionals, and construction/program/project managers (if
5.5 Predesign-Phase Training Identification Requirements known).
5.5.1 Training requirements for facility, system, and assem- 6.2.1.3 Responsibilities of the Cx Team during the
bly operation and maintenance are addressed in the OPR. Design Phase include the following:
a. Build and maintain cohesiveness and cooperation among
6. DESIGN PHASE
the project team.
6.1 Introduction b. Assist Owner in preparing requests for project services
6.1.1 During the Design Phase of the project delivery pro- that outline the Cx Process roles and responsibilities
cess, the OPR is applied to the construction documents. A developed in the Cx Plan.
document called the BoD is created that clearly conveys the c. Verify that Cx Process Activities are clearly stated in all
assumptions made in developing a design solution that fulfills project scopes of work.
the intent and criteria in the OPR document. Narrative d. Develop the scope and budget for project-specific Cx Pro-
descriptions of facility systems and assemblies are developed cess Activities.
and included in the BoD, and the Cx Plan is expanded to e. Identify specialists who will be responsible for accom-
include the details of Construction and Occupancy/Opera- plishing the Cx Process Activities for specific systems and
tions-Phase activities. assemblies.
f. Conduct and document Cx Team meetings.
6.1.2 Design-Phase Cx Process objectives include the fol-
g. Inform all Cx Team members of decisions that result in
lowing:
modifications to the OPR.
a. Verifying the BoD document with the OPR document. h. Integrate the Cx Process Activities into the project schedule.
b. Updating the Cx Plan to include Construction and Occu- i. Track and document issues and deviations relating to the
pancy/Operations-Phase Cx Process Activities. OPR and document resolutions in the Issues and Resolu-
c. Developing Cx Process requirements for inclusion in the tion Log.
construction documents. j. Verify documentation and updating of the BoD.
d. Developing draft construction checklists. k. Develop construction checklists.
e. Updating the scope and format of the project systems l. Develop Construction and Occupancy/Operations-Phase
manual. test requirements.
m. Develop training program requirements.
f. Defining training requirements.
n. Document Cx Process requirements and integrate them
g. Performing commissioning-focused design review.
into the contract documents.
h. Acceptance of Design-Phase Cx Process Activities. o. Update the Cx Plan.
6.1.3 Design-Phase Cx Process Activities described in this p. Review Design-Phase documents for compliance with the
section that are to be performed by the design team and spe- OPR.
cial consultants must be included in the scope of services q. Update the OPR.
described in the “Owner-Design Professional Service Agree- r. Write and review Cx Process Progress Reports.
ment.” These Cx Process Activities may be more than are 6.2.2 Basis of Design (BoD) Documentation
normally required in their scope of services. The scope of ser-
6.2.2.1 The BoD, developed and updated throughout the
vices in the “Owner-Design Professional Service Agreement”
Design Phase, is required with each design submission and
should also include the requirement to cooperate with the
should include the following:
CxA during Predesign, Design, and Construction phases of
the project. This may include testing soils, evaluating or a. System and assembly options
checking existing conditions, surveying, or other require- b. System and assembly selection reasoning
ments during Design. c. Facility, system, and assembly performance assumptions
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

1. Assumptions for calculations/sizing 6.2.3.6 The communication protocols to be used during


2. Analytical procedures and tools the Construction-Phase and Occupancy/Operations Phase
3. Environmental conditions shall be clearly defined in the Cx Plan. This includes how the
4. Limiting conditions flow of information among the team members will be coordi-
nated and distributed.
5. Reference make and model
6.2.3.7 The Cx Process procedures to be implemented
6. Operational assumptions
during the Construction-Phase and Occupancy/Operations
d. Narrative system and assembly descriptions
Phase must be clearly documented in the Cx Plan. These
e. Codes, standards, guidelines, regulations, and other refer-
include the following:
ences
f. Owner guidelines and directives a. Review of submittals
g. Specific descriptions of systems and assemblies b. Scheduling and holding of meetings
h. Consultant, engineering, and architectural guidelines for c. Site visit procedures
design developed by the design team or others d. Issues identification, documentation, tracking, and resolu-
6.2.2.2 The BoD documents how each criterion in the tion
OPR is implemented in the design. For any criterion that e. Construction-Phase test preparation, implementation, and
could not be met, documentation detailing what was done, its follow-up
impact on the OPR, and how the OPR was modified shall be f. The responsibilities of each member of the Cx Team
included. g. Who is responsible for costs related to verification and
6.2.3 Update Cx Plan testing—including retesting or verification activities
h. Systems manual development and review
6.2.3.1 The Cx Plan must be updated to reflect changes in
i. Training program
the OPR and include additional information developed during
the Design Phase. j. Occupancy/Operations-Phase test preparation, implemen-
tation, and follow-up
6.2.3.2 During the Design Phase, the following is added
to or updated in the Cx Plan: 6.2.3.8 The test procedure requirements developed during
the Design Phase are general in nature, structure, and com-
a. Systems and assemblies to be verified and tested
plexity but must clearly convey the level and amount of test-
b. Schedule of Construction-Phase and Occupancy/Opera-
ing (see Section 7.2.9) required by manufacturers and
tions-Phase Cx Process Activities
contractors.
c. Roles and responsibilities of new Cx Team members
d. Construction-Phase and Occupancy/Operations-Phase 6.2.4 Cx Process Requirements in the Construction
documentation and reporting requirements, including pro- Documents
cedures and formats 6.2.4.1 The Cx Process requires that certain quality-
e. Construction-Phase and Occupancy/Operations-Phase assurance and quality-control procedures, envisioned in the
communication protocols Cx Plan, be performed as part of the construction contract.
f. Construction-Phase and Occupancy/Operations-Phase Cx 6.2.4.2 The OPR should be included in the contract docu-
Process procedures ments and labeled as for “Informational Purposes Only” to
6.2.3.3 The milestones to be incorporated in the schedule differentiate it from the contractor’s contractual obligations.
should include the prebid meeting, preconstruction meeting, In addition, as much BoD information should be included in
Cx Team meetings, training sessions, shop drawing submit- the contract documents as possible. This information is
tals, systems manual submittal, special tests or code official included in the contract documents to aid the contractors in
inspection and acceptance, tests, test periods, substantial understanding the design, material requirements, sustainabil-
completion, occupancy, seasonal testing, initial Cx Process ity and energy goals, and the desired use and intent of the
Report submittal, warranty review two months prior to end of facility. Such information aids in the successful implementa-
warranty period, lessons-learned meeting, and final Cx Pro- tion of the Cx Process but does not relate directly to the con-
cess Report. tract requirements.
6.2.3.4 The Construction-Phase and Occupancy/Opera- 6.2.4.3 Specific Cx Process requirements are included in
tions-Phase roles and responsibilities of the individual mem- the contract specifications. For this guideline, specification
bers of the Cx Team, including any new members, should be division numbers and section titles consistent with the Con-
clearly defined based on the unique experience and knowl- struction Specifications Institute MasterFormat® are used.
edge of the team members. Professional and services agree- This is done to simplify a lengthy list of specification require-
ments must be modified to reflect the scope of work. ments. Cx Process Activities that address systems and assem-
blies need to be included in Division 1 sections and those that
6.2.3.5 The Cx Plan must define the documentation that
address equipment and components should be included in
will be required as part of the Cx Process during the Con-
Divisions 2 through 16, as described further in the following:
struction-Phase and Occupancy/Operations Phase. This
includes the specific formats to be used (electronic/paper, a. The obligations to perform Cx Process Activities must be
software program and version), the information to be documented in the contract between the Owner and con-
included, the frequency of submittal, and the distribution. tractor.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

9
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

b. Detailed scope and responsibilities of the contractor shall 6.2.5.6 When a test data form is required for a specific
be included in the “Summary of Work” section in Divi- system or assembly, there should be an item in the associated
sion 1. construction checklist for the test data form to be submitted to
c. The Cx Process requirements for documentation, training, the CxA.
and testing facility systems and assemblies are integrated 6.2.5.7 Construction checklists should be kept as short as
into commissioning sections in Division 1. possible and the questions should be worded clearly so that
d. Specific equipment and component performance docu- the correct answer is typically yes.
mentation requirements and use of construction checklists
6.2.5.8 Construction checklists are used by the Cx Team
should be integrated into specification sections in Divi-
to verify that the installation meets the OPR. They can also be
sions 2 through 16, with appropriate cross-references.
used by the contractors to track progress of construction
6.2.4.4 The Cx Process Activities to be integrated include against the schedule of values.
the following: 6.2.5.9 Annex M contains sample formats for construc-
a. Performance, installation, and operations information tion checklists.
requirements as part of shop drawing submittals in Divi- 6.2.6 Systems Manual
sions 2 through 16 sections 6.2.6.1 The systems manual should provide the informa-
b. Completion of construction checklists in Division 1 and tion needed to understand, operate, and maintain the systems
references to Division 1 in Divisions 2 through 16 sec- and assemblies and to inform those not involved in the design
tions and construction process about the systems and assemblies.
c. Contractor involvement in the Cx Team in Division 1 The systems manual should be the repository of information
d. Test requirements in Division 1 on updates and corrections to systems and assemblies as they
e. Training program development and implementation occur during the Occupancy/Operations Phase.
requirements in Division 1 6.2.6.2 The systems manual expands the scope of the tra-
f. Systems manual requirements in Division 1 ditional operating and maintenance documentation to include
the additional information gathered during the Cx Process
6.2.4.5 A guide specification section template for general
and to provide a systems-based organization of information.
Cx Process requirements in Division 1 is included in Annex L.
6.2.6.3 Contractor documentation requirements for the
6.2.5 Construction Checklists
systems manual shall be clearly stated in the construction
6.2.5.1 Construction checklists aid the installers by pro- documents.
viding specific information on the OPR for equipment and
6.2.6.4 The following should be included in the systems
assemblies for long-term operation. Checklists typically
manual (see Annex O for an example format):
include the following:
a. Equipment/assembly verification a. Index of systems manual with notation as to content stor-
b. Preinstallation checks age location if not in actual manual
c. Installation checks b. Executive summary
d. Any negative responses c. OPR
d. BoD documents
6.2.5.2 The first section of the checklist is equipment/ e. Construction record documents, specifications, and
assembly verification. This section should include vital infor- approved submittals
mation on the equipment or materials being supplied (specific
f. A list of recommended operational record-keeping proce-
listings of vital information are included in the technical
dures, including sample forms, logs, or other means, and a
guidelines developed for various facility systems). This sec-
rationale for each
tion contains information on what equipment/material was
g. Ongoing optimization guidance
specified/submitted and space to document/verify what was
h. Operations and maintenance manuals (includes operating
actually delivered to the site.
procedures for all normal, abnormal, and emergency
6.2.5.3 The preinstallation section of the checklist is used modes of operation; maintenance procedures; parts and
to verify the condition of the equipment/material at the site recommended spare parts list; troubleshooting guide; and
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

immediately prior to its installation. systems schematics (one-line diagrams)


6.2.5.4 The installation section of the checklist is used to i. Training materials
verify proper installation. This section focuses on the ability j. Cx Process Report
of the installation to meet the construction documents and the
OPR. For equipment, this section focuses on the physical 6.2.7 Training Requirements
installation and its start-up when applicable. For assemblies, 6.2.7.1 During the Design Phase, the training require-
the focus is typically on installation and performance. ments of the operations and maintenance personnel and occu-
6.2.5.5 The negative responses section is a space pro- pants are identified relative to the systems and assemblies to
vided to document the reason for any negative responses and be installed in the facility. It is critical that the operations and
whether any action has been taken to correct the problem or maintenance personnel have the knowledge and skills
problems that led to the negative responses. required to operate the facility to meet the OPR. The occu-

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

pants need to understand their impact on the use of the facility f. Repair procedures: instructions for diagnosing problems
and its ability to meet the OPR. and for disassembly, component removal, replacement,
6.2.7.2 These training requirements can be obtained and reassembly
using a nominal group technique workshop, interviews, or g. Upkeep of the systems manual and associated mainte-
surveys. The requirements are obtained after the systems and nance documentation and logs
assemblies have been decided on, and prior to issuance of the 6.2.7.8 In the specifications, as a minimum, define the
construction documents, to ensure that the requirements for time requirements for each type of system/assembly that
training are clearly conveyed in the construction documents. requires demonstration and training or include an allowance
The results of the workshop, interviews, or surveys should for demonstration and training capabilities. Also include the
address the following: expected experience and knowledge of trainer, the number of
a. The systems, subsystems, equipment, and assemblies for unique training sessions, the need for repeating the training
which training will be required. for multiple shifts, and submittal of training plan, handouts,
b. The capabilities and knowledge of the occupants and record of the training, and electronic recording of on-site
operations and maintenance personnel. training.
c. The number and type of training sessions. The training 6.2.7.9 Training materials should include or utilize the
program should be organized into a series of instructional following items:
modules, each covering a portion of the facility's systems,
a. Copy of the training plan including schedule, syllabus,
equipment, and assemblies.
and agenda
d. Measurable learning objectives and teaching outlines
b. Systems manual
should be developed to clearly describe the specific skills
c. Manufacturers’ training manuals
and knowledge that the participant is expected to master.
d. Electronic media or videotapes of manufacturers’ or ven-
6.2.7.3 The first training session should be general in dors' training and service materials
nature for the operations and maintenance personnel and the
6.2.8 Review of Design Professional Submittals
occupants, and it should review the OPR and the BoD. This
provides the background on why the facility is being con- 6.2.8.1 Complete targeted design reviews at strategic
structed and its limitations. times during the Design Phase. All design issues should be
resolved before continuing with design.
6.2.7.4 The majority of training should be planned to be
accomplished during the Construction Phase and prior to sub- 6.2.8.2 A targeted design review is composed of four
stantial completion. tasks:
6.2.7.5 Training during the Occupancy/Operations Phase a. General quality review of the documents, including legi-
may be required for certain systems and assemblies to achieve bility, consistency, and level of completeness.
or maintain the OPR. b. Coordination between disciplines.
6.2.7.6 The systems manual has a close functional rela- c. Discipline-specific review for achieving the OPR.
tionship with personnel training. A meaningful and useful d. Specification applicability and consistency with OPR and
training program typically includes using the operation and BoD.
maintenance components of the systems manual as the basis
6.2.8.3 The general quality of the documents is evaluated
of development.
by checking for consistent layout and legibility of the design
6.2.7.7 Review of documentation during training consists professional submittal and construction documents. Compli-
of reviewing the content of emergency, operation, and mainte- ance with the OPR along with ease of use and clarity are the
nance information in the systems manual, project record doc- major issues to check when looking at the complete package.
uments, system and equipment identification systems, This review looks for completeness of the drawings and for
warranties, and maintenance service agreements contained in items of concern identified during previous reviews.
the systems manual. Training should specifically address:
6.2.8.4 Sample areas of the facility, 10-20% of the total
a. Emergency instructions and procedures: those required area, are reviewed in detail to evaluate the coordination
for operating the facility during various emergencies, accomplished within and among disciplines. This includes
including step-by-step instructions for each type of emer- reviewing for constructability and interfaces among disci-
gency plines. The intent of this review is to determine if there are
b. Operation instructions and procedures: the procedures systematic errors, not to fully check the drawings. The
required for normal operation of the facility, including responsibility for complete checking of the drawings for coor-
step-by-step instructions for day-to-day operation dination and accuracy remains with the design team
c. Adjustment instructions: information for maintaining 6.2.8.5 A discipline-specific review involves a review of
operational parameters the construction documents along with the BoD, design cal-
d. Troubleshooting procedures: instructions for diagnosing culation assumptions, and methods for compliance with the
operating problems and procedures for testing and OPR. A sampling strategy of focusing on 10-20% of the
inspecting drawings provides for an in-depth analysis and evaluation of
e. Maintenance and inspection procedures the ability of the documents to meet the OPR.

11
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

6.2.8.6 A review of the specifications is performed to described in the “Owner-Design Professional Service Agree-
determine completeness and applicability to the project. A ment.” These Cx Process Activities may be more than are
review of 10-20% of the specification is performed in detail normally required in their scope of services. The scope of ser-
for verification of compliance with the OPR. Items checked vices in the “Owner-Design Professional Service Agreement”
include applicability of the section to the project, Cx Process should also include the requirement to cooperate with the
requirements, submittal requirements, applicability of equip- CxA during Predesign, Design, and Construction phases of
ment, training requirements, and coordination with other sec- the project. This may include material testing, TAB, perfor-
tions. mance tests, records, photography, outside training, Owner’s
6.2.8.7 See Annex N for additional guidance on how to furnished equipment vendors, and other requirements during
accomplish quality-based design reviews. the Construction Phase.
7.1.4 If the Cx Process on a particular project starts at the
6.3 Design-Phase Acceptance Requirements Construction Phase, Cx Process Activities described for the
6.3.1 The Cx Process should include the formal acceptance Predesign and Design Phases must be completed before the
by the Owner of the BoD and the updated OPR during the following Construction-Phase activities are begun.
Design Phase, following review and comment by the CxA.
7.2 Construction-Phase Cx Process Activities
6.4 Design-Phase Documentation Requirements 7.2.1 Construction-Phase Cx Process Responsibilities
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

6.4.1 Construction document commissioning requirements, 7.2.1.1 During the Construction Phase, the Cx Team
updated OPR, updated Cx Plan, the updated Issues and Reso- works to verify that systems and assemblies are installed in a
lution Log, and the Cx Process Progress Reports are the pri- manner that will achieve the OPR.
mary documentation requirements for the Design-Phase Cx 7.2.1.2 Use quality-based sampling for verification of
Process. each task and test determined to be related to the OPR during
6.4.2 The information in these deliverables is used through- the Construction Phase. (See Annex N for additional guid-
out subsequent project phases (including Occupancy and ance.)
Operations). 7.2.1.3 Conduct and document regularly scheduled Cx
6.5 Design-Phase Training Identification Requirements Team meetings to facilitate coordination and cooperation in
6.5.1 Training requirements for facility, system, and assem- delivering a facility that meets the OPR.
bly operation and maintenance are addressed during the 7.2.1.4 Essential team members during the Construction
Design Phase by the completion of a training requirements Phase include Owner’s representatives, the CxA, design pro-
identification workshop, development of the Construction- fessionals, contractors, suppliers/vendors, and construction/
Phase and Occupancy/Operations-Phase training program, program/project managers.
and inclusion of the training program requirements in the Cx 7.2.1.5 Responsibilities of the Cx Team during the Con-
Plan and construction documents. struction Phase include the following:
a. Participate in the prebid conference.
7. CONSTRUCTION PHASE
b. Coordinate participation of Owner’s representatives.
7.1 Introduction c. Identify specialists who will be responsible for accom-
7.1.1 During the Construction Phase of the project delivery plishing the Cx Process Activities for specific systems and
process, systems and assemblies are installed, inspected, assemblies.
tested, and placed into service to meet the Owner's Project d. Update the OPR to reflect decisions made during bidding
Requirements. This phase may also include bidding, negotia- and construction.
tion, and contracting activities. The systems manual is deliv- e. Update the Cx Plan.
ered during this phase and training is provided. f. Conduct a preconstruction Cx Process meeting.
g. Review the following submittals for compliance with the
7.1.2 Construction-Phase Cx Process objectives include the
OPR: coordination drawings, shop drawings, product
following:
data, preliminary systems manual, and training program.
a. Updating the OPR h. Schedule the Cx Process Activities and integrate them
b. Updating the Cx Plan into the project construction schedule.
c. Verifying that submittals meet the OPR i. Address schedule changes.
d. Developing detailed test procedures and data forms j. Develop and document test procedures and data forms.
e. Verifying that systems and assemblies comply with the k. Conduct and document ongoing Cx Team meetings.
OPR l. Monitor compliance with the OPR through periodic site
f. Delivering the systems manual visits.
g. Verifying training of the Owner’s operation and mainte- m. Verify completion of items indicated in the construction
nance personnel and occupants. checklists.
n. Witness tests.
h. Acceptance of Construction-Phase Cx Process Activities
o. Verify tests.
7.1.3 Construction-Phase Cx Process Activities described p. Verify test data reports.
in this section that are to be performed by the design team and q. Verify training of operation and maintenance personnel
special consultants must be included in the scope of services and occupants according to the OPR.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

r. Identify, diagnose, and track issues and deviations relating 7.2.6 Conduct Preconstruction Cx Process Meeting
to the OPR and document resolution of same. 7.2.6.1 Early in the Construction Phase, the CxA shall
s. Write and review Cx Process Progress Reports. conduct a preconstruction Cx Process meeting with the Cx
t. Review construction progress reports. Team.
u. Verify incorporation of new equipment and systems into 7.2.6.2 During the preconstruction meeting, the OPR,
the maintenance management program. BoD, and unique contract document requirements are
v. Verify updates to the BoD documentation. reviewed. In addition, the specific roles and responsibilities of
w. Verify updates to the systems manual. the contractors relative to the Cx Process Activities are
x. All Cx Team members are responsible for keeping the Cx reviewed.
Team informed of decisions that result in modifications to 7.2.7 Verify Submittals
the OPR.
7.2.7.1 It is recommended that a sampling strategy of ran-
y. Review contract modifications for compliance with OPR.
domly selecting 5% to 10% of the submittal be used to focus
7.2.2 Prebid Conference on the quality and ability of the submittal to achieve the OPR.
7.2.2.1 Time should be allotted during the prebid confer- If deviations are substantial, then review an additional 5% to
ence for the Cx Team to alert bidders to Cx Process require- 10%. If substantial deviations still exist, then reject the sub-
ments with which they may not be familiar. mittal and return it with comments. (See Annex N for addi-
tional guidance.)
7.2.3 Coordinate Owner’s Representatives Participation
7.2.7.2 Concurrent with design team and Owner review, a
7.2.3.1 Coordinate and schedule participation of Owner’s
designated Cx Team member reviews coordination drawings,
representatives in Cx Process Activities. Owner representa-
shop drawings, and project submittals for compliance with
tives may vary from one activity to another, both in number
the OPR. Special attention must be paid to substitutions and
and in the specific individuals. It is important for Owner’s
proposed deviations from the contract documents and the
representatives to participate in Cx Team meetings, review of
commissioning process reports, discussions of changes to the BoD that could adversely impact the OPR.
OPR, and staff and occupant training. Other Cx Process 7.2.7.3 Upon receipt, designated members of the Cx
Activities in which Owner’s representatives typically partici- Team shall review the systems manual for compliance with
pate include reviewing submittals and witnessing testing. the contract documents and the OPR.
7.2.4 Update OPR 7.2.7.4 Review training program, materials, and sched-
7.2.4.1 Changes to the OPR during bidding and the Con- ule, and monitor delivery of training to verify that it meets the
struction Phase may be initiated as the result of Owner- OPR for the preparation of operations and maintenance per-
directed changes to the OPR or design/construction process- sonnel.
initiated changes to the construction documents. 7.2.7.5 Training records are reviewed by designated
7.2.4.2 When the Owner initiates a change to the OPR, members of the Cx Team for proper documentation of attend-
the design shall be modified and reviewed as necessary to ees, material covered, and associated details.
meet the change. 7.2.8 Schedule Cx Process Activities
7.2.4.3 When the Owner considers changes initiated 7.2.8.1 The objective of scheduling Cx Process Activities
through the design/construction process, the Cx Team should is to integrate and coordinate them with other Construction-
review the proposed changes to determine if they compromise Phase activities and to allow all Cx Team members to plan
the OPR, paying special attention to the functional impacts of their work to achieve the OPR. Cx Process Activities should
value management proposals. If the Owner chooses to initiate be integrated into the construction schedule. Detailed integra-
a change after reviewing the Cx Team’s comments, the OPR tion of commissioning work with the construction schedule is
must be updated as necessary to match the change. critical to maintaining project schedule milestones.
7.2.5 Update the Cx Plan 7.2.8.2 The project schedule needs to include the start
7.2.5.1 Update the Cx Plan to include new or revised date, duration, description, and entity responsible for comple-
descriptions of Cx Process Activities during the Construction tion.
Phase. Incorporate the following: 7.2.8.3 As a minimum, the following should be included
in the project schedule:
a. Test procedures and data forms developed during the Con-
struction Phase. a. Cx Team meetings
b. Refinement and integration of Cx Process Activities in the b. Start and completion of each Construction Phase
construction schedule. c. Key system and assembly completion and tests
c. Roles and responsibilities of the Cx Team during the Con- d. Training sessions
struction Phase, including the identification of new team e. Substantial completion
members. f. Warranty start date
d. Identification of specialists responsible for accomplishing g. Occupant move-in
Cx Process Activities for specific systems and assemblies. h. Warranty review two months prior to end of warranty
e. Changes to the communication channels and procedures period
to be used during the Construction Phase. i. Lessons-learned meeting

13
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

7.2.9 Develop Test Procedures d. Identification of the system, equipment, or assembly


7.2.9.1 Test procedures define the means and methods to under test. List the location and the construction docu-
carry out the tests that are accomplished during the Construc- ment designation. Include the sampling strategy to be
tion-Phase. Test procedures provide the following: used for the test.
e. Conditions under which the test was conducted. For
a. Participants required for the test, which may include the
example, when testing, fully describe the ambient condi-
primary contractor, secondary contractors, design profes-
tions, setpoints, overrides, and the status and operating
sionals, the CxA, operators, the local authority having
condition of devices, systems, and equipment that impact
jurisdiction, and manufacturers associated with the equip-
the results of the test.
ment, system, or assembly.
b. Prerequisites for the test performance in terms of comple- f. Expected performance of the systems and assemblies at
tion of systems and assemblies and acceptable completion each step of the test.
of other activities. g. Observed performance of the system, equipment, or
c. Step-by-step instructions to exercise the specific systems assembly at each step of the test. When data forms are
and assemblies under test. Instructions include how to used, check boxes generally do not adequately describe
configure the system or assembly to start the test and how the system performance and therefore should be avoided
to restore the system to normal operation at the conclusion in most cases. A blank space in which the observed or
of the test. measured performance may be described provides more
d. List of instrumentation, tools, and supplies required for information for diagnostics and a future baseline for per-
the test. The list should indicate which of the participants formance.
is responsible for each of the items listed. The list should h. Notation to indicate whether the observed performance at
be specific as to make, model, range, capacity, accuracy, each step meets the expected results.
calibration, and other pertinent performance requirements. i. Other observations about system performance or test pro-
e. An indication, for each step of the procedure, of what cedure.
observations or measurements must be recorded and the j. Issue number, if any, generated as a result of the test.
range of acceptable results.
k. Dated signatures of the person performing the test and of
7.2.9.2 The Cx Team will develop a range of test verifica- the witness, if applicable.
tion procedures. These procedures include the following:
7.2.11 Cx Team Meetings
a. Component test procedures: verify the performance of 7.2.11.1 Consistent, periodic Cx Team meetings are
components under a full range of actions, responses to
essential to maintaining the progress of the project.
inputs, and loads.
b. System/assembly test procedures: verify the performance 7.2.11.2 The schedule of meetings should be documented
of subsystems, systems, and assemblies under a full range as early as possible during the Construction Phase and
of operating conditions (both normal and emergency), updated as required due to schedule changes. The meeting
responses to inputs, and loads. dates and times should be known a minimum of two weeks in
c. Intersystem test procedures: verify the interactions advance and should be coordinated with other meetings to
between systems and assemblies. minimize travel time and costs for various attendees.
d. OPR test procedures: verify that the various systems and 7.2.11.3 Team members represented at the meeting must
assemblies that comprise the facility deliver the intended be authorized to make commitments and decisions for their
OPR at the point of use. respective organizations to facilitate an effective Cx Team
e. Use quality-based sampling for verification of each test meeting.
determined to be related to the OPR. (See Annex N for 7.2.11.4 Prior to a meeting (usually a minimum of three
additional guidance.) days) an agenda should be distributed to all invited attendees.
7.2.9.3 In developing the test procedures, special atten- The agenda should include the following:
tion must be paid to issues of personnel safety, equipment/
a. Meeting location
assembly protection, and manufacturer’s recommendations to
protect the validity of the warranty. b. Start time
7.2.10 Develop Test Data Records c. List of invited attendees
d. List of items to cover (previous action items, outstanding
7.2.10.1 Test data records capture test data, observations,
and measurements. Data may be recorded on photographs, issues, schedule review, new issues, and other business)
forms, or other means appropriate for the application. The along with defined time allotments for each item
following minimum information should be recorded: e. End time
f. Attachments, if applicable
a. Test number.
b. Date and time of the test. 7.2.11.5 The meeting time and duration should be strictly
c. Indication of whether the record is for a first test or retest adhered to. This will set the tone for other Cx Process Activi-
following correction of a problem or issue. ties.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

7.2.11.6 Within a reasonable and established period (fre- 7.2.13 Test Execution
quently, three days) after the meeting, distribute meeting 7.2.13.1 During test execution there can be witnessing of
notes or minutes. This should include the following: tests, verification of tests, or verification of test data reports.
a. Date, time, and location of the meeting Typically, only one of these is performed by the CxA for a
specific test or series of tests. However, depending on the type
b. List of attendees
and complexity of the test, it is possible in some cases to wit-
c. Resolved action items and issues
ness a portion of the test, verify the test through a random
d. Outstanding action items and issues, including clear iden- sampling of components, and verify the test data report
tification of the responsible party and due dates through random sampling of the reported results.
e. Date, time, and location of the next meeting
7.2.13.2 Completion of tests should comply with the fol-
7.2.12 Accomplish Periodic Site Visits to Verify Compli- lowing:
ance with the OPR a. Tests shall be performed according to approved written

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
7.2.12.1 Site visits are the primary method used during procedures. Results of test performance shall be recorded
the Construction Phase to verify that the installed systems and on the test data forms and witnessed.
assemblies comply with the OPR. b. Deviations from the approved procedures, if permitted,
7.2.12.2 A clear, concise, and consistent procedure must should be documented in writing.
be followed for each site visit to properly identify Construc- c. Test data should be recorded under steady-state and stable
tion-Phase process problems and issues. conditions.
7.2.12.3 The site visit procedure uses statistical sampling d. If an issue is observed during a test, the test should be ter-
techniques for verification of the construction checklists and minated, within the scope of the contract. An issue report
record documents. This provides assurance that the verifica- is created at the time of observation. If the issue cannot be
tion process is not biased and has reliable consistency. The resolved within a reasonable time period, it may be
recommended procedure has the following general steps: required to run the test immediately, with the understood
options to run the test later, after all issues are resolved.
a. Identify the current state of construction to define the e. If an issue is discovered during review of the data, the
scope of systems and assemblies that can be verified. The issues shall be resolved or the test repeated in its entirety.
construction checklists completed since the previous site f. Upon completion of the test, the technician performing
visit provide one way to define this scope. the test and the witnesses sign the test data record, attest-
b. Randomly select between 2% and 10% of the systems and ing to the verity of the recorded observations.
assemblies identified for verification. This can be accom-
7.2.13.3 Generally, the sequence of testing will be exe-
plished by randomly selecting a starting point and selecting
cuted in the order of activities listed:
every tenth item from a list or by automatically generating a
random sample from a computerized database. a. The verification of the construction checklists begins with
c. Identify Cx Team members for the site visit. equipment or assembly delivery and continues through
d. Review OPR. start-up and testing.
e. Accomplish verification. This task is completed by going b. Tests verifying system and intersystem performance
to the selected system or assembly and comparing the according to the OPR cannot begin until the construction
installation to the completed (full or partial) construction checklists have been verified and accepted by the Cx
checklists. Any negative responses should be reviewed in Team.
detail. c. Other sequencing requirements, depending on the specific
f. Any consistent problems with the installation identified system, may be required to ensure the proper conditions
(typically more than 10% of the sample has the same are present or can be created.
issue), including record documents, are documented in d. A specified test is run according to contract documents or
general terms and provided to the contractor for resolu- to manufacturer’s requirements.
tion. The contractor is then responsible for 100% check- 7.2.14 Verify Training
ing of all affected systems or assemblies and making 7.2.14.1 Within a reasonable period (such as three weeks)
corrections as required. of each training program, between 5% and 10% of the train-
g. Any inconsistent problems (one or two occurrences) are ees shall be randomly selected and tested or informally evalu-
sent to the contractor, detailing the specific component, ated on the material covered in the specific program. The
system, or assembly for resolution. intent of this testing is to verify that the trainees were pro-
h. Meet with contractors to discuss any issues identified and vided with the pertinent information to operate and maintain
the general progress of the project. the facility according to the OPR.
i. Meet with the Owner’s representative to review the find- 7.2.14.2 It is not typically expected that the trainees will
ings, project schedule, and outstanding issues. have memorized everything from the training session but that
j. Develop a site visit report and distribute to the Cx Team they know where the information is, can find it, and under-
members and other interested parties. stand sufficiently to walk through the key steps to trouble-
k. Update the Issues and Resolution Log. shoot a problem and resolve it.

15
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

7.2.14.3 Attendee sign-in sheets should be used to verify 7.2.16 Verify Systems Manual Update
that training was delivered to the intended people. 7.2.16.1 Verify that the systems manual is updated to
7.2.15 Construction-Phase Cx Process Report incorporate materials generated during the Construction
7.2.15.1 The Construction-Phase Cx Process Report is Phase. Materials that should be added are:
the documentation of the commissioning work and results a. Test procedures and test data records
accomplished during the Construction Phase. The Construc-
b. Training plans
tion-Phase Cx Process Report contains the following:
c. Training records
a. Identification of any systems or assemblies that do not d. Record Drawings
perform in accordance with the OPR. For various reasons, e. Submittal review reports
the Owner may choose to accept performance that is at f. Updated OPR
variance with the OPR, either permanently or until sched- g. Updated BoD
ule and budget constraints allow for correction. The h. Updated Cx Plan
Owner’s acceptance of these conditions should be docu- i. Updated Issues and Resolution Log
mented along with the environmental, health, safety, com-
j. Cx Process Progress Reports
fort, energy, and operating and maintenance cost impacts.
The OPR must be updated to match the revised expecta- 7.2.17 Verify Update of the BoD
tions. 7.2.17.1 Verify that the BoD is updated to reflect any
b. Evaluations of the operating condition of the systems at changes to the design during the Construction Phase. Verify
the time of test completion. that design changes comply with the OPR. If necessary,
c. Construction checklist completion and verification sum- update the OPR.
mary.
7.3 Construction-Phase Acceptance Requirements
d. Results from the Issues and Resolution Log, including the
descriptions of issues and the measures taken to correct 7.3.1 The Cx Process should include the formal acceptance
them. The description should assess the importance of the by the Owner of the systems manual, verified test reports, and
issues and estimate the value of their correction in terms training reports, consistent with the recommendations of the
of environmental impact, improved health, safety, com- CxA and appropriate other Cx Team members.
fort, energy consumption, operating and maintenance 7.4 Construction-Phase Documentation Requirements
costs, and the ability of the facility to support its mission.
7.4.1 The primary Cx Process requirements for documenta-
e. Test procedures and data. This section should incorporate tion during the Construction Phase include the Construction-
the original test procedures and signed data forms, includ- Phase Cx Process Report and commissioning elements of the
ing additional data such as photos, computerized documen- systems manual.
tation, and other records of the tests. Data should include
the final accepted test, as well as earlier tests that failed to 7.4.2 The information in these deliverables is used through-
meet the specified criteria. This section should also include out the Occupancy/Operations Phase.
a set of blank data forms for future use in the Ongoing Cx 7.5 Construction-Phase Training Requirements
Process and Recommissioning. 7.5.1 The Cx Process training requirements for the Con-
f. Cx Process Progress Reports. Copies of progress reports struction Phase are discussed in Section 7.2.14.
generated throughout the Cx Process.
g. Deferred tests. Execution of some tests may be deferred 8. OCCUPANCY/OPERATIONS PHASE
until appropriate natural loads, such as occupancy or
8.1 Introduction
design weather conditions, are available. For these
deferred tests, the prerequisite conditions and an esti- 8.1.1 The Occupancy/Operations Phase of the Cx Process
mated schedule for their completion should be included. begins at substantial completion. As a minimum, the Cx Pro-
h. Lessons learned. Evaluation of the Cx Process used and cess Activities begun at this point should continue through the
changes that will improve the delivered project and form end of the contractual warranty/correction period and ideally
the basis for the Final Cx Process Report developed dur- continue throughout the life of the facility. During the Occu-
ing the Occupancy/Operations Phase. This is essential to pancy/Operations Phase, the ongoing operation, maintenance,
ensure that issues, benefits, and recommendations are cap- and modification of the facility systems and assemblies, and
tured in a written document while all team members are their associated documentation, are verified against the
available and information is fresh. updated OPR.
8.1.2 The active involvement of the CxA and Cx Team dur-
7.2.15.2 A draft Construction-Phase Cx Process Report ing the initial portion of the Occupancy/Operations Phase of a
should be submitted for Owner review. Submittal of the draft project is an integral aspect of the Cx Process.
Cx Process Report to other Cx Team members may also be
appropriate. 8.1.3 Occupancy/Operations-Phase Cx Process objectives
include the following:
7.2.15.3 The final Construction-Phase Cx Process Report
should incorporate review comments from the Owner and, a. Using the CxA’s project knowledge and experience to
optionally, from other Cx Team members. minimize contractor callbacks
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

b. Providing ongoing guidance on operations and mainte- he/she has the ability to identify which contractors should be
nance to achieve the OPR contacted to resolve an issue.
c. Completing seasonal testing of facility systems and 8.2.3 Verification of the performance of all systems and
assemblies assemblies being commissioned should be completed during
d. Documenting lessons learned from applying the Cx Pro- the Construction Phase. However, certain weather conditions,
cess for application to the next project load conditions, or occupant interactions are required to com-
e. Acceptance of Occupancy/Operations-Phase Cx Process plete some verification activities. Such deferred performance
Activities verification shall be conducted at an appropriate time, and
8.1.4 Occupancy/Operations-Phase Cx Process Activities under appropriate conditions, as early as possible after occu-
described in this section that are to be performed by the pancy.
design team and special consultants that must be included in 8.2.4 Training of the Owner’s operation and maintenance
the scope of services described in the “Owner-Design Profes- personnel on the fundamentals of facility and system/assem-
sional Service Agreement.” These Cx Process Activities may bly operations and the occupants on facility usage will ideally
be more than are normally required in their scope of services. occur primarily during the Construction Phase of a project.
The scope of services in the “Owner-Design Professional Ser- Some training, however, is likely to be best deferred until the
vice Agreement” should also include the requirement to Owner has assumed responsibility for the facility. Such train-
cooperate with the CxA during Predesign, Design, and Con- ing will be defined in the Cx Plan and contract documents.
struction Phases of the project. This may include training, 8.2.4.1 Ongoing training is an integral part of an Ongoing
seasonal tests, problem resolution, design evaluation, site vis- Cx Process. The Owner’s operation and maintenance person-
its, updating drawings and specifications, or other require- nel and the occupants will be critical members of the Cx
ments performed during the occupancy and initial operations Team responsible for these periodic efforts.
period defined for the project.
8.2.5 The final project Cx Process Report will be com-
8.1.5 If the Owner adopts the Cx Process on a project at the
pleted during this phase. The requirements for a successful
Occupancy/Operations Phase, then this process is termed
Cx Process Report are described in Section 7. Content not
“retrocommissioning” and, while it accomplishes some Cx
available or incomplete at the end of the Construction Phase
Process Activities described herein, it is sufficiently different
will be added during this phase.
from the Cx Process that it is not within the scope of this
guideline. 8.2.5.1 Should the Owner choose to implement the Ongo-
8.1.6 It is often desirable for the Owner to maintain the ing Cx Process for his/her facility, periodic Cx Process
benefits of the Cx Process well into the life of the facility. Reports will be created throughout the Occupancy/Operations
Phase to reflect the Cx Process Activities undertaken.
8.2 Occupancy/Operations-Phase Cx Process Activities
8.2.6 The final project systems manual will be completed
8.2.1 Occupancy/Operations-Phase Cx Process Respon-
during this phase. The requirements for a successful systems
sibilities
manual are described in Section 7. Content not available or
8.2.1.1 During the Occupancy/Operations Phase, the Cx incomplete at the end of the Construction Phase will be added
Team works to verify the ongoing compliance with the OPR. during this phase.
8.2.1.2 Essential team members during the Occupancy/ 8.2.6.1 The systems manual should be updated as
Operations Phase include Owner’s representatives, the CxA, changes are made to the facility throughout the entire Occu-
design professionals, contractors, and construction/program/ pancy/Operations Phase. This includes updating the OPR to
project managers. reflect current conditions and needs and updating the BoD to
8.2.1.3 Responsibilities of the Cx Team during the Occu- reflect changes to systems and assemblies.
pancy/Operations Phase include the following:
8.2.7 Dynamic systems and equipment, as well as static
a. Coordinate contractor callbacks. systems, assemblies, and components, tend to migrate from
b. Verify seasonal testing of facility systems and assemblies. their as-installed conditions over time. In addition, the needs
c. Verify continuing operation and maintenance personnel and demands of facility users and processes typically change
training. as a facility is used. To attain optimal performance of facility
d. Verify system and assembly operations meet updated systems, periodic verification of system, assembly, and com-
OPR. ponent condition and operation is essential. The systems man-
e. Verify continual updating of the systems manual. ual provides the tools and documented benchmarks for
f. Conduct and verify periodic performance evaluations of evaluation of ongoing performance. Such periodic verifica-
facility systems and assemblies. tion is often best done in the context of an Ongoing Cx Pro-
cess.
g. Convene lessons-learned workshop.
h. Complete the final Cx Process Report for the project. 8.2.8 The Ongoing Cx Process has the following key activ-
ities:
8.2.2 The CxA should aid in the coordination of the call-
back of contractors during the Occupancy/Operations Phase. a. Maintaining the OPR to reflect changes in use and opera-
Since the CxA has been involved since the Predesign Phase, tion of the facility.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

17
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

b. Maintaining the BoD to reflect changes in systems and mation in these deliverables is used throughout the life of the
assemblies due to renovations or in response to changes in facility.
the OPR. 8.4.2 If periodic performance verification is conducted for
c. Periodic evaluation of achieving the current OPR and the Owner, an Ongoing Cx Process Report and updates (as
against previous benchmarks by appropriate tests. necessary) to training and the systems manual should be pro-
d. Maintaining the systems manual to reflect changes in vided as deliverables.
OPR, BoD, and systems/assemblies.
e. Ongoing training of operations and maintenance person- 8.5 Occupancy/Operations-Phase Training Requirements
nel and occupants on current OPR and BoD and changes 8.5.1 The Cx Process training requirements for the Occu-
in systems and assemblies. pancy/Operations Phase are discussed in Section 8.2.4.
8.3 Occupancy/Operations Phase
Acceptance Requirements 9. REFERENCES
8.3.1 The Cx Process should include the formal acceptance 1. DeVor, R., T. Chang, and J. Sutherland. 1992. Statistical
by the CxA and the Owner of any deferred training, the final Quality Control: Contemporary Concepts and Methods,
project systems manual, and the final Cx Process Report dur- Macmillan Publishing Company, New York, Chapter 7.
ing the Occupancy/Operations Phase. 2. Gitlow, H. and S. Gitlow. 1987. The Deming Guide to Qual-
8.4 Occupancy/Operations-Phase Documentation Require- ity and Competitive Position, Prentice-Hall, Englewood
ments Cliffs, NJ, Chapter 3.
8.4.1 The final project Cx Process Report and final project 3. Juran, J.M. (Ed.). 1995. A History of Managing for Quality:
systems manual are the primary documentation requirements The Evolution, Trends, and Future Directions of Manag-
for the Occupancy/Operations-Phase Cx Process. The infor- ing for Quality, ASQC Quality Press, Milwaukee, WI.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This is a normative annex and is part of this guideline.) “The procedures, methods, and documentation require-
ments in this guideline describe the application of the Cx Pro-
NORMATIVE ANNEX A cess for each project delivery phase from Predesign through
GUIDE FOR DEVELOPING SUPPLEMENTARY Owner Occupancy and Operation for [insert topic] to support
TECHNICAL GUIDELINES FOR the Cx Process Activities described in ASHRAE Guideline 0-
THE COMMISSIONING PROCESS 2013, The Commissioning Process (also published by NIBS
The purpose of this annex is to provide the recommended as Guideline 0, The Total Building Commissioning Process).
format and content for Total Building Cx Process supporting This includes requirements for
technical guidelines. The objective is to use the same format a. [insert topic] to fully support the Total-Building Commis-
for all Cx Process guidelines. The National Institute of Build- sioning Process Activities;
ing Sciences (NIBS) is facilitating the development of a num- b. verification during each phase of the Cx Process;
ber of technical topic guidelines to support the effective c. acceptance at each phase;
implementation of the Total Building Cx Process. These d. documentation during each phase;
guidelines will be developed by various professional, techni- e. systems manual; and
cal, and trade organizations. For example, the technical guide- f. training for operations and maintenance personnel and
line for heating, ventilating, air-conditioning, and occupants.”
refrigeration (HVAC&R) will be developed by ASHRAE.
The technical guidelines are developed to assist the Cx Team A4. SECTION 3, UTILIZATION
in successfully using the Cx Process for various systems and
assemblies. The goal is to use the process as defined and pro- The following paragraphs should be included as the Uti-
vided in Guideline 0, “The Cx Process.” Further, it is desired lization section:
that each different system or assembly involved in the con- 3.1 The application of this guideline depends on the OPR and
struction, addition to, or rehab of buildings, structures, cam- how the project will be designed, built, and operated. This
puses, or utilities use the Cx Process from Guideline 0-2013 guideline is supplemental to the Cx Process detailed in
and not redefine it within the respective (topic) technical ASHRAE Guideline 0-2013.
guideline. 3.2 This guideline describes specific details required to prop-
The objective of both Guideline 0-2013 and the technical erly implement the Cx Process relative to [insert topic]. This
guidelines is to provide information on implementing the Cx includes documentation, test procedures, and checklists.
Process. The technical guidelines are not intended to be a
detailed user’s guide or provide guide specifications, full A5. SECTION 4, DEFINITIONS
commissioning plans, development of owner’s project Include definitions that are unique to the technical guide-
requirements, construction checklists, statistical or other line. Do not redefine or repeat those in ASHRAE Guideline 0;
quality tools, or other detailed requirements for implementing instead, include a statement referring to the definitions in Sec-
the Cx Process. tion 4 of Guideline 0.
The format of the technical guidelines should follow the
same format used in Guideline 0-2013. The following is the A6. SECTION 5, PREDESIGN PHASE
general organization to be used in the development of the
The following should be included in the Predesign-Phase
technical guidelines.
section for [insert topic]:
A1. FOREWORD a. List of Cx Team members
The Foreword should provide key information on what has b. List and description of criteria and items to be included in
led to success on previous projects, the role of the specific tech- the OPR document
nology in a successful building or construction project, and c. List of milestones
closely related supplementary technical guidelines or topics. d. List of specialists required for implementing the Cx Pro-
cess
A2. SECTION 1, PURPOSE e. List of items to focus on during the design reviews
f. List of items to be included in the Cx Plan
The following should be used as the general purpose for g. List of items to be included as part of the Issues and Reso-
each technical guideline: lution Log
“The purpose of this guideline is to describe the technical h. List of items required for acceptance of Predesign-Phase
requirements for the application of the Cx Process described commissioning
in ASHRAE Guideline 0-2013 that will verify that the [insert i. List of tests that need to be performed
topic, for example, fire systems or envelope assembly] j. Training requirements
achieves the OPR.”
k. Requirements for the systems manual, such as parts lists,
troubleshooting needs, operations and maintenance
A3. SECTION 2, SCOPE
requirements, system description, and the level at which
The following text should be used as the general scope each set of material needs to be written for clear under-
for each technical guideline: standing
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

19
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

A7. SECTION 6, DESIGN PHASE A9. SECTION 8, OCCUPANCY/OPERATIONS PHASE


The following should be included in the Design-Phase The following should be included in the Occupancy/
section for (topic). This will be the basis for Construction- Operations-Phase section for [insert topic]:
Phase documents for contractors, vendors, and equipment/
a. List of training items to be accomplished during the first
assembly manufacturers:
year of operation
a. List of items required for the BoD b. List of warranty items to be checked during the first year
b. Revision review procedure for Cx Team members and of operation
OPR c. List test requirements during occupancy, including peri-
c. List of coordination requirements and items provided by odic retesting for a successful continuous operation of the
others facility.
d. Key milestones that need to be reviewed d. List who should attend the lessons-learned workshop
e. Update lists of specialists required to implement the Cx e. List of criteria to be included in the final Cx Process
Process based on the actual design and interrelationship Report
with other systems and assemblies f. List of items required for acceptance of Occupancy/Oper-
f. List of items to be included in the construction documents ations-Phase commissioning
g. Lists of priority items and relate whenever possible to
safety, health, energy, environmental impact, aesthetics, A10. SECTION 9, REFERENCES
operations and maintenance, in addition to the OPR Include industry-specific references that support recom-
h. List of construction checklists to be used by the contractor mendations for benchmarking, testing, and other supporting
i. Samples of construction checklists (examples of construc- guidance in the development of the OPR, BoD, tests, and
tion checklists are included in Annex M to this guideline other Cx Process documents.
and in other annexes in other supplementary technical
guidelines (such as ASHRAE Guideline 1.1-2007, A11. APPENDICES
HVAC&R Technical Requirements for the Commissioning Appendices are to be used to provide additional informa-
Process.) tion, examples of documentation, examples of specifications,
j. List of items to be included in the systems manual, such as acceptance procedure details, and other items that are not
parts lists, troubleshooting needs, operations and mainte- required to achieve compliance with the technical guideline
nance requirements, system description, and the level at but will assist in implementing the Cx Process for the specific
which each set of material needs to be written for clear technical system or assembly. This is the place to illustrate
understanding best practices and to provide information on how to achieve
k. List of training requirements, timing, learning outcomes. best practice and economy in design. Annex Q, References,
l. List of tests that need to be performed should provide current articles, guides, and other information
m. List of items required for acceptance of Design-Phase on implementing the Cx Process for the specific supporting
commissioning technical requirements guidelines.
The desired goal is to have all Cx Process guidelines use
A8. SECTION 7, CONSTRUCTION PHASE the same annex designation. They should use the same annex
The following should be included in the Construction- letters as Guideline 0-2013. If an annex is not required, it
Phase section for [insert topic]: should specifically be so noted in each technical guideline—
suggested wording: “This annex is intentionally left blank” or
a. List of test procedures and data forms to verify achieve- “There is no supplemental information required for [insert
ment of OPR and BoD assembly or system] technology.” Annex A will be empty in
b. Samples of test procedures and data forms (Examples of all supplemental guidelines. Annex B is specific to Guideline
these are included in Annex U to other supplementary 0 and should not be changed in supplemental guidelines.
technical guidelines (such as ASHRAE Guideline 1.1- Appendices C through E may require no modification for
2007, HVAC&R Technical Requirements for the Commis- most supplemental guidelines.
sioning Process.) Informative Note: The list and numbering of annexes, to
c. List of coordination requirements and items provided by be in compliance with Guideline 0-2013, must be as follows:
others
d. List of specific items for the site visit procedures • Annex A—Guide for Developing Supplementary Techni-
e. Tests needs and schedule cal Guidelines for the Cx Process (used only in Guideline
0)
f. Cx Team meetings
g. Issues and Resolution Logs • Annex B—Commissioning (Cx) Process Flowchart (used
h. Input into the final Cx Process Report only in Guideline 0)
i. Lessons-learned workshop schedule during Occupancy/ • Annex C—Cost and Benefits of the Commissioning (Cx)
Operations Phase Process (typically only in Guideline 0)
j. List of items required for acceptance of Construction- • Annex D—Commissioning (Cx) Process Documenta-
Phase commissioning tion Matrix (typically only in Guideline 0)
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

• Annex E—Commissioning (Cx) Process Request for that provide examples and guidance on the following top-
Qualifications (typically only in Guideline 0) ics or should include notes such as “Not used,” or “This
• Annex F—Roles and Responsibilities annex is intentionally left blank,” or “There is no supple-
• Annex G—Commissioning (Cx) Plan mental information required.”
• Annex H—Acceptance Plan • Annex Q—Publications, Articles, References, Codes,
Regulations, and Standards
• Annex I—OPR Workshop Guidance
• Annex R—Integration Requirements
• Annex J—Owner’s Project Requirements (OPR)
• Annex K—Basis of Design (BoD) • Annex S—Interference and Coordination with Other
Systems and Assemblies
• Annex L—Specifications
• Annex T—Communications: What, When, and Who
• Annex M—Construction Checklists
• Annex U—Test Procedures and Data Forms
• Annex N—Quality-Based Sampling Examples
• Annex V—Predesign-Phase Commissioning (Cx) Pro-
• Annex O—Systems Manual
cess Specific Needs
• Annex P—Training Manual and Training Needs
• Annex W—Design-Phase Commissioning (Cx) Process
• Appendices Q through X—In addition to the annexes Specific Needs
(above) that are included in Guideline 0-2005, The Com-
missioning Process, all supplemental technical guide- • Annex X—Construction-Phase Commissioning (Cx)
lines should include the following annexes with specific Process Specific Needs
technical topic guidance or requirements, as appropriate. • Annex Y—Occupancy/Operations-Phase Commission-
It is the intent to have all technical guidelines use the ing (Cx) Process Specific Needs
same reference letter for each topic. That is, all examples • Annex Z (and, if needed, Annex AA and beyond) can be
of checklists would always be included in Annex M. The used as required for other topics that are determined to be
technical Cx Process guidelines should include annexes useful for a specific assembly or system.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

21
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- applicable commissioning technical guidelines tailored to
mative and does not contain requirements necessary for their specific projects.
conformance to the guideline.)
The flow chart shown in Figure B-1 depicts an example
INFORMATIVE ANNEX B for an owner who has adopted the Cx Process from project
COMMISSIONING PROCESS FLOW CHART inception. If the owner adopts the Cx Process after project
This annex provides an example of how to implement inception, then the tasks shown are still accomplished in
part of Guideline 0. It is not intended to be a comprehensive whatever phase the Cx Process begins. The Ongoing Cx Pro-
representation or a best practice example. Practitioners apply- cess is shown in the flow chart as ongoing tasks during the
ing the Cx Process should carefully follow Guideline 0 and Occupancy/Operations Phase after the last acceptance block.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

FIGURE B-1 Commissioning (Cx) process flow chart.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

23
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely C3. DISCUSSION OF BENEFITS
informative and does not contain requirements necessary
for conformance to the guideline.) For convenience and clarity, benefits will be discussed as
they relate to major participants in the Cx Process: the Design
INFORMATIVE ANNEX C Professional, the contractor, and the Owner.
COST AND BENEFITS OF THE C3.1 Benefits to the Design Professional. Potential benefits
COMMISSIONING PROCESS include the following:
This annex provides an example of how to implement
part of Guideline 0. It is not intended to be a comprehensive a. Facility will achieve the of OPR
representation or a best practice example. Practitioners apply- b. Reduced risk exposure
ing the Cx Process should carefully follow Guideline 0 and
c. Improved knowledge base for use in future designs and
applicable commissioning technical guidelines tailored to
installation
their specific projects.
d. Benefit of other participants’ input, leading to the most
C1. OVERVIEW cost-effective design and operation
The Cx Process focuses on producing a quality-based e. Reduced number of interference drawings during con-
system that achieves the OPR. struction due to improved communication and coordina-
This annex discusses the potential benefits and where tion throughout the project
they accrue and quantifies these benefits by providing evi-
C3.2 Benefits to the Contractor. Potential benefits include
dence of potential costs and savings.
the following:
C2. DISCUSSION OF NEW COST ITEMS a. Improved planning and coordination through the imple-
Ultimately, the owner of the facility will determine the mentation of the Cx Plan
extent of the Cx Process Activities and who will be responsi- b. Improved coordination between different trades and
ble for each phase of work. The intent here is to outline the reduced likelihood of site interference drawings required
scope of work that represents new cost items rather than to of contractors throughout the project. Reduced number of
assign responsibilities for each task. The cost of the Cx Pro- deficiencies at substantial completion. Reduced number
cess should be considered as a part of the project budget. of callbacks
C2.1 Design Professional. In addition to the design profes- c. Reduced number of calls for operational guidance due to
sional's typical scope of work, including the preparation of participation in training programs for operations and
design drawings and specifications, the Cx Process often maintenance personnel
requires that the design professional work with the CxA to
integrate the Cx Process Activities into the project specifica- C3.3 Benefits to the Owner. Potential benefits include the
tions. These activities typically include the following: following:
a. Test requirements and documentation a. Improved operator knowledge of how to optimize the
b. Operational, maintenance, and troubleshooting documen- facility operation and maintenance due to the early inclu-
tation requirements sion of operators in the Cx Process
c. Construction checklists b. Reduced training requirements due to continuously
d. Systems manual updated documentation of how systems should operate
e. Comprehensive training program for operation and main- and be maintained; personnel will only need to be trained
tenance personnel and users with regard to changes
The design professional may also be responsible for c. Facility performance is in accordance with the Owner's
reviewing the Cx Plan at the various phases of the process and Project Requirements
for delivering the BoD in a format specific for the owner. d. Systems manual provides an easy reference document for
C2.2 CxA. The activities accomplished by the CxA as system and assembly operation and maintenance
defined in this guideline require that additional funds be allo- e. Reduced downtime due to better diagnosis of failures
cated during the Predesign, Design, and Construction Phases.
These funds are allocated from the savings obtained through f. Improved ability to provide accurate information to occu-
fewer change orders and requests for information and through pants on facility operation and maintenance
reduced problems during start-up of the systems and occu- g. Lower operating costs due to improved operational tech-
pancy of the facility. niques
C2.3 Contractors. The completion of some detailed tests is h. Benefits to building occupants, including greater worker
unique to the Cx Process. The contractor will have additional productivity, reduced complaints, and reduced incidence
work and costs associated with completing these tests. of absenteeism
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor-


mative and does not contain requirements necessary for
conformance to the guideline.)

INFORMATIVE ANNEX D
COMMISSIONING PROCESS
DOCUMENTATION MATRIX
This annex provides an example of how to implement
part of Guideline 0. It is not intended to be a comprehensive
representation or a best practice example. Practitioners apply-
ing the Cx Process should carefully follow Guideline 0 and
applicable commissioning technical guidelines tailored to
their specific projects.
Table D-1 summarizes the documents that are produced
during the implementation of the Cx Process on a project.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

25
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TABLE D-1 Documentation Matrix


Reviewed/
Phase Document Input By Provided By Used By Notes
Approved By
O&M, Users,
Design Team
Predesign OPR Capital Projects, CxA or Designer Owner CxA, Design Team
may not be hired yet.
Design Team (?)
Owner, Design CxA, Owner, Design Team
Commissioning Plan CxA Owner
Team (?), CxA Design Team ay not be hired yet.
Systems Owner or May be included in
O&M, CxA Owner Design Team
Manual Outline CxA OPR
Training O&M, Users,
Owner or May be included in
Requirements CxA, Design Owner Design Team
CxA OPR
Outline Team
Issues and Resolution May be only format
CxA CxA N/A CxA, Design Team
Log at this phase
Design Team,
Issues Report CxA CxA Owner
Owner
Predesign-Phase
CxA CxA Owner Owner Close of Phase report
Cx Process Report
O&M, Users,
Design OPR Update Capital Projects, CxA or Designer Owner CxA, Design Team
Design Team

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
Design
Basis of Design Design Team Owner, CxA Design Team, CxA
Team
May also be provided
Construction Design Team, Design Team or Contractors, CxA,
Owner by Project Manager/
Specifications for Cx CxA, Owner CxA Design Team
Owner’s Rep.
Design Team,
Systems manual Design Team or Design Team, Contractor may not
CxA, O&M, Owner, CxA
Outline-Expanded CxA Contractor be hired yet.
Contractor (?)
Training O&M, Users,
Contractor may not
Requirements In CxA, Design Owner or CxA Owner Design Team
be hired yet
Specifications Team
Design Review
CxA CxA Owner Design Team
Comments
Issues and Resolution
CxA CxA N/A CxA, Design Team
Log
Design Team,
Issues Report CxA CxA Owner
Owner
Design-Phase
CxA CxA Owner Owner Close of Phase report
Cx Process Report
O&M, Users,
CxA, Design
Construction OPR Update Capital Projects, CxA or Designer Owner
Team, Contractors
Design Team
Basis of Design
Design Team Design Team CxA, Owner Design Team, CxA
Update
Design Team, CxA, Owner, CxA, Owner,
Cx Plan Update CxA, Owner, CxA Design Team, Design Team,
Contractor Contractor Contractors
Submittal Review
CxA Design Team Design Team Contractor
Comments
Notes:
1. The term “contractor” is understood to refer to any of several entities that provide construction services. Depending on the project, this could include, among others, the owner’s repre-
sentative, construction manager, contractors, and subcontractors.
2. Abbreviations: CxA: Commissioning Authority; O&M: operations and maintenance personnel; OPR: Owner’s Project Requirements.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TABLE D-1 Documentation Matrix


Reviewed/
Phase Document Input By Provided By Used By Notes
Approved By
Construction System Coordination Contractor, CxA, Design
Contractor Contractor, CxA
(contd.) Plans Design Team Team
CxA, Contractor, CxA, Design
Inspection Checklists CxA Contractor
Design Team Team
Inspection Reports Contractor CxA CxA, Owner Contractor
CxA, Contractor, CxA, Design
Test Procedures CxA Contractor
Design Team Team
Test Data Reports Contractor CxA CxA, Owner Contractor
Commissioning
Meeting Agendas
CxA CxA All All
and
Minutes
Design Team,
Contractor or O&M, Users,
Training Plans CxA, O&M, Owner, CxA
CxA Contractor
Contractor
Design Team,
Systems Manual CxA, O&M, Contractor Owner, CxA O&M, Users
Contractor
Issues and Resolution CxA, Design
CxA CxA N/A
Log Team, Contractor
Owner, Design Design Team,
Issues Report CxA CxA
Team Owner, Contractor
Preliminary
Construction CxA CxA Owner Owner Prior to Occupancy
Cx Process Report
Final Construction-
Phase Cx Process CxA CxA Owner Owner Close of Phase report
Report
Occupancy and O&M, Users, CxA, Design
OPR Update CxA or Designer Owner
Operations Design Team Team, Contractors
Basis of Design
Design Team Design Team CxA, Owner Design Team, CxA
Update
Maintenance O&M,
Owner or CxA Owner, CxA O&M, Users
Program Contractor, CxA
Contractor, CxA,
Design Team,
Test Procedures O&M, Design CxA Contractor
CxA
Team
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

Test Data Reports Contractor CxA CxA, Owner Contractor, O&M


CxA, Design
Issues and Resolution
CxA CxA N/A Team, Owner,
Log
Contractors
Design Team,
Issues Report CxA CxA Owner Owner,
Contractors
Cx Process Report CxA CxA Owner Owner Final report
Recommissioning O&M, Users,
CxA or Owner Owner Owner
Plan CxA
Notes:
1. The term “contractor” is understood to refer to any of several entities that provide construction services. Depending on the project, this could include, among others, the owner’s repre-
sentative, construction manager, contractors, and subcontractors.
2. Abbreviations: CxA: Commissioning Authority; O&M: operations and maintenance personnel; OPR: Owner’s Project Requirements.

27
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- E2.2 Cx Process During the Design Phase. The Cx Process
mative and does not contain requirements necessary for Activities completed by the CxA during the Design Phase
conformance to the guideline.) include the following:

INFORMATIVE ANNEX E • Working with the Cx Team to document the OPR for the
COMMISSIONING PROCESS REQUEST facility
FOR QUALIFICATIONS • Working with the design professionals in documenting
the BoD
This annex provides an example of how to implement • Verifying the BoD with regard to the OPR
part of Guideline 0. It is not intended to be a comprehensive • Developing a Cx Plan encompassing the Design, Con-
representation or a best practice example. Practitioners apply- struction, Occupancy/Operations Phases
ing the Cx Process should carefully follow Guideline 0 and • Determining the commissioning requirements and activi-
applicable commissioning technical guidelines tailored to ties to include in the construction documents, with
their specific projects. review by the design team, for integration into the proj-
ect's construction specifications
E1. BACKGROUND • Reviewing the in-depth design documentation developed
_____________________________ (Owner) is seeking by the design professionals
the services of a qualified CxA for • Performing statistically based quality design review at
_______________________. The project is a ____________ 35%, 50%, 95%, and 100% completion of the drawings
gross ft2, ___ story, Class ___ [type] ___________ building in and specifications
[city & state] ____________, _________, with a project bud-
get of $______ million. The facility is expected to be com- E2.3 Cx Process During the Construction Phase. The Cx
posed of ____% [space type], ____% [space type], and Process Activities accomplished by the CxA during the Con-
_____% [space type]. struction Phase include the following:

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
The project is currently in the early predesign phase. The • Organizing the Cx Process components and conducts a
expected schedule is to start design by ________________, prebid and preconstruction meeting where the Cx Pro-
start construction by ______________, and occupy by cess requirements are reviewed with the Cx Team
________________. • Organizing and conducts periodic Cx Team meetings
The management structure is traditional design/bid/build necessary to plan, develop the scope of, coordinate, and
with full design documents and specifications being devel- schedule activities and resolve problems
oped by an architectural/engineering firm. The construction • Reviewing submittals concurrent with the design profes-
documents will be let out to bid and a general contractor will sional’s review
be hired to complete the construction. The Owner’s primary • Working with contractors in completing construction
construction representative on site will be provided by the checklists and tracking of checklist completion
separately contracted services of a construction manager. The • Statistically sampling completion of construction check-
CxA will be hired by and report directly to the Owner. lists on a periodic basis to verify that contractor’s quality
process is achieving the Owner's Project Requirements
E2. SCOPE OF WORK • Developing specific test procedures. The contractors
review the procedures
The Owner has adopted the Cx Process as his/her quality
• Directing the execution of the tests by the contractors
process to plan, design, construct, and operate this facility. As
• Documenting the results of the tests
with any quality process, the Cx Process provides tools to
• Documenting the correction and retesting of noncompli-
enable everyone involved in the construction of the facility to
ance items by the contractor
verify that the final facility meets the OPR.
• Reviewing the systems manual for achieving the OPR
The following is a summary of the Cx Process that the • Reviewing, preapproving, and verifying the training pro-
Owner intends to implement on this project. The proposer is vided by the contractors
free to suggest changes and improvements to this process. • Verifying delivery of the systems manual
However, for this proposal the following process will be
assumed. E2.4 Cx Process During the Occupancy/Operations
E2.1 Cx Process During the Predesign Phase. The Cx Pro- Phase. The Cx Process Activities accomplished by the CxA
cess Activities completed by the CxA during the Predesign during the Occupancy/Operations Phase include the follow-
Phase include the following: ing:

• Developing and documenting the OPR • Scheduling and verifying deferred and seasonal testing
by the contractor
• Identifying a scope and budget for the Cx Process • Verifying continuing training
• Developing the initial Cx Plan • Reviewing warranties with the operations and mainte-
• Acceptance of Predesign-Phase Cx Process Activities nance staff two months prior to expiration of warranty

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

• Scheduling, organizing, and attending a lessons-learned require that this individual be committed to the project for
workshop. The workshop is facilitated by an independent its duration.
member of the CxA’s firm b. Provide project and professional references and experi-
• Completing the final Cx Process Report ence for three to five commissioning projects for which
the proposer was the principal CxA in the last three years.
E3. LIMIT OF RESPONSIBILITIES Include a description of the projects, identify when the
The CxA is not responsible for design concept, design proposer came into the projects, and describe the involve-
criteria, compliance with codes, design or general construc- ment of each individual on the proposer’s team in the proj-
tion scheduling, cost estimating, or construction management. ects. For each project, attach a sheet that includes the
The CxA may assist with problem-solving or resolving non- name and telephone number of the Owner’s project man-
conformance or deficiencies, but ultimately that responsibility ager, construction manager, facility administrator of the
resides with the general contractor and design professionals. building, the design professionals, and the contractors.
c. Describe any experience of the proposer’s team in the fol-
E4. FOCUS OF THE CX PROCESS lowing areas. List each party’s involvement.
The following systems and assemblies are the focus of 1. Quality process experience.
the Cx Process: 2. Operation and maintenance experience.
• [Insert list of systems and assemblies] 3. Design experience.
4. Life-cycle costing.
E5. DESIRED QUALIFICATIONS
5. [Insert other system or assembly specific experience
It is desired that the person designated as the CxA satisfy requirements].
as many of the following requirements as possible: d. Describe your proposed approach to managing the project
a. Has acted as the principal CxA for at least three projects expertly and efficiently, including your team participation.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
during the past year. [Note that the size of the project Describe what approach you will take to integrate the Cx
should be accounted for. Whereas one proposer may have Process into the normal design and construction process
done ten projects all small in size, another proposer that in order to make it “business as usual.”
accomplished one large and complex project may have e. Describe what you will do to foster teamwork and cooper-
equal credentials]. ation from contractors and designers and what you will do
b. Experienced in quality processes. to minimize adversarial relationships.
c. Knowledgeable in building operation and maintenance f. Describe how your work will facilitate the use of your
training. product as a prototype that may be subsequently used by
d. Excellent verbal and written communication skills. the Owner in future projects, including access to the elec-
Highly organized and able to work with both management tronic versions of all documents and forms.
and trade contractors. g. As an attachment, provide the following work products
e. A bachelor’s degree in [insert discipline] is strongly pre- that members of the proposer’s team wrote:
ferred and [insert type] certification or professional 1. Cx Plan that was executed
license is desired. 2. Integrated commissioning specifications
f. The CxA’s firm will demonstrate depth of experienced
3. Electronic Issues and Resolution Log
personnel and capability to sustain loss of assigned per-
sonnel without compromising quality and timeliness of 4. Construction checklists
performance. 5. Test procedure that was executed
g. The CxA will be an independent contractor and not an h. [Insert any other desired instructions].
employee or subcontractor of the general contractor or
any other subcontractor on this project, including the E7. SELECTION CRITERIA
design professionals. The submitted proposals will be reviewed and ranked
h. [Insert any qualifications or special requirements for a according to the following (items from the above numbered
specific system or assembly]. list):
E6. INSTRUCTIONS TO PROPOSERS a. Key individual experience 20 points
A proposer must propose to execute all phases of the Cx b. Staff experience 15 points
Process in a single proposal. The proposal must be signed by c. Similar project experience 20 points
an officer of your firm with the authority to commit the firm d. Team experience in related skill areas 15 points
and must include the following information: e. Management approach 20 points
f. Work examples 10 points
a. List the key individual who will be the CxA for this con-
tract and describe his or her relevant qualifications and 100 points
experience. This information is required in addition to any Reference checks will not be scored individually but may
detailed resumes the proposer submits. The contract will be used to supplement all categories. The Owner reserves the

29
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

right to eliminate or change the weight of extremely high or E9. LIMITATIONS AND PROVISIONS
extremely low fee proposals. [Insert wording on right to reject, to seek clarifications,
to negotiate a final contract; cost of proposal preparation not
E8. SUBMISSION AND SELECTION reimbursable; primary contact for questions; other necessary
legal language, etc.]
Consultants will submit [quantity__________] copies of
the written proposal, to be received in the Owner’s office at E10. MINIMUM REQUIREMENTS FOR CONTRACT
[address_____________________] by [date and EXECUTION
time____________________________]. Late proposals will
not be accepted. E10.1 General Conditions. Miscellaneous as required . ..
E10.2 Insurance. The CxA’s firm shall obtain, at the firm’s
Review and selection process ... expense, and keep in effect during the term of the project,
Requirement of personal interview for finalists... $[list required insurance amount].

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- c. Verify that the Cx Process Activities are clearly stated in
mative and does not contain requirements necessary for all scopes of work.
conformance to the guideline.) d. Integrate the Cx Process Activities into the project sched-
ule.
INFORMATIVE ANNEX F e. Prepare a Cx Plan that describes the extent of the Cx Pro-
ROLES AND RESPONSIBILITIES cess to meet the Owner's Project Requirements. Update
This annex provides an example of how to implement the Cx Plan during each phase of the project to incorpo-
part of Guideline 0. It is not intended to be a comprehensive rate changes and additional information.
representation or a best practice example. Practitioners apply- f. Review and comment on the ability of the design docu-
ing the Cx Process should carefully follow Guideline 0 and ments to achieve the OPR for the commissioned systems
applicable commissioning technical guidelines tailored to and assemblies.
their specific projects. g. Prepare the Cx Process Activities to be included as part of
Understanding and defining the role of each participant is the project specification. Include a list of all individual
vital to the success of the Cx Process. This annex provides an trade contractor responsibilities for all the Cx Process
example of the responsibilities of each participant in a com- Activities (list contractors by name, firm, and trade spe-
prehensive Cx Process. These responsibilities shall be docu- cialty if known).
mented in the contracts between the owner and the h. Execute the Cx Process through the writing and review of
contractor(s) and the owner and the design professionals. The Cx Process Reports, organization of all Cx Team meet-
responsibilities of each participant should be included in the ings, tests, demonstrations, and training events described
contract documents. in the contract documents and approved Cx Plan. Organi-
The responsibilities of the owner, CxA, design profes- zational responsibilities include preparation of agendas,
sionals, construction manager, contractors, and manufacturers attendance lists, arrangements for facilities, and timely
are detailed below. notification to participants for each Cx Process activity.
The CxA shall act as chair at all commissioning events
F1. OWNER and ensure execution of all agenda items. The CxA shall
prepare minutes of every Cx Process activity and send
a. Include a statement regarding design professional com- copies to all Cx Team members and attendees within five
missioning responsibilities and scope in the request for workdays of the event.
design services.
i. Review the plans and specifications (during the Predesign
b. Develop and commit to the Owner's Project Requirements and Design Phases) with respect to their completeness in
for the facility and its use. all areas relating to the Cx Process. This includes verify-
c. Assign operations and maintenance personnel and sched- ing that the OPR has been met, and that there are adequate
ule them to participate in the various meetings, training devices included in the design to properly test the systems
sessions, and observations/inspections as follows: and assemblies and to document the performance of each
1. Design-Phase coordination meetings piece of equipment, system, or assembly.
2. Construction-Phase coordination meetings j. Schedule all document review coordination meetings.
3. Initial owner-training session at initial placement of k. Attend the project’s prebid meeting to detail the design
major equipment professional or contractor Cx Process requirements.
4. Maintenance orientation and inspection l. Schedule the predesign and preconstruction Cx Process
meeting within 60 days of the award of the contract at
5. System testing verification meetings
some convenient location and at a time suitable to the
6. Procedures meeting for testing systems attendees. This meeting will be for the purpose of review-
7. Owner's training session ing the complete Cx Process and establishing tentative
8. Verification demonstrations schedules for the Design-Phase and Construction-Phase
9. Systems and assemblies tests commissioning activities.
10. Final review at acceptance meeting m. Develop the initial format to be used for Issues and Reso-
lution Logs throughout and for each phase of the Cx Pro-
d. Review and approve any changes made to OPR.
cess.
e. Review and approve the construction documents.
n. Schedule the initial owner training session so that it will
f. Provide qualified personnel for videotaping and editing of
be held immediately before the contractor training. This
training sessions.
session will be attended by the owner's O&M personnel,
g. Videotape construction progress.
the design professionals, the contractor, and the CxA. The
h. Review and comment on the CxA’s Cx Process Progress
CxA will review the OPR and the design professional(s)
Reports.
will review the BoD.
i. Review and comment on the CxA’s verification reports.
o. Review proposed contractor-provided training program to
j. Review and accept the CxA's Cx Process Report. verify that the OPR is met.
p. Attend a portion of the contractor-provided training ses-
COMMISSIONING AUTHORITY
sions to verify that the OPR is met.
a. Organize and lead the Cx Team. q. Receive and review the systems manual as submitted by
b. Facilitate and document the OPR. the contractor. Verify that it meets the OPR. Insert sys-
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

31
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

tems descriptions as provided by the design profes- q. Recommend final acceptance of the systems to the owner.
sional(s) in the systems manual.
r. Witness system and assembly testing. Verify the results F3. CONSTRUCTION MANAGER
and include a summary of deficiencies. a. Include costs for Cx Process Activities in the contract
s. Supervise the Cx Team members in completion of tests. price.
The test data will be part of the Cx Process Report.
b. Include Cx Process Activities and requirements in all con-
t. Periodically review record drawings for accuracy with tractors' contracts.
respect to the installed systems. Request revisions to
c. Provide adequate accessibility as required to properly
achieve accuracy.
operate and maintain the facility.
u. Verify that the systems manual and all other design and
d. Provide acceptable representation with the means and
construction records have been updated to include all
authority to prepare and coordinate implementation of the
modifications made during the Construction Phase.
Cx Process as detailed in the contract documents.
v. Repeat implementing of tests to accommodate seasonal
e. Issue a statement certifying that all work has been com-
tests or to correct any performance deficiencies. Revise
pleted and that the facility is operational, in accordance
and resubmit the Cx Process Report.
with contract documents.
w. Prepare the final Cx Process Report.
f. Issue the appropriate final reports to the design profes-
x. Assemble the final documentation, which includes the Cx sionals for review and acceptance.
Process Report, the systems manual, and all record docu-
g. Remedy deficiencies identified by the CxA during verifi-
ments. Submit this documentation to the owner for review
cation of the installation or testing.
and acceptance.
h. Review and comment on the final Cx Process Report.
y. Recommend acceptance of the individual systems and
assemblies to the owner (in accord with the defined proj- F4. CONTRACTOR
ect requirements).
a. Include costs for Cx Process Activities in the contract
F2. DESIGN PROFESSIONAL price.
b. Include Cx Process Activities and requirements in each
a. Participate and assist in the documentation of the initial
purchase order or subcontract written.
OPR.
c. Obtain cooperation and participation of all subcontractors
b. Document revisions to the OPR and obtain approval from
and manufacturers.
the owner.
d. Attend the preconstruction and Cx Team meetings.
c. Document the BoD.
e. Include Cx Process milestones in the project schedule.
d. Prepare contract documents, including the integration of
the Cx Process requirements and activities provided by f. Implement the training program as detailed in the contract
the CxA. documents.
e. Prepare contract documents that coordinate required inter- g. Provide submittals to the owner, design professionals, and
faces between Systems and Assemblies. the CxA.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

f. Attend the Predesign and Design-Phase coordination and h. Notify the CxA when systems and assemblies are ready
review meetings. for testing.
g. Respond to Cx Team design submission review comments i. Demonstrate the performance of assemblies and/or opera-
and other issues in a timely manner. tion of systems to the CxA.
h. Attend the prebid and preconstruction meetings as sched- j. Complete the construction checklists as the work is
uled by the CxA. accomplished. Provide the completed construction check-
i. Specify and verify that the operation and maintenance of lists to the CxA.
the systems and assemblies has been adequately detailed k. Continuously maintain the record drawings and submit as
in the construction documents. detailed in the contract documents.
j. Review and incorporate as appropriate the CxA’s com-
F5. MANUFACTURERS
ments from submittal reviews.
k. Participate in the initial operation and maintenance per- a. Provide all information required for the operation and
sonnel and occupant training session by presenting the maintenance of the system or assembly as part of the ini-
project BoD. tial submittal.
l. Participate in other training as detailed in the training pro- b. Provide the requirements to maintain the warranty as part
gram. of the initial submittal.
m. Review test procedures submitted by the contractor. c. Coordinate and accomplish factory tests as detailed in the
n. Review and comment on the CxA's periodic Cx Process contract documents.
Progress Reports and Issues and Resolution Log reports. d. Provide training as detailed in the training program con-
o. Review and accept record documents as required by con- tained in the contract documents.
tract documents. e. Demonstrate operation and performance of the system or
p. Review and comment on the final Cx Process Report. assembly as detailed in the contract documents.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- Accomplish Design Reviews
mative and does not contain requirements necessary for Develop Commissioning Process Contract Document
conformance to the guideline.) Requirements
Prebid Meeting
INFORMATIVE ANNEX G CONSTRUCTION PHASE
COMMISSIONING PLAN Conduct Preconstruction Meeting
This annex provides an example of how to implement Contractor Submittal Review
part of Guideline 0. It is not intended to be a comprehensive Construction checklists
representation or a best practice example. Practitioners apply- Delivery Book
ing the Cx Process should carefully follow Guideline 0 and Preinstallation Checks
applicable commissioning technical guidelines tailored to Installation and Start-Up Checks
their specific projects. Training
The following is an example outline for a Cx Plan. The Testing
basic structure of this example is such that each phase of the OCCUPANCY/OPERATIONS PHASE
plan has its own section detailing what activities will be Final Commissioning Process Report
accomplished and guidance on who accomplishes them and Seasonal Testing
how they are completed. The results from each activity are Ongoing Training
then included in an appendix. The intent of this format is for Warranty Review
the Cx Plan to become the Final Cx Process Report at the end Lessons-Learned Meeting
of the project by filling in the results as the project progresses. CONTACT INFORMATION
Depending on the size and scope of the Cx Process SCHEDULE REQUIREMENTS
Activities, it may be beneficial to have three Cx Plans: one for APPENDIX A—OWNER’S PROJECT REQUIREMENTS
the Predesign Phase, one for the Design Phase, and one for APPENDIX B—BASIS OF DESIGN (BOD)
the Construction Phase. If separate Cx Plans are used, then APPENDIX C—PROJECT SPECIFICATIONS
care must be taken to inform those that are involved in only a APPENDIX D—COMMUNICATION STRUCTURES
portion of the process of the previous material. APPENDIX E—ROLES AND RESPONSIBILITIES
APPENDIX F—COMMISSIONED SYSTEMS
G1. SAMPLE TABLE OF CONTENTS [listing of systems and assemblies]
COMMISSIONING PLAN OVERVIEW APPENDIX G—COMMISSIONING PROCESS SCHEDULE
COMMISSIONING PROCESS DESCRIPTION APPENDIX H—PREBID MEETING
PREDESIGN PHASE APPENDIX I—PRECONSTRUCTION MEETING
Develop OPR APPENDIX J—SUBMITTAL REVIEW
Develop Initial Cx Plan APPENDIX K—COMMISSIONING PROCESS ISSUES
Cx Process Issues APPENDIX L—CONSTRUCTION CHECKLISTS
Step 1—Identify and Record Issues APPENDIX M—TESTS
Step 2—Calculate Avoided Costs APPENDIX N—TRAINING
Step 3—Evaluate Range of Avoided Costs APPENDIX O—SYSTEMS MANUAL
DESIGN PHASE APPENDIX P—MEETING MINUTES
Review and Modify Project Specifications APPENDIX Q—CORRESPONDENCE
Verify BoD APPENDIX R—WARRANTY REVIEW
Update Commissioning Plan APPENDIX S—LESSONS LEARNED

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

33
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- b. The CxA evaluates the contract documents using random
mative and does not contain requirements necessary for sampling to determine their ability to achieve the OPR.
conformance to the guideline.) c. The CxA meets with the design professionals to discuss
and resolve comments.
INFORMATIVE ANNEX H d. Upon resolution of comments, the CxA recommends to
ACCEPTANCE PLAN the Owner acceptance of the documents.
This annex provides an example of how to implement e. Owner reviews the comments, their resolution, and
part of Guideline 0. It is not intended to be a comprehensive accepts the contract documents.
representation or a best practice example. Practitioners apply-
H3. CONSTRUCTION PHASE
ing the Cx Process should carefully follow Guideline 0 and
applicable commissioning technical guidelines tailored to The updated OPR, updated Cx Plan, updated BoD, sys-
their specific projects. tems manual, training program, and a preliminary and a final
Developing and documenting the acceptance procedures Construction-Phase Cx Process Report are formally accepted
in an acceptance plan is an important task for the successful by the Owner during the Construction Phase. The OPR, Cx
implementation of the Cx Process. The acceptance plan Plan, and BoD follow the same process as previously
details the key Cx Process Activities that must be accom- detailed.
plished at the end of each phase in a project in order to move The general process for accepting the systems manual is
on to the next phase. as follows:
The following provides a description of the details that a. The CxA tracks the contractor submittals for the required
should be included in the acceptance plan and demonstrates a documentation.
format that could be used. b. Within XX days of submittal acceptance for a system or
assembly, the contractor submits a draft systems manual
H1. PREDESIGN PHASE to the Owner, CxA, and design professionals.
The OPR and the Cx Plan are formally accepted by the c. The CxA consolidates the reviews and meets with the
Owner during the Predesign Phase, after review and comment design professionals to discuss and resolve.
by the CxA. The general process for accepting these docu- d. The contractor submits to the CxA changes to the
ments is: accepted submittals throughout construction.
e. XX days prior to the first training session, the contractor
a. The CxA develops a draft of each document and provides submits the final systems manual to the Owner, CxA, and
it to the Cx Team. design professionals.
b. The Cx Team provides comments on the draft documents. f. The Owner accepts the final systems manual based on the
c. The CxA works with the Cx Team to resolve any issues. recommendation of the CxA.
d. The CxA recommends acceptance of the documents to the
The general process for accepting the training program is
Owner and provides copies for review.
as follows:
e. The Owner reviews the modified documents and accepts.
a. The CxA provides the training agendas to the contractor.
H2. DESIGN PHASE b. The contractor develops the training program, including
The updated OPR, updated Cx Plan, BoD, and contract identifying the trainer, the schedule of sessions, and the
documents are formally accepted by the Owner during the material to be developed. This information is submitted to
the Owner, CxA, and design professionals for review and
Design Phase. The OPR and the Cx Plan follow the same pro-
comment.
cess as detailed in the Predesign Phase.
c. Based on the recommendation of the CxA, the Owner
The general process for accepting the BoD is as follows:
accepts the training program.
a. The CxA provides a list of information required and the d. The contractor then develops the training material and
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

format for the BoD to the design professionals prior to the submits it to the Owner, CxA, and design professionals
start of design. for review and comment XX days before the first training
b. The design professionals gather and organize the informa- session.
tion during the creation of the design. e. Based on the recommendation of the CxA, the Owner
c. The design professionals submit the BoD to the Owner accepts the training materials.
and CxA for review and comment with each design sub- f. The contractor implements the training program.
mittal. g. The CxA randomly quizzes the trainees two weeks after
d. Upon correction and resubmittal, the Owner accepts the the completion of a session.
BoD based on the recommendation of the CxA. h. The contractor submits copies of all training materials and
edited videotapes of the sessions.
The general process for accepting the contract documents i. The CxA recommends acceptance of the completed train-
is as follows: ing program to the Owner.
a. The design professionals submit the final package to the The general process for accepting the facility is as fol-
Owner and CxA for review. lows:

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

a. Throughout construction the CxA randomly samples the Phase. The OPR, BoD, and systems manual follow the same
completion of the construction checklists for meeting the process as previously detailed.
OPR. The general process for accepting the seasonal test
b. The CxA directs the completion of system and assembly results is as follows:
testing by the contractor and documents the results. a. The CxA directs the completion of seasonal system and
c. The CxA works with the contractor in resolving any assembly testing by the contractor and documents the
issues identified during testing. results.
d. The CxA verifies that all system documentation is b. The CxA works with the contractor in resolving any
received from the contractor. issues identified during testing.
e. The CxA presents a preliminary Construction-Phase Cx c. The CxA verifies that all updated system documentation
Process Report prior to occupancy that provides an evalu- is received from the contractor.
ation of meeting each element of the OPR, including rec- d. The CxA recommends to the Owner acceptance of the
ommendations to the Owner for acceptance/rejection of seasonal testing results.
the facility. The general process for accepting the Cx Process Report
f. The CxA provides a final Construction-Phase Cx Process is as follows:
Report with details on the Cx Process Activities com-
a. The CxA provides the Cx Process Report to the Owner,
pleted during the Construction Phase.
design professionals, and contractor for review and com-
ment.
H4. OCCUPANCY/OPERATIONS PHASE
b. The CxA incorporates comments and provides a final
The updated OPR, updated BoD, updated systems man- copy to the Cx Team members.
ual, seasonal test results, and Cx Process Report are formally c. The Owner accepts the Cx Process Report, ending the
accepted by the Owner during the Occupancy/Operations CxA’s responsibilities.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

35
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- d. Functional uses and requirements—In addition to general
mative and does not contain requirements necessary for documentation produced by the architect on functional
conformance to the guideline.) uses of the building (office, storage, kitchen, etc.), the spe-
cific requirements for each functional area must be docu-
INFORMATIVE ANNEX I mented. This can include such items as security, safety,
OWNER’S PROJECT REQUIREMENTS WORKSHOP comfort, energy, maintainability, and indoor air quality.
GUIDANCE e. Lifespan, cost, and quality—It is important to clearly doc-
This annex provides an example of how to implement ument the owner’s expectations for lifespan of materials,
part of Guideline 0. It is not intended to be a comprehensive cost of construction, and the level of quality desired. By
representation or a best practice example. Practitioners apply- providing this information, unrealistic expectations are
ing the Cx Process should carefully follow Guideline 0 and identified and eliminated.
applicable commissioning technical guidelines tailored to f. Performance criteria—Often the most difficult to define,
their specific projects. performance criteria detail minimum acceptable perfor-
The OPR is considered the heart and soul of the Cx Pro- mance benchmarks for various aspects of the facility.
cess. When the OPR is not developed, the owner, designer, g. Maintenance requirements—The maintenance require-
contractors, and operation and maintenance (O&M) person- ments are a mixture of the level of knowledge of the cur-
nel each interpret the building requirements, including their rent O&M staff (what can they maintain) and the expected
individual responsibilities, from the standpoint of their own complexity of the proposed systems (what they can learn).
specific needs. This often creates a range of diverse views of If there is a significant gap between the two, no matter
the constructed project’s needs. Unfortunately, while critical how well the building is constructed, it will not be main-
for a successful project, the OPR is rarely developed. Devel- tained or operated properly.
oping OPR that reflects the actual needs of the owner, the
users or occupants, service and operating units, and some- The following are examples of OPR elements that are
times the community is one of the, if not the, most important common to most of the Technical Cx Process Guideline top-
aspects for successful implementation of the Cx Process. ics:
The following sections detail an example format to fol- a. Benchmarks for performance—Specific criteria for the
low in developing the OPR and a discussion of how to obtain functional use of each space, assembly, and system must
the required information. Note that historically the OPR has be defined. These include temperature, humidity, airflow,
often been referred to as “design intent” or “project intent.” light, noise, durability, aesthetics (materials and colors),
service life, reliability, redundancy, and the like. Typi-
I1. FORMAT cally, upper and lower limits are provided for general
While there have been many formats used for presenting spaces, with exceptions noted as required.
criteria for the OPR, the OPR workshop is one that has been b. Problems to avoid—Because occupant/user/operator com-
well received by owners, designers, contractors, and O&M plaints are common, it is important to identify and docu-
personnel. The workshop initially addresses general needs/ ment those problems that have caused complaints in the
requirements and progresses to specific requirements (i.e., past. If these problems are not documented and the situa-
moves from project needs to system/equipment/control tion recurs, the occupants often consider the entire project
needs). It is organized around and focuses on assemblies and as a failure.
systems that have been identified as targets of the Cx Process. c. Specific occupant requirements—Specific items that are
The workshop needs to be well organized, and it is very desir- deemed important to the various occupants in a building
able to have the results formatted for immediate input into a must be identified and documented. In speculatively built
computer analysis program for rapid feedback on consensus buildings, this section would detail the limits to which
of the group. occupants can make use of their spaces. For example, a
Information from the workshop is only one of various chemical laboratory cannot be put in a space designed and
resources from which the OPR document is developed. Fol- constructed for general office use without significant
lowing is a description of some of the information that can be changes to the systems and possibly to the building as a
included in an OPR document. whole.
Key sections of the OPR document are:
I2. OBTAINING THE INFORMATION
a. Background—A narrative description to provide context
about the project. While it may be easy to obtain the information related to
b. Objectives—For any project there are goals that must be development of the OPR, it is difficult to obtain quality infor-
achieved for the project to be successful. Goals can range mation that the owner, O&M staff, service contractors, cus-
from first cost, to time schedule, to number of change tomers (i.e., students, patients, retail customers, renters),
orders, or to life-cycle cost. Regardless of which goals are visitors, subtenants, occupants, and the community all agree
identified, they must be summarized up front to ensure on. In quality-based processes, it is critical that input be
everyone is on the same page. obtained from all the users (the various user groups) and that
c. Green building concepts—This is an optional section for the consensus of and differences between the groups be docu-
owners who wish to focus on the sustainability aspects of mented. There usually are requirements for which users do
their building. not all agree. These must be documented as unresolved items.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

Normally, the owner will make final decisions on what the able?” but should be broader, such as “how do you define
priority order of elements will be. However, the owner and the comfort?” or “how will you measure the cost success of this
rest of the Cx Team must be aware of all requirements so that project?” (versus a broader question, such as “how will you
the final product will include as many individual group determine if this was a successful project?”).
requirements as are deemed appropriate and within the bud- I2.2 OPR Documentation. The OPR workshop will identify
get. key items and priorities important to the project team, the
A simple three-step process is recommended for develop- owner, users, and the Cx Team. However, it does not provide
ing the OPR: specific values. For example, the number one item in the OPR
1. OPR workshop may be good air circulation in the rooms. It is the responsibil-
2. OPR documentation (report) ity of the CxA to take the individual requirements developed
3. Project team approval of the OPR by the project team and translate them into physical proper-
ties that can be measured, designed, and documented.
I2.1 OPR Workshop. The OPR workshop is typically facili- This transformation of the OPR often requires input from
tated by the CxA, who elicits the primary concerns of the
a variety of sources, including the design team, contractors,
project team. The workshop is organized to encourage identi-
fication of all requirements, to encourage interaction and dis- specialists, standards, and guidelines. Typically, the CxA has
cussion among all team members, and to arrive at group sufficient experience in the planning, design, construction, and
consensus of priorities for the OPR. This is accomplished operation of facilities to provide the oversight of such a task. If
through the presentation of multiple questions in an ordered not, then experts should be retained to aid in the development
structure. A typical process uses a modified nominal group of the OPR.
technique workshop format. This is a formal means of gather- I2.3 Project Team Approval of the OPR. After several iter-
ing the highest level of consensus that approaches the real
ations and reviews of the OPR by the project and design
needs of the group. The procedure consists of the following
steps: teams, the requirements must be approved to provide the
design team adequate direction for their design. It is impor-
a. Provide each question or open concept to each individual tant to distinguish development of the OPR from the tradi-
participating in the workshop. tional role of the architect in the planning or programming
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

b. Allow three to five minutes of quiet writing time for each process. The OPR define the criteria required for success,
individual to respond with as many answers and ideas as whereas the architect’s document may only address specific
he/she can. space size and occupant flow requirements. Where the OPR
c. Record individual responses in a round-robin fashion—no may state that the functional use of the facility is X, Y, and Z,
discussion at this point, just record the responses on a the architect’s document may specify the locations of, the size
visual flipchart, overhead, chalkboard, or multicomputer of, and the flow of people through X, Y, and Z.
link to all participants.
d. Review all responses, consolidate similar ones, and clarify I3. SUMMARY
so all in the group have the same understanding of all
The OPR workshop is one means to provide consistency
responses.
in the implementation of the Cx Process from project to proj-
e. Have individuals rank the responses for importance (1
ect. It should be a topic addressed in the lessons-learned
through 5).
workshop during the Occupancy/Operations Phase of the Cx
f. Determine a group ranking from individual rankings.
Process. Other techniques for developing the OPR, such as
g. A rediscussion of the top 10 items—and any responses
interviews and surveys, do not allow interaction between the
ranked most important—is desired, followed by a second
user groups. Further, it has been shown that the results or
round of individual and group combined rating/ranking.
answers are biased by the beliefs of the expert who develops
The questions asked during this workshop must be broad the questions for the interviews or surveys. Frequently, using
in nature, elicit discussion, result in a variety of viewpoints, such techniques the questions can be analyzed and the con-
and must not leave the workshop. The questions should not clusions predetermined whether the interviews or surveys are
focus on such items as “at what temperature are you comfort- completed or not.

37
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- f. Occupancy Requirements—Includes the number of
mative and does not contain requirements necessary for occupants (users and visitors) and the schedule of occu-
conformance to the guideline.) pancy, including all special conditions.
g. Budget Considerations and Limitations—The expected
INFORMATIVE ANNEX J budgetary restrictions and considerations are contained in
OWNER’S PROJECT REQUIREMENTS this section.
h. Performance Criteria—The performance criteria on
This annex provides an example of how to implement which the project will be evaluated by the Cx Team are
part of Guideline 0. It is not intended to be a comprehensive included in this section. Each performance criterion
representation or a best practice example. Practitioners apply- should be measurable and verifiable. Include the follow-
ing the Cx Process should carefully follow Guideline 0 and ing subsections as appropriate to organize and explain the
applicable commissioning technical guidelines tailored to criteria:
their specific projects. 1. General
A general format for an OPR document is presented in 2. Economic
this annex. The structure provided is intended to encompass 3. User Requirements
the facility requirements and enable the addition of sections
4. Construction Process
depending on the systems and assemblies to be constructed.
5. Operations
a. Introduction—Includes an overview of the project and 6. Systems
the general reasons why the project is being undertaken. A 7. Assemblies
description of the owner’s processes (Cx Process) is typi- i. OPR Version History—Includes a summary of the
cally contained in this section. changes made throughout the Predesign, Design, Con-
b. Key OPR Items—Includes a listing of the key OPR that struction, and Occupancy/Operations Phases. This infor-
the Cx Process will focus on and that the owner (Cx mation is critical to understand and document the trade-
Team) has determined are critical to the success of the offs made over time and the resulting impact on the proj-
project. ect.
Table J-1 will assist in the development of the OPR
c. General Project Description—The size and scope of the
document in accordance with Section 5.2.2.4 using the
project are included in this section.
format presented in this annex. The table is also applica-
d. Objectives—The objectives for accomplishing this proj- ble for those developing technical supporting guidelines
ect are detailed in this section. as described in Annex A. Inclusion of specific criteria
e. Functional Uses—The expected functional uses (spaces) (such as the entries in this example matrix) will depend on
for the facility are detailed in this section. A short descrip- the project and the owner’s needs. The Key OPR Section
tion of each functional use is included to provide the con- should emphasize those OPR items that are essential to
text in which it was detailed. the success of the project.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TABLE J-1 Example Matrix for Developing OPR

OPR Section
Key Owner’s General
Guideline 0-2013
Project Project Functional Occupancy Budget Considerations
Subclause 5.2.2.4 Criteria
Introduction Requirements Description Objectives Uses Requirements and Limitations
1 2 3 4 5 6 7
(a) Project schedule and budget Schedule Budget
(b) Cx Process scope and budget Scope Budget
(c) Project documentation
requirements, including format
for submittals, training
materials, reports, and the
systems manual. Consideration ×
should be given to use of
electronic format documents
and records where appropriate
(d) Owner directives ×
(e) Restrictions and limitations ×
(f) User requirements ×
(g) Occupancy requirements and
schedules × ×
(h) Training requirements for
Owner’s personnel ×
(i) Warranty requirements ×

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
(j) Benchmarking requirements ×
(k) Operation and maintenance
criteria for the facility that
reflect the Owner’s expectations ×
and capabilities and the realities
of the facility type
(l) Equipment and system
maintainability expectations,
including limitations of × ×
operating and maintenance
personnel
(m) Quality requirements for
materials and construction ×
(n) Allowable tolerance in facility
system operations ×
(o) Energy efficiency goals × ×
(p) Environmental and
sustainability goals × ×
(q) Community requirements ×
(r) Adaptability for future facility
changes and expansion × × ×
(s) Systems integration
requirements, especially across ×
disciplines
(t) Health, hygiene, and indoor
environment requirements × ×
(u) Acoustical requirements ×
(v) Vibration requirements ×
(w) Seismic requirements ×
(x) Accessibility requirements ×
(y) Security requirements ×

39
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TABLE J-1 Example Matrix for Developing OPR (Continued)

OPR Section
General
Guideline 0-2013
Project Functional Occupancy Budget Considerations
Subclause 5.2.2.4 Criteria
Introduction Key OPR Description Objectives Uses Requirements and Limitations
1 2 3 4 5 6 7
(z) Aesthetics requirements ×
(aa) Constructability requirements ×
(bb) Communication requirements ×
(cc) Applicable codes and standards ×
OPR Section
Performance Criteria
OPR
Guideline 0 Body User Construction Version
General Economic Requirements Process Operations Systems Assemblies History
8 9 10 11 12 13 14 15
(a) Project schedule and budget
(b) Cx Process scope and budget
(c) Project documentation
requirements, including format
for submittals, training
materials, reports, and the
systems manual. Consideration
should be given to use of
electronic format documents
and records where appropriate
(d) Owner directives

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
(e) Restrictions and limitations
(f) User requirements ×
(g) Occupancy requirements and
schedules
(h) Training requirements for
Owner’s personnel × ×
(i) Warranty requirements ×
(j) Benchmarking requirements × × × ×
(k) Operation and maintenance
criteria for the facility that
reflect the Owner’s expectations × × ×
and capabilities and the realities
of the facility type
(l) Equipment and system
maintainability expectations,
including limitations of × × ×
operating and maintenance
personnel
(m) Quality requirements for
materials and construction × × × ×
(n) Allowable tolerance in facility
system operations × ×
(o) Energy efficiency goals × × × ×
(p) Environmental and
sustainability goals ×
(q) Community requirements ×
(r) Adaptability for future facility
changes and expansion × × × ×

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TABLE J-1 Example Matrix for Developing OPR (Continued)

OPR Section
Performance Criteria
OPR
Guideline 0 Body User Construction Version
General Economic Requirements Process Operations Systems Assemblies History
8 9 10 11 12 13 14 15
(s) Systems integration
requirements, especially across × ×
disciplines
(t) Health, hygiene, and indoor
environment requirements ×
(u) Acoustical requirements × × ×
(v) Vibration requirements × ×
(w) Seismic requirements × ×
(x) Accessibility requirements × × × ×
(y) Security requirements × × ×
(z) Aesthetics requirements × × ×
(aa) Constructability requirements × ×
(bb) Communication requirements × × ×
(cc) Applicable codes and standards

41
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- tive that provides an overview of assemblies and systems in
mative and does not contain requirements necessary for verbal format is usually an integral element of the BoD.
conformance to the guideline.) The BoD will typically be developed incrementally as
work on a project moves from Predesign, to Design, and into
INFORMATIVE ANNEX K the Construction Phase. Changes to the BoD that often occur
BASIS OF DESIGN (BoD) as a design evolves must be documented.
This annex provides an example of how to implement Content of the BoD will vary from project to project and
part of Guideline 0. It is not intended to be a comprehensive system to system, but in general it should address the follow-
representation or a best practice example. Practitioners apply- ing:
ing the Cx Process should carefully follow Guideline 0 and a. Specific codes, standards, and guidelines considered dur-
applicable commissioning technical guidelines tailored to ing design of the facility and designer interpretations of
their specific projects. such requirements.
The BoD records the major thought processes and b. Information regarding ambient conditions (climatic, geo-
assumptions behind design decisions made to meet the OPR. logic, structural, existing construction) used during
The OPR is intended to capture “what” the owner needs and design.
expects from a project. The construction documents detail c. Assumptions regarding usage of the facility.
“how” the OPR will be physically achieved. The BoD cap- d. Expectations regarding system operation and mainte-
tures important information linking the “what” and “how.” nance.
BoD documentation is distinct from the construction e. Performance criteria that the system was designed to
documents, is seldom included in drawings and specifica- meet—linked to the OPR.
tions, and is generally not needed by the contractor to meet f. Specific design methods, techniques, software used in
his/her obligations. It is exceptionally valuable to the Cx design.
Team, however, when evaluating the ability of a design and its g. A narrative statement of design that describes how the
components to meet the OPR. designer intends to meet the OPR.
The objective of specifically documenting BoD informa- h. A narrative statement of operation that details how the
tion is to provide the parties involved with a project, at each facility is expected to operate under various situations
phase in the process, an understanding of the underlying (such as normal operation, extreme event, emergency).
thinking that led to the selection of specific components, i. A listing of specific manufacturer makes and models used
assemblies, systems, and system integrations. A design narra- as the basis for drawings and specifications.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- designs for systems or assemblies to be signed and sealed by
mative and does not contain requirements necessary for licensed professionals.
conformance to the guideline.)
L2. THE COMMISSIONING AUTHORITY (CXA)
INFORMATIVE ANNEX L L2.1 The primary role of the CxA is to verify achievement of
SPECIFICATIONS the OPR throughout the project, from Predesign Phase
This annex provides an example of how to implement through Occupancy/Operations Phase. The Owner should
part of Guideline 0. It is not intended to be a comprehensive perform this role.
representation or a best practice example. Practitioners apply- L2.2 When the Owner cannot perform the CxA duties with
ing the Cx Process should carefully follow Guideline 0 and qualified personnel, then the CxA should have a separate pro-
applicable commissioning technical guidelines tailored to fessional services agreement with the Owner, as this avoids
their specific projects. conflicts of interest and provides independence from the other
parties (the Owner’s project manager, designers of record,
L1. SPECIFICATIONS FOR THE Cx PROCESS construction managers, suppliers, and construction contrac-
L1.1 This annex provides guidance on writing specifications tors). This professional services agreement defines the duties,
for Commissioning (Cx) Process Activities to be performed rights, and responsibilities of the CxA for each phase of the
by construction contractors. A guide specification is included project. This separate relationship allows the CxA to act inde-
with the assumption that the construction contractor is pendently as director of Cx Process Activities, to focus on
involved only during the construction phase and for the cor- achieving the OPR, and to communicate directly with the
rection and warranty period. Owner.
L1.2 Cx is a quality-oriented process for achieving, verify- L2.3 The CxA is a group of personnel with expertise and
ing, and documenting that the performance of facility systems experience in the design, construction, and operations of the
and assemblies meets defined objectives and criteria. The Cx various systems and assemblies included in the project. These
Process begins at project inception during the Predesign personnel are led by an individual who has expertise and
Phase and continues for the life of the facility through the experience in successfully implementing the Cx Process.
Occupancy/Operations Phase. During the Predesign Phase, L2.4 If the CxA is an employee, associate, or partner of the
the OPR (OPR) are determined and documented by the Cx same organization as the designer of record or construction
Team, which includes the Owner, Cx Authority (CxA), design management firm, there is a conflict of interest. While not a
professionals, operation and maintenance personnel, occu- recommended approach, in these instances the CxA must
pants, and users. Throughout each phase of the project, deliv- have a separate professional services agreement, be organiza-
erables (drawings, specifications, submittals, construction, tionally separate from the design team or construction man-
training, documentation, etc.) are verified against the OPR. agement team, and define and manage the conflicts of interest
L1.3 An important document created during the Cx Process to provide the Owner with the independence required for the
is the Basis of Design document or report (BoD). The design Cx Process to be successful.
professionals create this document or report during the design L2.5 The CxA does not perform testing; it directs the process
phase. The BoD records the concepts, calculations, decisions, and directs the recording of the results. The CxA plans,
and product selections to meet the OPR and to satisfy applica- schedules, and supervises Cx Process Activities to verify
ble regulatory requirements, standards, and guidelines. It can achievement of the OPR. The contractor completes construc-
include energy, environmental, sustainability, and other certi- tion checklists, performs tests, and accomplishes other Cx
fication criteria, both formal and informal. The BoD includes Process Activities.
both narrative descriptions and lists of individual items that

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
support the design process. L3. ORGANIZATIONAL STRATEGY FOR INCLUSION
L1.4 ASHRAE or NIBS Guideline 0 provides guidance on OF COMMISSIONING ACTIVITIES IN THE
content and basic format. While the OPR is Owner-developed SPECIFICATIONS
criteria, few Owners have the resources to develop the OPR. L3.1 Specifications (as a part of the construction contract
Owners without these resources depend on the Cx Team (see documents) should include only the Cx Process Activities the
a definition and discussion of the term Cx Team in this guide- contractors perform during the life of the construction con-
line) to assist them in developing the OPR. tract, including the work required during the correction period
L1.5 The OPR and BoD must be included or referenced in and for warranties.
the construction contract documents for informational pur- L3.2 Supplementary Conditions: Modify the general condi-
poses only. tions of the contract for construction in a document titled
L1.6 The construction contractor's obligation is to construct “Supplementary Conditions.” Among other provisions, define
the building and its systems and assemblies according to the the CxA and include the CxA's duties, rights, responsibilities,
requirements prescribed in the contract documents. There and limits of authority and additional requirements for sub-
normally are no performance requirements relating to the stantial completion. AIA Document A511, “Guide for Sup-
OPR stated in the contract documents. The exceptions to this plementary Conditions,” provides guidance about how to
include situations where contractors are required to provide write supplementary conditions.

43
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TABLE L-1 Description of Specification Sections


Section
Document/Section List of Contents Scope of Contents
Number
01100 SUMMARY Work covered by contract Describe Cx Process Activities as a part of the project.
documents
Alert the contractor that the Owner has contracted for
Identification of separate prime commissioning with a separate CxA.
contractors
Delineate scope of Cx Process.
01290 PAYMENT PROCEDURES No special Cx Process requirements.
01310 PROJECT MANAGEMENT AND Provisions about coordination of Add requirements to include CxA in coordination
COORDINATION Cx Process Activities among meetings (particularly “Preconstruction Meeting”).
contractors and subcontractors; Coordination of meetings and conferences.
project meetings.
01330 SUBMITTAL PROCEDURES Procedures for submittals Submittal requirements for Cx Process Activity Reports
and schedules should be specified in Sections 01811 to
01819.
Add requirements here for additional copies from
contractor to CxA and for approved submittals to be
distributed to CxA.
01400 QUALITY REQUIREMENTS Coordinate with Cx Process Activities, witnessing of
tests, and test reports.
01500 TEMPORARY FACILITIES AND Include office space for CxA and utility services for Cx
CONTROLS Process Activities.
01600 PRODUCT REQUIREMENTS No special Cx Process requirements.
01731 CUTTING AND PATCHING No special Cx Process requirements.
01770 CLOSEOUT PROCEDURES Include key Cx Process milestones to achieve
substantial completion and closeout.

01782 OPERATION AND Include requirements for CxA to review and


MAINTENANCE DATA recommend approval of systems manual.
Same procedures as described for Section 01330—
Submittals.
01810 GENERAL COMMISSIONING General administrative and procedural requirements
REQUIREMENTS without regard to specific systems and assemblies.
01811 BUILDING ASSEMBLY Substructure Lists of construction checklists
CX REQUIREMENTS Superstructure Prerequisites to testing
Building Shell System or assembly test requirements
Exterior Wall Assemblies Test reports
Roof Assemblies
Building Interior
Separations
Paths of Egress
01812 CONVEYING SYSTEM Elevators and Lifts Lists of construction checklists
CX REQUIREMENTS Escalators and Moving Walks Prerequisites to testing
System or assembly test requirements
Test reports
01813 PROTECTIVE SYSTEM Fire Suppression (including Lists of construction checklists
CX REQUIREMENTS pumps, sprinkler and standpipe Prerequisites to testing
piping, and terminal devices) System or assembly test requirements
Detection and Alarms (including Test reports
fire, smoke, gas, and leak)
Lightning Protection (this is not
part of electrical distribution)
Cathodic Protection (this is not
part of electrical distribution)

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TABLE L-1 Description of Specification Sections (Continued)


Section
Document/Section List of Contents Scope of Contents
Number
01814 PLUMBING SYSTEM Water Distribution Lists of construction checklists
COMMISSIONING Sanitary Waste Prerequisites to testing
REQUIREMENTS Storm Drainage System or assembly test requirements
Other Plumbing Systems Test reports
01815 HVAC&R SYSTEM Heat Generation (including central Lists of construction checklists

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
COMMISSIONING equipment, distribution systems, Prerequisites to testing
REQUIREMENTS and terminal devices) System or assembly test requirements
Refrigeration (including central Test reports
equipment, distribution systems,
and terminal devices)
Ventilation (including central
equipment, distribution systems,
and terminal devices)
HVAC Control Systems (including
central equipment, distribution
systems, and terminal devices)
01816 ELECTRICAL SYSTEM Power Distribution (including Lists of construction checklists
COMMISSIONING central equipment, distribution Prerequisites to testing
REQUIREMENTS circuits, and terminal devices) System or assembly test requirements
Lighting (includes fixtures and Test reports
controls)
01817 COMMUNICATIONS SYSTEMS Voice and Data Lists of construction checklists
COMMISSIONING Sound and Video Prerequisites to testing
REQUIREMENTS System or assembly test requirements
Test reports
01818 Security Access, Perimeter Lists of construction checklists
ELECTRONIC SAFETY AND Security, Intrusion Detection, Prerequisites to testing
SECURITY SYSTEMS Alarm and Detection Systems System or assembly test requirements
Cx REQUIREMENTS (including fire and smoke and leak Test reports
detection)
01820 DEMONSTRATION Coordination requirements with the CxA
INDIVIDUAL SECTIONS IN Field Quality Control Tests A statement requiring system, subsystem, or equipment
DIVISIONS 2 THROUGH 16 Adjusting and Balancing to be commissioned as a part of its parent system.
Cleaning A statement requiring contractor to complete
Demonstration construction checklists and perform tests.

L3.3 General Requirements for the Cx Process: Specifica- table of contents because section numbers and titles may have
tions in Division 1 include the general requirements for con- changed.
tractors relating to Cx Process Activities. The “Summary” L3.3.3 Extent of Testing: The contractor’s involvement in
Section describes, in general, how the contractors, separate Cx Process tests must be clearly defined. The extent of this
contractors (if there is more than one prime contractor), or the testing is determined by the Cx Team during the Design
construction manager must interact with the CxA. Adminis- Phase based on the OPR.
trative procedures for the Cx Process are specified in the Divi-
sion 1 Section “Commissioning.” L3.4 Component Cx Process Specifications: Sections in
Divisions 2 through 16 should specify testing and reporting
L3.3.1 The remainder of the specification language, with requirements for products and equipment that are part of a
the exception of Division 1 sections for temporary facilities system or assembly and then be referenced to the appropriate
and controls, should be mute on the subject of who must per- Cx Process sections in Division 1 for the overall system or
form the work. assembly requirements.
L3.3.2 Other Division 1 Cx Sections should describe the L3.4.1 During construction, the CxA verifies that contrac-
testing requirements for systems and assemblies. tor activities, such as installation and start-up; testing; demon-
stration and training of the Owner’s operator and maintenance
L3.3.2.1 References in Table L-1 are to MASTERSPEC® personnel; and systems manual, meet the OPR. Coordinating
section numbers and titles existing at the time this annex was activities by the contractor in support of the CxA should be
written. Refer to the current MASTERSPEC consolidated specified within the section where the component is specified

45
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(i.e., in individual sections in Divisions 2 through 16) if spe- number of options that could occur making the use of
cial requirements are necessary. The following are examples [Optional text] impractical.
of requirements to include in individual sections in Divisions
2 through 16: © 2004 The American Institute of Architects (AIA)
Exclusively published and distributed by Architectural
L3.4.1.1 Installation and Start-Up: Include requirements Computer Services, Inc. (ARCOM) for the AIA
for involvement of factory-authorized service representative This MASTERSPEC Section is licensed by ARCOM for
in individual sections and for the completion of construction limited distribution by ASHRAE as a part of “ASHRAE Guideline
checklists. 0 - The Commissioning Process,” Annex L, “Specifications.” The
MASTERSPEC Section may be updated before Guideline 0 is
L3.4.1.2 Testing: Include requirements to support the
updated. For information about the latest edition of this MASTER-
CxA in verifying test results, ranging from coordinating test-
SPEC Section, contact ARCOM at (800) 424-5080.
ing, to witnessing the test, to utilizing contractor personnel
and test equipment to verify the test report.
SECTION 01 9113
L3.4.1.3 Demonstration and Training: Include special
GENERAL COMMISSIONING REQUIREMENTS
requirements unique to the component within its own section.
L3.4.1.4 Operation and Maintenance Data: Include This Section uses the term “Architect.” Change this term to
unique requirements for the type of information required match that used to identify the design professional as defined in the
(e.g., particular requirements about parts lists, service sched- General and Supplementary Conditions.
ules, preventive maintenance lists, and emergency operations) Throughout the Section, the optional text “[each ]” is
included with the term “contractor.” Retain “each” for projects that
for long-term maintenance of the OPR.
include multiple prime contractors; delete for projects that have a
L3.4.2 In each section include an article under “General” single prime contractor.
that refers to Division 1 for Cx Process Activities for system Verify that Section titles referenced in this Section are correct
or assembly requirements. An example is as follows: for this Project's Specifications; Section titles may have changed.
1.XX Cx Process Activities
PART 1—GENERAL
A. The roofing materials specified in this Section
are included in the Cx Process as a part of the 1.1 RELATED DOCUMENTS
building envelope system and roofing subsystem
and integrated with flashing, coping, and insula- A. Drawings and general provisions of the Contract, includ-
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

tion. ing General and Supplementary Conditions and other


B. Complete the construction checklists and per- Division 01 Specification Sections, apply to this Section.
form tests specified in the Division 1 Section
“Building Assemblies Commissioning Require- Documents referenced in paragraph below should be
ments.” prepared during schematic design phase or earlier and updated as
design progresses. They should be provided to contractor when the
commissioning process is implemented on Project.
L4. INTRODUCTION TO GUIDE SPECIFICATIONS
This Specification Section was written in cooperation with
B. OPR and BoD documentation are included by reference
Architectural Computer Services, Inc. (ARCOM), who are the
for information only.
exclusive publishers and distributors of MASTERSPEC, a prod-
uct of the American Institute of Architects. MASTERSPEC 1.2 SUMMARY
Section 01 9113—General Commissioning Requirements—is
included in Guideline 0 by special agreement betweenASHRAE
A. This Section includes general requirements that apply to
and ARCOM.
implementation of the commissioning process without
L4.1 The section includes boxed notes that are instructions to regard to specific systems, assemblies, and components.
guide specifiers during editing of the specifications for a project.
B. Related Sections include the following:
L4.2 The section includes optional text in boldface font and
square brackets (e.g., [optional text]). These optional text List below only requirements that the reader might expect to
items include text that often occurs and provides an easy way find in this Section but are specified elsewhere. The first four and
to include these requirements in the master for consideration the last three subparagraphs are not yet available in MASTER-
for each project. SPEC but should be written and included if total building commis-
sioning is implemented.
L4.3 The section includes insert instructions in boldface font
and angle brackets (e.g., <Insert instructions>). These
instructions are placed where text must be inserted and pro- 1. Division 01 Section “Facility Substructure Commission-
vide some guidance about the nature of the text that must be ing” for commissioning process activities for foundations
inserted. Insert instructions are used when there are an infinite and basement systems and assemblies.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

2. Division 01 Section “Facility Shell Commissioning” for D. OPR: Owner's Project Requirements. A document, pre-
commissioning process activities for superstructure, exte- pared by Owner, that details the functional requirements
rior enclosure, and roofing systems and assemblies. of Project and expectations of how it will be used and
3. Division 01 Section “Interiors Commissioning” for operated. This document includes Project goals, measur-
commissioning process activities for interior construction, able performance criteria, cost considerations, bench-
stairways, and interior finishes systems and assemblies. marks, success criteria, and supporting information.
4. Division 14 Section “Commissioning of Conveying E. Systems, Assemblies, Equipment, and Components:
Equipment” for commissioning process activities for Where these terms are used together or separately, they
dumbwaiters, elevators, escalators and moving walks, shall mean “as-built” systems, assemblies, equipment,
lifts, turntables, and scaffolding systems, assemblies, and components.
equipment, and components.
5. Division 21 Section “Commissioning of Fire Suppres- 1.4 COMMISSIONING TEAM
sion” for commissioning process activities for fire
A. Members Appointed by Contractor(s): Individuals, each
suppression systems, assemblies, equipment, and compo-
having authority to act on behalf of the entity he or she
nents.
represents, explicitly organized to implement the commis-
6. Division 22 Section “Commissioning of Plumbing” for
sioning process through coordinated actions. The commis-
commissioning process activities for plumbing systems,
sioning team shall consist of, but not be limited to,
assemblies, equipment, and components.
representatives of [each ]contractor, including Project
7. Division 23 Section “Commissioning of HVAC&R” for superintendent and subcontractors, installers, suppliers,
commissioning process activities for commissioning heat- and specialists deemed appropriate by the CxA.
ing, ventilating, air-conditioning, and refrigeration B. Members Appointed by Owner:
systems, assemblies, equipment and components.
8. Division 25 Section “Commissioning of Integrated Auto- 1. CxA: An entity identified by the Owner who leads,
mation” for commissioning process activities for commis- plans, schedules, and coordinates the commissioning
sioning integrated automation systems, assemblies, team to implement the commissioning process.
equipment and components. Owner will engage the CxA under a separate contract.
9. Division 26 Section “Commissioning of Electrical” for 2. Representatives of the facility user and operation and
commissioning process activities for electrical systems, maintenance personnel.
assemblies, equipment, and components. 3. Architect and engineering design professionals.
10. Division 27 Section “Commissioning of Communica-
tions” for commissioning process activities for communi- 1.5 OWNER’S RESPONSIBILITIES
cation systems, assemblies, equipment, and components.
11. Division 28 Section “Commissioning of Electronic Safety A. Provide the OPR documentation to the CxA and
and Security” for commissioning process activities for [each ]contractor for information and use.
electronic safety and security systems, assemblies, equip- B. Assign operation and maintenance personnel and sched-
ment, and components. ule them to participate in commissioning team activities.
12. Division 33 Section “Commissioning of Utilities” for
commissioning process activities for water, wells, sanitary Coordinate activities specified in paragraph below with
Owner-Architect and Architect-Consultant agreements.
sewerage, storm drainage, fuel distribution, hydronic and
steam energy, electrical, and communications utilities
systems, assemblies, equipment, and components. C. Provide the BoD documents, prepared by Architect and
approved by Owner, to the CxA and [each ]contractor for
1.3 DEFINITIONS use in developing the commissioning plan, systems man-
ual, and operation and maintenance training plan.
Retain acronyms, abbreviations, and terms below that remain
1.6 [EACH]CONTRACTOR'S RESPONSIBILITIES
after this Section has been edited.

Coordinate this Article with requirements specified in Divi-


A. BoD: Basis of Design. A document, prepared by Archi- sion 01 Section “Summary of Multiple Contracts” for Project
tect, that records concepts, calculations, decisions, and Coordinator's responsibilities.
product selections used to meet the OPR and to satisfy
applicable regulatory requirements, standards, and guide- A. [Each ]contractor and their subcontractors shall assign
lines. The document includes both narrative descriptions representatives with expertise and authority to act on their
and lists of individual items that support the design pro- behalf and schedule them to participate in and perform
cess. commissioning process activities including, but not
B. Cx Plan: A document, prepared by CxA, that outlines the limited to, the following:
organization, schedule, allocation of resources, and docu-
mentation requirements of the commissioning process. 1. Evaluate performance deficiencies identified in test
C. CxA: Commissioning Authority. reports and, in collaboration with entity responsible
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

47
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

for system and equipment installation, recommend C. Convene commissioning team meetings.
corrective action.
2. Cooperate with the CxA for resolution of issues D. Provide project-specific construction checklists and com-
recorded in “Issues and Resolution Log.” missioning process test procedures.
3. Attend and participate in commissioning team meet- E. Verify the execution of commissioning process activities
ings held [weekly] [biweekly] [monthly] [variable] using random sampling. The sampling rate may vary
<Insert frequency>. from 1 to 100 percent. Verification will include, but is not
4. Integrate and coordinate commissioning process limited to, equipment submittals, construction checklists,
activities with construction schedule. training, operating and maintenance data, tests, and test
5. Review and accept construction checklists provided reports to verify compliance with the OPR. When a ran-
by the commissioning authority. dom sample does not meet the requirement, CxA will
6. Complete [paper] [electronic] construction check- report the failure in the “Issues and Resolution Log.”
lists as Work is completed and provide to the commis- F. Prepare and maintain issues log.
sioning authority on a [daily] [weekly],<Insert
G. Prepare and maintain completed construction checklist
frequency>. basis.
log.
7. Review and accept commissioning process test proce-
dures provided by the commissioning authority. H. Witness systems, assemblies, equipment, and component
8. Accomplish commissioning process test procedures. startup.
I. Compile test data, inspection reports, and certificates and
1.7 CxA’S RESPONSIBILITIES include them in the systems manual and commissioning
process report.
Include CxA responsibilities in this Article that have impact
on contractor activities and responsibilities. PART 2—PRODUCTS (NOT USED)
PART 3—EXECUTION (NOT USED)
A. Organize and lead the commissioning team.
B. Provide commissioning plan. END OF SECTION 01 9113
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- Construction checklists consist of two types:
mative and does not contain requirements necessary for
a. Component/Equipment Based. These construction
conformance to the guideline.)
checklists are used for components and pieces of equip-
ment that are delivered, installed, and started up during
INFORMATIVE ANNEX M construction. There is an individual checklist for each
CONSTRUCTION CHECKLISTS individual component or piece of equipment.
This annex provides an example of how to implement b. System/Assembly Based. These construction checklists
part of Guideline 0. It is not intended to be a comprehensive are used for systems and assemblies where separate
representation or a best practice example. Practitioners apply- checklists cannot be applied to subcomponents of the sys-
ing the Cx Process should carefully follow Guideline 0 and tem or assembly. There is a single checklist for the entire
applicable commissioning technical guidelines tailored to system.
their specific projects. The following provides a generic structure to follow for the
development of construction checklists for any equipment,
M1. OVERVIEW component, system, or assembly.

[INSERT EQUIPMENT/COMPONENT NAME] CHECKLIST

TAG ID:________

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
GENERAL INSTRUCTIONS:
1. This form is to be completed as the work is completed on [insert equipment/component name].
2. Complete Section 1—Model verification on delivery of equipment/component to either the job site or storage location.
3. Complete Section 2—Preinstallation checks just prior to initial installation.
4. Complete Section 3—Installation as installation progresses.
5. Fill in data, circle item, and initial as indicated.

1. [INSERT EQUIPMENT/COMPONENT NAME] MODEL VERIFICATION

Specified Submitted Installed


[list items to check, such as make, model, and size]

2. PREINSTALLATION CHECKS
The following must be completed on delivery of equipment/component to the work site.

Contractor Initial CxA


2A Physical Checks
[insert physical checks to be verified prior to installation, Yes / No
such as “free of damage” and cleanliness]
Yes / No
Yes / No
Yes / No
2B Component Verification
[insert component checks to be verified prior to installation, Yes / No
such as location and type of components]
Yes / No
Yes / No
Yes / No

49
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

3. INSTALLATION
The following items need to be verified during installation. Fill in blanks with check, specific information, or circle “yes” or
“no.” For any negative responses, complete Section 4.

Contractor Initials CxA


3A [insert title of major installation step]
[insert items to verify as installation step is accomplished] Yes / No
Yes / No
Yes / No
Yes / No
3B [insert title of major installation step]
[insert items to verify as installation step is accomplished] Yes / No
Yes / No
Yes / No
Yes / No
3C [insert title of major installation step]
[insert items to verify as installation step is accomplished] Yes / No
Yes / No
Yes / No
Yes / No
3D [insert title of major installation step]
[insert items to verify as installation step is accomplished] Yes / No
Yes / No
Yes / No
Yes / No
3E [insert title of major installation step]
[insert items to verify as installation step is accomplished] Yes / No
Yes / No
Yes / No
Yes / No

4. NEGATIVE RESPONSES (ATTACH SHEETS AS NECESSARY)

Item Reason for Negative Response Resolution


--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

[INSERT SYSTEM/ASSEMBLY NAME] INSTALLATION CHECKLIST

GENERAL INSTRUCTIONS
1. This form is to be completed daily by each [insert system/assembly name] work crew at the end of its shift.
2. Date and describe work completed in the appropriate section (1 for preinstallation and 2 for installation).
3. Verify achievement of quality requirements by circling “Yes” or “No.” For negative responses, complete Section 3.
4. Initial.

1. [INSERT SYSTEM/ASSEMBLY NAME] PREINSTALLATION CHECKS

Description of Items (see descriptions below)


Work Percent
Date Performed [Insert Title A] [Insert Title B] [Insert Title C] [Insert Title D] [Insert Title E] Complete Initial

Yes / No Yes / No Yes / No Yes / No Yes / No


Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

Yes / No Yes / No Yes / No Yes / No Yes / No


Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No

[INSERT TITLE A]: [INSERT DESCRIPTION OF TITLE A]

[INSERT TITLE B]: [INSERT DESCRIPTION OF TITLE B]

[INSERT TITLE C]: [INSERT DESCRIPTION OF TITLE C]

[INSERT TITLE D]: [INSERT DESCRIPTION OF TITLE D]

[INSERT TITLE E]: [INSERT DESCRIPTION OF TITLE E]

51
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

2. [INSERT SYSTEM/ASSEMBLY NAME] INSTALLATION CHECKS

Description of Items (see descriptions below)


Work Drawings Percent
Date Performed [Insert Title F] [insert Title G] [insert Title H] [insert Title I] Updated? Complete Initial

Yes / No Yes / No Yes / No Yes / No Yes / No


Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No
Yes / No Yes / No Yes / No Yes / No Yes / No

[INSERT TITLE F]: [INSERT DESCRIPTION OF TITLE F]


--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

[INSERT TITLE G]: [INSERT DESCRIPTION OF TITLE G]

[INSERT TITLE H]: [INSERT DESCRIPTION OF TITLE H]

[INSERT TITLE I]: [INSERT DESCRIPTION OF TITLE I]

DRAWINGS UPDATED: THE INSTALLED SYSTEM IS SHOWN ON THE RECORD DRAWINGS.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

3. CONFLICTS (ATTACH SHEETS AS NECESSARY)

Date Description of Conflict Suggested Resolution Resolved?


Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

53
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- 7, etc., for each remaining area. This selection is accom-
mative and does not contain requirements necessary for plished typically using the architectural sheets.
conformance to the guideline.) b. Select Review Samples on Drawings: Using the sampling
strategy chosen in Step 1, mark the sample areas to be
INFORMATIVE ANNEX N reviewed in each area. This should be accomplished for
QUALITY-BASED SAMPLING EXAMPLES each trade (landscaping, architectural, structural, plumb-
This annex provides an example of how to implement ing, mechanical, electrical, etc.).
part of Guideline 0. It is not intended to be a comprehensive c. Accomplish Coordination Review: For each area, compare
representation or a best practice example. Practitioners apply- the squares between each discipline. The intent of this
ing the Cx Process should carefully follow Guideline 0 and review is to identify coordination problems with the
applicable commissioning technical guidelines tailored to placement and installation of components. Items of spe-
their specific projects. cific interest include the following:
1. Placement of multiple pieces of equipment/compo-
N1. DESIGN-PHASE SUBMISSIONS nents in the same location
A critical step in the Cx Process is the review of the 2. Accessibility to equipment/components for mainte-
design submissions from the design professionals. It is impor- nance/replacement
tant to remember that the role of the CxA is to verify that the
3. Use of consistent terminology (e.g., room numbers)
OPR is met and that the system is designed in a quality man-
ner. There are three distinct reviews that are completed on a 4. Elevations provided where multiple systems are
drawing set: general, coordination, and field specific. A placed in the same area
review of the specifications is also required. The general steps 5. Other trade duties clearly identified (e.g., electric wir-
of completing a drawing review are as follows: ing for HVAC equipment, holes for sinks)
N1.1 General Review If significant coordination problems are identified, stop
a. Review the OPR: Since the drawing review is to verify the review and contact the design professionals to discuss. If
that the OPR is met, prior to the review, the OPR should the coordination is good, continue on with the Field-Specific
be reviewed to familiarize the reviewer with the key crite- Review.
ria of the facility. N1.3 Field-Specific Review
b. Document the General Review Criteria: The criteria from
which to accomplish the general review of the submission a. Determine the Review Sampling Procedure: Use random
must be documented. The criteria should be based on gen- sampling that selects every xth square on the drawings to
eral quality characteristics and specific OPR criteria. The be verified. Squares that are completely blank (no walls,
general quality characteristics should include items such equipment, etc.) are not included in the counting. For
as the following: example, if there are 10 pages of drawings and each draw-
ing is split into 15 grids (5 × 3), there will be 150 potential
1. Continuation of items (ductwork, pipes, etc.) from
grids to review. If a 20% sample rate is desired, then 30
page to page
grids would be reviewed, or every 5 grids. The starting
2. Labeling, including correct room numbering grid should be chosen using a random selection process
3. Details corresponding to actual components (die, 1–6 in a hat, etc.).
4. Schedules including BoD information b. Document Review Criteria: The criteria from which to
5. All information legible (not hidden by crossing lines review the drawings should be based on specific OPR cri-
or text) teria. This typically includes items such as accessibility,
maintainability, meeting sustainability goals, comfort con-
6. OPR information is included on drawings
ditions, documentation of OPR and BoD, and operating
c. Accomplish Quick General Review: The general review is
details.
intended to familiarize the reviewer with the submission.
If, during this review, significant items are identified as of c. Select Review Samples on Drawings: Using the sampling
poor quality, then the review process should be stopped strategy chosen in Step 1, mark the sample areas to be
and the design professionals contacted to discuss the qual- reviewed.
ity concerns. If the general quality is good, move on to the d. Accomplish Detailed Statistical Review: Using the review
Coordination Review. criteria from Step 2 and the selections from Step 3,
accomplish a detailed review of the drawings. This
N1.2 Coordination Review includes verifying that the specifications match those
a. Determine Sampling Areas: For each floor plan area (i.e., shown on the drawings (see below for specification review
if there are five sheets for each floor, then there are five details). For example, if a VAV box is in the selected
floor plan areas for each floor) select a single 10 × 10 in. square, the steps in accomplishing the detailed review
(250 × 250 mm) square randomly. A simple way to do this might include the following:
is to divide the drawing sheet into 15 squares (5 × 3) and 1. Review design calculation inputs for matching archi-
select square number 3 on the first sheet (area) and then 5, tectural assumptions and the OPR.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

2. Compare calculation results with the total airflow of reviews all submittals against the contract documents (specifi-
the diffusers downstream of the VAV box and with the cations), the CxA compares a sample (typically 5%–10%) of
VAV box schedule. a submittal against the OPR and BoD. This different approach
3. Compare location of VAV box with maintenance is due to the fact that the commissioning process role is to
requirements of the selected make and model (BoD). verify achievement of the OPR using quality tools.
4. Compare VAV box location on drawings with require- The following are general guidelines for implementing
ments in the specifications. quality based sampling on contractor submittals:
5. Review the OPR for other issues that the VAV box a. Submittal Received: Verify submittal falls within commis-
could impact. sioning process scope.
e. Document Concerns: During the review of the drawings b. Select Sample for Review
keep detailed notes of problems found or concerns with 1. Single/Few (<10) Components: Choose every xth part
certain items. Also, at the end of the review, a general of the submittal—for example, for a 10-page submit-
summary of the quality of the drawings should be devel- tal, to get a 10% sample, divide each page into 6 parts
oped. A letter detailing the quality of the drawings should and select every 10th block (resulting in 6 blocks to
then be sent to the design professionals and the owner check).
with specific recommendations and directions given. 2. Multiple Components: choose every yth component
f. Review the Drawing Review Procedure: After the drawing (typically 20%–30% of components) and then divide
review is completed, this document should be reviewed and select blocks as detailed above for “Single/Few
and modified to improve the process for the next time. (<10) Components.”
N1.4 Specification Review c. Accomplish Review: For each sample block, review infor-
mation contained against the OPR and BoD. Identify dis-
a. Determine the Review Sampling Procedure: The purpose continuities.
of this review is to determine the general quality of the
d. Results: Document results of the review. Typically, if con-
specifications. During the Field-Specific Review, the
sistent issues are identified, the general quality of the sub-
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

actual details are checked. The sampling procedure should


mittal to achieve the OPR is lacking and the
check approximately 10% of the specifications. The easi-
recommendation provided to the design professional
est way of doing this is to check every xth page of the
should be to reject the submittal. In the CxA write-up, it is
specifications (i.e., if there are 100 pages, check every
important to state that a sampling approach was used to
10th page).
avoid having the design professional or others assume that
b. Accomplish General Review: The review should focus on the CxA reviewed everything.
the quality of the specification, specifically as follows:
1. Are there extraneous sections that do not pertain to the N3. CONSTRUCTION-PHASE TESTS
project (i.e., medical gas in an office building, 15 types AND VERIFICATIONS
of valves when only 2 used, etc.)?
The role of accomplishing site visits and commissioning
2. If a manufacturer has been listed, has the engineer process tests is the ongoing verification of OPR achievement.
checked to verify that the OPR is met? Because the contractor is responsible for 100% construction
3. Are there any “or as equals”? (“As equal” should and checking of work, the commissioning process utilizes a
always be defined) sampling strategy in accomplishing verifications and tests.
4. Are the directions clear and concise?
a. Construction Checklist Verifications: During site visits,
c. Develop Summary of Review—Develop a summary of the
the completed construction checklists are verified (typi-
review. If there are problems with the specifications, con-
cally 2%–10%). The following is general guidance for
tact the design professionals and discuss.
selecting and verifying construction checklists.
N1.5 Design Professional Actions. Comments provided by 1. Identify completed construction checklists: Identify
the CxA should be formally replied to by the design profes- the construction checklists that have been completed
sionals. If systemic issues are identified during the CxA’s since the last site visit.
review, the design process should be stopped and the issues 2. Select Sample: Depending on the pace of construction
resolved. It is expected at the next submission that the CxA and the size of the project, the number of new con-
will again use random sampling that will result in a review of struction checklists can vary widely. The following is
different areas on the drawings and the specifications and that a general guide for sample rates based on the number
will identify whether the systemic issue has been resolved. of new construction checklists. Please note that this is
Back-checking of the specific items may be appropriate, but not meant to be used directly for your project due to
not as the sole means of verifying resolution of the issue. the many variables in determining acceptable sample
rates and owner input. Randomly select the construc-
N2. CONTRACTOR PHASE SUBMISSIONS tion checklists to be verified. Note that you often want
The focus of the review of contractor submittals by the to sample similar components as a group so that if
CxA during construction is different from that accomplished there is only 1 or 2 of a particular component, it is not
by the design professional. Whereas the design professional missed. Because the sampling rate is lower for these

55
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

# New Construction Checklists Overall Sample Rate Component Sample Rate

1–10 100% 70%–100%

11–20 80% 50%–70%

21–50 50% 30%–50%

51–100 30% 15%–30%

>100 2–20% 2%–10%

than for other components, you can compare results This process approach then utilizes sampling to bet-
between similar components more easily. ter evaluate achievement of the OPR as the sampling
3. Accomplish Verification: For the chosen sample, com- allows for more in-depth testing as well as analysis of the
pare the completed construction checklist to the actual results.
installation. Pay particular attention to common OPR, The same sampling approach used for construction
such as accessibility, maintainability and future instal- checklists can be used for Cx Process tests. The differ-
lation steps. Also, verify the record drawings with the ence is that instead of using completed construction
actual installation. checklists as the sampling group, the focus of the test is

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
b. Cx Process Tests: The preparation for the Cx Process the selection group. For example, the following are
Tests includes all of the activities completed during Prede- potential selection groups for their OPR:
sign, Design, and Construction Phases, including design 1. Comfort: The individual rooms/spaces in the building
reviews, submittal reviews, construction checklist verifi-
cations, and verification of contractor completed tests and 2. Exterior Enclosure: The individual components or
system startup. Therefore, the role of the Cx Process tests assembly types, or each interface between compo-
is to provide the final report card for the project, with the nents/assemblies
expectation of getting an A+. 3. Energy: Energy-using components

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- with their contact information should be included in
mative and does not contain requirements necessary for this section.
conformance to the guideline.) 2. OPR (facility level). A copy of the final OPR for the
facility is included in this section. This document was
INFORMATIVE ANNEX O initially developed during the Predesign Phase and
SYSTEMS MANUAL was updated throughout the project by the Owner,
This annex provides an example of how to implement CxA, or design professionals.
part of Guideline 0. It is not intended to be a comprehensive 3. Basis of Design (facility level). This section includes
representation or a best practice example. Practitioners apply- the final BoD document at a facility level. This docu-
ing the Cx Process should carefully follow Guideline 0 and ment is written by the design professionals during the
applicable commissioning technical guidelines tailored to Design Phase and is updated by them to include any
their specific projects. changes during the Construction Phase.
Developing the systems manual encompasses gathering 4. Construction record documents and specifications
all of the information related to the systems, assemblies, and (not included in specific systems sections). This sec-
the Cx Process and incorporating it into a usable information tion includes elements of the record set of construction
resource with indexes and cross-references. This resource documents (including specifications) that are not cov-
shall include the final OPR, BoD, the final Cx Plan, Cx Pro- ered under specific systems—updated to reflect the
cess Report, manufacturer installation manuals, manufacturer final installation.
operations and maintenance manuals, system schematics, ver- 5. Approved submittals (not included in specific sys-
ified record drawings, and test results. This information is tem sections). This section includes a copy of the
edited and organized to focus on the key systems (roofing, approved submittals (not included under specific sys-
walls, fire alarm, chilled water, hot water, etc.) in the building. tems) with all field modifications and accessories
Coordination with operations and maintenance personnel in clearly marked. In addition, the comments from origi-
developing standard formats and divisions (shops) is accom- nal submittals shall be included.
plished to simplify future systems manual development. 6. Facility operating procedures for all normal,
Also included in the systems manual is the development abnormal, and emergency modes of operation
of periodic maintenance and information for insertion into a (facility level). This section includes detailed operat-
computer maintenance management system (CMMS), includ- ing procedures for the facility during normal, abnor-
ing equipment make and model information, checking mal, and emergency modes of operation. This is not
requirements, maintenance requirements, and troubleshooting intended to be automatic control sequences, but gen-
items. eral operating procedures. This would include items
The CxA shall be responsible for verifying the develop- such as building access during various situations (nor-
ment of the systems manual. mal operation, after-hours operation, fire alarm, civil
The entity responsible for developing the systems manual disturbance operation, emergency power operations,
shall include all items involved in the project and capture the etc.).
system and assembly data in either an electronic or printed 7. A list of recommended operational record keeping
version. In addition, printed operations, service, maintenance, procedures at the facility level, including sample
spare parts list, and repair manuals may be provided. This forms, trend logs, or others, and a rationale for each.
entity (owner, contractor, design professional, other) shall This section includes direction to the operation and
have the skills of design, construction, and operations maintenance personnel as to what information needs to
required to develop a cohesive systems manual. be documented and kept on the operation of the facility
The required details for a full systems manual are and why these records are important or will benefit the
enhanced in each of the technical Cx Process guidelines. The Owner or operations and maintenance personnel in the
systems manual will have multiple sections depending on the future.
number of systems focused on during the Cx Process. The
8. Maintenance procedures, schedules, and recom-
systems manual will include a detailed table of contents with
mendations (facility level). This section includes the
a notation as to resource storage location if not in the actual
manufacturer’s recommendations for maintenance pro-
manual. The following outline is a recommended format:
cedures and when maintenance should be performed
a. General on systems not included in specific system sections.
1. Executive summary (facility level). This section 9. Ongoing optimization (facility level). This section
includes an overall description of the building and its includes guidance for the ongoing optimization of the
systems, including a listing of major capabilities and facility. Included in the section are schedules of peri-
limitations imposed by the design or building code. odic benchmarking using checklists and tests devel-
The description should include type of facility, general oped for the original construction, procedures for
description (number of floors, gross area, net area, maintaining the OPR and BoD documents, and guid-
type of occupancy, etc.), and general system descrip- ance on what to do when the OPR is not met.
tions. A list of contractors, subcontractors, suppliers, 10. Attachments. Cx documents listing and storage loca-
architects, and engineers involved in the project along tion.
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

57
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

[The following section is completed for each system or procedures for xxx systems/assemblies during normal,
assembly requiring operation and maintenance.] abnormal, and emergency modes of operation. This is
not intended to be automatic control sequences, but
b. xxx System/Assembly general operating procedures.
1. Executive summary (xxx System/Assembly). This 7. A list of recommended operational record-keeping
section includes a description of the systems/assem- procedures, including sample forms, trend logs, or
blies covered in this section, including a listing of others, and a rationale for each (xxx System/
capabilities and limitations imposed by the design or Assembly). This section includes direction to the
building code. The description should include type of operations and maintenance personnel as to what
system/assembly, general description, and schemat- information needs to be documented and kept on the
ics. A list of contractors, subcontractors, suppliers, operation of the systems and why these records are
and design professionals involved with this system important or will benefit the Owner or operations and
along with their contact information should be maintenance personnel in the future.
included. 8. Maintenance procedures, schedules, and recom-
2. OPR (xxx System/Assembly level). A copy of the mendations (xxx System/Assembly). This section
final OPR dealing with this system/assembly is includes the manufacturer’s recommendations for
included in this section. This document was initially maintenance procedures and when maintenance
developed during the Predesign Phase and was updated should be performed.
throughout the project by the Owner, CxA, or design 9. Ongoing optimization (xxx System/Assembly). This
professionals. section includes guidance for the ongoing optimiza-
3. Basis of Design (xxx System/Assembly level). This tion of the system/assembly. Included in the section
section includes the final BoD (including the design are schedules of periodic benchmarking using check-
intent) as related to the specific systems included in lists and tests developed for the original construction,
this section. This document is typically written by the procedures for maintaining the OPR and BoD docu-
design professionals during the Design Phase and is ments, and guidance on what to do when the OPR is
updated by them to include any changes during the not achieved.
Construction Phase. 10. Operations and maintenance manuals (xxx System/
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

4. Construction record documents and specifications Assembly). This section includes the manufacturer’s
(xxx System/Assembly). This section includes the printed operations and maintenance manuals for the
record set of construction documents (including speci- specific equipment/components provided for the xxx
fications) that has been updated to reflect the final system/assembly. Also included is a parts and recom-
installation of the specific system/assembly included mended spare parts list, a troubleshooting guide for
in this section. common situations, and one-line diagrams for each
5. Approved submittals (xxx System/Assembly). This applicable system.
section includes a copy of the approved submittals for 11. Training records (xxx System/Assembly). This sec-
the components associated with the system/assembly tion includes information on training provided and
with all field modifications and accessories clearly attendees. In addition, information on ongoing train-
marked. In addition, the comments from original sub- ing shall be provided.
mittals shall be included. 12. Cx Process Report for xxx System/Assembly. This
6. Operating procedures for all normal, abnormal, section includes the final Cx Process Report for the
and emergency modes of operation (xxx System/ xxx system/assembly, including all test procedures,
Assembly). This section includes detailed operating test results, and blank test forms.

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This annex is not part of this guideline. It is merely infor- A receipt acknowledging completion of each item of
mative and does not contain requirements necessary for instruction will be secured.
conformance to the guideline.) The training will be evaluated based on the criteria in the
attached evaluation form.
INFORMATIVE ANNEX P
P1.3 Electrical Systems. The training shall include the fol-
TRAINING MANUAL AND TRAINING NEEDS
lowing:
This annex provides an example of how to implement
a. General familiarization and operating procedures for the
part of Guideline 0. It is not intended to be a comprehensive
entire electrical installation
representation or a best practice example. Practitioners apply-
ing the Cx Process should carefully follow Guideline 0 and b. Routine maintenance procedures for equipment
applicable commissioning technical guidelines tailored to c. Specific operating and maintenance procedures for the
their specific projects. following:
This annex is a collection of various requirements for 1. Switchboards
training and identifies needs for the training manual. The
2. Emergency power supply system
training manual includes the training plan, which is composed
of the training syllabus and agenda that are provided to the 3. Fire alarm system
contractor by the Owner with help from the CxA. The train- Factory-trained technicians will provide operating and
ing manual also contains the results of training, including the maintenance instructions on the following:
training material and training evaluations completed by the
contractor. It is an example to provide direction, in that train-
ing needs vary substantially for each construction project or System/Equipment Minimum Session Duration, h
new building. The following is an example of a training man-
ual outline or syllabus with a focus on electrical and mechani- Emergency power supply system ×
cal systems. ×
Fire alarm system

P1. TRAINING SYLLABUS Lighting control systems ×


P1.1 Overview. This syllabus describes the objectives of the
Switchboards ×
various sessions, lectures, and demonstrations that form a part
of the training program developed for the Do-It-Right Building. Medium voltage pad-mounted
P1.2 Sessions. There are two main sessions on the electrical switchgear ×
systems and two main sessions on the mechanical systems
that will provide training to the OK Service personnel. The
P1.4 Mechanical Systems. The training shall include the
first session will be conducted at the time of start-up and
following:
check-out and the second session will be about two months
later. Sessions will be a minimum of two days duration for the a. General familiarization with and operating procedures for
basics in each system and be conducted as specified below. the entire plumbing, laboratory gas, pure water, com-
The sessions will be conducted at the site. pressed air, fuel, HVAC&R, and fire protection systems
All training sessions will be visually recorded using installation.
either videotape (VHS format) or standard compact disk (CD) b. Routine maintenance procedures for equipment.
in PC format. The CD format is desired for longevity and key- c. Specific operating and maintenance procedures for the
word searching. The sessions can be recorded on videotape following:
and then transferred to CDs. 1. Hot-water system consisting of boilers, pumps, con-
A training agenda in the format enclosed will be provided trols, and hydronic specialties
for each session. This will be submitted three weeks prior to
2. Chilled-water systems consisting of chillers, cooling
the scheduled training session. All listed owner’s representa-
towers, pumps, controls, and hydronic specialties
tives will sign this prior to proceeding with the training.
3. Automatic temperature control system consisting of
A list of training topics that are appropriate for consider-
all associated hardware, software, and program logic,
ation are listed in the attached Training Agenda Topics list.
arranged by systems
The Commissioning Authority (CxA) will be notified of
4. Laboratory air-side control system consisting of sup-
the scheduled training time and provided with a copy of the
ply, hood, and general exhaust valves, reheat coils, and
training material fifteen days prior to each training session.
room control panel
The CxA will review the material and share comments with
the Owner and the design professionals. If any aspects do not 5. Clean agent fire suppression systems, including emer-
meet the requirements of the specifications, this will be com- gency procedures, abort functions, and safety require-
municated through the design professionals. The CxA will ments
attend 25% or more of the training sessions. 6. Laboratory hood exhaust air system
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

59
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

Factory-trained technicians will give instruction on the P1.5 DDC System. There will be two formal training ses-
following specialty systems and equipment: sions on the DDC system. Each of the sessions will be con-
ducted by factory-trained personnel for a minimum duration
of xx 8-hour days. Materials and training will be provided for
System/Equipment Minimum Session Duration, h up to xx operators per session (selected by the Owner).
There will be a separate training course provided on the
Variable-speed drives × DDC system for supervisory personnel. This training will
Chillers × briefly cover the material of the operator training session but
will be focused on the more advanced features of the system
Automatic temperature with emphasis on the energy conservation strategies and
controls
×
reporting capabilities of the system and how to implement
Water treatment systems × them. The training session will be conducted by factory-
trained personnel for a minimum duration of xx 8-hour days,
Laboratory control systems × for a total of xx training hours. Materials and training will be
provided for up to xx persons selected by the Owner.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

Project: Do-It-Right—Wonderful Sky Building

Systems manual; Evaluation Forms; Record Forms; Specification Sections, Miscellaneous


Training Material:
Manufacturer’s Documentation, Field Equipment (for demonstrations)

SECTION 1. AUDIENCE AND GENERAL SCOPE


 O&M Staff,  Supervisory Personnel
Intended audience type:
 Laboratory Users  __________________
General scope of training:  A. Overview  B. Intermediate  C. Detailed

SECTION 2. INSTRUCTORS
ID Instructor (Factory Trained) Company
1) _____________________________________ ___________________________________________
2) _____________________________________ ___________________________________________
3) _____________________________________ ___________________________________________
4) _____________________________________ ___________________________________________
5) _____________________________________ ___________________________________________

SECTION 3. AGENDA
SESSION A—ELECTRICAL AND FIRE PROTECTION SYSTEMS
Duration Instructor
Lectures/Demonstrations Dates Location (h × freq*) ID(s)

A1 Emergency power supply system ______________ _______ 82 _________

A2 Fire alarm system ______________ _______ 82 _________

A3 Lighting control ______________ _______ 42 _________

A4 Switchboards ______________ _______ 42 _________

A5 Medium voltage pad-mounted switchgear ______________ _______ 42 _________

O&M procedures for clean agent fire suppression systems,


A6 including emergency procedures, abort functions, and safety ______________ _______ 4v2 _________
requirements

Total duration of training (h) -------------------------------------------------------------------------> 64

SESSION B—MECHANICAL AND PLUMBING SYSTEMS


Duration Instructor
Lectures/Demonstrations Dates Location (h × freq*) ID(s)

B1 Variable speed drives ______________ _______ 42 _________

B2 Chillers ______________ _______ 42 _________

General familiarization and operating procedures for plumbing


B3 ______________ _______ 32 _________
equipment

B4 Water treatment systems ______________ _______ 22 _________

Total duration of training (h) -------------------------------------------------------------------------> 26

61
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

SESSION C—CONTROL SYSTEM


Duration Instructor
Lectures/Demonstrations Dates Location (h × freq*) ID(s)
C1 Laboratory control systems _____________ _______ 8  2* _________
C2 Automatic temperature controls _____________ _______ 10  2* _________
C3 DDC system operations (for up to xx operators) _____________ _______ 32  2* _________
DDC system emphasis on advanced features of system, energy
C4 conservation strategies, and reporting capabilities and how to _____________ _______ 16  1 _________
implement them (for up to xx supervisors)

Total duration of training (h) -------------------------------------------------------------------------> 116

* Frequency is 2 formal training sessions as per spec. sections 15900, pg. 16, Part 2.1, and 16800, pg. 5, Part 7.3. The first session shall be conducted at the
time of start-up and check-out and the second session shall be approximately 2 months later.

SECTION 4. APPROVALS
This Training Program has been approved by the following individuals, subject to any additions and clarifications noted.
(This is not an approval of training completion.)

_____________________________________________ _____________________________________
Do-It-Right, Inc. Representative Date

_____________________________________________ ____________________________________
Cx Authority Date
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

TRAINING AGENDA TOPICS


(Suggested General Topics to Be Included)

Requested by
Desired
Suggested List of Subjects D-I-R, Inc.
Duration, h
()

1. Overview and description of the purposes of the system

System troubleshooting: description of diagnostic step-by-step procedures for determining the source
2.
of problems on the system level; review technical service manual in detail

Component maintenance: instruction of required procedures for weekly, monthly, and annual
3.
preventive checks and timely repairs to preserve system integrity

Component troubleshooting: description of diagnostic procedures for determining the source of


4.
problems on the component level

5. Review of control drawings and schematics (have copies for attendees)

Startup, loading, normal operation, unloading, shutdown, unoccupied operation, seasonal changeover,
6.
etc., as applicable

7. Integral controls (packaged): programming, troubleshooting, alarms, manual operation

Building automation system (BAS) controls: programming, troubleshooting, alarms, manual


8.
operation, interface with integral controls

9. Interactions with other systems, operation during power outage and fire

10. Relevant health and safety issues and concerns and special safety features

11. Energy-conserving operation and strategies

12. Any special issues to maintain warranty

Common troubleshooting issues and methods, control system warnings and error messages, including
13.
using the control system for diagnostics

14. Special requirements of tenants for this equipment’s function

15. Service, maintenance, and preventive maintenance (sources, spare parts inventory, special tools, etc.)

16. Question and answer period

Total hours requested

Total hours required by specifications

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

63
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

Training Evaluation
Session: _______________________________
Date: ____________ Location: _______________________
Purpose: This form is used to evaluate each training session. Based on this evaluation, later sessions can be improved. This form will be
completed by the CxA and one D-I-R employee in the training session after each session.
Every attendee fills out one copy of this form. Mark questions that are not applicable with N/A.
1 = very well to 5 = not at all
1. How were the objectives of this training session met? 1 2 3 4 5 N/A
2. Do you know where the components/systems are located? 1 2 3 4 5 N/A
3. Do you know what area the components/systems are serving? 1 2 3 4 5 N/A
4. Do you understand the various types and purpose of these components/systems? 1 2 3 4 5 N/A
Do you understand/know how to systematically troubleshoot common problems with
5. 1 2 3 4 5 N/A
these components/systems?
6. Do you know how the components/systems operate under all normal modes? 1 2 3 4 5 N/A
How well do you understand the importance of meeting the design intent for the systems
7. 1 2 3 4 5 N/A
covered?
Are you able to efficiently find the relevant information in the systems manual to operate
8. 1 2 3 4 5 N/A
and maintain the systems/components you were trained for in this session?
Do you know how to perform the needed maintenance on the equipment and/or do you
9. 1 2 3 4 5 N/A
know to get the information you need?
10 Do you know how to get updated technical service information for the components/
1 2 3 4 5 N/A
. systems?
Explain why any questions got very low or very high ratings from you:

What topics would you desire to be covered that were absent from this training session?

You may provide other comments concerning anything about this training session (e.g., information prior to training, content):

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This appendix is not part of this guideline. It is merely informative and does not contain requirements necessary for con-
formance to the guideline. Unresolved objectors on informative material are not offered the right to appeal at ASHRAE.)

INFORMATIVE ANNEX Q
ADDENDA DESCRIPTION INFORMATION
ASHRAE Guideline 0-2013 incorporates ASHRAE Guideline 0-2005 and Addenda a, b, c, and d into ASHRAE Guideline
0-2013. Table Q-1 lists each addendum and describes the way in which the guideline is affected by the change. It also lists the
ASHRAE approval dates for each addendum.

TABLE Q-1 Addenda to ASHRAE Guideline 0-2005

Approval Dates:
Addendum Section(s) Affected Description of Changes* • Standards Committee
• ASHRAE BOD

This addendum corrects an oversight in the guideline in that


Section 7.2.1.2 requires that a sampling approach be utilized for
January 23, 2010
a Sections 7.2.9.1 and 7.2.10.1 the Commissioning Process Tests, but it was not referenced in
January 27, 2010
--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---

7.2.9.1 or 7.2.10.1. The added sentence in item “d” directs the user
to include the sampling strategy.
This addendum clarifies the meaning of Section 7.2.12.3, item a.
The current wording has caused confusion regarding what defining
the scope in this section entails, specifically when the
January 23, 2010
b Section 7.2.12.3 Commissioning Process is not being applied to an entire project.
January 27, 2010
The revision clarifies how to define the scope of systems and
assemblies that can be verified when the Commissioning Process
is not being applied to an entire project.

This addendum clarifies item “b” of Section 7.2.12.3. The current


January 23, 2010
c Section 7.2.12.3 wording implies that you randomly select from all systems, not
January 27, 2010
just those that were identified in item “a” of 7.2.12.3.

This addendum clarifies what the guideline means by “quality-


based sampling.” Currently, Annex N only provides guidance for
the completion of design reviews and does not address the other
Sections 7.2.1.2, 7.2.7.1, quality-based sampling referenced in the main body of the January 23, 2010
d
7.2.9.2, and Annex N guideline. The changes described in this addendum provide better January 27, 2010
guidance on just what quality-based sampling is in order to avoid
confusion by practitioners and owners and to avoid improper
application of the guideline.
* These descriptions may not be complete and are provided for information only.

65
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

NOTICE

INSTRUCTIONS FOR SUBMITTING A PROPOSED CHANGE TO


THIS GUIDELINE UNDER CONTINUOUS MAINTENANCE

This guideline is maintained under continuous maintenance procedures by a Standing Guideline Project Committee (SGPC)
for which the Standards Committee has established a documented program for regular publication of addenda or revisions,
including procedures for timely, documented, consensus action on requests for change to any part of the guideline. SGPC con-
sideration will be given to proposed changes within 13 months of receipt by the manager of standards (MOS).

Proposed changes must be submitted to the MOS in the latest published format available from the MOS. However, the MOS
may accept proposed changes in an earlier published format if the MOS concludes that the differences are immaterial to the
proposed change submittal. If the MOS concludes that a current form must be utilized, the proposer may be given up to
20 additional days to resubmit the proposed changes in the current format.

ELECTRONIC PREPARATION/SUBMISSION OF FORM


FOR PROPOSING CHANGES

An electronic version of each change, which must comply with the instructions in the Notice and the Form, is the preferred
form of submittal to ASHRAE Headquarters at the address shown below. The electronic format facilitates both paper-based
and computer-based processing. Submittal in paper form is acceptable. The following instructions apply to change proposals
submitted in electronic form.

Use the appropriate file format for your word processor and save the file in either a recent version of Microsoft Word (pre-
ferred) or another commonly used word-processing program. Please save each change proposal file with a different name (for
example, “prop01.doc,” “prop02.doc,” etc.). If supplemental background documents to support changes submitted are
included, it is preferred that they also be in electronic form as word-processed or scanned documents.

For files submitted attached to an e-mail, ASHRAE will accept an electronic signature (as a picture; *.tif, or *.wpg) on the
change submittal form as equivalent to the signature required on the change submittal form to convey non-
exclusive copyright.

Submit an e-mail containing the change proposal files to:


change.proposal@ashrae.org

Alternatively, mail paper versions to:


ASHRAE
Manager of Standards
1791 Tullie Circle, NE
Atlanta, GA 30329-2305

Or fax them to:


Attn: Manager of Standards
404-321-5478

The form and instructions for electronic submittal may be obtained from the Standards section of ASHRAE’s Home
Page, www.ashrae.org, or by contacting a Standards Secretary via phone (404-636-8400), fax (404-321-5478), e-mail
(standards.section@ashrae.org), or mail (1791 Tullie Circle, NE, Atlanta, GA 30329-2305).

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

FORM FOR SUBMITTAL OF PROPOSED CHANGE TO AN


ASHRAE GUIDELINE UNDER CONTINUOUS MAINTENANCE

NOTE: Use a separate form for each comment. Submittals (Microsoft Word preferred) may be attached to e-mail (preferred)
or submitted in paper by mail or fax to ASHRAE, Manager of Standards, 1791 Tullie Circle, NE, Atlanta, GA 30329-2305.
E-mail: change.proposal@ashrae.org. Fax: +1-404/321-5478.

1. Submitter:
Affiliation:

Address: City: State: Zip: Country:

Telephone: Fax: E-Mail:

I hereby grant ASHRAE the non-exclusive royalty rights, including non-exclusive rights in copyright, in my proposals. I
understand that I acquire no rights in publication of the guideline in which my proposals in this or other analogous form is
used. I hereby attest that I have the authority and am empowered to grant this copyright release.

Submitter’s signature: _____________________________________________ Date: ____________________________

All electronic submittals must have the following statement completed:

I (insert name) , through this electronic signature, hereby grant


ASHRAE the non-exclusive royalty rights, including non-exclusive rights in copyright, in my proposals. I understand that I
acquire no rights in publication of the guideline in which my proposals in this or other analogous form is used. I hereby attest
that I have the authority and am empowered to grant this copyright release.

2. Number and year of guideline:

3. Page number and clause (section), subclause, or paragraph number:

4. I propose to: [ ] Change to read as follows [ ] Delete and substitute as follows


(check one) [ ] Add new text as follows [ ] Delete without substitution
Use underscores to show material to be added (added) and strike through material to be deleted (deleted). Use additional pages if needed.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
5. Proposed change:

6. Reason and substantiation:

7. Will the proposed change increase the cost of engineering or construction? If yes, provide a brief explanation as
to why the increase is justified.

[ ] Check if additional pages are attached. Number of additional pages: _______


[ ] Check if attachments or referenced materials cited in this proposal accompany this proposed change. Please verify that all
attachments and references are relevant, current, and clearly labeled to avoid processing and review delays. Please list your
attachments here:

Rev. 1-7-2013
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

POLICY STATEMENT DEFINING ASHRAE’S CONCERN


FOR THE ENVIRONMENTAL IMPACT OF ITS ACTIVITIES

ASHRAE is concerned with the impact of its members’ activities on both the indoor and outdoor environment. ASHRAE’s
members will strive to minimize any possible deleterious effect on the indoor and outdoor environment of the systems and
components in their responsibility while maximizing the beneficial effects these systems provide, consistent with accepted
standards and the practical state of the art.
ASHRAE’s short-range goal is to ensure that the systems and components within its scope do not impact the indoor and
outdoor environment to a greater extent than specified by the standards and guidelines as established by itself and other
responsible bodies.
As an ongoing goal, ASHRAE will, through its Standards Committee and extensive technical committee structure,
continue to generate up-to-date standards and guidelines where appropriate and adopt, recommend, and promote those new
and revised standards developed by other responsible organizations.
Through its Handbook, appropriate chapters will contain up-to-date standards and design considerations as the material is
systematically revised.
ASHRAE will take the lead with respect to dissemination of environmental information of its primary interest and will seek
out and disseminate information from other responsible organizations that is pertinent, as guides to updating standards and
guidelines.
The effects of the design and selection of equipment and systems will be considered within the scope of the system’s
intended use and expected misuse. The disposal of hazardous materials, if any, will also be considered.
ASHRAE’s primary concern for environmental impact will be at the site where equipment within ASHRAE’s scope
operates. However, energy source selection and the possible environmental impact due to the energy source and energy
transportation will be considered where possible. Recommendations concerning energy source selection should be made by
its members.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
ASHRAE · 1791 Tullie Circle NE · Atlanta, GA 30329 · www.ashrae.org

About ASHRAE
ASHRAE, founded in 1894, is an international building technology society with more than 50,000 members worldwide.
The Society and its members focus on building systems, energy efficiency, indoor air quality, refrigeration, and
sustainability. Through research, standards writing, publishing, certification and continuing education, ASHRAE shapes
tomorrow’s built environment today.

For more information or to become a member of ASHRAE, visit www.ashrae.org.

To stay current with this and other ASHRAE standards and guidelines, visit www.ashrae.org/standards.

Visit the ASHRAE Bookstore


ASHRAE offers its standards and guidelines in print, as immediately downloadable PDFs, on CD-ROM, and via ASHRAE
Digital Collections, which provides online access with automatic updates as well as historical versions of publications.
Selected standards are also offered in redline versions that indicate the changes made between the active standard and
its previous version. For more information, visit the Standards and Guidelines section of the ASHRAE Bookstore at
www.ashrae.org/bookstore.

--`,,`,,,,,,``,`,```,,`,`,``,,`,-`-`,,`,,`,`,,`---
IMPORTANT NOTICES ABOUT THIS STANDARD

To ensure that you have all of the approved addenda, errata, and interpretations for this
standard, visit www.ashrae.org/standards to download them free of charge.

Addenda, errata, and interpretations for ASHRAE standards and guidelines are no
longer distributed with copies of the standards and guidelines. ASHRAE provides
these addenda, errata, and interpretations only in electronic form to promote
more sustainable use of resources.

Product code: 86821 1/14