KEBABANGAN NORTHERN HUB DEVELOPMENT

1 Month Integrated Lock Plan


Jul 2023

(Updated on 23-06-23) 1
Jul 2023 Activities Highlight
Maintenance & HSSE Scopes
List of Activity Date Remark Deferred Activity:

FWP-B Pump Change Out 20 Jun – 04 Jul Ongoing • MPM I-Care Visit deferred to
VPAD (Valve Passing Acoustic Detection) 20 Jun – 04 Jul Ongoing September due to SWP
readiness.
GTG C & D Cooler Bolt Replacement 27 Jun – 18 Jul Ongoing
Fabric Maintenance Campaign 20 Jun – 31 Jul Ongoing • Ex-Verification (Electrical &
Instrument) deferred to W4
CPBM Inspection 04 Jul – 18 Jul July due to readiness.
Utility Water Pump A Removal 11 Jul – 18 Jul
• Hydraulic Pump Crane West
Telecommunication PM 11 Jul – 25 Jul 6M PM & East deferred to October
Well Greasing 11 Jul – 25 Jul 6M PM due to SWP readiness.

LPKO Pump B Reinstatement 18 Jul – 25 Jul • PSV Recertification deferred


Metering Validation 18 Jul – 01 Aug due to manpower readiness.

LEV Certification 18 Jul – 25 Jul Delay mob by 1 week • Noise Identification &
Ex Verification (Electrical & Instrument) 25 Jul – 24 Oct To confirm manpower availability Engineering Study deferred to
August due to manpower
Technical Services Scopes readiness.

List of Activity Date Remark • HRA & Exposure Monitoring


Asset Integrity deferred to August due to
manpower readiness.
Instrument Tubing Inspection 2022 & 2023 11 Jul – 01 Aug
1Y Flexible Hose Inspection 25 Jul – 15 Aug
Small Project
KBB Cooling Fan Sprocket & GI For Cooler Fan System 27 Jun – 11 Jul Ongoing
Deck Ponding 2023 Campaign 04 Jul – 25 Jul
F&G Phase 3 (Flame Detector Installation) 04 Jul – 01 Aug
Install & Commission of CCTV Flame Marshalling Cabinet 25 Jul – 01 Aug Deferred from May plan
2
July 2023 Activities Highlight & Histogram
100
Maintenance 90
80
Fabric Maintenance 70
60
Small Projects 50
40
Asset Integrity 30
20
Core Crew 10
0
LQ POB Limit

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

95

94

94

94

94

94

94

94
Total POB Jul-23

mon

mon

mon

mon

mon
wed

wed

wed

wed
sun

thu

sun

thu

sun

thu

sun

thu

sun
tue

tue

tue

tue
sat

sat

sat

sat

sat
Day

fri

fri

fri

fri
Jul-23

01-Jul

02-Jul

03-Jul

04-Jul

05-Jul

06-Jul

07-Jul

08-Jul

09-Jul

10-Jul

11-Jul

12-Jul

13-Jul

14-Jul

15-Jul

16-Jul

17-Jul

18-Jul

19-Jul

20-Jul

21-Jul

22-Jul

23-Jul

24-Jul

25-Jul

26-Jul

27-Jul

28-Jul

29-Jul

30-Jul

31-Jul
Activity Name / Date
Jul-23
Core Crew Jul-23 63 63 63 68 68 68 68 68 68 68 66 66 66 66 66 66 66 64 64 64 64 64 64 64 65 65 65 65 65 65 65
Total Visitor Jul-23 32 32 32 27 27 27 27 27 27 27 29 29 29 29 29 29 29 31 31 31 31 31 31 31 29 29 29 29 29 29 29
LQ POB Limit Jul-23 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95 95

Allowable Visitor Activity Type

1
Jul-23
Fabric Maintenance Jul-23 10 10 10 13 13 13 13 13 13 13 5 5 5 5 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Fabric Maintenance Maint. Campaign Jul-23 10 10 10 13 13 13 13 13 13 13 5 5 5 5 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6

Maintenance Jul-23 18 18 18 4 4 4 4 4 4 4 15 15 15 15 15 15 15 16 16 16 16 16 16 16 9 9 9 9 9 9 9
Metering Validation Compliance Jul-23 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Vibration Monitoring (CPBM Inspection) Routine Maint. Jul-23 1 1 1 1 1 1 1 1 1 1 1 1 1 1
GTG C & D Cooler Bolt Replacement Corrective Maint. Jul-23 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
FWP-B Pump Change Out Corrective Maint. Jul-23 11 11 11
P-5511A 3Y Utility Water Pump Removal/Installation Routine Maint. Jul-23 5 5 5 5 5 5 5
P-4103B 3Y LPKO Pump Removal/Installation Routine Maint. Jul-23 5 5 5 5 5 5 5
Ex Verification (Electrical & Instrument) Maint. Campaign Jul-23 6 6 6 6 6 6 6
6M, Telecommunication Routine Maint. Jul-23 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Well Greasing 6M Routine Maint. Jul-23 3 3 3 3 3 3 3 3 3 3 3 3 3 3
VPAD (Valve Passing Acoustic Detection) Inspection Jul-23 3 3 3
LEV Certification HSE Jul-23 2 2 2 2 2 2 2
SGS Laboratory Technician Laboratory Jul-23 1 1 1
Asset Integrity Jul-23 0 0 0 0 0 0 0 0 0 0 4 4 4 4 4 4 4 4 4 4 4 4 4 4 7 7 7 7 7 7 7
1Y Flexible Hose Inspection Inspection Jul-23 3 3 3 3 3 3 3

Instrument Tubing Inspection 2022 & 2023 Inspection Jul-23 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4


Small Projects Jul-23 4 4 4 10 10 10 10 10 10 10 5 5 5 5 5 5 5 5 5 5 5 5 5 5 7 7 7 7 7 7 7

Deck Ponding 2023 Campaign MOC Jul-23 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

F&G Phase 3 (Flame Detector Installation) MOC Jul-23 3 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3

KBB Cooling Fan Sprocket & GI For Cooler Fan System MOC Jul-23 4 4 4 4 4 4 4 4 4 4

Install & Commission of CCTV Flame Marshalling Cabinet MOC Jul-23 4 4 4 4 4 4 4

Placeholder Activity date shifted Update from previous 90D plan


3
July - 23 Activities Readiness
Schedule Date Work
Activities - Maintenance Contractor Workpack/ Materials / Vaccination Duration
Item POB WO Number PIC RO Permit Competency Remark
& HSSE Manpower Procedures Services Status (D)
Mob Demob Status

Jul Metering Validation - Jul 23 18-Jul-23 01-Aug-23 3


90000064869
(Multiple WOs)
Fahmi
l l l l l l l 14

Jul CPBM Inspection Jul 2023 04-Jul-23 18-Jul-23 1


90000064682
90000064681
Anthony
l l l l l l l 14

Jul
P-4103B 3Y LPKO PUMP
Installation
18-Jul-23 25-Jul-23 5 90000066146 Spencer
l l l l l l l 7

Jul
Utility Pump P-5511A
Removal
11-Jul-23 18-Jul-23 5 90000064485 Spencer
l l l l l l l 7

Jul LEV Certification 04-Jul-23 11-Jul-23 2 90000068147 Julius


l l l l l l l 7

Jul Well 6M PM (Jul 2023) 11-Jul-23 25-Jul-23 3


90000066674
(Multiple WOs)
MD Shah
l l l l l l l 14 Please issue RO by 4/7/23

Jul
Ex-Verification (Electrical &
Instrument)
25-Jul-23 31-Oct-23 6
90000066637
(Multiple WOs)
Kenneth
l l l l l l l 42

Jul TELCO 1Y/6M PM 11-Jul-23 25-Jul-23 3


90000064548
(Multiple WOs)
Hadry
l l l l l l l Pending RO creation

Schedule Date Work


Contractor Workpack/ Materials / Vaccination Duration
Item Activities - AI & SP POB WO Number PIC RO Permit Competency Remark
Mob Demob Manpower Procedures Services Status (D)
Status

Jul
Instrument Tubing
Inspection 2022 & 2023
11-07-23 01-08-23 4
90000067040
(Multiple WOs)
Jessey
l l l l l l l 21 Workpack AFC Target : 3/7/23

Jul 1Y Flexible Hose Inspection

FWP, UWP and PCW


25-Jul-23 15-Aug-23 3 90000061920 Jessey
l l l l l l l 21
Pending Manpower Confirmation
Workpack AFC Target : 3/7/23

Hypochlorite Dosing Line


Jul
Improvement

Phase 1A : Caisson Cover


11-Jul-23 18-Jul-23 Sharing 90000045078 Zadora
l l l l l l l 7
Jul Scope :
UWP-A Removal

modification

Complete Partially Complete Pending


July - 23 SCE PM Outlook

SCE PM with OLAFD in Jul 2023 WORK ORDER STATUS


PLANNER GROUP NUMBER OF WO TO RAISE SCEDRA, 12
KLI 8 PENDING CNF, 6
KMECH 8
KLP 48 ONGOING, 2
KINST 19
CNF, 38
KLOGS 2
KMECH 5
KSAFE 14
KTELCO 8
KOH 94
KELEC 4
KINSP 1
JULY PLAN, 92
KINST 23
KMECH 23
KPROD 24
KSAFE 19
Grand Total 150
Notes:
• 5 WOs required SCEDRA due to unavailability of HVAC Contract
• 5 WOs required SCEDRA to align with GTC 8K PM
• 2 WOs required SCEDRA to align with Malikai Nov ESD or
potentially execute online by KBB

5
SCEDRA WO

Main WorkCtr Planner group LAFD MaintActivType Order Functional Loc. Description
KINST KLP 20-07-2023 S03 90000063437 KBB-67FD-0021 1Y, FIRE DAMPER INSPECTION LQL2 NON HAZ
KINST KLP 27-07-2023 S03 90000063438 KBB-67FD-0031 1Y, FIRE DAMPER INSPECTION LQL3 NON HAZ
KINST KLP 24-07-2023 S03 90000063439 KBB-67FD-0041 1Y, FIRE DAMPER INSPECTION LQL4 NON HAZ
KMECH KLP 07-07-2023 S03 90000063434 KBB-U-67-NA-6701 1Y, VENTILATION SYS VISUAL INSP 6701
KINST KLP 06-07-2023 S03 90000063807 KBB-23VTZ-1009 1Y SCE VIBRATION TRANSMITTER FT (X-2307)
KINST KLP 06-07-2023 S03 90000063808 KBB-23VTZ-1088 1Y SCE VIBRATION TRANSMITTER FT (X-2306)
KINST KLP 10-07-2023 S03 90000063798 KBB-26NFD-2101 1Y, FIRE DAMPER INSPECTION SYS 26 TR 2
KINST KOH 03-07-2023 S03 90000064171 KBB-26BEZ-1700A 6M, DETECTOR FLAME UV/IR GTC 1 FT
KINST KOH 05-07-2023 S03 90000064174 KBB-26GCZ-1107 6M, DETECTOR GAS GTC 1 FUNCTION TEST
KINST KOH 03-07-2023 S03 90000064175 KBB-26GP-1102 6M, DETECTOR OIL MIST GTC 1 FT
KINST KOH 04-07-2023 S03 90000064172 KBB-26HFZ-1101 6M, DETECTOR HEAT GTC 1 FUNCTION TEST
KINST KOH 03-07-2023 S03 90000064173 KBB-26HFZ-1107 6M, DETECTOR TEMP AIR VENT SYS GTC 1 FT

Notes:
• 5 WOs required SCEDRA due to unavailability of HVAC Contract
• 5 WOs required SCEDRA to align with GTC 8K PM
• 2 WOs required SCEDRA to align with Malikai Nov ESD or potentially execute online by KBB