Professional Documents
Culture Documents
003 Background Scope of Works - AMD3
003 Background Scope of Works - AMD3
RFP DOCUMENTS:
PT PEMBANGKIT INDONESIA EPSILON
Page 1
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Table of Contents
A. INTRODUCTION .............................................................................................................. 4
1. Background..................................................................................................................... 4
2. The Project ...................................................................................................................... 4
3. Project Features ............................................................................................................. 5
4. Abbreviation and Definitions ......................................................................................... 8
B. SCOPE OF WORK ......................................................................................................... 11
1. Phase A: Pre- Construction ......................................................................................... 11
1.1 Phase A-1 – Tender Design, Permitting and EPC Contractor RFP Document
Preparation ..................................................................................................................... 11
(a) Tender Design Assistance ..................................................................................... 11
(b) Assistance during Data Collection / Verification, Topographic, Geological, and Soil
Investigation................................................................................................................. 12
(c) Preparation of EPC Contractor RFP Document...................................................... 13
(d) Assistance to the Permitting Related to the Dam Construction ............................... 13
(e) Deliverables ........................................................................................................... 13
(f) Schedule ................................................................................................................ 14
1.2 Phase A-2 – EPC Contractor Tender Process .......................................................... 14
(a) Pre-Tender Phase.................................................................................................. 14
(b) Tender Phase ........................................................................................................ 15
(c) Tender Evaluation Phase ....................................................................................... 15
(d) EPC Contract Finalization Phase ........................................................................... 16
(e) Deliverables ........................................................................................................... 16
(f) Schedule ................................................................................................................ 17
1.3 Meeting and Project Reporting .................................................................................. 17
(a) Meetings ................................................................................................................ 17
(b) Reports .................................................................................................................. 17
2. Phase B: Construction Works and Preparation ......................................................... 18
2.1 Assistance During Detail Engineering ....................................................................... 18
(a) Detail Engineering Design for Construction ............................................................ 18
(b) Access Roads, Bridges, and Jetties ....................................................................... 19
(c) Site Installation....................................................................................................... 19
2.2 Construction.............................................................................................................. 19
(a) Implementation Schedule ....................................................................................... 19
(b) Construction Activities ............................................................................................ 20
(c) Factory Acceptance Testing (FAT) ......................................................................... 21
(d) Project Management and Control ........................................................................... 22
(e) Variations Prevention ............................................................................................. 23
2.3 Quality and Safety Assurance ................................................................................... 24
2.4 Risk Assessment ...................................................................................................... 24
2.5 Meeting, Reporting and Deliverables ........................................................................ 25
(a) Meetings ................................................................................................................ 25
Page 2
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 3
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
A. INTRODUCTION
1. Background
EPSILON intends to develop HEPP in North Kalimantan with output capacity of 1,950
MW and will be owned by EPSILON (“Project”). The Project are being developed to
support Government of Indonesia’s plan to provide green electricity to KIPI and KIKI
as part of National Strategic Project. Overall, the development of KIPI and KIKI and
the Project would stimulate the economic growth, provide massive job opportunities as
well as improve the welfare of the community around the Project sites.
Based on the FS, EPSILON seeks to appoint OE to realise the Project with the scope
of works as stipulated in Section B of this 003 – Background and Scope of Works.
2. The Project
The Project is located in Kayan river, Bulungan Regency North Kalimantan Province.
River authority is under the authority of local government in North Kalimantan,
including the Public Works and Housing Agency in North Kalimantan Province (Dinas
Pekerjaan Umum dan Perumahan Rakyat – “Dinas PUPR”). The Project indicative
location is shown below.
When completed, the Project will comprise the following main features:
Page 4
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
• Surface power station located downstream of the dam, with 4 units giving a total
installed capacity of 1,950 MW.
• Four steel lined underground penstocks leading from the power intake structure
to the power station.
• Hydromechanical plant and equipment at the spillway, power intake, and power
station.
• Electromechanical plant and equipment at the spillway, power intake, and power
station.
• Indoor 500 kV gas insulated switching station (GIS), located adjacent to the
upstream wall of the power station and auxiliary buildings.
• 500 kV double circuit conductor and 150kV double circuit conductor overhead
transmission lines and 500kV/150kV substation with reactors.
• Permanent access roads.
• Camp construction for EPSILON’s operation and maintenance staff.
3. Project Features
Page 5
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Stepped spillway
Type
with plunge pool
Approach Level m 154
Crest Level m 140
Spillway
No. of Gates TBA
Type of Gate TBA
Size of Gate (W x H) m TBA
Spillway clear width (Chute) m 578.5 - 120
Page 6
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 7
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Note that the information contained in the above table relates to the EPSILON’s FS
and is for reference only.
All the abbreviations and definitions herein shall be used for the purposes of reading
this 003 – Background and Scope of Works document. Any other capitalized letters
not defined otherwise herein shall have the same meaning as defined under 002 –
Instruction to Bidders document.
Page 8
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 9
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 10
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
B. SCOPE OF WORK
1.1 Phase A-1 – Tender Design, Permitting and EPC Contractor RFP
Document Preparation
EPSILON intends to appoint a Tender Design Consultant, who will carry out
such tender design exercise, carry out further site investigations and assist
EPSILON in obtaining Dam Certification and Construction Permit issued by the
IDSU / IDSC.
The Tender Design Assistance shall consider, but not limited to, the
following aspects:
Page 11
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
• Review and approve the model test plan and methodology proposed
by the Tender Design Consultant, ensuring alignment with industry
standards and best practices.
• Analyse the model test results and provide feedback to the Tender
Design Consultant, identifying any discrepancies, deficiencies, or
areas for improvement in the design.
• Provide technical guidance and clarification to the Tender Design
Consultant on engineering matters or design requirements.
• Review and approve proposed design changes or modifications,
ensuring compliance with applicable regulations and contractual
agreements.
• Monitor the quality and accuracy of deliverables produced by the
Tender Design Consultant, identifying any deficiencies or areas for
improvement.
• Review project cost estimates prepared by Tender Design Consultant
to ensure EPSILON will have a reliable owner’s estimate for EPC
Contractor Tender Process.
• Coordinate with other project stakeholders, such as third-party
consultants, to address specific project requirements or regulatory
compliance issues.
• Assist in the resolution of technical queries or disputes that may arise
during the tender design phase, working collaboratively with all
involved parties to reach mutually acceptable solutions.
• Prepare regular progress reports detailing the status of the detail
engineering activities, including key milestones achieved, challenges
encountered, and action plans for mitigation.
• Provide ongoing support and guidance to EPSILON's project
management team, ensuring effective communication and
coordination with the Tender Design Consultant throughout the detail
engineering process.
• Perform any other tasks or duties as may be reasonably required by
EPSILON to ensure the successful completion of the tender design
within the specified timeframe.
Page 12
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
This scope requires the OE to prepare the EPC Contractor RFP Document
for EPC Contractor Tender Process in parallel with the tender design
activities.
The implementation of the Project will adhere to the guidelines set forth in
FIDIC contracts.
(e) Deliverables
Page 13
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
(*) Obtained by Tender Design Consultant with full support from OE.
(f) Schedule
Phase A-1 shall commence upon issuance of NTP for such phase (or
document of similar nature) by EPSILON to OE, which shall be issued after
the signing of the Contract. Phase A-1 shall be deemed to end upon the
issuance of the Dam Design Certification and Construction Permit as well
as submission of deliverables, i.e. Tender Design Final Report and Draft
EPC Contractor RFP document for EPC Contractor Tender Process,
which will trigger the issuance of Completion Certificate for Phase A-1.
The Bidder shall indicate in the Proposal the number of days required for
the OE to commence work upon receipt of such NTP of Phase A-1.
The OE will play a pivotal role in overseeing the EPC Contractor Tender
Process on behalf of EPSILON. Building upon the groundwork laid in Phase A-
1, where the tender design was prepared, Phase A-2 marks the transition to
the next critical stage of the project.
During this phase, the OE will actively engage in facilitating the tender process,
ensuring adherence to project specifications, and promoting transparency and
fairness in the selection of the EPC Contractor. Through diligent oversight and
strategic coordination, the OE aims to optimize the efficiency and effectiveness
of the tender process, ultimately paving the way for the successful execution of
the EPSILON project. Details of each scope of work for this Phase A-2 is further
outlined below.
During this phase, the OE shall provide support and input to the following
activities:
Page 14
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
The OE shall play a crucial role in the technical and contractual evaluation
of tenders. In this regard, the following aspects shall be evaluated, but not
limited to:
Page 15
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Upon successful negotiations with the best evaluated bidder, the OE shall
actively participate in the contract finalization process. The OE shall
extend their assistance in the contract finalization process, particularly in
the scenario where negotiations with the best evaluated bidder are
unsuccessful. In such cases, the OE shall provide support in finalizing the
contract with the second-best evaluated bidder.
During this phase, the OE's role will encompass reviewing the technical
specifications, schedules, and quality requirements, which will be included
in the EPC Contract. They will work closely with EPSILON (and its
advisors) and the selected bidder to address any outstanding issues,
clarify ambiguities, and finalize the contractual documentation.
(e) Deliverables
Page 16
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
(f) Schedule
Phase A-2 shall commence upon the issuance of NTP by EPSILON to OE,
for such phase. Subject to the terms under the Contract, this NTP of Phase
A-2 is aimed to be issued no later than one (1) month after the issuance
of Completion Certificate (or any other documents with similar nature) for
Phase A-2, as determined by EPSILON.
The Bidder shall indicate in the Proposal the number of days required for
the OE to commence work upon receipt of such NTP of Phase A-2.
(a) Meetings
During the duration of the Services, EPSILON requires the OE to provide,
at the minimum, the following:
(b) Reports
(i). Weekly Report (applicable for Phase A-1), shall be submitted every
week and shall include the following information:
Page 17
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
(ii). Monthly Report (applicable for Phase A-1 and A-2), shall be
submitted every month and shall include a comprehensive overview
of the activities performed during the reporting period, highlighting
key milestones achieved, project risks and issues identified, and any
necessary recommendations or actions. The reports shall provide a
clear and concise summary of the project status, progress against
the agreed schedule, and any deviations from the planned activities.
The detail engineering shall consider, but not limited to, the following
aspects:
Page 18
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
During the design phase, the OE shall identify suitable locations for site
infrastructure, workers accommodation and waste disposal. The waste
disposal sites must be carefully selected, taking into account the volume
required, transportation distance, sufficient clearance from rivers and
communities, geological activities in the area (active landslides or creeps),
and restoration and maintenance possibilities.
The OE shall ensure that the identified areas meet all necessary environmental
and safety standards and regulations. The findings of this site analysis shall be
documented and shared with the EPC Contractor(s) and relevant stakeholders.
The OE shall provide clear instructions and guidelines for the placement and
management of the dumping sites to minimize the risk of environmental harm
and ensure the smooth operation of the construction phase.
2.2 Construction
Page 19
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Parts of the implementation schedule are also the different procurement (to
include long lead items), construction works, installations, including
temporary works, and river diversion.
Page 20
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 21
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 22
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 23
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
The OE shall review the development of standards, measures and methods for
quality and safety assurance during design, plan for construction, installation,
and operation phase for reliable and sustainable HEPP by EPC Contractor(s),
including but not limited to:
• Define quality and safety measures and standards for the services and
installed equipment of the E&M contractor.
• Define codes and general standards applied, for design, construction, and
equipment.
• Define schedule, quantities, and type of testing procedures.
• Define testing and commissioning procedures and standards.
• Develop a Quality and Safety Management Strategy that defines the quality.
• Develop water quality management and monitoring procedures to ensure that
the project does not negatively impact water quality and availability during
pre-construction, construction, and post construction.
• Techniques and standards to be applied and the various responsibilities for
achieving the required levels during the project.
The OE shall review EPC Contractor(s) risk assessment activities that includes
but not limited to:
• Conduct a risk analysis and advise EPSILON on potential risks during the
design, construction, commissioning, and operational phases of the project,
including risk mitigation and contingency planning, to outline strategies for
reducing or avoiding risks and preparing for potential impacts.
• Develop a Risk Management Strategy that describes the specific risk
management techniques and standards to be applied and the responsibilities
for achieving an effective risk management procedure which includes risk
monitoring and reporting, to ensure that the risk management process is
regularly reviewed and updated, and that progress is reported to relevant
stakeholders.
• Outline a report of strengths and weaknesses of the hydropower project with
detailed suggestion and guidance to EPSILON of optimisation and
sustainability for the next project phases.
• The EPC Contractor(s) has to take into account a worst-case scenario for
different risks and show the caused impact and elaborate the mitigation
plans.
Page 24
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
(a) Meetings
(ii). Overall Project Schedule, all working steps in sufficient details and
indicate the major milestones and work tasks of the Project.
(iii). Weekly Report, shall be submitted every week and shall include the
following information:
(iv). Monthly Report, shall be submitted every month and shall include the
following information:
Page 25
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
(v). Final Report, shall be submitted upon completion of the Project and
shall include the following information:
EPSILON may request the OE to prepare other reports related to the Project
as may be required by EPSILON within the capability of resources of the
OE.
All reports/deliverables shall be submitted in one (1) hard copy and in a soft
copy. EPSILON shall review and comment on the submitted reports within
two weeks from the date of receipt. The OE shall be expected to incorporate
these comments within two (2) weeks. Finally, the documents must be
resubmitted as one (1) hard copy and in a soft copy.
The OE shall be responsible for ensuring that all reports are accurate,
complete, and timely. The OE shall also be responsible for ensuring that all
reports are submitted in accordance with the requirements of this clause.
This Phase B will cover a total period of 60 (sixty) months since the issuance of
NTP for Phase B, by EPSILON, for OE to commence these Phase B scope of
works. Subject to the terms under the Contract, this NTP of Phase B is aimed to
be issued by Epsilon to OE, by no later than one (1) month after the issuance of
Page 26
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
completion certificate (or any other documents with similar nature) of Phase A-2,
as determined by EPSILON.
In issuing the NTP of Phase B, EPSILON shall consider all matters related to the
commencement of the Project’s construction timeline. EPSILON may reserve the
right to amend the timeline of the NTP issuance by its own sole discretion and
after considering the Project’s construction timeline.
The OE shall indicate in the proposal the number of days required for the OE to
commence work upon receipt of such NTP of Phase B.
• In the event that defects or deficiencies are identified during the inspections
or reported by EPSILON, the OE shall oversee the rectification process.
• This involves coordinating with the EPC Contractor or relevant parties
responsible for the defects and ensuring that the necessary corrective
actions are taken promptly.
• The OE shall monitor the progress of the rectification works and verify that
they are carried out in accordance with the specified standards and
requirements.
• The OE shall prepare Punch List in post construction and manage the
rectification / closing punch list to be done by EPC Contractor.
Page 27
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
• The OE shall facilitate the effective transfer of knowledge from the EPC
Contractor to EPSILON. This process aims to ensure that critical insights,
technical expertise, and operational know-how acquired during the project's
construction and commissioning phases are seamlessly communicated to
the EPSILON team.
• During the project's execution, the OE shall work closely with the EPC
Contractor to identify and document key project insights, technical details,
and operational nuances. The OE will organize knowledge transfer
sessions, workshops, or create comprehensive knowledge repositories to
convey this information to the EPSILON personnel.
(a) Meetings
Page 28
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 29
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
This phase will cover a total period of about 12 (twelve) months since the
issuance of NTP for Phase C by EPSILON, for OE to commence these Phase
C scope of works. Subject to the terms under the Contract, this NTP of Phase
C is aimed to be issued by Epsilon to OE, by no later than one (1) month after
the issuance of completion certificate (or any other documents with similar
nature) of Phase B, as determined by the EPSILON. The OE shall indicate in
the Proposal the number of days required for the OE to commence work upon
receipt of such NTP of Phase C.
During the Post Construction Phase, the OE's primary focus is on ensuring the
quality and integrity of the completed HEPP and play a crucial role in
conducting inspections, overseeing defect rectification, and facilitating the
handover process from EPC Contractor to EPSILON.
4. Personnel Requirement
Experiences
(Similar in Number of
No. Position Background Location
position & Personnel
project)
A. Phase A
Team Leader / Project Civil /
1. 25 years 1 Office
Manager / Dam Expert Hydro Civil
Hydrology & Hydraulic Civil /
2. 20 years 1 Office
Expert Hydro Civil
Civil /
3. Civil Dam Expert 20 years 1 Office
Hydro Civil
4. Geologist Expert Geology 20 years 1 Office
5. Geodetic Expert Geodesy 20 years 1 Office
6. Mechanical Expert Mechanical 20 years 1 Office
7. Electrical Expert Electrical 20 years 1 Office
Page 30
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Experiences
(Similar in Number of
No. Position Background Location
position & Personnel
project)
Dam Instrumentation Civil /
8. 20 years 1 Office
Expert Hydro Civil
Environmental and
9. Environmental 20 years 1 Office
Social Expert
10. Computer Operator Engineering 3 years 1 Office
B. Phase B & C
Team Leader / Project Civil /
1. 25 Years 1 Site
Manager / Dam Expert Hydro Civil
Hydrology & Hydraulic Civil /
2. 20 Years 1 Site
Expert Hydro Civil
Civil /
3. Grouting Expert 20 Years 1 Site
Hydro Civil
Civil /
4. Material Expert 20 Years 1 Site
Hydro Civil
Civil /
5. Civil Dam Expert 20 Years 1 Site
Hydro Civil
Civil / Hydro
6. Civil Dam Supervisor 10 Years 4 Site
Civil
Civil /
7. Civil Tunnel Expert 20 Years 1 Site
Hydro Civil
Civil /
8. Civil Tunnel Supervisor 10 Years 2 Site
Hydro Civil
Civil Intake & Penstock Civil /
9. 20 Years 1 Site
Expert Hydro Civil
Civil Intake & Penstock Civil /
10. 10 Years 2 Site
Supervisor Hydro Civil
Civil Structure – Civil /
11. 20 Years 1 Site
Powerhouse Expert Hydro Civil
Civil Structure – Civil /
12. 10 Years 2 Site
Powerhouse Supervision Hydro Civil
13. Geologist Expert Geology 20 years 1 Site
Geologist Eng.
14. Geology 10 years 2 Site
Supervisor
15. Geodetic Expert Geodesy 20 years 1 Site
Geodetic Eng.
16. Geodesy 10 years 2 Site
Supervisor
17. Mechanical Expert Mechanical 20 years 1 Site
Mechanical Eng.
18. Mechanical 10 years 2 Site
Supervisor
Page 31
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Experiences
(Similar in Number of
No. Position Background Location
position & Personnel
project)
19. Electrical Expert Electrical 20 years 1 Site
Electrical Eng.
20. Electrical 10 years 2 Site
Supervisor
Dam Instrumentation Civil /
21. 20 years 1 Site
Expert Hydro Civil
Dam Instrumentation Civil /
22. 10 years 2 Site
Supervision Hydro Civil
Environmental & Social
23. Environmental 20 years 1 Site
Expert
24. HSSE Expert Environmental 20 years 1 Site
25. HSSE Supervision Environmental 10 years 2 Site
26. Legal Contract Expert Legal 20 years - Office
27. CAD Drafter Civil 5 years 1 Site
Project Planning and
28. Engineering 10 years 1 Site
Control Specialist
Civil /
29. Doc. Control Specialist 10 years 1 Site
Hydro Civil
Commissioning Civil /
30. 20 years 1 Site
Specialist Hydro Civil
Civil /
31. Performance Specialist 20 years 1 Site
Hydro Civil
Page 32
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 33
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 34
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 35
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 36
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 37
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 38
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 39
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
Page 40
Owner’s Engineer Consultancy
Services for Epsilon Hydroelectric
Power Plant Project
003 – Background and Scope of Works
• All personnel proposed by the Bidder for the Services shall be dedicated
to EPSILON's Project (please also refer to our response in Bid Bulletin 4)
and able to communicate in writing and verbal in English.
• Any replacement of the OE’s personnel during the services period shall
have qualifications that are similar or better than the requirements
mentioned earlier. The OE shall inform EPSILON of the proposed
assignment/replacement for the Projects at least two (2) weeks in advance.
• EPSILON retains the right to confirm the individual proposed by the OE for
inclusion in the Projects team.
Page 41