Abyatona Hills Housing Project

Progress % Summary
Status Date 29-Feb-24

Sl No Contractor Name Block No. No. of Builds No. of Units Avg. Prog % Remarks

1 Al Tasmim 1 14 476 8.80%

2 Self Construction 2 12 408 6.91%

3 TBA 3 5 170 1.41%

4 TBA 4 7 238 1.65%

Grand Total 4 38 1,292 5.9%


Abyatona Hills Housing Project
Physical Progress Tracking Sheet - Overall Project 38 Buildings, Sub Structure, and Super Structure Works
Act % = Performance % Comp Activities in Progress (Act %) Status Date 29-Feb-24

Sub Structure Super Structurre

Raft Foundation

Roof Floor Slab


Roof Floor Col
2nd Floor Slab
Slab on Grade

3rd Floor Slab

4th Floor Slab

5th Floor Slab

6th Floor Slab

7th Floor Slab


1st Floor Slab
Grade Beams

G.F Columns
No. of Units

Foundation
Build Code

Excavation
Build Type

Backfilling
Block No.

Build No.

Columns

Columns

Columns

Columns

Columns

Columns

Columns

Columns
2nd Floor
G.F Slab

3rd Floor

4th Floor

5th Floor

6th Floor

7th Floor
1st Floor
PCC for
Sl No

Neck
Contractor Name Total Prog % Remarks

1 Al Tasmim 1 1 B 34 BK01-B01 100% 100% 80% 8.40%


2 Al Tasmim 1 2 B 34 BK01-B02 100% 100% 100% 20% 10.29%

3 Al Tasmim 1 3 B 34 BK01-B03 100% 100% 80% 8.40%


4 Al Tasmim 1 4 B 34 BK01-B04 100% 100% 80% 8.40%

5 Al Tasmim 1 5 B 34 BK01-B05 100% 100% 100% 10.09%


6 Al Tasmim 1 6 B 34 BK01-B06 100% 100% 100% 20% 10.29%

7 Al Tasmim 1 7 B 34 BK01-B07 100% 100% 80% 8.40%


8 Al Tasmim 1 8 B 34 BK01-B08 100% 100% 80% 8.40%
On Hold (Clash
9 Al Tasmim 1 9 B 34 BK01-B09 100% 0.93% with Electrical
Room)
10 Al Tasmim 1 10 B 34 BK01-B10 100% 100% 80% 8.40%
11 Al Tasmim 1 11 B 34 BK01-B11 100% 100% 100% 20% 10.29%

12 Al Tasmim 1 12 B 34 BK01-B12 100% 100% 100% 20% 10.29%

13 Al Tasmim 1 13 B 34 BK01-B13 100% 100% 100% 30% 10.39%

14 Al Tasmim 1 14 B 34 BK01-B14 100% 100% 100% 20% 10.29%


15 Self Construction 2 1 B 34 BK02-B01 100% 100% 100% 10.09%

16 Self Construction 2 2 B 34 BK02-B02 100% 100% 80% 8.40%


17 Self Construction 2 3 B 34 BK02-B03 100% 100% 100% 10.09%
18 Self Construction 2 4 B 34 BK02-B04 100% 100% 80% 8.40%
On Hold (Clash
19 Self Construction 2 5 B 34 BK02-B05 100% 0.93% with Electrical
Room)
On Hold (Clash
20 Self Construction 2 6 B 34 BK02-B06 50% 0.47% with Electrical
Room)
21 Self Construction 2 7 B 34 BK02-B07 100% 100% 80% 8.40%
22 Self Construction 2 8 B 34 BK02-B08 100% 100% 80% 8.40%

23 Self Construction 2 9 B 34 BK02-B09 100% 100% 10% 2.49%


24 Self Construction 2 10 B 34 BK02-B10 100% 100% 80% 8.40%
25 Self Construction 2 11 B 34 BK02-B11 100% 100% 80% 8.40%

26 Self Construction 2 12 B 34 BK02-B12 100% 100% 80% 8.40%

27 3 1 B 34 BK03-B01 100% 100% 1.65%


28 3 2 B 34 BK03-B02 50% 0.47%
29 3 3 B 34 BK03-B03 100% 100% 1.65%

30 3 4 B 34 BK03-B04 100% 100% 1.65%


31 3 5 B 34 BK03-B05 100% 100% 1.65%
32 4 1 B 34 BK04-B01 100% 100% 1.65%

33 4 2 B 34 BK04-B02 100% 100% 1.65%

34 4 3 B 34 BK04-B03 100% 100% 1.65%


35 4 4 B 34 BK04-B04 100% 100% 1.65%
36 4 5 B 34 BK04-B05 100% 100% 1.65%

37 4 6 B 34 BK04-B06 100% 100% 1.65%


38 4 7 B 34 BK04-B07 100% 100% 1.65%

Grand Total in % 38 1292 97.37% 89.47% 51.32% 3.42% 5.91%

Grand Total in No's (100% Comp. Activities) 36 34 9