Professional Documents
Culture Documents
KAFD - Technical Evaluation Criteria
KAFD - Technical Evaluation Criteria
Tender No:
Tender Title:
Subject:
Schedule/Programme:
- A proposed Accepted resource loaded tender
schedule/programme covering all the planned * A practicable programme including sufficient detail
activities, with particular reference to the activities to be accepted, aligned with all other aspects of the
included in the method statements, at the level of Tender;
detail which would allow the programme when * A robust, identifiable and deliverable critical path,
submitted under the Contract to be accepted in a with logical sequencing and sound logic links;"
timely manner; in accordance with the conditions Activity and total time risk allowances / floats
of contract and Scope of Works. displayed which are adequate provision; Achievable
- The schedule shall include key milestone dates, activity durations aligned to the productivity
4.2 through the project phases (to include the assumptions stated in the Narrative; Design, testing 7%
procurement, pre-construction, construction, and commissioning and taking-over/handover,
commissioning and completion, acceptance activities and interdependencies
taking-over/handover and defects liability period) - (including activities by Others where there are
submitted in both Primavera P6 and PDF formats. interdependencies) are all identified, allowed for
- Provide a Programme Narrative including the and compliant with all programme constraints;
following sections: - Documents used; - Key * A programme that meets the requirements for
assumptions underpinning the schedule; - Critical forming an Accepted Programme stipulated by the
path; - Float and time risk allowance; - Summary of conditions of contract and Scope of Works.
key dates; - Productivity assumptions; - Taking-
Over/Hand-over strategy.
6 Equipment 8%
* Detailed Plan illustrating the Tenderer approach
6.1 Equipment Mobilization Plan towards mobilization of equipment and period of 2%
mobilization.
* Tenderer to submit a management plan with a list
of manpower and equipment for 24/7 operations.
6.2 Equipment Management Plan 2%
Including Average Age and Condition of all
Equipment
* Tenderer to provided equipment list showing type
6.3 Equipment List of critical equipment and the percentage of owned 4%
and rented equipment.
No. Description of Evaluated Criteria Expected Deliverable Check Weighting
7 QA/QC - Quality Management 9%
5% 5% 5% 5% 5%
100% 15% 100% 15% 100% 15% 100% 15% 100% 15%
100% 100% 100% 100% 100%
8% 8% 8% 8% 8%
8% 8% 8% 8% 8%
7% 7% 7% 7% 7%
5% 5% 5% 5% 5%
5%
100% 1%
100% 2%
100% 1%
100% 1%
100%
10%
100% 1%
100% 6%
100% 3%
15%
100% 2%
100% 4%
100% 3%
100% 1%
100%
100% 5%
33%
100% 15%
100%
100% 7%
100% 2%
100% 5%
100% 4%
8%
100% 2%
100% 2%
100% 4%
100%
9%
100% 4%
100% 3%
100% 2%
8%
100% 3%
100%
100% 3%
100% 2%
7%
100% 4%
100% 3%
5%
100% 5%