Project goal
• Rehabilitation of Metropolitan Town of Le Havre and its Halls for esteemed
engineering firm "Saint-Gobain"
• Scan-to-BIM : 3D Modeling from a 3D point cloud captured using a LiDAR
scanner
• 3D LOD 400 modeling of the structural model of 2700 m², with 3787 structural
framing elements (1550 in wood, 2109 in steel, 128 in reinforced concrete) using
Revit, completed in 55 hours over 7 days, against 14 days planned. Less
Skills and deliverables
Autodesk Revit
Point Cloud to BIM
Solution - BIM model with over 3787 elements (beam, truss, column) - Structural
and architectural plans annotated for the future rehabilitation
Final BIM model with over 3787 elements (beam, truss, column)
Construction of 9 collective housing units in mixed
wood/concrete
Close the dialog
Role
I was the lead structural engineer on the load calculations & modeling