DECEMBER MONTH LOOK-AHEAD SCHEDULE

FIRST WEEK 1 WEEK OUT 2 WEEKS OUT 3 WEEKS OUT 4 WEEKS OUT FIRST WEEK JAN
TOWER 1 01-Dec-22 08-Dec-22 15-Dec-22 22-Dec-22 29-Dec-22 05-Jan-23

TASK ID TASK Forecast Actual Finish 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 NOTES

1 Slab 39 Part 1 3-Dec-22 5-Dec-22



2 Slab 39 Part 2 4-Dec-22 7-Dec-22

3 Slab 39 Part 3 5-Dec-22 7-Dec-22

4 Columns 39 - 40 Part 1 5-Dec-22 10-Dec-22

5 Columns 39 - 40 Part 2 18-Dec-22

6 Columns 39 - 40 Part 3 18-Dec-22

7 Deshuttering Slab Level 38 13-Dec-22 19-Dec-22

8 Slab 40 Part 1 22-Dec-22

9 Slab 40 Part 2 25-Dec-22

10 Slab 40 Pour Strip 8-Jan-23

11 Deshuttering Slab 40 Part 1 3-Jan-23

12 Deshuttering Slab 40 Part 2 6-Jan-23

13 Deshuttering Slab 40 Pour Strip 22-Jan-23

14 Columns 40 - 41 Part 1 24-Dec-22



15 Columns 40 - 41 Part 2 27-Dec-22

16 Corewall 1A Level 40 - 41 1-Jan-23

17 Slab 41 Part 1 4-Jan-23

18 Slab 41 Part 2 7-Jan-23

19 Slab 41 Pour Strip 21-Jan-23

20 Lifting Hoist L35 - L37 9-Dec-22



21 Lobby Slab Level 36 4-Jan-23

25 Lobby Slab Level 40 13-Feb-23

26 Lobby Slab Level 41 23-Feb-23

27 Staircase 2 Level 33-34 22-Dec-22



28 Staircase 2 Level 34-35 1-Jan-23

29 Staircase 1 Level 23-24 24-Dec-22

30 Staircase 1 Level 24-25 3-Jan-23

31 Columns 41 - 42 Part 1 6-Jan-23

32 Columns 41 - 42 Part 2 9-Jan-23

33 Lifting Placing Boom 1 FLOOR 7-Jan-23

34 Lifting Crane 3 FLOORS 24-Dec-22

35 Corewall 1B Level 41 - 42 14-Jan-23

36 Corewall 1A Level 41 - 42 15-Jan-23

37 Slab 42 Part 1 18-Jan-23

38 Slab 42 Part 2 21-Jan-23

39 Columns 42 - 43 Part 1 20-Jan-23

40 Columns 42 - 43 Part 2 23-Jan-23