Construction Methodology - Access Hole - Rev03

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

REHABILITATION OF PIER STRUCTURES

PIERS 3,5,9 & 15


Manila South Harbor, Port Area, Manila

METHOD STATEMENT FOR DEMOLITION AND RESTORATION OF ACCESS HOLE


(INTENDED FOR UNDERDECK REPAIR WORKS)

1.0 Introduction

This method statement describes in details all the scope involved in demolition and restoration
works.

2.0 Objective

The objective of this Method Statement is to provide a detailed procedure on how the
Works or part thereof are to be carried out in compliance with the Contract, and to carry- out
the Work Safely, quality workmanship and in timely manner.

3.0 Scope

This Method Statement (Methodology) shall apply for the demolition and restoration of access
hole intended for under deck repair works.

CQC in coordination with Project Supervision Team (Consultant) in-situ inspection for
compliance to the desired quality of the works.

4.0 Setting-out and Securing the Work Area (Site Possession - SP)

Generally, on turn-over of the Work Area (Site Possession) by ATI the Contractor’s
Survey Team together with assigned Safety Group and in coordination with the Project-
Supervision Team (AECOM Phils. Inc.) shall:

a. pre-establish the limits of the Site Possession area [Four (4) corners, minimum)] and
thereafter,
b. completely secure the Work Area
c. set-out in-situ the location and establish the limits of the access hole to be
demolished, complete with visible markings and reference gridlines.
d. Established records of access hole photos for reference.

5.0 Procedure

5.1 Demolition/removal of access hole for the repair of under deck elements

a. Workers all set with complete PPE’s appropriate to the activity, Including
environmental protection, i.e. noise and dust control

b. Install warning signage’s at underdeck, conspicuously displayed and highly visible.

c. Demolish slab to the required limits using hand-held jack hammer, pneumatic type
or AC operated or any appropriate equivalent. Start the demolition approximately
at L/4 of the slab with dimension not exceeding 500mm x 500mm. Slab may be
broken into small chunks.

d. Cut the rebar needed at mid part and bend upside so that pipes and other materials
necessary for easy access during concrete pouring.

Page 1 of 4
e. Dispose offsite concrete slab chunks /other debris resulting from the demolition
work.

f. Neat-cut proposed construction joints using concrete saw (cutter).

5.2 False works, form setting, restoration of steel reinforcement, concrete placement
and inspection.

a. Upon completion of underdeck repair, install forms using phenolic boards, knotted
with tie wire on existing rebar.

b. Restor the steel reinforcement using approved method (welded connection) (refer
to Structural Welding Code- Reinforcing Steel –AWS D1.4).

RESTORE THE CUT REINFORCING STEEL AS DETAILED BELOW:

CASE 1: Cut rebars in good condition, clearance/gap (root) between ends


after re bending, root = ±3mm.

Detail 1: Grooved bevelled (butt) joint (with splice rebar)

CASE 2: Cut rebars in good condition, clearance/gap (root) between ends


after rebending, root varies between 4mm and 20mm (due to
deformation after rebending).

Detail 2: Square butt joint with splice rebar

CASE 3 : Cut rebars not in good condition, either heavily corroded or badly
deformed due to bending and not straight as before, or a
combination of both.

a. Cut remove and replace with new rebar the defective portion of
existing rebar of the same diameter.

Page 2 of 4
Detail 3: 2 Point weld joint

Notes:
1. Splice bar shall be deformed type as existing reinforcement.
 Use 16mm for 12mm
 Use 20mm for 16mm
 Length ± 200mm (min)
2. Presentation is applicable to all/any of existing reinforcement to be
restored.

 Arc strikes outside the area of permanent welds shall be avoided, especially
on reinforcing bars.
 Tack welds that do not become a part of permanent welds shall be prohibited.
Tack welds shall be subject to welding requirement of the code (AWS
D1.4), including pre heat, electrode selection and discontinuity acceptance
criteria.
 Electrode for SMAW shall conform to the requirements of the latest edition of
ANSI/AWS A5.1, Specification for Carbon Steel Electrodes for Shielded Metal
Arc Welding Electrodes.

ATTACHMENT:

Annex A: Welders Name and Qualifications

Annex B: Actual Field Condition on the gap


between ends of cut rebar

c. Apply zinc-rich epoxy paint to all existing exposed reinforcements (propriety


product …Sealbond – ZRP-epoxy-Zinc Rich primer or approved equivalent
following manufacturers recommendation.

d. CQC in coordination with Project Supervision Team (AECOM Phils. Inc.) in-situ
inspection for compliance to the desired quality of the works prior to concrete
placement.

e. Apply old to new concrete binder (propriety product…sealbond 215-B or approved


equivalent following manufacturers recommendation.

f. Coordinate for batching and delivery or ready mix-concrete (of approved


design mix, quantity and time of placement), as such, is the sole responsibility of
the Contractor.

g. Protect newly cast concrete from possible damage and cure in accordance with
the requirements set-forth in the Technical Specifications / and or
engineering/construction industry practices.

5.3 Removal, stripping of forms, false works

a. Formworks shall be removed, tripped after all verification tests of hardened concrete
are conducted and tests results are made available.

6.0 Equipment/Tools & PPE

 Air Compressor
 Hand Held Jack Hammer
 Chipping Hammer
 Cutting Outfit
 Concrete Vibrator

Page 3 of 4
 Hard hat
 Safety Googles
 High Visibility Vest
 Health protocols vs. covid-19

Prepared by: Checked and Noted by:

ROMMEL G. ANTONIO JULIAN C. RAMIREZ


QCE-JRBuilders Co. Inc. PM- JRBuilders Co. Inc.

Page 4 of 4

You might also like