Soil Nailing Pull-Out Test Kiri Dam (SL-1 - SL-3)
Soil Nailing Pull-Out Test Kiri Dam (SL-1 - SL-3)
PLTA POSO 1
AREA DAM
PT. POSO ENERGY PAMONA SATU
Pull-Out
Load Displacement
(ton) Rata2 Dial (1/100 mm) Dial 1 Dial 2
0 0 0 0
4 160 160 160
8 336.5 318 355
12 417.5 445 390
16 529 581 477
Displacement Dial Gauge
Load vs Displacement
3000
(Dial Gauge) Chart
2500
2000
1500
1000
500
0
Load (Ton)
0 4 8 12 16 20 24
PLTA POSO 1
AREA DAM
PT. POSO ENERGY PAMONA SATU
Pull-Out
Load Displacement
(ton) Rata2 Dial (1/100 mm) Dial 1 Dial 2
0 0 0 0
4 204 203 205
6 262 259 265
8 367.5 364 371
10 406 403 409
12 502.5 494 511
14 568.5 568 569
16 682.5 670 695
18 755.5 739 772
Displacement Dial Gauge
Load vs Displacement
(Dial Gauge) Chart
3000
2500
2000
1500
1000
500
0 Load (Ton)
0 5 10 15 20 25
PLTA POSO 1
AREA DAM
PT. POSO ENERGY PAMONA SATU
Pull-Out
Load Displacement
(ton) Rata2 Dial (1/100 mm) Rata2 Dial (mm) Dial 1 Dial 2
0 0 0 0 0
4 95 0.95 90 100
8 214.5 2.145 200 229
12 320 3.2 310 330
( 1/100 mm)
24 680 6.8 669 691
Load vs Displacement
10
(Dial Gauge) Chart
8
0 Load (Ton)
0 4 8 12 16 20 24
7 411
8 755 13
9 884
10 1055 12
11 1215
12 1587 11
13 2140
Pull-Out Load (tf)
14 2422 10
15 3090
9
0
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000 9.000 10.000
Displacement (mm)
Disetujui :
PT. Poso Energy Satu Pamona