SATIP-S-070-02 Rev 7 Irrigation Piping
SATIP-S-070-02 Rev 7 Irrigation Piping
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
See See
1.1 Hydrostatic Package See SATIP-A-004-02 Pressure Testing
Remarks Remarks
See See
2.1 Thermoplastic and RTR piping See SATIP-S-070-03 Thermoplastic and RTR piping
Remarks Remarks
3.0 INSTALLATION
Motor Operated Valves, Control Valves See See See SATIP-J-700-01 Motor Operated Valves and Control
3.2
and Valves Remarks Remarks Valves and SATIP-L-108-01 Valves as applicable
Piping lay-out SAIC SAIC Saudi Aramco to be notified on start of this activity for
3.3
Inspection S-4052 S-4052 W W each location
See See
3.5 RTR & Thermoplastic Piping See SATIP-S-070-03 Thermoplastic and RTR Piping
Remarks Remarks
See See
3.6 Hydrostatic Testing See SATIP-A-004-02 Pressure Testing
Remarks Remarks
Control Wiring (Same Trench) SAIC SAIC Saudi Aramco to be notified on start of this activity for
3.7
Inspection S-4032 S-4032 W W each location / area
Page 1 of 2
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3 is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
Page 2 of 2