Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Irrigation Piping SATIP-S-070-02 30-Apr-13 PLUMBING


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

See See
1.1 Hydrostatic Package See SATIP-A-004-02 Pressure Testing
Remarks Remarks

2.0 MATERIAL RECEIVING

See See
2.1 Thermoplastic and RTR piping See SATIP-S-070-03 Thermoplastic and RTR piping
Remarks Remarks

3.0 INSTALLATION

See See See SATIP-S-070-01 Excavation and Backfilling for


3.1 Trench Inspection
Remarks Remarks Underground Utilities

Motor Operated Valves, Control Valves See See See SATIP-J-700-01 Motor Operated Valves and Control
3.2
and Valves Remarks Remarks Valves and SATIP-L-108-01 Valves as applicable

Piping lay-out SAIC SAIC Saudi Aramco to be notified on start of this activity for
3.3
Inspection S-4052 S-4052 W W each location

Irrigation Piping Accessories SAIC SAIC


3.4
Inspection S-4053 S-4053 W S

See See
3.5 RTR & Thermoplastic Piping See SATIP-S-070-03 Thermoplastic and RTR Piping
Remarks Remarks

See See
3.6 Hydrostatic Testing See SATIP-A-004-02 Pressure Testing
Remarks Remarks

Control Wiring (Same Trench) SAIC SAIC Saudi Aramco to be notified on start of this activity for
3.7
Inspection S-4032 S-4032 W W each location / area

See See See SATIP-S-070-01 Excavation and Backfilling for


3.8 Backfill placement and compaction
Remarks Remarks Underground Utilities

Page 1 of 2
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Irrigation Piping SATIP-S-070-02 30-Apr-13 PLUMBING


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

4.0 PRE-COMMISSIONING

4.1 Not applicable

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3 is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 2 of 2

You might also like