SATIP-S-060-07 Rev 7 Neutralization Tank and Apparatuses
SATIP-S-060-07 Rev 7 Neutralization Tank and Apparatuses
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC SAIC
2.1 Neutralization Tank Receiving
S-4044 S-4044 W W
See See
2.3 Thermoplastic and RTR Piping See SATIP S-070-03 Thermoplastic and RTR Piping
Remarks Remarks
3.0 INSTALLATION
See See
3.2 Thermoplastic and RTR Piping See SATIP S-070-03 Thermoplastic and RTR Piping
Remarks Remarks
See See
3.4 Valves See SATIP-L-108-01 Valves
Remarks Remarks
Page 1 of 2
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Neutralization Tank and Apparatuses SATIP-S-060-07 30-Apr-13 PLUMBING
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3 is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection