SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
See See
1.2 Piping material traceability See SATIP-L-350-01 On-Plot Metallic Piping
Remarks Remarks
Piping and Fittings SAIC SAIC Saudi Aramco shall be notified on initial delivery of Piping
2.1
Receiving Inspection S-4055 S-4055 H W and fittings by type or manufacturer
3.0 INSTALLATION
See See
3.4 Pressure Testing See SATIP-A-004-02 - Pressure testing of On-Plot Piping
Remarks Remarks
4.0 PRE-COMMISSIONING
Page 1 of 2
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
Page 2 of 2