SATIP-S-070-03 Rev 7 Thermoplastic and RTR Piping

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Thermoplastic and RTR Piping SATIP-S-070-03 30-Apr-13 PLUMBING


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

RTR & Thermoplastic Installers SAIC SAIC


1.1
Qualifications S-4054 S-4054 RH RH

See See
1.2 Piping material traceability See SATIP-L-350-01 On-Plot Metallic Piping
Remarks Remarks

2.0 MATERIAL RECEIVING

Piping and Fittings SAIC SAIC Saudi Aramco shall be notified on initial delivery of Piping
2.1
Receiving Inspection S-4055 S-4055 H W and fittings by type or manufacturer

Pipe and Fittings Handling, Storage and SAIC SAIC


2.2
Preservation S-4056 S-4056 W S Contractor to perform weekly Inspection

3.0 INSTALLATION

Saudi Aramco shall be notified on start of this activity for


each location
Thermoplastic Piping Installation and SAIC SAIC
3.1
Assembly Inspection S-4057 S-4057 H W Contractor QA/QC shall be notified on the start of this
activity and inspect the first five joints made in each
location / area

Saudi Aramco shall be notified on start of this activity for


each location
RTR piping Laying and Assembly SAIC SAIC
3.2
Inspection S-4058 S-4058 H W Contractor QA/QC shall be notified on the start of this
activity and inspect the first five joints made of each
location / area

Application of Safety Color Coding &


See See See SATIP-H-100-01 paint Application of Liquid Coating
3.3 Stenciling of Equipment/Piping
Remarks Remarks System for Industrial Facilities
Identification

See See
3.4 Pressure Testing See SATIP-A-004-02 - Pressure testing of On-Plot Piping
Remarks Remarks

4.0 PRE-COMMISSIONING

4.1 Not Applicable

Page 1 of 2
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Thermoplastic and RTR Piping SATIP-S-070-03 30-Apr-13 PLUMBING


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 2 of 2

You might also like