Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 226

S.

No STRATEGIC OBJECTIVE WTG UNIT EXE

1 Gross Energy Generation-Hydro 15 MU 7200


Energy Generation from NJHPS
2 2 MU 1.5
Solar Power Plants

3 Plant Availability Factor 10 % 98

Maximum number of Machine


days for Annual Plant Machine
4 5 55
Maintenance of 1500MW Days
NJHPS

Setting up of NABL Compliant


5 5 Date 31.05.2024
Lab for testing of Gases

Cleaning of debris on the Down


6 3 Date 31.05.2024
stream of Natpa Dam
Slope stabilization/ Bolder
7 Arresting Arrangment above 3 Date 30.06.2024
Nathpa Dam Intake Area
Trench Weir guide wall
8 strengthening at Sholding 3 Date 30.06.2024
Complex
Complete Dismantling and
9 Major Overhauling of BTRDT 3 Date 31.08.2024
Pump No. 05 (400KW BHM50)
Coating of two (02) repaired
10 Runners of NJHPS 5 Date 31.12.2024

Carrying out Dam Safety


11 Inspection through External 4 Date 31.12.2024
Agency

Chemical treatment of U/S face


12 of the dam at NJHPS, Nathpa- 3 Date 31.12.2024
Completion of 1st phase of work

Technical Audit from external


13 3 Date 31.12.2024
agency
Upgradation of old DOL based
Cooling water System Control
Cubicle with latest soft starters
and associated equipment’s
14 meeting the existing control 6 Date 31.01.2025
logic along with supply of
Squirrel Cage Induction Motors
for next two Nos Generating
Units of NJHPS Jhakri.

Retrofitting of Existing
Generator Protection System
(System B) for balance 03 Nos.
Unit with latest protection
15 5 Date 31.01.2025
system relays & associated
equipment's from OEM at
existing 250MW Generator Unit
of 1500MW NJHPS.

Repair / Refurbishment of Dam


16 5 Date 31.01.2025
Sluice Radial Gate & SFT Gates

Diversion of Sholding Khad by


17 4 Yes/No Yes
15.09.2024
Maintaining Forced Outage to
18 current level i.e 51 hrs of 2023- 3 Yes/No Yes
24
Compliance of Public
Procurement Policy for Micro
19 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME.
20 Utilization of CSR Budget 3 % 100

21 Procurement from GeM 2 % 100

22 Gross Energy Generation 15 MU 2100

23 Plant Availability Factor 10 % 98

Maximum no. of machine days


Machine
24 for annual plant maintenance 10 55
Days
(2024-25)
Assessment of accumulation of
25 5 Date 30.06.2024
silt in TRT pool at Jhakri
Repair of Runners dismantled
26 during APM 10 Date 15.12.2024
2023-24(Repair of six runners)

Upgradation of existing obsolete


PLC (Hardware & Software) with
latest technology based PLC
System (Hardware & Software)
at existing TRT outfall gates
control panel along with
27 10 Date 28.02.2025
Ethernet based encoder for
smooth & safe operation of TRT
outfall gate at Jhakri along with
engineering/operator
workstation, network switch
and firewall.

Up-gradation of existing
obsolete Windows XP based
MaX DNA HMI Control System
installed in Various Panels and
Server Stations at Rampur HPS
and TOS OWS at NJHPS with
28 12 Date 01.03.2025
latest Windows 10 based Max
DNA HMI Control System
which includes Design,
Engineering, Manufacturing,
Supply, Installation, Testing &
Commissioning

Recovery of Energy by setting


up 100KW Pump-as-Turbine &
Induction Generator unit from
29 10 Date 10.03.2025
existing make-up line used for
cooling of Generator
Transformer of RHPS
Assessment of all material
30 5 Date 30.04.2024
useability
Compliance of Public
Procurement Policy for Micro
31 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME.
32 Utilization of CSR Budget 3 % 100
33 Procurement from GeM 2 % 100

Utilization of Budget (CAPEX)


34 10 Rs. (Cr.) 400
FY 2024-25
CAPEX utilization till end of 3rd
35 4 Rs. (Cr.) 300
quarter 75% CAPEX
Commissioning of Steel Truss
36 5 Date 30.04.2024
Bridge
Dam Excavation- Left & Right
37 Bank Dam Abutments upto 4 Date 30.04.2024
660M
Transformer Hall- Excavation of
38 Adit to Transformer Hall 3 Date 30.06.2024
Bottom
Transformer Hall- Excavation of
39 3 Date 15.07.2024
Crown - Pilot Excavation
Power House- Excavation of
40 3 Date 15.07.2024
crown- Pilot Excavation
Power House- Main Access
41 3 Date 31.07.2024
Tunnel (605M)
Dam Excavation below EL
42 3 Date 15.09.2024
660m to River Bed Level
Transformer Hall- Excavation of
43 3 Date 30.09.2024
Crown- Widening
Establishment of 22KV Supply
and Transformer with Meter &
44 connection from HPSEB for 3 Date 30.09.2024
Office complex & Bachelor
accommodation.
Completion of Bachelor
45 Accommodation (02 Nos. 4 Date 31.10.2024
Blocks)
Landscaping works around
46 Office complex & Bachelor 3 Date 31.10.2024
Accommodation
Water supply & Sewerage
Treatment arrangements for
47 3 Date 31.10.2024
Office complex & Bachelor
accommodation
Power House- Excavation of
48 3 Date 31.10.2024
crown- Widening
Establishment of Area
illumination & Street lighting at
49 3 Date 30.11.2024
Office complex & Bachelor
accommodation.
Intake Structure- Adit to
50 4 Date 31.12.2024
Pressure shaft Bottom
51 Completion of Office Building 3 Date 31.12.2024
Power House- Excavation upto
52 4 Date 31.01.2025
Service Bay Level
Dam Concreting- River Bed
53 3 Date 28.02.2025
Level to EL 645M
Transformer Hall- Excavation of
54 3 Date 28.02.2025
TH Cavern
Power House- Excavation of
horizontal Busduct /cable
55 3 Date 31.03.2025
gallery from power house
service bay
Submission of Half Yearly
Environmental Clearance
56 2 Yes/No Yes
Compliance during Year 2024-
25
Sharing of Contractors' Claim
57 with Contract Deptt./CMC, 2 % 100
CHQ
Punching of daily progress
against finalized L2 Schedule
58 2 % 95
on Project System Module of
SAP/ERP
Compliance of Public
Procurement Policy for Micro
59 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME
Procurement of Goods &
60 3 % 100
Services through GeM
61 Utilization of CSR Budget 3 % 100

62 CAPEX Budget Utilization 10 Rs.(Cr.) 450


75% CAPEX Utilization till end
63 5 Rs.(Cr.) 337.5
of 3rd quarter
64 Delivery of EOT crane 5 Date 15.04.2024
Erection of EOT-1 Crane at
65 5 Date 15.05.2024
Service Bay by EM Agency
Completion of Dam concreting
66 5 Date 31.05.2024
up to EL 803 m
Construction of flood protection
67 wall for Power House up to EL 4 Date 31.05.2024
830 m.

Handover of site for installation


68 5 Date 15.06.2024
of Draft tube for Unit-1&2
To obtain the FCA Stage-1
approval from forest
69 3 Date 30.06.2024
department for transmission
line works

Handover of site for installation


70 3 Date 15.07.2024
of Draft tube for Unit-3&4

Starting of construction works


71 3 Date 31.07.2024
of T/L (220KV)
To obtain the FCA Stage-2
approval from forest
72 3 Date 31.08.2024
department for transmission
line works
Handing over site by EM for
73 Concrete of Stage-II Pour-I 4 Date 31.10.2024
(Draft tube foot and elbow)
Completion Of DT erection for
74 unit 1 including 2nd Stage 3 Date 15.11.2024
concreting
Completion Of DT erection for
75 unit 2 including 2nd Stage 3 Date 15.12.2024
concreting
Completion Of DT erection for
76 unit 3 including 2nd Stage 3 Date 31.01.2025
concreting
Completion Of DT erection for
77 unit 4 including 2nd Stage 3 Date 20.02.2025
concreting
Completion of Dam concreting
78 5 Date 31.03.2025
up to EL 840 m
Mutation of 100% land except
79 family dispute cases between 3 Yes/No Yes
owners

Completion of Budgetary claim


80 for enabling infrastructure 3 Date 31.03.2025
works by 31.03.2025

Sharing of Contractors' claim


with Contract Deptt/ CMC in
81 3 % 100
real time basis (Parameters to
be shared by CM&C).
Punching of daily progress
82 against finalized L2 Schedule 3 % 95
on SAP/ERP
Submissions of details/ status
of all claims including contracts
awarded by site pending before
83 2 No. 12.00
EIC to Civil Contract
Department by 7th of each
month.
Compliance of Public
Procurement Policy for Micro
84 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME.

85 Utilization of CSR Budget 3 % 100

86 Procurement from GeM 3 % 100

87 CAPEX Budget Utilization 10 Rs (Cr) 425


75% Capex Utilization till end of
88 2 Rs (Cr) 319
3rd Quarter.
Concreting of Draft Tube up to
89 Stay Ring Pedestal of Unit - I & 4 Date 15.05.2024
II
Construction of Flood
90 Protection Wall for Power House 5 Date 15.06.2024
up to EL 495 m

Installation and Commissioning


91 5 Date 30.06.2024
of EOT crane in service bay

Erection of Spiral case of Unit -


92 5 Date 15.09.2024
I & II
Completion of trunion beam in
93 one of the Dam block upto EL 5 Date 15.10.2024
508m
Concreting of Columns and
94 Beams in Machine Hall of 4 Date 15.11.2024
Power House.
Organising Blood donation
95 1 Date 15.11.2024
camp

Handing over of civil front to


96 EM contractor for erection of 5 Date 31.12.2024
Generator, Turbine & boxing up

Handing over of civil front to


97 EM contractor for erection of 4 Date 31.12.2024
Transformer.
Completion of Transmission
98 6 Date 28.02.2025
line
Erection of DT Gates including
99 5 Date 13.03.2025
hoists
100 Dam concreting up to EL 515 m 5 Date 15.03.2025

101 Erection Penstock Steel Liners 3 Date 23.03.2025


Erection Power Intake: Service
102 3 Date 27.03.2025
Gate including Hoist
Erection of Sluice Radial Gates
103 3 Date 31.03.2025
and Stoplog Gates
Spillway Flap and Stoplog
104 Gates including Gantry Crane 3 Date 31.03.2025
erection
Erection Power Intake:
105 3 Date 31.03.2025
Trashracks including TRCM

Erection Power Intake: Stoplogs


106 3 Date 31.03.2025
including Gantry Crane

Punching of real time data on


ERP with all contractual
107 correspondence and digitized 1 % 100
record as per parameters given
by CM&C)
Punching of daily progress
against finalized L2 Schedule
108 2 % 95
on SAP/ERP

Sharing of Contractors claim


with Contract Deptt/ CMC in
109 1 % 100
real time basis as per
parameters shared by CM&C
Submission of details/ status of
all claims including contract
awarded by site pending before
110 1 No. 12
EIC to Civil Contract
Department by 7th of each
month
Compliance of Public
Procurement Policy for Micro
111 1 Yes/No Yes
and Small Enterprises issued
by M/o MSME.

112 Utilization of CSR Budget 2 % 100

113 Procurement from GeM 1 % 100


Submission of Finalized/
Accepetd Schedule for 3.5 MW
114 Auxiliary unit to CM&C after 2 Days 15
acceptance of award by
contractor

115 Capex Utilization 15 Cr. 2

Submission of discharge data


for eight major nallahs in
116 12.5 Date 30.06.2024
between dam & power house
during:- Pre-monsoon period
Approval of GoI for development
117 25 Date 30.09.2024
of Devsari HEP
Submission of discharge data
for eight major nallahs in
118 12.5 Date 30.11.2024
between dam & power house
during: -Post-monsoon period
Submission of monthly Silt &
119 climatological data to Hydrology 5 No. 12
cell
Submission of monthly
Procurement/ Environment
120 5 Yes/No Yes
data to CHQ before 7th of every
month.
Achievement of targets as
121 5 % 100
allocated by CSR dept.
Compliance of Public
Procurement Policy for Micro
122 5 Yes/No Yes
and Small Enterprises issued
by M/o MSME.

123 Utilization of CSR Budget 5 % 100

124 Procurement from GeM 5 % 100

125 CAPEX Budget Utilization 15 Rs. (Cr.) 20

Assessment of additional land


126 required as per approved 5 Date 10.04.2024
revised layout

Inputs for submission of online


127 application for amendment in Date 30.04.2024
ToR of Reoli Dugli HEP
Submission of input for revised
128 ToR of Environment Clearance 5 Date 30.06.2024
to Corporate Environment

Submission of fresh FC case on


129 5 Date 30.06.2024
Parivesh Portal
130 Completion of drilling works 4 Date 31.05.2024
Submission of FC case on
131 4 Date 30.06.2024
Parivesh Portal

Completeion of Geo
132 5 Date 31.07.2024
Technical/In-SITU test for DPR

Preparation CAT Plan Report of


133 4 Date 31.07.2024
Bardang HEP
Readiness of all documents for
134 purchase/ acquisition of Private 5 Date 31.08.2024
Land
Preparation of Township Plan
135 4 Date 31.08.2024
for Chenab Projects
136 Completion of drilling works 4 Date 31.05.2024
Submission of FC case on
137 4 Date 30.06.2024
Parivesh Portal

Completeion of Geo
138 5 Date 31.07.2024
Technical/In-SITU test for DPR

Preparation CAT Plan Report of


139 4 Date 31.07.2024
Bardang HEP
Readiness of all documents for
140 purchase/ acquisition of Private 5 Date 31.08.2024
Land
Preparation of Township Plan
141 4 Date 31.08.2024
for Chenab Projects
Submission of FC case on
142 5 Date 31.05.2024
Parivesh Portal

143 Award of work 5 Date 28.02.2025


Carrying out IN-SITU tests for
144 5 Date 30.06.2024
DPR
Carrying out geological
145 4 Date 31.07.2024
exploration works for DPR

Readiness of Land Diversion/


146 4 Date 31.07.2024
Acquisition proposals

Submission of FC case on
147 4 Date 31.07.2024
Parivesh Portal
148 Preparation of CAT Plan Report 4 Date 31.08.2024

Compliance of Public
Procurement Policy for Micro
149 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME.

150 Utilization of CSR Budget 3 % 100

151 Procurement from GeM 2 % 100

152 Gross Energy Generation 10 MU 280

Inputs for total cost to


153 completion to CP for Board 5 Date 30.04.2024
Aproval
Pre- Monsoon inspection of all
154 5 Date 30.04.2024
HM components of NMHPS
Taking Over of EM store
alongwith Mandatory Spares,
155 5 Date 30.04.2024
etc. from EM Contractor &
Transmission contractor
Operationalization of EM Store
156 5 Date 15.05.2024
in SAP
Guarantee Test of Units
157 depending upon required water 5 Date 31.05.2024
availability
Purchase of tools & tackles for
maintenance of Transmission
158 5 Date 30.06.2024
Line except provisioned in
contract
Erection and Commissioning of
159 Trash Rack Cleaning Machine 5 Date 31.08.2024
(TRCM)
Post- Monsoon inspection of all
160 5 Date 30.09.2024
HM components of NMHPS
Inspection of all Civil
161 Structures by Internal 5 Date 15.10.2024
Committee
Carrying out Dam Safety
162 inspection through External 4 Date 30.11.2024
Agency
163 Contract Closure of NMHPS 5 Date 31.03.2025
Monthly inspection of
Transmission Line from
Switchyard of NMHPS to
164 Pooling Station near Snail and 5 No. 12
submission of corrective action
taken and submission of its
report to ED, CHQ & CM&C.

Monthly monitoring of installed


instruments at the various
project component and
165 4 No. 12
submitting Data to Corp.
Design & Corp. Geology Dept.’s,
Shimla.
Settlement of all due claims
166 i.r.o. EM pkg after due 5 Days 45
submission
Annual Plant Maintenance
167 5 Days 14
during lean session

R&R plan- Standing Committee


168 3 Yes/ No Yes
meeting etc. (NMHPS)

Compliance of Public
Procurement Policy for Micro
169 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME.

170 Utilization of CSR Budget 3 % 100

171 Procurement from GeM 3 % 100

CAPEX Budget achievement for


172 10 Rs.(Cr) 7065
Renewable Projects
75% CAPEX utilization till end
173 2 Rs.(Cr) 5298.75
of 3rd quarter

Participation in bidding process


174 3 No. 6
for allocation of RE Projects

Obtaining new Renewable


175 6 MW 1200
Energy Projects of capacity
Finalization of EPC price bid
176 recommendation after opening 3 Days 70
of major tenders
Approval of L2 schedule after
177 3 Days 30
issuance of award letter
Issuance of MDCC/ Drawings
178 3 Days 5
and Quality Plans
Carrying out Pre-MDCC
179 inspection after receipt of 3 Days 7
proposal from the contractor
Raising of provisional bills of
operation projects after receipt
of Regional Energy
180 Account/Joint Meter 3 Days 2
Reading/State Energy Account
& requisite details from projects
sites

Appointment of Internal Auditor


181 3 Date 30.06.2024
for FY 2024-25 of SGEL

Audit of Annual Accounts from


182 Statutory Auditor for FY 2023- 3 Date 21.05.2024
24
183 COD of Nangal FSPP (15MW) 1 Date 15.07.2024
184 COD of Bagodara SPP (70MW) 1 Date 31.08.2024
185 COD of Bikaner-Unit 1 1 Date 30.09.2024
186 COD of Bikaner-Unit 2 1 Date 30.11.2024
187 COD of Bikaner-Unit 3 1 Date 31.01.2025
188 COD of Bikaner-Unit 4 2 Date 31.03.2025
COD of Jamui SPP Phase I
189 1 Date 31.01.2025
75MW
190 COD of Banka SPP (75MW) 1 Date 31.01.2025
191 COD of Khavda SPP (200MW) 1 Date 31.03.2025
192 COD of Bhuj SPP(260 MW) 1 Date 15.01.2025
193 COD of Bhuj SPP (100MW) 1 Date 15.01.2025
COD of Punjab SPP(50 MW)
194 2 Date 30.09.2024
Chandpur Roorki
COD od Punjab SPP (50 MW)
195 1 Date 30.09.2024
Pojewal
Generation of Energy Parasan
196 1 MU 165
SPP
Generation of Energy Gurhah
197 1 MU 160
SPP
Generation of Energy Gujrai
198 1 MU 105
SPP
Generation of Energy
199 1 MU 250
Ragnesdha SPP
Generation of Energy Bagodra
200 1 MU 135
SPP
Generation of Energy
201 1 MU 175
Omkareshwar SPP
Generation of Energy Bikaner
202 1 MU
SPP
Generation of Energy Nangal
203 1 MU 20
FSPP
Generation of Energy Punjab
204 1 MU 110
SPP
Completion of Tax Audit by Tax
205 3 Yes/No Yes
Auditor before due date.
Recovery of billed amount from
206 3 Days 45
Buyers ( within 45 days)

Approval and issuance of BBU


207 after final correspondence 3 Date 7
received from the contractor

New vendor approval/


208 disposition of Non 3 Days 7
Conformances Report (NCR)
Completion of CAG audit for FY
209 3 Date 24.07.2024
2023-24
Participation in one number
210 tender for battery storage 2 Date 31.10.2024
system
Participation in one number
211 tender regarding green 2 Date 30.11.2024
hydrogen
Participation in one number
212 2 Date 31.12.2024
tender regarding RTC power
Financial closure within due
213 2 Yes/No Yes
dates of RE projects
Awarding of work for online
214 3 Date 31.03.2025
monitoring of RE Projects
Signing of JV agreement of
215 3 Date 31.07.2024
Assam (APDSL)
216 Generation of Energy 15 MU 165
Submission of Daily Generation
217 Reports to concerned 10 % 100
departments
Processing of Main Contractor
218 15 Days 15
O&M Bills
Ensuring submission of
required inputs directly by
219 concerned sites to C&SO Deptt. 10 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
220 SPIA/LSPDCL towards 12 Days 7
Annual/Statutory Charges
221 Contract Closure 12 Date 31.07.2024
Compliance of Public
222 Procurement Policy for Micro 9 Yes/No Yes
and Small Enterprises

223 Utilization of CSR Budget 12 % 100

224 Power Generation 15 MU 160


225 Final EOT of contract 15 Date 30.06.2024
Submission of Daily Generation
226 Reports to concerned 15 % 100
departments
Processing of Main Contractor
227 15 Yes/No Yes
Bills
Ensuring submission of
required inputs directly by
228 concerned sites to C&SO Deptt. 10 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
229 SPIA/LSPDCL towards 15 % 100
Annual/Statutory Charges
Compliance of Public
230 Procurement Policy for Micro 10 Yes/No Yes
and Small Enterprises
231 Generation of Energy 15 MU 135

232 CAPEX Utilization 15 Crore 50


233 COD of Project 10 Date 31.08.2024
Final Acceptance of Bagodara
234 10 Date 30.11.2024
Solar Power Project
Submission of Daily Generation
235 Reports to concerned 10 % 100
departments
Ensuring submission of
required inputs directly by
236 concerned sites to C&SO Deptt. 10 Days 5
regarding raising of monthly
bills
237 Finalization EOT 15 Date 31.01.2025
Compliance of Public
238 Procurement Policy for Micro 10 Yes/No Yes
and Small Enterprises
239 Capex Utilization 12 INR (Cr) 2500
75% Capex Utilization till end of
240 5 INR (Cr) 1875
3rd Quarter
Connection from Switchyard to
241 5 Date 01.05.2024
Bikaner-II Sub-station

Completion of CMCS to Power


242 5 Date 15.07.2024
Transformer Connection
243 Commissioning of Plant
244 Unit-1 (250 MW) 5 Date 30.09.2024
245 Unit-2 (250 MW) 5 Date 30.11.2024
246 Unit-3 (250 MW) 5 Date 31.01.2025
247 Unit-4 (250 MW) 5 Date 31.03.2025

Processing of bills of M/s TPSSL


248 after submission of complete 6 Days 7
documents as per contract

249 Generation of Power 15 MU 400


Ensuring submission of
required inputs directly by
250 concerned sites to C&SO Deptt. 6 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
SPIA/ towards
251 6 Days 7
Annual/Statutory Charges (to
be checked)
Submission of Daily Generation
252 Reports to concerned 6 % 100
departments
Compliance of Public
253 Procurement Policy for Micro 3 Yes/No Yes
and Small Enterprises
Utilization of allocated CSR
254 6 % 100
budget
255 Generation of Energy 15 MU 250
Operational acceptance of
256 Raghanesda SPP as per 10 Date 15.07.2024
Contract
Submission of daily/monthly
257 Generation report to concerned 10 % 100
departments
Processing of bills to EPC
258 contractor in O&M stage after 10 Days 7
receipt of documents
Ensuring submission of
required inputs directly by
259 concerned sites to C&SO Deptt. 10 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
260 SPIA/LSPDCL towards 10 Days 7
Annual/Statutory Charges

261 Final EOT of contract 10 Date 31.10.2024

Compliance of Public
262 Procurement Policy for Micro 10 Yes/No Yes
and Small Enterprises
Utilization of CSR Budget by
263 10 % 100
31.03.2025
264 Generation of Energy 15 MU 105
Submission of Daily Generation
265 Reports to concerned 10 % 100
departments
Processing of Main Contractor
266 15 Days 7
Bills
Ensuring submission of
required inputs directly by
267 concerned sites to C&SO Deptt. 10 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
268 SPIA/LSPDCL towards 10 Days 7
Annual/Statutory Charges
269 Final EOT of contract 15 Date 31.07.2024
Compliance of Public
270 Procurement Policy for Micro 10 Yes/No Yes
and Small Enterprises

271 Utilization of CSR Budget 10 % 100

272 Generation 8 MU 30

273 Capex Utilization 10 INR (CR) 250

75% capex utilization till end of


274 5 INR (CR) 188
3rd quarter

Completion of physical
275 boundary fencing and leveling 10 Date 15.04.2024
work of 75 MW Jamui SPP site

Installation of pre fabricated


276 site office for the functioning of 10 Date 15.05.2024
office at site
Installation of 1st Block of MMS
as per agreed L1 schedule from
277 10 Date 30.06.2024
letters of award of BOS
contract.
Installation of 2nd Block of
MMS as per agreed L1 schedule
278 10 Date 31.07.2024
from letters of award of BOS
contract.
Instaltion, testing and
279 8 Date 30.11.2024
commissioning of switchyard
Instalation of all 6 block of
MMS as per agreed L1 schedule
280 8 Date 15.01.2025
from letter of award of BOS
contract

Completion of transmission line


281 and charging/synchronised 8 Date 15.01.2025
with grid

Commissioning of 75 MW
282 Jamui SPP and synchronized 8 Date 31.01.2025
with grid
283 Capex utilization 10 INR (CR) 200
75% capex utilization till end of
284 5 INR (CR) 150
3rd quarter
285 Energy Generation 5 MU 27
Physical boundary fencing of
286 Banka site after completion of 5 Date 30.04.2024
registry date
Commencement of site
development work & Civil work
287 10 Days 15
from Zero date stipulated in
BOS contract
Construction of approach road
288 10 Date 15.05.2024
to access the control

Commencement of construction
289 10 Date 15.07.2024
work of transmission line

Installation of control room for


290 10 Date 31.07.2024
the functioning of office at site

Completion of Civil work and


291 10 Date 15.11.2024
erection of MMS
Installation, Testing and
292 10 Date 31.12.2024
Commissioning of Switchyard
Commissioning of 75 MW SPP
293 10 Date 31.01.2025
and synchronized with grid
% Completion of acquisition of
294 15 % 95
land by 30.04.2024
295 CAPEX Utilization 10 INR Cr. 250
Mobilisation of BoS Vendor at
296 5 Date 01.05.2024
Site
Completion of all Foundations
297 10 Date 30.09.2024
of PSS
Installation of 100% MMS
298 10 Date 31.10.2024
Tables

Processing of bills to BOS and


Module Supply contractor after
299 10 Days 7
receipt of documents complete
in all respects

Completion of 220 kV
300 10 Date 31.12.2024
Transmission System
301 Installation of 100% Modules 10 Date 31.12.2024
302 Commissioning of Project 10 Date 15.01.2025
Compliance of Public
303 Procurement Policy for Micro 5 Yes/No Yes
and Small Enterprises
% Completion of acquisition of
304 15 % 95
land by 30.04.2024
305 CAPEX Utilization 10 INR Cr. 250
Mobilisation of BoS Vendor at
306 5 Date 01.05.2024
Site
Completion of all Foundations
307 10 Date 30.09.2024
of PSS
Installation of 100% MMS
308 10 Date 31.10.2024
Tables

Processing of bills to BOS and


Module Supply contractor after
309 10 Days 7
receipt of documents complete
in all respects

Completion of 220 kV
310 10 Date 31.12.2024
Transmission System
311 Installation of 100% Modules 10 Date 31.12.2024
312 Commissioning of Project 10 Date 15.01.2025
Compliance of Public
313 Procurement Policy for Micro 5 Yes/No Yes
and Small Enterprises
314 CAPEX Utilization 10 INR Cr. 400
Completion of topography &
315 Geotechnical Survey of the 10 Date 15.05.2024
project
Completion of Civil works of
316 10 Date 30.06.2024
Main Control Room
317 Installation of 50% Modules 5 Date 31.07.2024
Installation of 100% MMS
318 10 Date 15.08.2024
Tables
319 Installation of 100% Modules 5 Date 31.08.2024
Completion of foundation works
of Inverter Duty Transformers,
320 5 % 100
Inverters, ICOG panels by
15.08.2024

Processing of bills to BOS and


Module Supply contractor after
321 10 Days 7
receipt of documents complete
in all respects

Ensuring 100 % supply of BOS


322 10 Date 01.11.2024
material at site
323 SCOD of Project 10 Date 31.03.2025
Compliance of Public
324 Procurement Policy for Micro 10 Yes/No Yes
and Small Enterprises
325 Capex Utilization 10 Cr 15
326 Energy generation 10 MU 20
Completion Of Supply Of Major
327 10 Date 15.04.2024
Items (i.e. PV Modules, Floaters)

Completion of all site


328 development activities including 10 Date 30.04.2024
Civil works
Erection, testing &
329 commissioning of all the 10 Date 31.05.2024
equipments
330 Readiness for Plant COD 10 Date 15.07.2024
Completion of operational
331 5 Date 15.09.2024
acceptance test subject to COD

Issuance of final acceptance


certificate after receipt of all
332 relevant documents complete in 5 Days 7
all respect as per contract
agreement
Submission of daily generation
333 reports to concerned 5 % 100
departments
Processing of contractor's bills
334 against epc contract after 5 Days 7
recieviing of all documents

Ensuring submission of
required inputs directly by
335 concerned sites to C&SO Deptt. 5 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
PSPCL/state power developing
336 5 Days 7
agencies towards Annual/
Statutory Charges
Compliance of Public
337 Procurement Policy for Micro 5 Yes/No Yes
and Small Enterprises
338 Utilization of CAPEX 15 Cr. 50
339 Generation of Energy 15 MU 195
340 COD of Plant 10 Date 15.05.2024
Operational acceptance of
341 Omkareshwar FSPP as per 10 Date 15.09.2024
Contract
Submission of daily generation
342 report to concerned 10 % 100
departments
Processing of bills to EPC
343 contractor in O&M stage after 10 Days 7
receipt of documents
Ensuring submission of
required inputs directly by
344 concerned sites to C&SO Deptt. 10 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
345 SPIA towards Annual/Statutory 5 Days 7
Charges
Utilization of CSR Budget by
346 5 % 100
31.03.2025
Compliance of Public
347 Procurement Policy for Micro 5 Yes/No Yes
and Small Enterprises
348 Capex Utilization 10 Cr 200

349 Generation of Energy 10 MU 115


Completion of supply of Major
items Power & Inverter
350 Transformers, PV Modules, 6 Date 15.04.2024
Floaters( Chandpur Rurki
(50MW) site
Completion of supply of Major
items Power & Inverter
351 7 Date 15.07.2024
Transformers, PV Modules,
Floaters Pojewal (50MW) site
Completion of all site
development activities including
352 6 Date 30.04.2024
Civil works - Chandpur Rurki
(50MW) site
Completion of all site
development activities including
353 6 Date 31.07.2024
Civil works - Pojewal (50MW)
site

Erection, Testing &


Commissioning of all the
354 5 Date 30.04.2024
equipments - Chandpur Rurki
(50MW) site

Erection, Testing &


Commissioning of all the
355 5 Date 31.07.2024
equipments - Pojewal (50MW)
site
Plant COD -Chandpur Rurki
356 5 Date 30.09.2024
(50MW) site
357 Plant COD -Pojewal (50MW) site 5 Date 30.09.2024

Submission of daily Generation


358 reports to Concerned 5 % 100
Departments

Processing of Contractor's bills


359 against EPC Contract after 5 Days 7
receiving of all documents.

Ensuring submission of
required inputs directly by
360 concerned sites to C&SO Deptt. 5 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
PSPCL/state power developing
361 5 Days 7
agencies towards
Annual/Statutory Charges
362 Operational Acceptance 10 Date 31.01.2025
Submission of daily Generation
363 reports to Concerned 5 % 100
Departments

Processing of Contractor's bills


364 against EPC Contract after 5 Days 7
receiving of all documents.

Ensuring submission of
required inputs directly by
365 concerned sites to C&SO Deptt. 5 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
PSPCL/state power developing
366 5 Days 7
agencies towards
Annual/Statutory Charges
367 Operational Acceptance 10 Date 31.01.2025
Submission of daily Generation
368 reports to Concerned 5 % 100
Departments

Processing of Contractor's bills


369 against EPC Contract after 5 Days 7
receiving of all documents.

Ensuring submission of
required inputs directly by
370 concerned sites to C&SO Deptt. 5 Days 5
regarding raising of monthly
bills
Processing of Invoices Raised by
PSPCL/state power developing
371 5 Days 7
agencies towards
Annual/Statutory Charges

372 Operational Acceptance 10 Date 31.01.2025

373 Capex - Generation 10 INR Cr. 1700

374 Capex - Transmission 5 INR Cr. 175

75 % of Capex utilization till


375 1 INR Cr. 1275
31.12.2024- Generation
75 % of Capex utilization till
376 1 INR Cr. 131
31.12.2024- Transmission
Finalization of annual accounts
of SAPDC as per the
377 requirement of holding co. I.e. 1 Date 31.05.2024
SJVN ltd for the year ending
31.03.2024
Completion of Dam concreting
378 2 Date 30.06.2024
upto EL 795 M
Completion of all Civil
structures I/C GIS/CRP
379 building, Tower foundation & 2 Date 30.06.2024
other misc. Structures for Pot
Head Yard in switch yard.
Acquisition of land/diversion of
380 Forest Land for Tower 2 Date 31.07.2024
Foundation -TW-01 Package
Completion of Dam concreting
381 2 Date 31.08.2024
upto EL 809.85 M
382 Erection of Intake Gates 2 Date 31.08.2024
383 Pit free Unit 1 & 2 3 Date 31.08.2024
384 Pit free Unit 3 & 4 3 Date 30.09.2024
Concreting of Draft Tube Gate
385 2 Date 30.09.2024
Shaft (1 to 4)
Completion of Overt lining of
386 2 Date 30.09.2024
HRT
Assembly & lowering of rotor for
387 3 Date 15.10.2024
1st & 2nd unit
Completion of Surge shaft I/C
388 3 Date 31.10.2024
Concrete lining
Finalization of annual accounts
of SAPDC and submission for
389 1 Date 31.10.2024
audit as per Nepal`s FY ending
15.07.2024
Assembly & lowering of rotor for
390 3 Date 15.11.2024
3rd & 4th unit
Erection of towers for tw-01 Pkg
391 2 Date 30.11.2024
by
Installation of main inlet valves
392 1 Date 30.11.2024
for 1st & 2nd unit

Installation of Generator
393 3 Date 30.11.2024
transformer for 1st & 2nd unit

Erection of Pressure Shaft Steel


394 3 Date 15.12.2024
Liner
395 Erection of Draft Tube Gates 2 Date 15.12.2024
Completion of Dam concreting
396 3 Date 31.12.2024
for Project Commissioning
Concrete invert lining of HRT in
397 3 Date 31.12.2024
all respects including Adits Plug
398 Erection of Surge Shaft Gates 2 Date 31.12.2024
Installation of main inlet valves
399 1 Date 31.12.2024
for 3rd & 4th unit
Completion of transmission line
400 1 Date 31.12.2024
in tw-02 Package
401 Erection of Sluice Radial gates 3 Date 15.01.2025

Completion of GIS works


402 including testing & Pot head 3 Date 15.01.2025
yard
403 Boxing up 1st & 2nd unit 3 Date 31.01.2025
Completion of transmission line
404 3 Date 31.01.2025
in tw-01 package

Installation of Generator
405 3 Date 28.02.2025
Transformer for 3rd & 4th unit
406 Boxing up 3rd & 4th unit 3 Date 28.02.2025
Commissioning of 1st & 2nd
407 2 Date 28.02.2025
unit
Commissioning of 3rd & 4th
408 2 Date 31.03.2025
unit
Ensuring processing of all
purchase orders/ contract
409 2 Date 30.04.2024
based payments through SAP
standard process
Punching of daily progress
410 against finalized L2 Schedule 2 % 95
on SAP/ERP
411 Capex Budget utilization 10 INR Cr. 15

75% Capex Budget utilization


412 10 INR Cr. 11
till end of 3rd quarter

Approval of Layout from


413 10 Date 31.05.2024
CEA/CWC
Finalization of JV Agreement
414 10 Date 30.06.2024
with NEA
Completion of detailed
investigation required for DPR
415 15 Date 31.12.2024
preparation based upon
approved layout
Submission of Pre-DPR
416 20 Date 31.12.2024
chapters to CEA, GoI.
Preparation & completion of
417 20 Date 31.03.2025
DPR
418 Capex budget utilization 10 INR Cr. 300
75% Capex budget utilization
419 5 INR Cr. 225
till end of 3rd quarter

Lease agreement of govt. Land


420 5 Date 30.04.2024
and diversion of forest land

Finalization of annual accounts


of SLPDC as per the
421 requirement of holding co. I.e. 5 Date 31.05.2024
SJVN Ltd. for the year ending
31.03.2024
CCEA Clearance from Govt. Of
422 5 Date 30.06.2024
India
423 Award of Major Civil works 5 Date 10.07.2024
424 Acquisition of 80 % land 5 Date 31.07.2024
Issuance of of construction
drawings for grouting at outfall
425 pond/ intake area and Head 6 Date 31.07.2024
Race Tunnel from STA.. 0.00 to
STA. 100.00.
Submission of draft Disaster
426 6 Date 30.09.2024
Mangement plan to IBN
Finalization of annual accounts
of SLPDC and submission for
427 5 Date 30.09.2024
audit as per Nepal`s FY ending
15.07.2024

Submission of draft
428 downstream irrigation projects 5 Date 31.10.2024
and other studies report to IBN

Issuance of miscellaneous
construction drawings required
429 for completion of outfall pond 6 Date 31.12.2024
intake structure, hrt from STA.
0.00 to STA. 100.00 m

Construction of approach roads


430 up to Surge Shaft and HRT 6 Date 31.12.2024
Adits

Submission of draft IEE report


431 7 Date 15.01.2025
of LILO to OIBN
Award of works for Electro-
432 7 Date 28.02.2025
Mechanical package
Completion of Excavation of
433 7 Date 31.03.2025
Power House

434 CAPEX Budget Utilization 10 Cr. 500

75% CAPEX Utilization till end


435 5 Cr. 375
of 3rd quarter
Deposit of Land Compensation
436 with 6 Date 15.04.2024
State Govt.
Finalization of Packages for
437 3 Date 15.04.2024
Etalin HEP
Award of Work for Hiring of
Manpower for running and
438 maintenance of Office-cum- 5 Date 15.04.2024
Residential Complex of Etalin
HEP
Identification and finalisation of
land for New Office cum
439 6 Date 01.05.2024
Residential Complex along Dri
Limb.
Inputs for Design &
440 4 Date 31.05.2024
Engineering for Etalin HEP
Procurement and erection of
441 2no. of DG Sets for office cum 5 Date 31.05.2024
residential complex.
Award of renovation work of
existing
442 4 Date 15.06.2024
Office-cum-Residential Complex
of Etalin HEP
443 Stage-1 Forest Clearance 6 Date 31.07.2024
Inputs for Major Civil Works
444 1 Date 31.07.2024
Package C1
Procurement of requisite IT
hardware like Work Station,
445 5 Date 31.08.2024
Printer, Desktop etc. for Etalin
HEP
446 Environment Clearance 3 Date 31.08.2024
447 Stage-2 Forest Clearance 6 Date 31.10.2024
NIT for hiring of agency for
setting up IT
communication/networking for
448 3 Date 31.10.2024
existing Main Office cum
Residential Complex of Etalin
HEP
Erection of supply of 11kV
449 Power Line for office & 5 Date 31.10.2024
residential complex of EHEP
Re-establishment of 3 nos. G&D
450 5 Date 31.10.2024
Site.
Demarcation of Forest/Pvt land
451 in consultation with Distt. 5 Date 31.10.2024
Administration/Forest
Finalization of estimate for Fuel
452 Depot at existing office cum 5 Date 31.12.2024
residential complex.
453 Award of Major Civil Package 3 Date 31.12.2024
454 Utilization of Budget (CAPEX) 10 Cr. 10
455 Award of Drifting works 4 Date 15.04.2024
Obtaining NOC from State
456 Forest Department for Survey & 5 Date 30.04.2024
Investigation Work
457 Establishment of G&D Site. 5 Date 31.05.2024
Award of work for preparation
458 5 Date 31.05.2024
of CAT Plan
To carry out Physical Model
studies of Dam, Intake and DC:
459 4 Date 31.07.2024
Latest survey of Dam and
Reservoir Area
Completion of Tree
460 Enumeration work by State 5 Date 15.08.2024
Forest Department
To carry out Numerical Model
studies in PH Cavern-
461 4 Date 31.08.2024
Hydrofracture Test (Results) in
PH Drift

For carrying out Numerical


462 Model studies for a profile in 4 Date 31.08.2024
reservoir: Silt data at dam site

463 Award of Groutability Test 4 Date 31.08.2024


Obtaining NOC from Ministry of
464 5 Date 31.08.2024
Tribal Affairs, GOI
465 Stage-I Forest Clearance 6 Date 15.09.2024
Erection of supply of 11kV
Power Line for office &
466 10 Date 31.10.2024
residential complex of Attunli
HEP
467 Land Acquisition 8 Date 31.12.2024
Construction Material Survey &
468 Testing of Quarry site 5 Date 31.12.2024
materials.
469 Environment Clearance 5 Date 31.12.2024

Submission of Draft EIA/EMP


report to Corporate
470 3 Date 30.11.2024
Environment Department after
completing all Seasonal Studies

Finalization of Civil & EM


471 3 Date 28.02.2025
Packages for Attulni HEP
Utilization of Budget (CAPEX)
472 10 Cr. 10
as allocated.
Submission of Report on
confirmation of domains
473 5 Date 30.04.2024
(FRL,TWL) for Emini, Amulin &
Mihumdon HEPs
Submisson of data/Report
showing Proposed/
Operational / Under
474 Construction HEPs in the 10 Date 31.05.2024
vicinity of Emini, Amulin &
Mihumdon HEPs affecting the
planning of these projects

Procurement of relevant Survey


475 of India Toposheets i.r.o Emini, 10 Date 15.05.2024
Amulin & Mihumdon HEPs

Identification/Establishment of
location (latitude/Longitude) of
476 10 Date 30.06.2024
Dam axis PH sites for Emini,
Amulin & Mihumdon HEPs

Providing necessary
input/support during Site
477 Visits in respect of preparation 10 Yes/No Yes
of PFRs for Emini, Amulin &
Mihumdon HEPs

Establishmentof Guage &


478 Discharge site for the three 10 Date 31.12.2024
Projects
Completion of Topographical
479 5 Date 28.02.2025
survey of the Projects
Completion of Geological
480 Mapping and Geo-Physical 5 Date 15.03.2025
survey of the Projects
Construction material survey &
481 laboratory investigation of 5 Date 15.03.2025
course & fine aggregates
Providing inputs for TOR
482 application to Environment 5 Yes/No Yes
Department
Identifying and finalizing the
483 buildings for establishment of 5 Date 31.06.2024
Office and Transit Camp.
Hiring of security services for
484 5 Date 31.10.2024
Office and Transit Camp.
Power Generation from Khirvire
485 15 MU 50
Wind Power project
Capacity Utilization Factor
486 10 % 13.25
(CUF)
487 Award of O&M Contract 5 Date 30.06.2024
Ensuring Half-yearly
488 Preventive Maintenance of 5 Date 31.08.2024
WEGs
Submission of proposal for
489 upgradation / performance 5 Date 30.09.2024
improvement of the plant
Forwarding of O&M Budget (RE
490 2023-24, BE 2023-24) to 3 Date 07.10.2024
Corporate Finance.
Comprehensive yearly
491 preventive maintenance of all 8 Date 15.02.2025
56 nos. WEGs

Submission of daily generation


492 and outage reports to 7 Yes/No Yes
concerned departments.

Payment of Main Contractor


493 8 Days 15
Bills
494 Safety Audit of plant 5 Yes/No Yes
Submission of inputs to C&SO Days
495 Dept. for tendering of Insurance 5 before 90
Coverage of KWPS due date
Payment of DSM Charges arise
496 due to scheduling and 5 Days 3
forecasting
Ensuring submission of
required inputs directly by
497 concerned sites to C&SO 5 Week 1
Deptt., regarding raising of
monthly bills of Khirvire WPS.
Compliance of Public
Procurement Policy for Micro
498 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME
Procurement of Goods &
499 3 % 100
Services through GeM
500 Utilization of CSR Budget 3 % 100
Power Generation from Sadla
501 15 MU 105
Wind Power Station.
Capacity Utilization Factor
502 6 % 23
(CUF)
Submission of Daily Generation
Reports to concerned
503 6 % 100
Departments after receipt from
contractor.
Submission of O&M Budget (RE
504 2023-24, BE 2024-25) to 6 Date 07.10.2024
Director-in-Charge.
Ensuring Half-yearly
505 Preventive Maintenance of 6 Date 31.12.2024
WEGs
Ensuring Yearly Preventive
506 10 Date 15.02.2025
Maintenance of WEGs
Payments of invoices towards
507 statutory charges after receipt 6 Week 3
of invoices.
Payment of DSM Charges arise
due scheduling and forecasting
508 6 Days 3
within specified time limit after
receiving.

Submission of inputs to C&SO Days


509 Dept. for tendering of Insurance 6 before 90
Coverage of Sadla WPS due date

510 Safety Audit of plant 7 Yes/ No Yes

Ensuring submission of
required inputs directly by
511 concerned sites to C&SO Dept. 6 Week 1
regarding raising of monthly
bills of Sadla WPS.
Submission of Inputs/
Documents on to Arbitration
512 6 % 100
Cell regarding ongoing
arbitrations.
Compliance of Public
Procurement Policy for Micro
513 3 Yes/No Yes
and Small Enterprises issued
by M/o MSME
Procurement of Goods &
514 3 % 100
Services through GeM
515 Utilization of CSR Budget 3 % 100
Power Generation from
516 15 MU 8
Charanka Solar Power Project
Submission of Daily Generation
Reports (DGR) to concerned
517 10 % 100
departments after receipt from
contractor
Capacity Utilization Factor
518 15 % 17.5
(CUF)
Payment of DSM Charges arise
due scheduling and forecasting
519 10 Days 3
within specified time limit after
receiving.
Payment of invoices towards
520 statutory charges after receipt 10 Week 1
of invoices.
Forwarding of O&M Budget (RE
521 2024-25, BE 2025-26) to C&SO 10 Date 07.10.2024
Department.
Ensuring Yearly Preventive
522 Maintenance of Plant 10 Date 15.01.2025
Equipments
Compliance of Public
Procurement Policy for Micro
523 5 Yes/No Yes
and Small Enterprises issued
by M/o MSME
Procurement of Goods &
524 5 % 100
Services through GeM

525 Utilization of CSR Budget 5 % 100

Review of design of different


categories of landslide affected
locations after receipt of
526 2 Days 15
complete data from NHAI in
respect of NH-5 (Parwanoo-
Solan-Shimla)
Review of design of different
categories of landslide-affected
527 locations after receipt of 3 Days 15
complete data from NHAI (other
locations)
Issuance of construction
drawings for Powerpack control
528 rooms for radial gates of Arun-3 1 Days 35
HEP after receipt of data from
EM/HM

Award of Physical Model studies


529 2 Date 31.08.2024
in respect of Attulni HEP

Award of Numerical model


studies for sediment profile
530 2 Date 30.09.2024
formed in reservoir of Attulni
HEP.
Providing Inputs required for
531 preparation of Bid Documents 2 Date 31.12.2024
of Attulni HEP

Review of Design Reports and


Drawings after receipt from
532 3 Days 15
Project Head : Dam,for all major
components i.r.o DSHEP.

Completion of Phase -2- R&D


Studies of high Performance
533 3 Date 31.12.2024
Concrete for Spillways and
Barrages through IIT, Delhi
Inspection of all HM Structures
of NJHPS, RHPS and NMHPS by
534 1 Date 15.05.2024
Internal Committee-Pre-
monsoon
Inspection of all HM Structures
of NJHPS, RHPS and NMHPS by
535 1 Date 31.10.2024
Internal Committee-Post-
monsoon

Final approval/comments on
contractor’s design & drawings
after receipt from SAPDC- Gates
536 & Hoists at TRT Outfall of 2 Days 30
Arun-3 HEP for Tandem
operation of Arun-3 HEP and
Lower Arun HEP.

Final review/comments on
contractor’s design & drawings
after receipt from EIC- Gates,
537 4 Days 21
Hoists and Penstocks of Luhri
Stage-I HEP, Dhaulasidh HEP
and Sunni Dam HEP.
Preparation of bid documents
comprising of technical
specifications, specification
538 3 Date 31.12.2024
drawings and price schedule in
respect of HM works packages
for Etalin HEP.

Preparation of HM Chapter of
DPR of upcoming Hydroelectric
539 1 Days 35
Projects after receipt of input
data from Civil Design Deptt.
Queries/Comments/
Observations of
540 CEA/CWC/Other Agencies on 1 Days 10
submitted DPR Chapters: Reply
within
Preparation/ Periodic Review of
hydrological aspects of different
541 3 Days 20
Hydro Projects at PFR/DPR
Stages

Inspection of all Civil


Structures of for all Operational
542 3 Date 15.05.2024
Projects by Internal Committee-
Pre-Monsoon

Inspection of all Civil


Structures of for all Operational
543 3 Date 31.10.2024
Projects by Internal Committee-
Post-Monsoon

Carrying out Dam Safety


544 Inspection through External 3 Date 31.12.2024
agency for NJHPS and NMHEP.

Updating of Cost Estimates up


to the nearest month on Index
545 2 Days 5
Basis for Tariff calculation after
the receipt of inputs.

Preparation of DPR Cost


Volume of upcoming
546 3 Days 45
Hydroelectric Projects after
receipt of inputs from Project
Checking of estimates of Civil
547 Works requiring approval at 3 Days 5
CHQ
Inputs for Award of
Consultancy of PFR/FSR
548 3 Date 30.04.2024
preparation of Emini, Amulin
and Mihumdhon HEP
Inputs regarding Design
549 Engineering of Etalin HEP to 3 Date 31.05.2024
CCD

Inputs for Major Civil Works


550 2 Date 31.07.2024
Package C1 Etalin HEP to CCD

Clearance of chapter of Dam


and HCD w.r.t. Bardang
551 HEP/Reoli Dugli HEP and Sach 2 Date 31.10.2024
Khas HEP from CWC/
Appraising Authority
Submission of DPR of Bardang
552 2 Date 31.12.2024
HEP to CEA
Submission of DPR of Sach
553 2 Date 31.01.2025
Khas HEP to CEA
Submission of DPR of Reouli
554 2 Date 28.02.2025
Dugli HEP to CEA
Review of Design Reports and
Drawings after receipt from
555 3 Days 21
Project Head i.r.o LHEP-1 &
SDHEP

Vetting of downstream surge


556 gallery design considering 3 Date 31.10.2024
different alternatives of SDHEP

557 Contract Closure of NMHPS 3 Date 30.06.2024


Finalization of proposal for
558 reusability of NJHPS 1 Date 31.03.2025
dismantled TRT Gates
Self-identification of one new
559 PSP and preparation of 1 Date 15.11.2024
identification report
Finalization of 1 no. of the
560 Feasibility Report of Bihar PSPs 1 Date 30.06.2024
in Kaimur District
Finalization of Civil & EM
561 1 Date 28.02.2025
Packages for Attulni HEP
Effective use of Engineering
562 2 % 95
Drawing management System
Finalization of L2 Schedule of
563 DSHEP 3.5 MW after receipt of 3 Days 15
input from site
Issuance of Architectural Detail
Drawings for: Office Building,
564 Residential Building 1 Days 30
Auditorium Building etc after
receipt of requirement

Response related to queries and


requirements of drawings at
565 1 Days 15
CHQ (Allied Works) on receipt of
requirements

Site Layout of Colony for


566 1 Date 31.07.2024
Arunachal Projects
Site Layout of Colony for
567 1 Date 31.12.2024
Chenab Valley Projects
Preparation of 3D walk through
568 1 Date 31.12.2024
model for Etalin HEP
Architectural Concept Drawings
569 of Buildings for Chenab Valley 1 Days 45
Projects

Issuance of Architectural
570 Concept Drawings of Buildings 1 Days 40
for Arunachal Projects

Issuance of Architectural
571 Drawings of Residential Type 0.5 Days 30
Quarters at SDHEP
Architectural Interior Drawings
572 of Powerhouse for SDHEP, 0.5 Days 40
DSHEP & LHEP
Start of the Field Survey after
573 receipt of request from Sites / 0.5 Days 15
Civil Design
Processing, Checking and
Plotting of data and issuing of
574 drawings within 45 days after 0.5 Days 45
field survey for every 2 sq.km
area.

Procurement of Digital
Topographical Sheets for Project
areas from SOI/NRSC/ Other
575 0.5 Days 50
Outsource Agency to
site/design after receiving
request.
Contour Survey of Sliding zone
576 above dam intake area of 0.5 Date 31.05.2024
NJHPS
Tendering of major Civil & HM
works of Hydro projects:
Uploading of NIT/Bid
577 5 Days 5
documents from the date of
receipt of approval of competent
authority

Tendering of major Civil & HM


works of Hydro projects:
Submission of
578 Technocommercial Bid 5 Days 60
evaluation report for approval of
competent authority after
opening of Technical proposal.

Tendering of major Civil & HM


works of hydro projects:
Submission of board agenda for
579 approval for award of major 5 Days 30
Civil & HM works from the date
of receipt of approval of
Technical Evaluation Report.

Tendering of other than major


works: Issuance of NIT from the
580 date of receipt of the approval of 4 Days 3
Bid document by Compettent
Authority

Tendering of other than major


works: Submission of TEC
recommendation for opening of
581 4 Days 30
Price Bids for approval of
Competent Authority after
opening of Technical bids.

Tendering of other than major


works: Issue of award from the
582 4 Days 3
date of receipt of approval for
award.
Settlement of claims DRB/
583 CCIE/ Arbitration (% of total 7 % 25
claims as on 31.03.2024)
Submission of SOC/ SOD i.r.o.
claims/ dispute as per due date
given by DRB/AT and
submission of interim reply /
584 8 % 100
documents on the basis of draft
SOC/ SOD submitted by
concerned commiittee & law
firm.

Submission of recommendation
of standing committee
comprising of HOD/HOP for
585 6 Days 60
approval of competent authority
i.r.o. challenge of DRB/AT
awards .
Submission of reply on the
queries raised by court of Law
586 department pertaining to CCD 3 % 100
i.r.o. ongoing pending claims
within due date.
Monitoring of punching of real
time data on ERP for all
587 3 % 100
contractual correspondence and
digitized record
Organizing one day knowledge
588 sharing workshop on Contract 3 Date 28.02.2025
Management
Monthly submissions of
details/ status of all claims
589 including contracts awarded by 3 No. 12
site pending at any stage, for
apprisal of management

Contract Management –
monitoring of compliance of
related system circulars issued
590 3 No. 12
by (CHQ) SJVN and
submission of report to
Management on monthly basis
Presentation on "status of
pending claims of all under
construction projects (Hydro &
Thermal)" on quarterly basis in
the form of agenda note duly
591 4 No. 4
supplemented with an updated
power point presentation in
board meeting held immediately
at the end of each quarter of
financial year.

Ensuring compliance of public


procurement policy for micro
592 4 Yes/No Yes
and small enterprises issued by
M/o MSME
593 Procurement from GeM portal 4 % 100
Award of Major Civil Package of
Etalin HEP C1 subject to
594 receipt of complete inputs by 4 Date 31.12.2024
31.07.2024 from indenting
deptt.
Award of FR of Emini, Amulin &
Mihumdin HEP subject to
595 receipt of complete inputs by 4 Date 30.06.2024
02.04.2024 from indenting
deptt.
596 Contract Closure of NMHPS 4 Date 31.03.2025

Award of Design Engineering


consultancy contract of Etalin
597 HEP subject to receipt of 4 Date 30.09.2024
complete inputs by 31.05.2024,
from indenting deptt. by CCD.

Finalization of L2 Schedule of
598 DSHEP 3.5 MW after receipt of 4 Days 15
input from site
Submission of Inputs for
procurement of items beyond
the scope of Contract of CFMD
related to areas of HR & IT for
timely procurement of items for
the timely Operatization of GH
599 5 Date 15.04.2024
& Auditorium viz like kitchen
equipments, crockery,
furnishing that includes
curtains, carpets,Gym setup,
LAN,Communication, Broad
Band/Security Cameras etc.

Handing over the Auditorium


600 5 Date 01.04.2024
Site for LAN/ Wifi
Operationalization of
601 5 Date 25.04.2024
Auditorium block at CHQ
Handing over the Guest House
602 5 Date 31.07.2024
Site for LAN/ Wifi
Award of Service Contract for
603 Operationalization of 1st & 2nd 5 Date 15.05.2024
block of Parking at CHQ
Operationalization of 1st & 2nd
604 block of Parking Guest House 5 Date 31.05.2024
building at CHQ

Preparation of Comprehensive
plan for installation of Solar
System in SJVN including Roof
Top and water heating in , CHQ
605 3 Date 31.05.2024
Complex ( Guest House &
Auditorium)including provision
of water heating for GH to
Design Deptt

Obtaining Clearances from


appropriate authority for
606 3 Date 31.08.2024
operationalization of Lifts for
GH CHQ

Obtaining Necessarry Clerance


607 3 Date 31.08.2024
Certificate from Fire Deptt.

Operationalization of 3rd block


608 of Parking at Guest House 4 Date 31.08.2024
building ,CHQ
Procurement of mandatory
609 spares of Lifts and Escalators in 2 Date 30.09.2024
office building,CHQ
Obtaining completion
Certificate from Municipal
610 5 Date 30.09.2024
Corporation for GH/
Auditorium
Operationalization Of Guest
611 8 Date 31.10.2024
House Building at CHQ
Completion of Beautification/
Landscaping of SJVN Corporate
612 Office Complex 7 Date 31.10.2024

Closing Of CFMD Contracts


613 Within 04 Months after 5 Yes/No Yes
Completion Of Work.
Installation of roof top solar
614 system for GH & Auditorium 5 Date 31.03.2025
CHQ
Quarterly Mock Drill At CHQ
615 For Employees As Per Industry 3 No. 4
Standards
Ensuring release Of EMD to
616 unsuccessful Bidders as per 3 % 100
Contract provisions.
Ensuring release Of Security
Deposit Within 07 Days Of
617 3 % 100
Becoming Payable after Closing
The Contract

Submission Of Six Monthly


Reports To Corporate
618 3 Days 7
Environment Dept. for Further
Submission To MOEF&CC.

Compliance Of Public
Procurement Policy For Micro
619 3 Yes/No Yes
and Small Enterprises Issued
By M/o MSME.
Compliance Of Procurement
620 From Gem Portal In % As 2 Yes/No Yes
Prescribed In MOU 2024-25
Identification and submission of
inputs of additional IT needs of
621 3 Date 15.04.2024
the GH to IT Deptt. for its
execution
Submission of baseline data for
MoU FY 2024-25 on DPE
622 4 Yes/ No Yes
dashboard within the timeline
prescribed by DPE
Signing of MoU for FY 2024-25
623 of SJVN with MoP within the 4 Yes/No Yes
date prescribed by DPE.
Submission of online data for
framing of MOU for FY 2025-26
624 3 Yes/ No Yes
within the date prescribed by
DPE on DPE dashboard.
Submission of Performance
Evaluation Report of MoU
625 4 Yes/ No Yes
2023-24 within the date
prescribed by DPE.
Finalization of MOU targets for
FY 2024-25 of SAPDC for
626 construction linked incentive 3 Yes/ No Yes
scheme within prescribed
timeline.
Evaluation of MOU targets for
FY 2023-24 of SAPDC for
627 construction linked incentive 4 Yes/ No Yes
scheme within prescribed
timeline
Submission of Board agenda on
the status of Compliance of
Make in India Orders, Pending
628 4 % 100
MII Grievances and purchase
from GeM, Payments to
MSMEs.
Finalization of EM Packages for
629 3 Date 15.04.2024
Etalin HEP
Finalization of SOP for
prepration of revised cost
630 3 Date 31.05.2024
estimate of construction
projects
Finalization of SOP for
631 preparation of Capital Budget 3 Date 31.05.2024
and its review
Approval of RCE of NMHPS by
632 4 Date 31.05.2024
Board
CCEA Clearance from GoI for
633 4 Date 30.06.2024
Lower Arun HEP

Finalisation of report on SJVN


634 4 Date 15.09.2024
for Public Enterprise Survey
Submission of draft Annual
Action Plan (Capital Budget) of
SJVN including Revised
635 3 Date 30.09.2024
Estimate 2024-25 and Budget
Estimate 2025-26 to
Management.
Submission of information on
636 SJVN for annual report 4 Date 15.01.2025
published by MoP.
Annual review of perspective
637 plan of SJVN and submission of 4 Date 31.01.2025
report
Relisation of first installment of
638 revenue from sale of Carbon 3 Date 28.02.2025
Credits for NMHPS
Finalization of Civil & EM
639 3 Date 28.02.2025
Packages for Attulni HEP
Submission of Board Agenda on
640 quarterly CAPEX/Budget 3 % 100
performance

Submission of information to
MoP for the visits/ meetings for
Parliamentary Committees/
641 3 Yes/ No Yes
Ministers/external agencies/
CEA etc within one week of
receipt of letter

Follow up for allotment /


642 5 Yes/No Yes
signing of MoU i.r.o PSPs

Compliance of guidelines for


643 8 Yes/No Yes
Time and Cost over run of MOP

Reply to Parliamentary
644 Questions/ Assembly Questions 4 Yes/No Yes
within 02 days.
Preparation & submission of
information regarding
PIBs/RCEs/Status of various
645 3 Days 5
projects to MoP/CEA for review
meeting on receipt of
letter/email.
Submission of monthly CAPEX
646 report to MoP within days of 3 No. 2
following month.
Submission of weekly report to
647 Management on issues related 2 % 100
to State Government
Submission of online
application for amendment in
ToR of Reoli Dugli HEP after
finalization of Project salient
648 7 Date 15.05.2024
features including requirement
of twin tunnel (HRT)and land
details etc. by project and
concerned departments.

Updation of SOP related to


649 6 31.05.2024
Environment Clearance
Providing comments on Draft
CAT Plan of Sach Khas HEP to
650 7 Days 30.09.2024
Project after receipt from the
project.

Appointment of consultant for


651 monitoring of CHQ Complex 7 Date 01.10.2024
Environment parameters

Submission of online
application for Environmental
652 Clearance after issuance of 7 Days 45
MoM of Public Hearing of Reoli
Dugli HEP.

Submission of online
application for amendment in
ToR of Bardang HEP after
653 finalization of Project salient 7 Days 15
features and land details etc. by
Project and concerned
departments.

Providing comments to Project


on Draft EIA/EMP reports of
654 Reoli/Purthi/Bardang HEP 7 Days 15
after its receipt from the
Project.

Filing of E-Waste Return to


HPSPCB before 30th June after
655 8 Yes/ No Yes
receiving inputs from Projects
sites and offices of HP.
Timely submission of six-
monthly compliance reports for
Operation & Construction
Projects & CFMD to MoEF & CC
656 8 Yes/ No Yes
-twice a year in the month of
June & December (NJHPS,
NMHPS, DSHEP, RHPS, LHEP-
I, SDHEP, Office Building CHQ).

Submission of online
application to MOEF&CC for
TOR i.r.o.
Amulin/Mihumdon/Emini after
657 7 Days 15
first consultation meeting and
receiving of details from
projects and concerned
departments.

Providing comments to Project


on seasonal reports (EIA/EMP
658 7 Days 15
Study) of Attunli HEP after
receipt from the Project.

Finalization of Draft EIA/EMP


659 Report of Attunli HEP after 5 Days 15
receipt from Project.
Preparation of Replies to
queries received from MoP/
660 Parliament/ RTI/ Projects/ 5 Days 5
Departments/IA-CAG/Other
offices.
Review and Comments on
Reports/ Acts/
Policies/UNFCCC reports etc.
661 7 Yes/No Yes
as received from time to time
from GoI (MOEF&CC, MoP, etc)
within 15 days.
First Bi-Annual Instrumenation
662 report of NJHPS and Rampur 6 Date 15.04.2024
HPS
Geological report on Nathpa
663 10 Date 30.06.2024
Dam Intake Slope Area
Second Bi-Annual
664 Instrumenation report of 6 Date 15.10.2024
NJHPS and Rampur HPS
Submission of chapter on
665 Geological aspects for DPR of 6 Date 30.11.2024
Bardang HEP to Civil deisgn.
Submission of chapter on
666 Geological aspects for DPR of 6 Date 31.12.2024
Sach Khas HEP to Civil deisgn.

Land Hazard Zonation mapping


667 of the intake area of Rampur 10 Date 20.02.2025
HPS.
668 Contract Closure of NMHPS 8 Date 31.03.2025
Submission of chapter on
Geological aspects for DPR of
669 Reoli Dugali HEP to Civil Design 10 Days 60
after the clearance of general
layout chapter.

Updation of Geological Chapter


of Etalin HEP & Attulni HEP
670 10 Days 60
after the completion of balance
investigation work.

Submission of Comprehensive
Geological report of Etalin HEP
671 & Attulni HEP to Civil Design 10 Days 45
for Bid Document before
issuance of NIT

Visit to under-construction
projects and submission of
672 6 No. 8
report to the Director (Project)
and Monitoring department.

Submission of report on
Geological aspects of the
concerned project to the
673 7 Days 15
concerned Department viz
BD&E, Consultancy etc. on
receipt of its

Recommendation (iro Arun -3


HEP)/Approval (iro SJVN
projects) of
drawings/design/documents
674 within 15 days after 12 % 100
incorporation of comments by
the contractors iro Hydro
projects, Solar projects &
transmission line.
Recommendation (iro Arun -3
HEP)/Approval (iro SJVN
projects) for disposal of
deviation/ change proposal/
675 3 Days 7
NCR etc. after receipt from
QA&I/EIC iro Hydro projects,
Solar projects & transmission
line.
Submission of EM inputs (EM
chapter drawings , etc) after
676 requisition/request made by 5 Days 35
Civil Design/CP, etc iro DPR of
Chenab Projects.
Submission of EM inputs iro
DPR of Arun-4 HEP after
677 5 Days 30
requisition/request made by
Civil Design, Nepal.

Review of documents submitted


by consultants/Civil
678 4 Days 10
Design/EIC iro PFR/FSR/DPR
of Arunachal Projects and PSPs.

Providing all inputs iro


Grounding design study of
679 Lower Arun HEP (after 4 Days 30
requisition/request made by
SLPDC).
Evaluation of technical bids of
EM works of Lower Arun HEP &
680 SDHEP (after 8 Days 30
requisition/request made by
SLPDC & SDHEP).
Finalization of integrated L-2
schedule for EM works of Lower
681 5 Yes/No Yes
Arun & SDHEP as per contract
provisions.
Review & approval of Model test
report of SDHEP and Lower
682 Arun HEP (if 5 Days 20
requisition/request made by
SLPDC).
Providing all approved inputs to
Electrical Contracts department
in respect of Elevator Package,
683 3 Date 05.04.2024
PA & Communication, Security
& Surveillance and Air
Conditioning of DSHEP.

To Provide all inputs for the


684 tendering of the Electro- 3 Date 05.04.2024
Mechanical Package of SDHEP

Finalization of EM Packages for


685 2 Date 15.04.2024
Etalin HEP
Finalization of detailed scope of
work including cost estimate in
686 respect of Remote Monitoring 3 Date 31.05.2024
cum Management Centre
(RMC).
Finalization of proposal for Grid
687 Power (Supply of 11kV line) 1 Date 31.05.2024
Etalin HEP
Proposal related to 2 No. Bays
688 at ISTS Pooling Station of 3 Date 31.05.2024
Luhri-I HEP.
Finalization of technical
specification and other inputs
of comprehensive plan for
689 installation of Solar System in 2 Date 30.06.2024
SJVN, CHQ Complex including
provision of water heating for
GH

Providing all approved inputs to


Contracts department (ECD) for
690 the tendering in respect of 3 Date 30.06.2024
Remote Monitoring cum
Management Centre (RMC).

Finalization of R&D/ Innovation


691 Plan for FY 2024-25 and 3 Date 15.07.2024
circulation thereof.

Vetting of downstream surge


692 gallery design considering 4 Date 31.10.2024
different alternatives of SDHEP

Preparation of TS, cost


693 estimate and MQR for 4 Date 30.11.2024
Transmission line of SDHEP.
Package approval of EM works
694 2 Date 31.12.2024
of Etalin HEP.

Evaluation of technical bids for


E&M works of Transmission
695 Line of SDHEP after receipt of 3 Days 30
inputs from Electrical Contract
Department.

Expenditure on R&D/
696 Innovations initiatives as % of 3 % 0.5
PBT.
Effective use of Engineering
697 2 95
Drawing management System
Finalization of L2 Schedule of
698 DSHEP 3.5 MW after receipt of 3 Days 15
input from site

699 Revenue from Operations 15 Rs(Cr.) 4314

Trade Receivables (Net) as


700 number of days of Revenue 15 Days 45
from Operations (Gross).

Raising of provisional bills


of Operational Projects
after receipt of Regional
Energy Account (REA)
/Joint Meter Reading
701 7 Days 2
(JMR)/Wind Energy
Certificate (WEC)/State
Energy Account (SEA) and
requisite details from
Project site (if any).

Reconciliation of Energy
Bills with beneficiaries for Days at
702 billing upto Qtr. ending 4 the end 45
March, June, September, of Qtr
December 2023

Customer Satisfaction
703 Index i.r.o. all the 3 % 90
Beneficiaries.
Submission of inputs to
ECD for tendering of
Insurance Coverage of
704 6 Days 120
Hydro & Renewable Power
Stations Days before due
date
Arrear billing of Hydro
Projects after receipt of
705 5 Days 30
Tariff Order from CERC, if
any
Submission of reply /
comments of CERC /
Beneficiaries related to the
706 petition (s) after receipt of 4 Yes/No Yes
information / data from
the concerned deptt. within
due date.
Submission of
information / data to CEA
for fixation of Hydro
707 Generation Target after 4 Yes/No Yes
receipt of data from
respective project/ deptt.
within the prescribed date
Updation of energy billing
708 data in PRAAPTI Portal 4 Days 5TH
after raising of energy bill
Filing of truing up petition
31.10.202
709 for Tariff determination for 8 Date
4
NJHPS and RHPS
Filing of petition for Tariff
determination for NJHPS 31.10.202
710 8 Date
and RHPS for the control 4
period 2024-29

Forwarding of inputs
related to O&M Budget (RE
31.10.202
711 2024-25, BE 2025-26) of 3 Date
4
CHQ and O&M Projects to
Corporate Finance Deptt.
31.03.202
712 Organising Customer Meet 2 Date
5
Long term arrangement for 31.03.202
713 3 Date
PPA of NMHPS 5
15.06.202
714 REC for NMHPS 4 Date
4
Issuance of Billing break-up
after receipt of final proposal
715 5 Days 20
from Contractors as per
Contract Provisions

Renewable of Insurance for


716 NJHPS, RHPS, NMHPS, Khirvire 12 Yes/ No Yes
& Sadla one day before expiry

EM Package of SDHEP A)
Submission of
717 Technocommercial 5 Days 30
recommendation after opening
of technical bids.

B) Submission of Board agenda


for approval of EM Package of
718 5 Days 30
SDHEP after approval of
technical evaluation report.

C) Issue of Award of SDHEP


719 5 Days 7
after issue of Board Minutes
Award for procurement of goods
through GeM after receipt of
720 approved indent: Direct 5 Days 15
Purchase i.e. without bidding
on the GeM

Award for procurement of goods


through GeM after receipt of
approved indent: through
721 bidding process on GeM: A) 5 Days 30
Submission of Techno
commercial recommendation
after opening of technical bids.

B) Submission of award
recommendation for approval
722 for procurement of goods 5 Days 30
through GeM after approval of
technical evaluation report.
Award for procurement of goods
through GeM after receipt of
723 approved indent: through 4 Days 75
bidding process on GeM with
ERA
Punching of data (i.e. LOA, PO,
Contract ) on ERP with all
724 Contractual correspondence 4 % 75
and Digitized Record from
approved indent
Compliance of Public
Procurement Policy for Micro
725 4 Yes/ No Yes
And Small Enterprises issued
by M/o MSME.

726 Procurement from GeM 4 % 100

Examination and final


727 recommendation on EOT/Claim 5 Days 7
cases after receipt of cases

Submission of Board agenda for


728 approval for LOA of EM Package 5 Date 16.08.2024
of SDHEP
Award of balance packages of
729 7 Date 31.08.2024
DSHEP
Award of work related to
installation of Solar System in
730 SJVN, CHQ Complex including 5 Date 31.12.2024
provision of water heating for
GH
Finalization of L2 Schedule of
DSHEP 3.5 MW after
731 5 Days 15
acceptance of award and receipt
of input from site

Award of works related to


installation of IT related
Systems/equipments i.e
732 5 Date 30.09.2024
Communication, broadband,
Security Camera for Guest
House and Auditorium at CHQ

Submission of approved indent


to ECD for renewal of software
733 for paperless Board Meetings in 4 Days 10
SJVN after receipt of requisition
from Company Secretary.
VAPT audit of IT infrastructure
734 3 Yes/No Yes
in CHQ
Disposal of old/obsolete
735 computers, if identified, on 5 No. 4
quarterly basis.

Ensuring the Security Audit


736 Certification for SJVN Website 5 Date 31.08.2024
by CERT-IN empanelled agency

Design, Development and


implementation of redesigned
737 5 Days 180
SJVN Website from the date of
issuance LoA by ECD.
Renewal of SSL certificate on
738 5 Date 20.08.2024
SJVN website annually

Compliance of applicable cyber


threat mitigation guidelines
received from NCIIPC, CERT-
739 Hydro and patching of 3 Yes/No Yes
vulnerabilities as received time
to time in network firewall,
maintaining record for the same

Renewal of various Internet


Services/ MPLS connectivity
740 5 Yes/No Yes
before its expiry for ensuring
continuity
Ensuring continuation of
741 existing AMC in IT&C before its 5 % 100
expiry

Ensuring Annual Maintainance


742 5 Date 30.04.2024
Contract of SAP ERP System.

Development of Mobile App for


743 5 Date 31.05.2024
Retired Employees

Maintaining & ensuring


availability of Public facing
744 applications including e- 5 % 95
Tendering Portal, e-Recruitment
Portal, VTMS etc.

Additional enhancements in
existing ERP applications as per
745 SJVN business requirement 5 Date 30.11.2024
received from user dept. till
31.03.2024
Ensuring availability of Data
Centre resources for Production
746 environment (Servers, Virtual 5 % 95
Machines, Storage, Operating
System, Security Components)

Conduction of Internal Audit of


Quality Management System
Yes/
(half year ending June, 2024
747 3 No Yes
and Dec, 2024) and submission
of report to Management on
System Improvement required.

Conduction of Management
Review Committee Meeting Yes/
748 (twice a year) on 3 No Yes
implementation of ISO
9001:2015

Conduction of Corporate Level Yes/


749 Risk Steering Committee 5 No Yes
Meeting (twice a year).

Ensure implementation of
750 5 Date 21.04.2024
FLM/ERP System in EHEP

Inputs for installation of IT


related system/equipments like
751 communication system , 3 Date 30.04.2024
broadband, security camera etc
for GH and Auditorium CHQ

Operationalization of IT related
systems/equipments like
752 communication system , 5 Date 30.11.2024
broadband, security camera etc
for GH and Auditorium CHQ

Award of works related to


installation of IT related
system/equipments like
753 3 Date 30.09.2024
communication system ,
broadband, security camera etc
for GH and Auditorium CHQ

Temporary operationalization of
754 LAN/ Wifi of Auditorium after 3 Days 30
handing over the site by CFMD
Preparation and submission of
Quality Assurance Test
requirements (Manufacturing &
755 Field) for new proposal after 10 Days 40
receipt of approved technical
specifications from the Design
Deptt/ Indenting Deptt.

Preparing & submitting Quality


Assurance Plans from the date
756 of receipt of approved technical 10 Days 15
specifications for single item
from indenting deptt.

Hydro Projects (EM Package):


Review of Quality Assurance
Plans from the date of its
757 receipt from contractor/ vendor 10 Days 10
and communicating back the
approval/ clarifications Post
Award Stage

For Renewable/ Transmission


Line /Single item: Review of
Quality Assurance Plans from
the date of its receipt from
758 10 Days 7
contractor/ vendor and
communicating back the
approval/ clarifications post
award stage

Disposal of Minor NCR: Review


and communicating back the
acceptance/ clarification after
the receipt of Minor NCR from
759 9 Days 7
Manufacturer/EIC (during
Erection) and comments, if
required from concerned Design
Deptt. & Site
Disposal of Major NCR: Review
and communicating back the
acceptance/ clarification after
the receipt of Major NCR from
760 10 Days 15
Manufacturer/EIC (during
Erection) and comments, if
required from concerned Design
Deptt. & Site

Approval/ comments of new/


addition of sub vendor (during
Post Award Stage) after receipt
of request and documents as
761 10 Days 10
per contract from contractor/
supplier and any inputs if
required from
contractor/electrical design

Evaluation of QAP/ Quality


Assurance documents of
762 various bidders received from 10 Days 15
Contract Deptt. During Pre-
Award Stage.
Attending inspection calls/
waiver of inspection at
manufacturer's works from
763 6 Days 5
indicated date(s) in accordance
with approved QAP and
Contract conditions.

Issuance of Material Dispatch


Clearance Certificate (MDCC)
764 10 Days 5
from completion of inspection/
waiver of inspection.

765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
VG GOOD AVERAGE POOR

7000 6612 6512 <6512

1.3 1.2 1 <1

97 96 95 <95

60 62 65 >65

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

30.06.2024 > 30.06.2024

>30.06.2024

07.07.2024 14.07.2024 21.07.2024 >21.07.2024

10.09.2024 20.09.2024 30.09.2024 >30.09.2024

15.01.2025 31.01.2025 28.02.2025 >28.02.2025

10.01.2025 20.01.2025 31.01.2025 >10.02.2025

15.01.2025 31.01.2025 15.02.2025 > 15.02.2025

15.01.2025 31.01.2025 15.02.2025 > 15.02.2025


10.01.2025 20.01.2025 31.01.2025 >31.01.2025

15.02.2025 28.02.2025 15.03.2025 >15.03.2025

10.02.2025 20.02.2025 28.02.2025 >10.03.2025

No

No

No

90 80 70 <70

<100

1980 1878 1868 <1850

97 96 95 <95

60 62 65 >65

>30.06.2024
25.12.2024 31.12.2024 05.01.2025 >05.01.2025

10.03.2025 20.03.2025 31.03.2025 >31.03.2025

10.03.2025 20.03.2025 31.03.2025 >31.03.2025

15.03.2025 20.03.2025 31.03.2025 >31.03.2025

>30.04.2024

No

90 80 70 <70
<100

360 320 280 <280

270 240 210 <210

>30.04.2024

15.05.2024 31.05.2024 15.06.2024 >15.06.2024

15.07.2024 31.07.2024 15.08.2024 >15.08.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

15.08.2024 31.08.2024 15.09.2024 >15.09.2024

30.09.2024 15.10.2024 31.10.2024 >31.10.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.12.2024 31.12.2024 15.01.2025 >15.01.2025


15.01.2025 31.01.2025 15.02.2025 >15.02.2025
15.01.2025 31.01.2025 15.02.2025 >15.02.2025
15.02.2025 28.02.2025 15.03.2025 >15.03.2025

15.03.2025 31.03.2025 _ >31.03.2025

15.03.2025 31.03.2025 >31.03.2025

>31.03.2025

No

95 90 <90

90 85 80 <80

No

90 80 70 <70

90 80 70 <70

400 350 300 <300

300 262.5 250 <250

>05.04.2024

31.05.2024 15.06.2024 30.06.2024 >30.06.2024

15.06.2024 30.06.2024 15.07.2024 >31.07.2024

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

30.06.2024 15.07.2024 31.07.2024 >31.07.2024


10.07.2024 20.07.2024 31.07.2024 >31.07.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

10.08.2023 20.08.2023 31.08.2024 >31.08.2024

15.09.2024 30.09.2024 15.10.2024 >15.10.2024

10.11.2024 20.11.2024 30.11.2024 >30.11.2024

30.11.2024 15.12.2024 31.12.2024 >31.12.2024

31.12.2024 15.01.2025 31.01.2025 >31.01.2025

15.02.2025 28.02.2025 15.03.2025 >15.01.2025

06.03.2025 21.03.2025 31.03.2025 >31.03.2025

>31.03.2025

No

>31.03.2025

95 90 >90

90 85 80 <80
11.00 10.00 >10

No

90 80 70 <70

<100

382 340 320 <320

300 285 275 <275

31.05.2024 15.06.2024 30.06.2024 >30.06.2024

30.06.2024 10.07.2024 15.07.2024 >15.07.2024

10.07.2024 20.07.2024 27.07.2024 >27.07.2024

23.09.2024 30.09.2024 07.10.2024 >07.10.2024

22.10.2024 29.10.2024 06.11.2024 >06.11.2024

25.11.2024 30.11.2024 05.12.2024 >05.12.2024

15.01.2025 15.02.2025 15.03.2025 >15.03.2025

15.01.2025 25.01.2025 31.01.2025 >31.01.2025

15.01.2025 25.01.2025 31.01.2025 >31.01.2025

07.03.2025 15.03.2025 22.03.2025 31.03.2025


20.03.2025 27.03.2025 31.03.2025 >31.03.2025

20.03.2025 25.03.2025 31.03.2025 >31.03.2025

31.03.2025 >31.03.2025

31.03.2025 >31.03.2025

>31.03.2025

>31.03.2025

>31.03.2025

>31.03.2025

95 90 85 <85

90 85 80 <80

95 90 85 <85

11 10 9 <9

No

90 80 70 <70

<100
20 25 30 >30

1.5 1 0.5 <0.5

15.07.2024 31.07.2024 16.08.2024 >16.08.2024

31.10.2024 30.11.2024 31.12.2024 >31.12.2024

15.12.2024 31.12.2024 15.01.2025 >15.01.2025

11 10 9 <9

No

95 85 80 <80

No

90 80 70 <70

<100

18 16 <16

17.04.2024 24.04.2024 01.05.2024 >01.05.2024

>30.04.2024
07.07.2024 14.07.2024 21.07.2024 >21.07.2024

07.07.2024 14.07.2024 21.07.2024 >21.07.2024


10.06.2024 20.06.2024 30.06.2024 >30.06.2024
07.07.2024 14.07.2024 21.07.2024 >21.07.2024

10.08.2024 20.08.2024 31.08.2024 >31.08.2024

31.08. 2024 30.10.2024 30.11.2024 >30.11.2024

15.09.2024 30.09.2024 15.10.2024 >15.10.2024

15.09.2024 30.09.2024 15.10.2024 >15.10.2024


10.06.2024 20.06.2024 30.06.2024 >30.06.2024
07.07.2024 14.07.2024 21.07.2024 >21.07.2024

10.08.2024 20.08.2024 31.08.2024 >31.08.2024

31.08. 2024 30.10.2024 30.11.2024 >30.11.2024

15.09.2024 30.09.2024 15.10.2024 >15.10.2024

15.09.2024 30.09.2024 15.10.2024 >15.10.2024

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

15.03.2025 31.03.2025 30.04.2025 >31.05.2025

15.07.2024 30.07 .2024 15.08.2024 >15.08.2024

15.08.2024 31.08.2024 15.09.2024 >15.09.2024

15.08.2024 31.08. 2024 15.09.2024 >15.09.2024

15.08.2024 31.08. 2024 15.09.2024 >15.09.2024


15.09.2024 30.09.2024 15.10.2024 >15.10.2024

No

90 80 70 <70

<100

265 252 239 <239

>30.04.2024

15.05.2024 31.05.2024 >31.05.2024

15.05.2024 31.05.2024 15.06.2024 >15.06.2024

30.05.2024 15.06.2024 30.06.2024 >30.06.2024

07.06.2024 14.06.2024 21.06.2024 >21.06.2024

10.07.2024 20.07.2024 31.07.2024 >31.07.2024

10.09.2024 20.09.2024 30.09.2024 >30.09.2024

15.10.2024 31.10.2024 >31.10.2024

22.10.2024 29.10.2024 05.11.2024 >05.11.2024

10.12.2024 21.12.2024 31.12.2024 >31.12.2024

>31.03.2025
11 10 9 <9

11 10 9 <9

60 75 90 >90

15 16 17 >17

No

No

90 80 70 <70

<100

6500 6000 5500 <5500

4875 4500 4125 <4125

5 4 3 <3

1000 800 700 <700

80 90 100 >100

35 40 45 >45

7 9 11 >11
10 13 15 >15

3 4 5 >5

>30.06.2024

>21.05.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024


15.09.2024 30.09.2024 15.10.2024 >15.10.2024
15.10.2024 31.10.2024 10.11.2024 >10.11.2024
15.12.2024 31.12.2024 10.01.2025 >10.01.2025
15.02.2025 28.02.2025 10.03.2025 >10.03.2025
>31.03.2025
15.02.2025 28.02.2025 15.03.2025 >31.03.2025
15.02.2025 28.02.2025 15.03.2025 >31.03.2025
>31.03.2025
31.01.2025 15.02.2025 28.02.2025 >28.02.2025
31.01.2025 15.02.2025 28.02.2025 >28.02.2025
15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

155 145 135 <135

150 140 130 <130

100 90 80 <80

200 175 150 <150

100 90 75 <75

180 165 150 <150


15 12 10 <10

90 80 65 <65

No

55 60 70 >70

10 12 15 >15

10 12 15 >15

31.07.2024 07.08.2024 14.08.2024 >14.08.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.12.2024 31.12.2024 15.01.2025 >15.01.2025

15.01.2025 31.01.2025 15.02.2025 >15.02.2025

No

>31.03.2025

>31.07.2024
155 145 135 <135

95 90 85 <85

20 25 30 >30

6 7 8 >8

10 12 15 >15

>31.07.2024
No

95 90 85 <85

150 140 130 <130


15.07.2024 31.07.2024 15.08.2024 >15.08.2024

95 90 85 <85

No

6 7 8 >8

95 90 85 <85

No

100 90 75 <75

40 30 20 <20
15.09.2024 30.09.2024 15.10.2024 >15.10.2024
15.12.2024 31.12.2024 15.01.2025 >15.01.2025

95 90 85 <85

6 7 8 >8

15.02.2025 28.02.2025 15.03.2025 >15.03.2025

No

2250 2000 1750 <1890


1687.5 1500 1312.5 <1313
15.05.2024 31.05.2024 15.06.2024 >15.06.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

15.10.2024 31.10.2024 10.11.2024 >10.11.2024


15.12.2024 31.12.2024 10.01.2025 >10.01.2025
15.02.2025 28.02.2025 10.03.2025 >10.03.2025
>31.03.2025

10 12 15 >15

350 300 250 <250

6 7 8 >8

10 12 15 >15

95 90 85 <85

No

95 90 85 <85
200 175 150 <150

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

95 90 85 <85

10 12 15 >15

6 7 8 >8
10 12 15 >15

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

No

90 85 80 <80
100 90 80 <80

95 90 85 <85

10 12 15 >15

6 7 8 >8

14 21 28 >28

31.08.2024 15.09.2024 30.09.2024 < 30.09.2024

No

95 90 85 <85

28 25 22 <22

200 150 100 <100

150 113 75 <75

30.04.2024 15.05.2024 31.05.2024 >31.05.2024

31.05.2024 15.06.2024 30.06.2024 >30.06.2024


15.07.2024 31.07.2024 15.08.2024 >15.08.2024

15.08.2024 31.08.2024 15.09.2024 >15.09.2024

15.12.2024 31.12.2024 15.01.2025 >15.01.2025

31.01.2025 15.02.2025 28.02.2025 >28.02.2025

31.01.2025 15.02.2025 28.02.2025 >28.02.2025

15.02.2025 28.02.2025 15.03.2025 >15.03.2025

175 150 125 <125


131 113 94 <94
25 23 21 <21

15.05.2024 31.05.2024 15.06.2024 >15.06.2024

20 25 30 >30

31.05.2024 15.06.2024 30.06.2024 >30.06.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

15.08.2024 31.08.2024 15.09.2024 >15.09.2024

30.11.2024 15.12.2024 31.12.2024 >31.12.2025

15.01.2025 31.01.2025 15.02.2025 >15.02.2025

15.02.2025 28.02.2025 15.03.2025 >15.03.2025


85 75 65 <65
225 200 175 <175
15.05.2024 31.05.2024 15.06.2024 >15.06.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

10 12 15 >15

15.01.2025 31.01.2025 07.02.2025 >07.02.2025


15.01.2025 31.01.2025 07.02.2025 >07.02.2025
31.01.2025 15.02.2025 28.02.2025 >28.02.2025

No

85 75 65 <65
225 200 175 <175
15.05.2024 31.05.2024 15.06.2024 >15.06.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

10 12 15 >15

15.01.2025 31.01.2025 07.02.2025 >07.02.2025


15.01.2025 31.01.2025 07.02.2025 >07.02.2025
31.01.2025 15.02.2025 28.02.2025 >28.02.2025

No

350 300 250 <250

31.05.2024 15.06.2024 30.06.2024 >30.06.2024


15.07.2024 31.07.2024 15.08.2024 >15.08.2024
15.08.2024 31.08.2024 15.09.2024 >15.09.2024
31.08.2024 15.09.2024 30.09.2024 >30.09.2024
15.09.2024 30.09.2024 15.10.2024 >15.10.2024

90 80 70 <70

10 12 15 >15

15.11.2024 30.11.2024 15.12.2024 >15.12.2024


> 31.03.2025

No

12 10 8 <8
15 12 10 <10

22.04.2024 30.04.2024 07.05.2024 >07.05.2024

10.05.2024 20.05.2024 31.05.2024 >31.05.2024

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

30.09.2024 15.10.2024 31.10.2024 >31.10.2024

10 13 16 >16

95 90 85 <85
10 13 16 >16

6 7 8 >8

10 12 15 >15

No

40 30 20 <20
180 165 150 <150
31.05.2024 15.06.2024 30.06.2024 >30.06.2024

30.09.2024 15.10.2024 31.10.2024 >31.10.2024

95 90 85 <85

10 12 15 >15

6 7 8 >8

10 12 15 >15

90 85 80 <80

No

150 100 75 <75

110 100 85 <85


22.04.2024 30.04.2024 07.05.2024 >07.05.2024

22.07.2024 31.07.2024 07.08.2024 >07.08.2024

10.05.2024 20.05.2024 31.05.2024 >31.05.2024

10.08.2024 20.08.2024 31.08.2024 >31.08.2024

10.05.2024 20.05.2024 31.05.2024 >31.05.2024

10.08.2024 20.08.2024 31.08.2024 >31.08.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

95 90 85 <85

10 12 15 >15

6 7 8 >8

10 12 15 >15
15.02.2025 28.02.2025 15.03.2025 >15.03.2025

95 90 85 <85

10 12 15 >15

6 7 8 >8

10 12 15 >15

15.02.2025 28.02.2025 15.03.2025 >15.03.2025

95 90 85 <85

10 12 15 >15

6 7 8 >8

10 12 15 >15

15.02.2025 28.02.2025 15.03.2025 >15.03.2025

1400 1300 1200 <1200

140 130 120 <120

1050 900 800 <800

110 95 80 <80
15.06.2024 22.06.2024 29.06.2024 >29.06.2024

31.07.2024 31.08.2024 30.09.2024 >30.09.2024

15.07.2024 31.07.2024 15.08.2024 >15.08.2024

>31.07.2024

30.09.2024 31.10.2024 30.11.2024 >30.11.2024


30.09.2024 31.10.2024 30.11.2024 >30.11.2024
15.09.2024 30.09.2024 - >30.09.2024
15.10.2024 31.10.2024 - >31.10.2024
15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

31.10.2024 15.11.2024 30.11.2024 >30.11.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.11.2024 22.11.2024 29.11.2024 >29.11.2024

01.12.2024 15.12.2024 31.12.2024 >31.12.2024

>30.11.2024

15.12.2024 31.12.2024 15.01.2025 >15.01.2025

15.12.2024 31.12.2024 15.01.2025 >15.01.2025

31.12.2024 31.05.2025 25.02.2025 >25.02.2025


31.12.2024 31.01.2025 28.02.2025 >31.03.2025

31.01.2025 15.02.2025 28.02.2025 >28.02.2025


31.01.2025 15.03.2025 31.03.2025 >31.03.2025

15.01.2025 31.01.2025 15.02.2025 >15.02.2025


15.01.2025 31.01.2025 15.02.2025 >15.02.2025

31.01.2025 15.02.2025 28.02.2025 >28.02.2025

31.01.2025 15.02.2025 28.02.2025 >28.02.2025

25.01.2025 05.02.2025 15.02.2025 >15.02.2025

15.02.2025 28.02.2025 15.03.2025 >15.03.2025


15.02.2025 01.03.2025 15.03.2025 >15.03.2025

15.03.2025 31.03.2025 >31.03.2025

15.03.2025 >15.03.2025
15.03.2025 31.03.2025 >31.03.2025

>31.03.2025

07.05.2024 14.05.2024 21.05.2024 >21.05.2024

90 85 80 <80

13.5 13 12 <12

10 9 8 <8

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

15.07.2024 31.07.2024 15.08.2024 >15.08.2024

31.01.2025 28.02.2025 31.03.2025 >31.03.2025

15.01.2025 31.01.2025 15.02.2025 >15.02.2025


>31.03.2025
280 270 260 <260

220 215 210 <210

15.05.2024 31.05.2024 30.06.2024 >30.06.2024

15.06.2024 22.06.2024 29.06.2024 >29.06.2024

15.07.2024 22.07.2024 29.07.2024 >29.07.2024


25.07.2024 10.08.2024 25.08.2024 >25.08.2024
31.08.2024 30.09.2024 31.10.2024 >31.10.2024

15.08.2024 31.08.2024 15.09.2024 >15.09.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.01.2025 31.01.2025 15.02.2025 >15.02.2025

31.01.2025 28.02.2025 31.03.2025 >31.03.2025

31.01.2025 15.02.2025 28.02.2025 >28.02.2025


10.03.2025 20.03.2025 31.03.2025 >31.03.2025

>31.03.2025

450 400 350 <350

340 300 265 <265

30.04.2024 15.05.2024 30.06.2024 >30.06.2024

>15.04.2024

25.04.2024 10.05.2024 15.05.2024 >15.05.2024

16.05.2024 31.05.2024 15.06.2024 >15.06.2024

10.06.2024 20.06.2024 30.06.2024 >30.06.2024

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

25.06.2024 10.07.2024 25.07.2024 >25.07.2024

15.08.2024 31.08.2024 15.09.2024 >15.09.2024


>31.07.2024

10.09.2024 20.09.2024 30.10.2024 >30.09.2024

15.09.2024 30.09.2024 15.10.2024 >15.10.2024


15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.11.2025 20.11.2025 30.11.2025 >30.11.2025


>31.10.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

10.01.2025 20.01.2025 31.01.2025 >31.01.2025

15.01.2025 31.01.2025 15.02.2025 >15.02.2025


8 5 4 <4
25.04.2024 05.05.2024 15.05.2024 >15.05.2024

10.05.2024 20.05.2024 31.05.2024 >31.05.2024

10.06.2024 20.06.2024 30.06.2024 >30.06.2024


10.06.2024 15.06.2024 20.06.2024 >20.06.2024

>31.07.2024

31.08.2024 15.09.2024 30.09.2024 >30.09.2024

>31.08.2024

>31.08.2024

15.09.2024 30.09.2024 15.10.2024 >15.10.2024


>31.08.2024
30.09.2024 15.10.2024 31.10.2024 >31.10.2024

>31.10.2024

15.01.2025 31.01.2025 15.02.2025 >15.02.2025

10.01.2025 20.01.2025 31.01.2025 >31.01.2025


15.01.2024 31.01.2024 15.02.2024 >15.02.2024

>30.11.2024

10.03.2025 20.03.2025 31.03.2025 >31.03.2025

8 6 4 <4

15.05.2024 31.05.2024 ­ >31.05.2024

15.06.2024 30.06.2024 ­ >30.06.2024

15.06.2024 30.06.2024 ­ >30.06.2024

15.07.2024 31.07.2024 ­ >31.07.2024

No

15.01.2025 28.02.2025 15.03.2025 >15.03.2025

15.03.2025 31.03.2025 ­ >31.03.2025

31.03.2025 ­ ­ >31.03.2025

31.03.2025 ­ ­ >31.03.2025
­ ­ ­ No

31.07.2024 31.08.2024 30.09.2024 >30.09.2024

30.11.2024 31.12.2024 31.01.2025 >31.01.2025

48 46 44 <44

12.75 12.5 12.25 <11.25


>30.06.2024

10.09.2024 20.09.2024 30.09.2024 >30.09.2024

>30.09.2024

15.10.2024 21.10.2024 - >21.10.2024

15.02.2025

No

20 25 30 >30
No

80 70 60 <60

5 7 9 >9

2 3 4 >4

No
90 80 70 <70

90 80 70 <70

95 85 80 <80

22 21 20 <20

98 <98

15.10.2024 23.10.2024 31.10.2024 >31.10.2024

>31.12.2024

>15.02.2025

5 7 9 >9

5 7 9 >9

80 70 60 <60

No

2 3 4 >4

95 90 85 <85

No
90 80 70 <70

90 80 70 <70

7.5 7 6 <6

98 <98

17 16 15 <15

5 7 9 >9

2 3 4 >4

15.10.2024 21.10.2024 - >21.10.2024

20.01.2025 25.01.2025 - >25.01.2025

No

90 80 70 <70

90 80 70 <70

22 29 35 >35

22 29 35 >35
42 49 56 >56

15.09.2024 30.09.2024 15.10.2024 >15.10.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

>31.12.2024

22 29 35 >35

15.01.2025 31.01.2025 15.02.2025 >15.02.2025

25.05.2024 05.06.2024 15.06.2024 >15.06.2024

10.11.2024 20.11.2024 30.11.2024 >30.11.2024

35 40 45 >45

26 31 35 >35
15.01.2025 31.01.2025 15.02.2025 >28.02.2025

40 45 50 >50

12 14 16 >16

25 30 35 >35

25.05.2024 5.06.2024 15.06.2025 >15.06.2024

10.11.2024 20.11.2024 30.11.2024 >30.11.2024

10.01.2025 20.01.2025 31.01.2025 >31.01.2025

7 9 11 >11

55 65 75 >75

7 9 11 >11
07.05.2024 14.05.2024 21.05.2024 >21.05.2024

>31.05.2024

>31.07.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

10.01.2025 20.01.2025 31.01.2025 >31.01.2025

10.02.2025 20.02.2025 28.02.2025 >28.02.2025

10.03.2025 20.03.2025 31.03.2025 >31.03.2025

26 31 35 >35

07.11.2024 14.11.2024 21.11.2024 >21.11.2024

>30.06.2024

>31.03.2025

30.11.2024 15.12.2024 31.12.2024 >31.12.2024

15.07.2024 31.07.2024 15.08.2024 31.08.2024

10.03.2025 20.03.2025 31.03.2025 >31.03.2025

90 85 80 <80

20 25 30 >30
40 50 60 >60

20 25 30 >30

10.08.2024 20.08.2024 31.08.2024 >31.08.2024

10.01.2025 20.01.2025 31.01.2025 >31.01.2025

>31.12.2024

60 75 100 >100

55 70 85 >85

40 50 60 >60

47 54 60 >60

20 25 30 >30

50 55 60 >60

55 60 65 >65
>31.05.2024

7 9 11 >11

70 80 90 >90

40 50 60 >60

5 7 9 >9

40 50 60 >60

5 7 9 >9

20 15 <15
90 80 70 <70

65 70 75 <75

90 80 70 <70

95 90 - <90

15.03.2025 31.03.2025 - >31.03.2025

11 10 9 <9

11 10 9 <9
3 2 1 0

- - - No

95 90 85 <85

15.01.2025 31.01.2025 15.02.2025 >15.02.2025

15.07.2024 31.07.2024 15.08.2024 >15.08.2024

>31.03.2025

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

20 25 30 >30
>15.04.2024

10.04.2024 20.04.2024 30.04.2024 >30.04.2024

30.04.2024 05.05.2024 10.05.2024 >10.05.2024

15.08.2024 31.08.2024 15.09.2024 >15.09.2024

>15.05.2024

>31.05.2024

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

>31.08.2024

>31.08.2024

>31.08.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024


07.10.2024 17.10.2024 27.10.2024 >27.10.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

15.11.2024 30.11.2024 15.12.2024 >15.12.2024

No

>31.03.2025

3 2 <2

95 90 85 <85

95 90 85 <85

14 21 28 >28

No

No

22.04.2024 29.04.2024 06.05.2024 >06.05.2024

- - - No
- - - No

- - - No

- - - No

- - - No

- - - No

75 50 - <50

25.04.2024 05.05.2024 15.05.2024 >15.05.2024

>31.05.2024

>31.05.2024

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

15.07.2024 31.07.2024 15.08.2024 >15.08.2024

30.09.2024 - - >30.09.2024
15.10.2024 31.10.2024 15.11.2024 >15.11.2024

31.01.2025 15.02.2025 - >15.02.2025

15.02.2025 28.02.2025 15.03.2025 >15.03.2025

>28.02.2025

10.03.2025 20.03.2025 31.03.2025 >31.03.2025

75 50 - <50

No

No

No

No

7 9 11 >11

_ 3 - >3

90 80 70 <70
22.05.2024 29.05.2024 05.06.2024 >05.06.2024

10.06.2024 20.06.2024 30.06.2024 >30.06.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

11.10.2024 21.10.2024 31.10.2024 31.10.2024

60 70 80 >80

20 30 40 >40

20 30 40 >40

- No
No

20 30 40 >40

20 30 40 >40

20 30 40 >40

7 10 15 >15

No

25.04.2024 05.05.2024 15.05.2024 >15.05.2024

>30.06.2024

25.10.2024 05.11.2024 15.11.2024 >15.11.2024

15.12.2024 31.12.2024 15.01.2025 >15.01.2025


15.01.2025 31.01.2025 15.02.2025 >15.02.2025

01.03.2025 10.03.2025 20.03.2025 >20.03.2025

>31.03.2025

70 80 90 >90

70 80 90 >90

60 70 80 >80

7 6 5 >5

20 25 30 >30

90 85 80 <80
10 15 20 >20

50 65 80 >80

40 50 60 >60

15 20 25 >25

40 50 60 >60

40 50 60 >60

No

30 40 50 >60
>05.04.2024

>05.04.2024

30.04.2024 15.05.2024 31.05.2024 >31.05.2024

10.06.2024 20.06.2024 30.06.2024 >30.06.2024

>31.05.2024

>31.05.2024

10 days

15.07.2024 31.07.2024 15.08.2024 >15.08.2024

31.07.2024 15.08.2024 31.08.2024 >31.08.2024

07.11.2024 14.11.2024 21.11.2024 >21.11.2024

15.12.2024 31.12.2024 15.01.2025 >15.01.2025


10.01.2025 20.01.2025 31.01.2025 >31.01.2025

40 50 60 >60

0.4 0.3 0.2 >0.2

90 85 80 <80

20 25 30 >30

4098 3893 3699 3514

3 4 5 >5

60 75 90 >90

85 80 75 >75
135 150 165 >165

40 50 60 >60

No

No

6TH 7TH 8TH >8TH

>31.10.202
4

>31.10.202
4

>15.12.202
15.11.2024 30.11.2024 15.12.2024
4
>31.03.202
5
>31.03.202
5
>15.06.202
4

25 30 35 >35

No

45 60 70 >70

45 60 70 >70

8 9 10 >10

20 25 30 >30

45 60 70 >70

45 60 70 >70
90 105 120 >120

90 105 120 >120

No

95 90 85 <85

10 12 15 >15

23.08.2024 31.08.2024 07.09.2024 >07.09.2024

07.09.2024 14.09.2024 21.09.2024 >21.09.2024

15.01.2025 31.01.2025 15.02.2025 >15.02.2025

20 25 30 >30

15.10.2024 >15.10.2024

11 12 14 >14
No

3 2 <2

10.09.2024 20.09.2024 31.10.2024 >31.10.2024

195 210 225 >225

20.09.2024 20.10.2024 20.11.2024 >20.11.2024

No

No

<100

15.05.2024 31.05.2024 15.06.2024 >15.06.2024

15.06.2024 30.06.2024 15.07.2024 >15.07.2024

93 91 89 <89

31.12.2024 31.01.2025 28.02.2025 >28.02.2025


93 91 89 <89

No

No

No

28.04.2024 05.05.2024 12.05.2024 >12.05.2024

15.05.2024 31.05.2024 15.06.2024 >15.06.2024

15.12.2024 31.12.2024 >31.12.2024

15.10.2024 31.10.2024 15.11.2024 >15.11.2024

37 44 51 >51
45 50 55 >55

20 25 30 >30

12 15 18 >18

9 11 13 >13

9 11 13 >13
20 25 30 >30

12 15 18 >18

20 25 30 >30

6 7 8 >8

6 7 8 >8
Director In Operational
Department/Project Section
Charge Status
NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational


NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

NJHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational


RHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational

RHPS D(Projects) Operational


RHPS D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational


SDHEP D(Projects) Operational
SDHEP D(Projects) Operational
SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

SDHEP D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational


LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational


LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

LHEP-I D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational


DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational

DSHEP D(Projects) Operational


DSHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

DHEP D(Projects) Operational

CHENAB PROJECTS D(Projects) Operational

CHENAB PROJECTS REOLI-DUGLI D(Projects) Operational

CHENAB PROJECTS REOLI-DUGLI D(Projects) Operational


CHENAB PROJECTS REOLI-DUGLI D(Projects) Operational

CHENAB PROJECTS REOLI-DUGLI D(Projects) Operational


CHENAB PROJECTS BARDANG HEP D(Projects) Operational
CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational


CHENAB PROJECTS BARDANG HEP D(Projects) Operational
CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational

CHENAB PROJECTS BARDANG HEP D(Projects) Operational

TINDI SMALL HEP


CHENAB PROJECTS D(Projects) Operational
(4.4 MW)
TINDI SMALL HEP
CHENAB PROJECTS D(Projects) Operational
(4.4 MW)
CHENAB PROJECTS SACH KHAS HEP D(Projects) Operational

CHENAB PROJECTS SACH KHAS HEP D(Projects) Operational

CHENAB PROJECTS SACH KHAS HEP D(Projects) Operational

CHENAB PROJECTS SACH KHAS HEP D(Projects) Operational


CHENAB PROJECTS SACH KHAS HEP D(Projects) Operational

CHENAB PROJECTS D(Projects) Operational

CHENAB PROJECTS D(Projects) Operational

CHENAB PROJECTS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational


NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

NMHPS D(Projects) Operational

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)
SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)
SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)
SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)

SGEL D(Finance)
Parasan SPP D(Finance)

Parasan SPP D(Finance)

Parasan SPP D(Finance)

Parasan SPP D(Finance)

Parasan SPP D(Finance)

Parasan SPP D(Finance)


Parasan SPP D(Finance)

Parasan SPP D(Finance)

Gurhah SPP D(Finance)


Gurhah SPP D(Finance)

Gurhah SPP D(Finance)

Gurhah SPP D(Finance)

Gurhah SPP D(Finance)

Gurhah SPP D(Finance)

Gurhah SPP D(Finance)

Bagodra SPP D(Finance)

Bagodra SPP D(Finance)


Bagodra SPP D(Finance)
Bagodra SPP D(Finance)

Bagodra SPP D(Finance)

Bagodra SPP D(Finance)

Bagodra SPP D(Finance)

Bagodra SPP D(Finance)

Bikaner SPP D(Finance)


Bikaner SPP D(Finance)
Bikaner SPP D(Finance)

Bikaner SPP D(Finance)

Bikaner SPP D(Finance)


Bikaner SPP D(Finance)
Bikaner SPP D(Finance)
Bikaner SPP D(Finance)
Bikaner SPP D(Finance)

Bikaner SPP D(Finance)

Bikaner SPP D(Finance)

Bikaner SPP D(Finance)

Bikaner SPP D(Finance)

Bikaner SPP D(Finance)

Bikaner SPP D(Finance)

Bikaner SPP D(Finance)


Raganesda SPP D(Finance)

Raganesda SPP D(Finance)

Raganesda SPP D(Finance)

Raganesda SPP D(Finance)

Raganesda SPP D(Finance)


Raganesda SPP D(Finance)

Raganesda SPP D(Finance)

Raganesda SPP D(Finance)

Raganesda SPP D(Finance)


Gujrai SPP D(Finance)

Gujrai SPP D(Finance)

Gujrai SPP D(Finance)

Gujrai SPP D(Finance)

Gujrai SPP D(Finance)

Gujrai SPP D(Finance)

Gujrai SPP D(Finance)

Gujrai SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)


Jamui SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)

Jamui SPP D(Finance)

Banka SPP D(Finance)


Banka SPP D(Finance)
Banka SPP D(Finance)

Banka SPP D(Finance)

Banka SPP D(Finance)

Banka SPP D(Finance)

Banka SPP D(Finance)

Banka SPP D(Finance)

Banka SPP D(Finance)

Banka SPP D(Finance)

Banka SPP D(Finance)


Bhuj 260MW D(Finance)
Bhuj 260MW D(Finance)
Bhuj 260MW D(Finance)

Bhuj 260MW D(Finance)

Bhuj 260MW D(Finance)

Bhuj 260MW D(Finance)

Bhuj 260MW D(Finance)


Bhuj 260MW D(Finance)
Bhuj 260MW D(Finance)

Bhuj 260MW D(Finance)

Bhuj 100MW D(Finance)


Bhuj 100MW D(Finance)
Bhuj 100MW D(Finance)

Bhuj 100MW D(Finance)

Bhuj 100MW D(Finance)

Bhuj 100MW D(Finance)

Bhuj 100MW D(Finance)


Bhuj 100MW D(Finance)
Bhuj 100MW D(Finance)

Bhuj 100MW D(Finance)

Khavda SPP D(Finance)

Khavda SPP D(Finance)


Khavda SPP D(Finance)
Khavda SPP D(Finance)
Khavda SPP D(Finance)
Khavda SPP D(Finance)

Khavda SPP D(Finance)

Khavda SPP D(Finance)

Khavda SPP D(Finance)


Khavda SPP D(Finance)

Khavda SPP D(Finance)

Nangal FSPP D(Finance)


Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)


Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

Nangal FSPP D(Finance)

OM FSPP D(Finance)
OM FSPP D(Finance)
OM FSPP D(Finance)

OM FSPP D(Finance)

OM FSPP D(Finance)

OM FSPP D(Finance)

OM FSPP D(Finance)

OM FSPP D(Finance)

OM FSPP D(Finance)

OM FSPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)


Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)


Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Punjab SPP D(Finance)

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III


Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III


Nepal Projects ARUN-III
Nepal Projects ARUN-III
Nepal Projects ARUN-III
Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III


Nepal Projects ARUN-III

Nepal Projects ARUN-III


Nepal Projects ARUN-III

Nepal Projects ARUN-III


Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III


Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III


Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-III

Nepal Projects ARUN-IV

Nepal Projects ARUN-IV

Nepal Projects ARUN-IV

Nepal Projects ARUN-IV

Nepal Projects ARUN-IV

Nepal Projects ARUN-IV


Nepal Projects ARUN-IV
Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC


Nepal Projects SLAPDC
Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC

Nepal Projects SLAPDC


Nepal Projects SLAPDC

Nepal Projects SLAPDC

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN


Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN


Arunachal Projects ETALIN

Arunachal Projects ETALIN


Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN

Arunachal Projects ETALIN


Arunachal Projects ATTUNLI
Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI


Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI


Arunachal Projects ATTUNLI
Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI


Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects ATTUNLI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI


Arunachal Projects EMINI

Arunachal Projects EMINI

Arunachal Projects EMINI

KWPS Operational

KWPS Operational
KWPS Operational

KWPS Operational

KWPS Operational

KWPS Operational

KWPS Operational

KWPS Operational

KWPS Operational
KWPS Operational

KWPS Operational

KWPS Operational

KWPS Operational

KWPS Operational
KWPS Operational

KWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational

SWPS Operational
SWPS Operational

SWPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

CSPS Operational

Civil Design CD-1 D(Projects)

Civil Design CD-1 D(Projects)


Civil Design CD-1 D(Projects)

Civil Design CD-1 D(Projects)

Civil Design CD-1 D(Projects)

Civil Design CD-1 D(Projects)

Civil Design CD-2 D(Projects)

Civil Design CD-2 D(Projects)

Civil Design CD-3 D(Projects)

Civil Design CD-3 D(Projects)

Civil Design CD-3 D(Projects)

Civil Design CD-3 D(Projects)


Civil Design CD-3 D(Projects)

Civil Design CD-3 D(Projects)

Civil Design CD-3 D(Projects)

Civil Design CD-4 D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)

Civil Design CD-4 D(Projects)

Civil Design CD-4 D(Projects)

Civil Design CD-4 D(Projects)

Civil Design CD-4 D(Projects)


Civil Design CD-5 D(Projects)

Civil Design CD-5 D(Projects)

Civil Design CD-5 D(Projects)

Civil Design CD-5 D(Projects)

Civil Design CD-5 D(Projects)

Civil Design CD-5 D(Projects)

Civil Design CD-5 D(Projects)

Civil Design CD-6 D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)

Civil Design CD D(Projects)


Architecture D(Projects)

Architecture D(Projects)

Architecture D(Projects)

Architecture D(Projects)

Architecture D(Projects)

Architecture D(Projects)

Architecture D(Projects)

Architecture D(Projects)

Architecture D(Projects)

CSU D(Projects)

CSU D(Projects)

CSU D(Projects)
CSU D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)


Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)


Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)

Civil Contracts D(Projects)


CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)
CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CFMD D(Projects)

CP D(Projects)
CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)
CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)

CP D(Projects)
Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)
Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Environment D(Projects)

Geology D(Projects)

Geology D(Projects)

Geology D(Projects)

Geology D(Projects)
Geology D(Projects)

Geology D(Projects)

Geology D(Projects)

Geology D(Projects)

Geology D(Projects)

Geology D(Projects)

Geology D(Projects)

Geology D(Projects)

Electrical Design D(Projects)


Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)


Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)


Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

Electrical Design D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)
CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

CSO D(Projects)
CSO D(Projects)

CSO D(Projects)

CSO D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)


Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

Electrical Contracts D(Projects)

IT&SE D(Projects)
IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)
IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)

IT&SE D(Projects)
QA&I D(Projects)

QA&I D(Projects)

QA&I D(Projects)

QA&I D(Projects)

QA&I D(Projects)
QA&I D(Projects)

QA&I D(Projects)

QA&I D(Projects)

QA&I D(Projects)

QA&I D(Projects)
Criticality Type of Target Qtr.status Center

Critical

Critical

Critical

Critical

Critical
Critical

Critical

Critical

Critical
Critical

Critical

Critical

Critical
Critical

Critical
Critical
Critical

Critical

Critical
Critical

Critical

Critical

Critical
Critical

Critical

Critical

Critical

Critical

Critical
Critical

Critical

Critical
Critical

Critical
Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center
Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Civil Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center
Electrical Center

Electrical Center

Electrical Center

Electrical Center

Electrical Center

You might also like