Professional Documents
Culture Documents
Cbs Boosting Application Guide 2019 Global en
Cbs Boosting Application Guide 2019 Global en
COMMERCIAL BUILDINGS
APPLICATION GUIDE
1
INTRODUCTION
PREFACE
People move together at a pace like never before. sufficient water to a tall building is a discipline of
PREFACE..................................................................................................................................................... 2
Urbanisation is here to stay. Globally, city popula- its own.
tions are growing by 65 million every year with In addition, buildings in general account for 40% WATER BOOSTING................................................................................................................................. 4
most of this growth taking place in Asia and of the world’s energy consumption so tall build- When is water boosting necessary?......................................................................................... 4
China. It is projected that by 2025, more than 2.5 ings is a good place to start if we want to save History of water supply and sanitation.......................................................................................................5
billion people will live in Asian cities, which is half energy globally. We believe that water boosting is Insufficient coverage from the mains..........................................................................................................6
of the world’s total city dwellers. Water boosting applications............................................................................................................................6
an overlooked area for optimisation and there is
As people move closer together, buildings need considerable difference between the best and the COMSUMERS........................................................................................................................................... 6
to be taller. The acceleration in the numbers of worst booster system designs. Load Profiles............................................................................................................................................................6
tall buildings can be seen in the figure below. How to evaluate the best way to do it will be Tap pressure............................................................................................................................................................8
The development and construction of these tall Fire Fighting............................................................................................................................................................8
examined in this water boosting guide, and we
Supply of water for cooling towers...............................................................................................................9
buildings increased from the start of the new will present a number of arguments for water
millennium. boosting. SYSTEM LAYOUT....................................................................................................................................10
Tall buildings require water for tap water and System elements............................................................................................................................10
cooling towers to function properly, and providing Enjoy. Break tanks........................................................................................................................................................... 10
Boosting with break tank............................................................................................................................... 11
1000 Booster pumps ................................................................................................................................................... 12
Risers and Branches.......................................................................................................................................... 12
Number of 200 m+ buildings
900 Pressure reduction valves (PRV)................................................................................................................... 13
Number of super tall buildings (300 m+) 800 Layouts ..............................................................................................................................................15
Single booster system...................................................................................................................................... 15
Number of mega tall buildings (600 m+) Zone-divided booster system....................................................................................................................... 16
700
Roof-Tank Systems............................................................................................................................................. 17
600
Series-connected systems with intermediate break tanks.............................................................. 18
500 Series-connected systems without intermediate break tanks....................................................... 19
SIZING.......................................................................................................................................................20
400
Pressure head...................................................................................................................................................... 20
300
Head Rise............................................................................................................................................................... 20
Static height......................................................................................................................................................... 21
200 Major head loss.................................................................................................................................................. 21
Friction losses...................................................................................................................................................... 23
100 Determining pipe dimensions and required booster capacity....................................................... 24
2 3
WATER BOOSTING
Pressure boosting can be necessary for more One early example is the Indus Valley civilisation
reasons. Let us go through a few: in Asia, which showed early evidence of public
water supply and sanitation. The system the
• Buildings placed on a hilltop where pres- Indus developed and managed included a number
sure supplied from mains is inadequate. of advanced features. A typical example is the
Indus city of Lothal where all houses had their
• Tall buildings where the height of the own private toilet connected to a covered sewer
building prevents the community water network. Since then, engineering and plumbing
from reaching the top floors. For example, Pont du Gard, a Roman aqueduct in France. have developed significantly.
In areas with buildings placed on hilltops, it can be
a mains pressure of 3.0 bar should, necessary to boost water pressure.
theoretically, be sufficient for a 300 m tall Now, things have changed as we have water
building, but in reality this is not the case. towers and pump stations.
There must be sufficient surplus pressure The use of water towers increased drastically
to cover resistance in riser pipes, single Typical building during mid-19th century.
components such as shower heads, toilets A water tower is an elevated structure supporting
and cooling towers. a water tank constructed at a height sufficient to
pressurise a water supply system for the distribu-
• The peak load flow might be greater than tion of potable water, and to provide emergency
what is possible to supply from the mains. storage for fire protection. Water towers are
In these cases, a break tank is supplied able to supply water even during power out-
to the building, from where one or more ages, because they rely on hydrostatic pressure
booster sets take the water and boost it to produced by elevation of water (due to gravity)
the required pressure level. to push the water into domestic and industrial
water distribution systems. However, they cannot
Water pressure supplied from the mains is not sufficient supply the water for longer periods without
The normal specifications are that the pressure The principle of an elevated water tower.
to cover top floors. power, because a pump is typically required to
on each floor does not fall below 1.5 bar and
refill the tower. A water tower also serves as a
does not exceed 5 bar.
reservoir to help with water needs during peak
usage times. The water level in the tower typically
falls during peak usage hours during the day, and
then a pump fills it back up during the night. This
process also keeps the water from freezing in
cold weather, since the tower is constantly being
drained and refilled.
4 5
WATER BOOSTING
Flow [GPM]
Insufficient coverage from the one knows about the actual use, the more likely
300
mains it is that the final annual energy consumption
250 can be as low as possible.
Every building has its own load profile in the
sense that peak flow occurs at a specific time of
200 Qyear m3/year:
the day for the building in question.
How much water is consumed on a yearly basis
The water work supplying water to the build- 150 per person (e.g. 25 m3/year/person in an office
ing may, however, be unable to provide the
building).
maximum flow required. In such cases, break 100
tanks have to be installed. These tanks serve as Consumption period, days/year:
storage tanks from where pump systems can 50 How many days a year the building is projected
provide the flow required for the entire build- to be in operation.
0
ing. An example of a typical booster application 0 2 4 6 8 10 12 14 16 18 20 22 24
is shown on this page. Q (m)day / m3/day :
Hours per day
How much water is consumed per person per
Water consumption load profile during a 24-hour period.
day (office building: 25/250= 0,1)
Water boosting applications
fd: Concurrency factor.
When do you need water boosting? The rea-
ft: Peak flow factor.
sons for water boosting can be many:
Max. flow rate, m3/h
Max. flowrate per hour per unit; e.g. 0.018 m3/h
• High-rise buildings.
per employee in an office building.
• HVAC; where water needs to be pressur-
ised for heating and cooling applications.
• Fire fighting Consumer Unit QYear Consumption Qday fd Q (m)day ft Max flow
m3/year period m3/day m3/day rate m3/h
• Irrigation; a golf course, for example. days/years
• Commercial water supply. Residence Residence 183 365 0,5 1,3 0,65 1,7 0,046
building (2.5 per-
sons)
This document will only focus on high-rise
Office Employee 25 250 0,1 1,2 0,12 3,6 0,018
buildings. building
Shopping Employee 25 300 0,08 1,2 0,1 4,3 0,018
centre
CONSUMERS Supermar-
ket
Employee 80 300 0,27 1,5 0,4 3,0 0,05
6 7
WATER BOOSTING
8 9
SYSTEM LAYOUT
10 11
SYSTEM LAYOUT
Adjustable
orifice
Inlet pressure Controlled pressure
Spring B
In one type of PRV, a diaphragm flexes in response to the pressure on the outlet side of the valve. This
diaphragm is attached to the moving part of a variable orifice valve. The movement of the diaphragm is
Building with one branch per floor
counteracted by two springs and an adjustable screw to adjust the output pressure.
12 13
SYSTEM LAYOUT
Layouts
The presence of PRVs will cause a waste of built-up pressure and thus energy. This is illustrated by Booster systems may be designed in several
a simple example. different ways with the elements described
A high-rise building needs pressure boosting from the basement floor. In the example, a above. Which layout to choose depends on
maximum water tap pressure of 4 bar is allowed. However, due to the system layout, excessive many factors and the specific task in question,
pressure is present in the lower part of the system. This is dealt with by installing PRVs in main e.g. local legislation and traditions, flexibility
branches before the taps. Below it is illustrated how an excess pressure of 8 bar is reduced to the requirements or the possibility for future expan-
allowed 4 bar. The pipe will supply a water flow of 4 m3/h. sions etc. Not one system layout is ideal for all
scenarios.
Below, the advantages and disadvantages
of some the most used system layouts are
described.
After the PRV, the pressure is halved from 8 bar to 4 bar, resulting in only half the hydraulic power,
Single Booster System
P2 = 0.45 kW. As such, the PRV represents a power loss of 0,45 kW. Depending on the number of
operating hours, this necessary excess pressure will potentially consume a lot of energy. For, e.g., Advantages
4,000 hours of operation per year, this PRV alone will ‘consume’ 1,800 kWh/year.
Only one riser needed (simple design)
Disadvantages
Excess pressure on lower floors in buildings
exceeding ten floors (PRVs and high-pressure
Zoom of the basement in the single booster graded pipes needed)
system.
14 15
SYSTEM LAYOUT
Disadvantages
Higher initial cost than single-zone systems
16 17
SYSTEM LAYOUT
Space required for booster sets and tank on Higher initial cost than single-zone systems
service floors
Space required for booster sets and tank on
Risk of microbiological growth in tanks service floors
Complex control
18 19
SIZING
20 21
SIZING
The friction factor is the tricky part of the calcu- The loss coefficient (KL) is a function of the
lation. It is a complex function of the Reynolds Reynolds number and the geometry of the
number and the roughness of the pipe that component. It is determined experimentally
cannot, as yet, be obtained from a theoretical and may be found in tables.
analysis. In practice, exhaustive set of curve- As noticed, the head loss (both major and
fitted experimental data is used, often in its minor) is a function of the fluid velocity, which
It’s not only straight pipes results in pressure losses, also bends and other components count is a factor when it
graphical form – the so-called Moody chart – or means that it will increase for higher flow rates
comes to reduceing pressure loss.
in the form of the Colebrook formula, which – it is a so-called dynamical pressure head.
requires an iterative solution scheme. Combined, it may be expressed as:
l
hL=hL major+hL minor= v (f= +∑KL )
2
2g D
22 23
SYSTEM LAYOUT EXAMPLE
Zone 3 7 floors 30m Apartments 450 residents 150 kPa 8.3 m3/h
Zone 2 6 floors 25 m Landscaped offices 640 employees 150 kPa 27.6 m3/h
KL-value (Zeta) can be calculated in Grundfos Product Center Zone 1 4 floors 17 m Shopping centres 100 employees 150 kPa 4.6 m3/h
24 25
SYSTEM LAYOUT EXAMPLE
10.9
10 9.8 9.5
0
Single-booster Zone-divided Rooftop tank Series-connected Series-
system booster system booster intermediate connected
system break tank booster system
Energy consumption and required hydraulic booster power using different system layouts.
26 27
SYSTEM LAYOUT EXAMPLE
In this example, series-connected pressure that truly influence the result instead of spend-
boosting systems with break tanks require the ing time determining and sizing parts of the
smallest boosting power closely followed by system that only influence the result marginally.
the roof tank solution. However, choosing a
zone-divided system, where each zone is sup- In the table below, some of the parameters often
plied by its own booster system will reduce the considered are listed and ranked according to
annual energy consumption by approximately their influence coefficient, when considering the
10% and only require approximately 15% hydraulic booster power, P4.
larger booster capacity. Additional benefits like Parameters marked in green have an IC value
eliminating the need of intermediate break above 50% and special attention should thus be
tank, separation of system in hydraulic zones paid to determining the correct value of those
etc. could easily make such systems favour- parameters. Likewise, parameters marked in red
able. only constitute IC values below 10% and are, as
The size of water tanks in booster systems such, negligible in the overall picture.
greatly affects the necessary booster capacity
and thus the result of the example given above
would change with a different tank volume.
Hydraulic power, P4
Key system parameters Rank IC Parameter Note
The pressure boosting system consist of many 1 100% Number of units (people)
parts all more or less influencing the system
size, performance and energy consumption. 1 100% Unit peak load
However, which ones are most important to 3 61-80% Building height
focus ones attention on in the design phase? 4 52-66% Tank volume (rooftop tanks and break Only relevant for C, D and F
Grundfos has recently carried out a research tanks)
study investigating the sensitivity of such
5 3-22% Tap pressure
parameters on the hydraulic side of pressure
boosting systems. This is done by means of 6 13-20% Number of subdivided hydraulic zones Only relevant for B, D, E and F
an influence coefficient (IC) describing the
7 4-19% Hourly load profile (variation in 1 hour) Only relevant for C and D
influence of changes in a given parameter, e.g.
pressure loss in riser pipes (Pa/m), on the total 8 2-9% Pressure loss in coupling pipes
hydraulic booster power necessary in a system.
As such, the IC value of a given input parame- 9 5% Pressure loss in riser pipes and branches
ter describes the magnitude of total variability
10 2-3% Pressure loss in water meter
in the output parameter that is caused by the
given input parameter. E.g. if the pressure loss 10 2-3 % Pressure loss in manifold
in riser pipes constitutes an IC value of 5%,
it means that only 5% of any change in pres- 12 0-2% Distance from riser to manifold (horizon- Not relevant for any system
sure loss is ‘felt’ by the booster pumps. Such tal)
knowledge is vital when designing systems, as 13 0% Consumption period (days per year)
it enables the designer to focus on parameters
Sensibility of system parameters
28 29
SIZING A BOOSTER – EXAMPLE
Example: Sizing a booster system Example: Sizing a booster system - Zone divided solution
A new hospital with 800 beds needs a booster } 4m First, we will take a look at a zone-divided solution, where we use five booster sets to service the
system for the whole building. In this example, hospital.
we will compare two solutions to see which is The five boosters are all placed in the basement. Booster 1 will deliver flow and pressure needed
around the basement. For example: Laundry room and cooling and heating activities ect.
better in relation to total energy consumption. The four remaining booster sets will handle the rest of the bulding and mainly cater for the needs
We will start by using Grundfos Product Center of patients and doctors. The four boosters will service four floors each.
to calculate the data we need to size our
booster pumps. Booster 1 ( 60% of total energy consumption)
30 31
SIZING A BOOSTER – EXAMPLE
Example: Sizing a booster system – Grundfos Product Center Example: Sizing a booster system – Grundfos Product Center
Now we know the values of Q and H, and we are ready to find the booster that matches the need
of our building. Let us take a look in Grundfos Product Center.
Step 2
Now we are ready to size the first of five booster pumps.
In this example, the installation we want is a break tank from the basement, as it is best suited for
this hospital.
The water consumption is calculated whereas a beds in the hospital. This booster will handle the
first 4 floors. (800 Beds / 19 floors = 42 beds per floor x 4 = 169 Beds
Each bed uses 800 l pr day.
The geodetic height is 80 m, friction loss on 0.8, and the discharge pressure for booster 1 is 2.5 bar
32 33
SIZING A BOOSTER – EXAMPLE
Example: Sizing a booster system – Grundfos Product Center Example: Sizing a booster system – Grundfos Product Center
34 35
SIZING A BOOSTER – EXAMPLE
Example: Sizing a booster system – Grundfos Product Center Example: Sizing a booster system – Grundfos Product Center
36 37
SIZING AA
SIZING BOOSTER
BOOSTER- EXAMPLE
SYSTEM
Example: Sizing a booster system Example: Sizing a booster system - One booster solution
One booster
300 x 800 = 240,000 m3/ year
240,000 / 365 = 657,53 m3/ day
658 / 24 = 27.4 m3/ hour
27.4 x 1.8 = 49.3 m3/ hour (Max consumption)
38 39
SIZING A BOOSTER - EXAMPLE
Example: Sizing a booster system – one-booster solution Example: Sizing a booster system – one-booster solution
The sizing result from Grundfos Product Center on the previous page shows the total energy con-
sumption for the one-booster solution of 103.440 kWh/year
Please also note that there will be a need for several PRVs which will add to initial cost and mainte-
nance for the one-booster solution.
Let us take a look at why the total energy consumption is so high, when using a one-booster solu-
tion.
The illustration below shows that the pressure increases as we move downwards in the building,
creating residual pressure. We actually pay the booster to produce this pressure which is unneces-
sary as shown in the -/+ column.
Pressure +/-
25 mWc
29 mWc
33 mWc
37 mWc
41 mWc +1
44 mWc +4
Sizing data for one booster 48 mWc +8
52 mWc +12
56 mWc +16
60 mWc +20
64 mWc +24
68 mWc +28
72 mWc +32
76 mWc +36
80 mWc +40
84 mWc +44
Sizing result for the one-booster solution
88 mWc +48
92 mWc +52
96 mWc +56
40 41
SUMMARY
Let us take a look at at the totalt energy consumption for the five booster sets, and compare the SUMMARY
results with the one-booster solution.
Providing water for people living and working
Total Energy Consumption 5 Booster sets: in a modern city is a prerequisite for the city to
function.
Booster 1: 28.741 kWh/year
Pressure boosting is required for different rea-
Booster 2: 7.603 kWh/year
sons, whether being an extension to an exist-
Booster 3: 10.130 kWh/year
ing building or part of a new high-rise building.
Booster 4: 12.093 kWh/year Whatever the reason, the design of these sys-
Booster 5: 14.370 kWh/year tems vary. In this document, we wanted to offer
inspiration for how this can be done.
Total: 72.937 kWh/year Our aim has been to be as objective as possible
and provide solid information about the pros
One Booster: 103.400 kWh/year * and cons of different system layouts. However,
local regulations must always be observed and
Difference: (103.400 – 72.937) = 30.503 kWh/year equal to 31 %
therefore some of the suggestions might not
* Notice that there will be a need for several PRV’s which will add to initial cost and maintenance for be applicable in certain countries.
the one booster solution. We hope that you found this material useful
and that you will contact us should you have
questions concerning pressure boosting.
42 43
GRUNDFOS BUILDINGS SERVICES
99085894 /0616
We offer solutions and expertise within the following applications:
Heating
Air Conditioning
owned by Grundfos Holding A/S or Grundfos A/S, Denmark. All rights reserved worldwide.
Water Boosting
The name Grundfos, the Grundfos logo, and be think innovate are registered trademarks
District Energy
Fire Fighting
Wastewater
Water Disinfection
Rainwater Harvesting
Domestic Hot Water Recirculation
44