PTW Icss

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

37 PTW

E&I activities Civil activities Mechanical activities ENPPI PTW closed

Depend on production instructions for


6 PTW availability of tanks to work on (tank roof
activities )

Work plan is to work on 2 tanks riser But because of malfunction in fuseable plugs
because of availability of 2 scaffolds - with and following production and saftey
3 PTW for cable trays on tank riser total 4 PTW , so 1 PTW for tank 1 is issued to instruction to stop the work , there is delay
close PTW of tank 14 and move the scaffold to move from tank 14 to tank 1 , as tank 2
5 PTW to tank 1 and start work there riser activity is on going

2 PTW for scaffolding

To be renewed until ending of all cable laying


3 PTW For main trench
to use them for backfilling activity

2 PTW For tanks 1,2 already the excavation


works finished and to start cleaning the
trench for cable laying activity 6 PTWs 3 PTWs 1 PTW 1 PTW
8 PTW For Excavation & backfilling works 4 PTW For excavation inside tanks 1,2,3,4
2 PTW for tanks 3,4 - to be started within 1
day

First time issuing and to be started within 1


1 PTW For excavation infront of dike of tanks 2,4
day

2 PTW For main cable laying in main trench


4 PTW
Cable laying Inside tanks 1,2 - waiting
2 PTW cleaning of thier trench and to be started
with in 1 day

1 PTW Loading and offloading cables drums

First time issuing and to be renewing until


1 PTW Cable termination inside new control room
finishing the termination for all main cables

You might also like