Professional Documents
Culture Documents
4.3 - PPPs and Sub-Nationals Lessons From Around The World - Infrastructure Development in India - Challenges and Opportunitie
4.3 - PPPs and Sub-Nationals Lessons From Around The World - Infrastructure Development in India - Challenges and Opportunitie
- Gajendra Haldea
400,000
350,000
250,000
200,000
150,000
100,000 XI Plan
X Plan (2002-07):
Actual: (Rs.8,46,186 cr.) Anticipated
50,000
$ 212 bn
-
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2009-10
2010-11
2011-12
2008-09
3
Investment in Infrastructure as % of GDP
(10th and 11th Five Year Plans)
8.00
Private 7.31 7.30
7.05
7.00 Public 6.35
Total
6.00 5.52
5.11
4.89
5.00 4.40 4.28 4.34
% of GDP
4.00
3.00
2.00
1.00
0.00
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2009-10
2008-09
2010-11
2011-12
Provisional Figures for 2010-12
4
Growth of Private Investment
(10th and 11th Five Year Plans)
250,000 (At 2006-07 prices)
Rs. 204,751
($ 51.19 bn)
200,000 Rs. 172,516
($ 43.13 bn)
($ 31.42 bn)
100,000
Rs. 44,704
Rs. 26,134 ($ 11.18 bn)
50,000 Rs. 16,934
($ 6.53 bn)
($ 4.23 bn)
-
-0 3
-0 4
-0 5
-0 6
-0 7
-0 8
-0 9
-1 0
-1 1
-1 2
2 00 2
2 00 3
2 00 4
2 00 5
2 00 6
2 00 7
2 00 8
2 00 9
2 01 0
2 01 1
Provisional Figures for 2010-12
5
Relative Share of Private Investment
(10th and 11th Five Year Plans)
100
Public Private
90
80
70
Per cent share
60
50
40
30
20
10
0
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2009-10
2008-09
2010-11
2011-12
Provisional Figures for 2010-12 6
Share of Private Investment in different Sectors
(10th and 11th Five Year Plans)
90 83 85
80
70
60
60
Per cent share
50
42
40 37
30
20
10 4
0
Electricity Telecom National Railways Ports Airports
Highways 7
Projected Investment in Infrastructure : 12th Plan
XII Plan:
1,200,000 Projected: (Rs.40,15,225 cr.)
XI Plan Anticipated $ 1,004 bn
800,000
Rs. Crore
600,000
400,000
200,000
XI Plan:
Anticipated: Rs.18,44,153 cr.)
$ 461 bn
-
2007-08
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2008-09
8
Methodology of Projections
Using 2011-12 as the base year, the following annual growth rates
have been assumed for Twelfth Plan period.
Growth rates have been assumed on the basis of past trends and
perceived sectoral dynamics in the Plan period.
9
Sectoral break-up of Projected Investment: 12th Plan
(at 2006-07 prices)
50.00
40.00
Per cent
30.00
20.00
10.00
0.00
2012-13 2013-14 2014-15 2015-16 2016-17 11
Investment by Centre, States & Private Sector
(Rs. crore at 2006-07 prices)
(per cent share in brackets)
14
Stages of PPPs
I. Public sector provision of Infrastructure: Command & Control
- PPP by exception
16
Financial Support to PPPs
Viability Gap Funding (VGF) upto 20% of capital costs based on
competetive bidding; another 20% VGF by project authority
IIFCL has sanctioned Rs. 27,572 cr. (US$ 7 bn) for 189 projects
17
Financing Constraints
Competing demands on budgetary resources: health, education,
rural development, livelihood support programmes etc.
18
Issues in Financing by Banks
Excessive reliance on commercial banks (51%); exposure up
from 1.8% of their lending in FY 2001 to 10.2% in FY 2009;
CAGR of 40%
21
Telecom: A spectacular success story
Private investment increased from Rs. 5,936 cr. (US$ 1.5 bn) in
2002-03 to Rs. 51,019 cr. (US$ 12.8) in 2009-10 (8.6 times)
Share of private investment increased from 28% in 2002-03 to
80% in 2009-10; CAGR of 36% during this period
Target of 15% tele-density by 2010 achieved 3 years ahead of
schedule
Over 10 million mobile connections added every month; total
of 860 million by August 2011
Lowest tariffs in the world
Competition and access to consumers was the driving force
22
Power: Constrained growth
T&D losses exceed 27%; provisional losses of Rs. 60,000 cr. (US$
15 bn) in 2010-11; 13% peak shortage & 10% energy shortage
23
Governance: Typical Issues
Ministries retain their role but work closely with CCI to develop
& implement the vision for world-class infrastructure
26
Typical documents for PPP projects
Substantive Documents
- Concession Agreements
Process Documents
- RFQ for pre-qualification of bidders
28
Model RFQ/RFP (contd.)
The evaluation criteria is divided into:
Technical Capability: based on project experience
30
MCA (contd.)
Safeguards the public exchequer & user interests
31
Framework Documents
Model Concession Agreements published for PPP in:
• National Highways
• State Highways
• Ports
• Operation & Maintenance of Highways
• Urban Rail Systems (Metro rail)
• Container Train Operation
• Redevelopment of Railway Stations
• Non-metro Airports
• Greenfield Airports
• Procurement-cum-Maintenance of Locomotives
• Transmission of electricity
32
Framework Documents (contd.)
Model Bidding Documents for PPP projects