Subcontract Data
PART ONE – DATA PROVIDED BY THE CONTRACTOR
Completion of the data in full, according to the Options chosen, is essential to create a
complete contract.
1. General
The conditions of subcontract are the core clauses and the clauses for the following main
Option, the Option for resolving and avoiding disputes and secondary Options of the NEC4
Engineering and Construction Subcontract June 2017 (with amendments January 2019)
Secondary Options
The Contractor is
Name :
Name :
1|Page
SUBCONTRACT DATA
except that
except that
2|Page
SUBCONTRACT DATA
If the Contractor has The key dates and conditions to be met are
identified work which is set
condition to be met key date
to meet a stated condition
by a key date (1)
(2)
(3)
3 Time
(1)
(2)
(3)
If the Contractor has decided The subcontract completion date for the whole of the
the subcontract completion subcontract works is ____________________
date for the whole of the
subcontract works
Taking over the subcontract The Contractor is / is not willing to take over the subcontract
works before the Subcontract works before the Subcontract Completion Date.
Completion Date (Delete as applicable)
3|Page
SUBCONTRACT DATA
If no programme is identified The period after the Subcontract Date within which the
in part two of the subcontractor is to submit a first programme for
Subcontract Data acceptance is : ______
4 Quality management
The period after the Subcontract Date within which the
Subcontractor is to submit a quality policy statement and
quality plan is :
5 Payment
The interest rate is % per annum (not less than 2) above the
If the period in which The period within which payments are made is
payments are made is not
four weeks and Y(UK)2 is
not used
If Option C or D is used The Subcontractor's share percentages and the share ranges are
from % to % %
from % to % %
greater than
on (date)
4|Page
SUBCONTRACT DATA
6 Compensation events
The weather data are the records of past weather measurements for each calendar month
which were recorded at
Where no recorded data are Assumed values for the ten year weather return weather data for each weather
available measurement for each calendar month are
If Option A or B is used The value engineering percentage is 50%, unless another percentage
is stated here, in which case it is
5|Page
SUBCONTRACT DATA
(2)
(3)
(1)
(2)
(3)
The minimum amount of cover for insurance against loss of or damage to property (except the subcontract works, Plant and
Materials and Equipment) and liability for bodily injury to or death of a person (not an employee of the Subcontractor)
arising from or in connection with the Subcontractor Providing the Subcontract Works for any one
event is ______________________________________________________
The minimum amount of cover for insurance against death of or bodily injury to employees of the Subcontractor arising out
of and in the course of their employment in connection with the subcontract for any one event is
_________________________________________
If the Client or Contractor is The insurance against loss of or damage to the subcontract works, Plant and Materials is to
to provide Plant and Materials include cover for Plant and Materials provided by the Client or Contractor for an amount
of
If the Client or Contractor The Client or Contractor provides these insurances from the Insurance Table
is to provide any of the
insurances stated in the (1) Insurance against
Insurance Table
Minimum amount of cover is
The deductibles are
If additional insurances are The Client or Contractor provides these additional insurances
to be provided
(1) Insurance against
6|Page
SUBCONTRACT DATA
The person or organisation who will choose an arbitrator if the Parties cannot agree a
choice or if the arbitration procedure does not state who selects an arbitrator is
Name (1)
7|Page
SUBCONTRACT DATA
Name (2)
Name
Name
X1: Price adjustment for inflation (used only with Options A, B, C and D) If Option X1 is used
The proportions used to calculate the Price Adjustment Factor are
0.
0.
0.
0.
0.
0. non adjustable
1.00
8|Page
SUBCONTRACT DATA
on (date)
(1)
(2)
(3)
(4)
If Option X6 is used with The bonus for each section of the subcontract works is
Option X5
section description amount per day
(1)
(2)
(3)
(4)
9|Page
SUBCONTRACT DATA
If Option X7 is used with Delay damages for each section of the subcontract works are
Option X5
(1)
(2)
(3)
(4)
The delay damages for the remainder of the subcontract works are
provided to
subcontract works
If no information execution The period after the Subcontract Date within which the Subcontractor is to submit a first
plan is identified in part two Information Execution Plan for acceptance is
of the Subcontract Data
The minimum amount of insurance cover for claims made against the Subcontractor
arising out of its failure to use the skill and care normally used by professionals providing
information similar to the Project Information is, in respect of each claim
The period following Completion of the whole of the subcontract works or earlier
termination for which the Subcontractor maintains insurance for claims made against it
arising out of its failure to use the skill and care is
10 | P a g e
SUBCONTRACT DATA
Advanced payment bond An advanced payment bond is /is not required. (Delete as applicable)
If Option X15 is used The period for retention following Completion of the whole of the subcontract works or
earlier termination is
The minimum amount of insurance cover for claims made against the Subcontractor arising out
of its failure to use the skill and care normally used by professionals designing works
similar to the subcontract works is, in respect of each claim
The period following Completion of the whole of the subcontract works or earlier
termination for which the Subcontractor maintains insurance for claims made against it
arising out of its failure to use the skill and care is
X16: Retention
Retention bond The Subcontractor may / may not give the Contractor a retention bond. (Delete as
applicable)
If Option X17 is used The amounts for low performance damages are
11 | P a g e
SUBCONTRACT DATA
for
for
for
for
The end of liability date is years after the Completion of the whole of the
subcontract works
12 | P a g e
SUBCONTRACT DATA
If Option Y(UK)2 is used and The period for payment is ______ days after the date on which payment becomes due
the final date for payment
is not fourteen days after
the date on which payment
becomes due
13 | P a g e
SUBCONTRACT DATA
1 General
The Subcontractor is
Name
Job
Responsibilities
Qualifications
Experience
Name (2)
Job
Responsibilities
Qualifications
Experience
14 | P a g e
SUBCONTRACT DATA
15 | P a g e
SUBCONTRACT DATA
5 Payment
Data for the Schedule of Cost Components (used only with Options C, D or E)
The listed items of Equipment purchased for work on the contract, with an on cost
charge, are
16 | P a g e
SUBCONTRACT DATA
Equipment rate
The rates for Defined Cost of manufacture and fabrication outside the Working Areas by the
Subcontractor are
The categories of design people whose travelling expenses to and from the Working
Areas are included as a cost of design of the subcontract works and Equipment done
outside the Working Areas are
Data for the Short Schedule of Cost Components (used only with Options A or B)
The people rates are
The rates for Defined Cost of manufacture and fabrication outside the Working Areas by the Subcontractor are
category of person
The rates for Defined Cost of design outside the Working Areas are category of person rate
The categories of design people whose travelling expenses to and from the Working Areas are included in Defined Cost
are
17 | P a g e