2. Photocell Data sheet – Noted 3. AC unit at Service Block with EER value – Noted 4. AC Unit tag service photo – Noted 5. Exterior Light fixtures Data sheet – Noted 6. Water Closet Data sheet – Flush / Flow rate – not Mentioned 7. Urinal Data sheet – Flush / Flow Rate – Not Mentioned 8. Basin Mixer Data sheet – Noted 9. Exterior wall mounted light photo & Data sheet – Noted 10. External wall & Glazing photo – Noted 11. Light fixture at shed photo & Data sheet – Noted 12. No smoking signage photo – Noted 13. Recycle Bin inside the storage & Open shed photo – Noted 14. Roll out Matt at service Block photo – Noted 15. T&C for AC unit sheet – Noted 16. TDS for External wall SRI value – Not Mentioned 17. WC & Urinal at Service Block photo – Noted 18. Ventilation Calculation sheet – Noted
Pending Documents:
1. Exterior Light controls / Photo cell – Photo
2. Glazing at service Block – Data sheet 3. Calculation sheet for Regional & Recycled Materials 4. As built U value calculation sheet for external wall along with Roof Assembly 5. Non-Technical User Guide of T&C 6. Commitment Letter for Pending works