Professional Documents
Culture Documents
Module - 5: Executing Projects Monitoring & Controlling Projects Project Contracting
Module - 5: Executing Projects Monitoring & Controlling Projects Project Contracting
Module - 5: Executing Projects Monitoring & Controlling Projects Project Contracting
Executing Projects
Monitoring & Controlling Projects
Project Contracting
Primary Process Groups in Project
Management
• Initiating
• Planning
• Executing
• Monitoring
• Controlling
• Closing
PDCA
• It is an integrative nature, referred to as “plan-
do-check-act,” that underlies these processes.
• The Initiating process starts the “plan-do-act-
check” cycle.
• The Planning process corresponds to the
“plan” component.
• The Executing process corresponds to the “do”
component.
• The Monitoring and Controlling process
corresponds to the “check-act” component.
• The Closing process ends them
Project Planning
• During the project planning phase, plans are
developed in the form of project baselines for
schedule, cost, scope, quality and risks, all of
which are components of the overall project
plan.
• This gives the project manager a basis for
monitoring project progress.
• It also provides the criteria for basing
decisions necessary for managing the changes
required to help get the project back on track.
Project Monitoring and Control
• Project monitoring and control also
provide information to support status
reporting, progress measurement,
forecasting and updating current cost and
schedule information.
• During this process, it is also important to
ensure that implementation of approved
changes are monitored when and they
occur.
Project Monitoring and Control
Let’s assume you have a four-month-long project, and you’re two months in,
but the project is only 25% complete.
In this case,
EV = 1 months (25% of four months),
and
PV = 2 months.
SPI = EV/PV.
Using SPI is different than simply comparing your progress against your baseline.
Comparing your actual schedule against your plan may indicate you’re behind on two tasks.
So, you know where your immediate problem is, but not necessarily how it impacts the overall project
or your expected completion date. Using earned value, you can calculate your SPI both by task and for
the project as a whole. When you take the SPI for each task and look at the bigger picture, you can see
that your project is ahead of schedule, even with two late tasks. This helps you better understand the
overall impact of the late tasks on the project.
Cost Performance Index (CPI)
• As with SPI, CPI allows you to simplify the answer for better analysis.
The CPI calculation is: CPI = EV/AC.
• When CPI is over 1.00, you’re under budget, and when it’s under 1.00, you’re
overspending.
• In the scenario above,
CPI = 60,000/ 70,000 = 0.86, indicating an overspend.
CPI can be used to forecast your project’s completion.
For example, you can divide your total project budget by your current CPI to get the
expected total cost at completion.
The formula is Estimate at Completion (EAC) = Budget/ CPI.
In the above example, this would be $100,000/ 0.86 = $116,279.07.
Meaning, that at this point in the project, based on current trends, you will likely end
up overspending your budget by $16,279.07.
Knowing this early allows you the time to either find ways to cut costs or secure more
funding.
Scope Creep
• Scope creep is a dreaded thing that can happen
on any project, wasting money, decreasing
satisfaction, and causing the expected project
value to not be met.
• Adding additional features or functions of a
new product, requirements, or work that is not
authorized (i.e., beyond the agreed-upon
scope).
• If an expansion of scope is approved, then it is
not scope creep.
Reasons for scope creep that include:
• Lack of clarity and depth to the original specification
document.
• Allowing direct [unmanaged] contact between client and
team participants.
• Customers trying to get extra work “on the cheap.”
• Beginning design and development of something before a
thorough requirements analysis and cost-benefit analysis has
been done.
• Scope creep “where you do it to yourself” because of lack of
foresight and planning.
• Poorly defined initial requirements.
• “Management promises the sun and the moon, and breaks
the backs of the developers to give them just that in
impossibly tight time frames.”
Project Audit
• A project audit is a formal review of a
project, often intended to assess the extent to which
project management standards are being upheld.
• Audits are generally carried out by a specially
designated audit department, the Project
Management Office, an approved management
committee or an external auditor.
• Whoever is responsible for performing the
audit must be in charge of the designated authority
and issue related recommendations.
• The final objective of a project audit is to ensure that
the project meets the standards of project
management through investigation and evaluation.
Objectives of Project Audit
1. Ensure the quality of products and services:
• A project audit acts as a quality assurance tool. It reviews
the project life cycle evaluating the results yielded during the different
stages, from the design phase to implementation.
• When reviewing the design phase, a project audit evaluates the
thoroughness of the design concepts, including the analysis of
alternative designs.
• Furthermore, it is assessed whether the solution is ready for the pilot
test and finally, during the implementation review, the project audit
assesses and confirms the implementation at each site where the
product is adopted.
• The identification of the errors during the process contributes to
the resolution of the problems and to understand if the project should
continue through a go/no-go decision at each stage.
2. Ensure the quality of project management
• A project audit ascertains that the project management
satisfies the standards by assessing whether it complies with
the organisation’s policies, processes and procedures. It
evaluates the methodology used to help identify gaps in
order to introduce the required improvements.
5. Learn
• A project audit can deliver learning opportunities through
assessments of project management expertise.
• Providing reviews and feedback allows individuals and
project teams to ponder their own performance.
Procurement management
• It follows a logical order.
• First, you plan what you need to contract; then you
plan how you’ll do it.
• Next, you send out your contract requirements to
sellers. They bid for the chance to work with you.
You pick the best one, and then you sign the contract
with them.
• Once the work begins, you monitor it to make sure
that the contract is being followed.
• When the work is done, you close out the contract
and fill out all the paperwork.
• You figure out what kinds of contracts make sense for
your project, and you try to define all of the parts of
the project that will be contracted out.
Contract Types
1. Fixed price contract cost of client:
• Fixed Price contracts are used when the scope of work is
clearly defined and the requirements are well understood.
The seller needs to understand the requirements and also all
the associated risks which may occur during the project
work, while making a fixed prices quotation.
• Once agreed, it becomes a win-win for both sides. The buyer
is assured of a fixed price to be paid once the defined scope
of work is completed by the seller.
• The payments will be made based on delivering well defined
outcomes.
• It will take solid maturity and clarity on both sides to come
up with fixed-price contracts. Negotiation may take some
time.
2. Time and Material Contract (T&M):
• Time and Material contracts are very popular contract type
which is used for regular purchases for standard items.
Items may include augmenting temporary manpower for
the project with well-defined skills and expertise level.
• Item also includes standard materials which may be
needed for consumption in the project.
• In T&M contracts, the organization will select some
preferred suppliers of such manpower and materials.
• The vendors will be selected based on their capabilities and
experience. There will be a negotiated price (or rate) for
such supplies. The final price paid will be for the amount of
quantity of such resources consumed or purchased.
• Managing T&M contracts is pretty simple. T&M contract
uses both the flavours of fixed price and reimbursement
based on consumption.
3. Cost Reimbursable Contract (CR):
• In cost reimbursable contract the buyer pays the
actual cost incurred by the seller and an additional
fee or profit.
• There are 2 components paid separately in this
kind of contract. While actual cost is reimbursed
as per actual, the fee amount is somewhat decided
upfront.
• This kind of contract is used when the
requirements are not clear.
• Cost reimbursable contracts are used for new
research and development
Outsourcing
• A majority of processes project management
outsourcing that could be outsourced are those for
project control.
• The concept could be understood in terms of
various structures, roles, and models.
• Although it has some advantages there are some
challenges as well.
• For example, an organization interested in
maintaining its focus on its core competency could
benefit from it. At the same time there could loss of
control or threat of loss of sensitive data.
Pros and Cons of Project Management
Outsourcing
Pros:
• Clients can focus on core competencies
• Faster ramp up time or time to market
• Fresh look from an outside view
• Vendor can ensure that best practices are
followed and can provide latest trends in specific
sectors
• Preparation for similar projects in future.
Cons:
• Commitment (buy-in) and resources required
internally, even though external resources are used
• Relationship with vendor needs to be managed
otherwise no benefits are accrued
• Because ownership of resources does not exist
with client, vendor can discontinue the
relationship
• Depending on the nature of the project, data
security may be compromised
• May cost more if the relationship does not work
out.