Brza saobraćajnica Požarevac - Golubac - Poddeonica 1 Prilog 7.1.

Mrežni plan

Динамика ПоГо Поддеоница 1 Фаза 1 Припремни радови Формирање привредног градилишта Мобилизација механизације и опреме Исколчавање трасе Чишћење терена Рушење објеката
Start: Tue 16/01/24ID: 1 Start: Tue 16/01/24ID: 2 Start: Tue 16/01/24ID: 3 Start: Tue 16/01/24 ID: 4 SS Start: Tue 16/01/24 ID: 5 SS Start: Tue 16/01/24 ID: 6 SS+5d Start: Sun 21/01/24 ID: 9 SS+5d Start: Sat 27/01/24 ID: 10
Finish: Thu 13/03/25
Dur: 357 days Finish: Thu 13/03/25
Dur: 357 days Finish: Thu 13/03/25
Dur: 357 days Finish: Mon 19/02/24Dur: 30 days Finish: Tue 23/01/24Dur: 7 days Finish: Fri 01/03/24 Dur: 40 days Finish: Mon 19/02/24Dur: 25 days Finish: Wed 07/02/24Dur: 10 days
Comp: 0% Comp: 0% Comp: 0% Res: Res: Res: Res: Res:

Постављање и одржавање привремене саобраћајне сигнализације


SS+2d Start: Thu 18/01/24 ID: 7
Finish: Thu 13/03/25Dur: 355 days
Res:

Формирање депонија и депоновање материјала


FS+2d Start: Fri 26/01/24 ID: 8
Finish: Thu 04/04/24Dur: 60 days
Res:

Земљани радови Скидање хумуса Ископ Набијање подтла Насип Хумузирање косина насипа
Start: Sat 27/01/24ID: 11 SS+5d Start: Sat 27/01/24 ID: 12 SS Start: Sat 27/01/24 ID: 13 SS+1d Start: Sun 28/01/24 ID: 14 SS+1d Start: Mon 29/01/24ID: 15 FS-20d Start: Thu 23/05/24ID: 16
Finish: Wed 26/06/24
Dur: 132 days Finish: Tue 19/03/24Dur: 45 days Finish: Tue 19/03/24Dur: 45 days Finish: Mon 25/03/24Dur: 50 days Finish: Sat 15/06/24 Dur: 120 days Finish: Wed 26/06/24Dur: 30 days
Comp: 0% Res: Res: Res: Res: Res:

Доњи носећи слојеви Планирање и збијање постељице ДКА 0/63 ДКА 0/31
Start: Thu 21/03/24ID: 17 SS+45d Start: Thu 21/03/24ID: 18 SS+20d Start: Sat 13/04/24 ID: 19 SS+40d Start: Wed 29/05/24ID: 20
Finish: Wed 28/08/24
Dur: 140 days Finish: Tue 02/07/24Dur: 90 days Finish: Thu 25/07/24Dur: 90 days Finish: Wed 28/08/24Dur: 80 days
Comp: 0% Res: Res: Res:

Одводњавање Земљани канали у ножици насипа Сепаратори Упојна поља


Start: Mon 04/03/24
ID: 21 SS Start: Thu 23/05/24ID: 22 FS Start: Wed 26/06/24ID: 24 FS Start: Sun 14/07/24 ID: 25
Finish: Sat 10/08/24Dur: 139 days Finish: Wed 26/06/24Dur: 30 days Finish: Sat 13/07/24 Dur: 15 days Finish: Thu 01/08/24Dur: 16.1 days
Comp: 0% Res: Res: Res:

Цевни систем атмосферске канализације


SS+14d Start: Mon 29/04/24ID: 23
Finish: Sat 10/08/24 Dur: 90 days
Res:

Цевасти пропусти
SS+30d Start: Mon 04/03/24ID: 26
Finish: Wed 24/04/24Dur: 45 days
Res:

Горњи строј Ивичњаци 18/24


Start: Tue 04/06/24ID: 27 SS+5d Start: Tue 04/06/24 ID: 28
Finish: Fri 11/10/24Dur: 113 days Finish: Sun 15/09/24Dur: 90 days
Comp: 0% Res:

Асфалтни коловози
Start: Fri 23/08/24 ID: 31 FF FF FF FS-20d
Finish: Sat 30/11/24Dur: 87 days
Comp: 0%

Уређење путног појаса Сетва траве


Start: Fri 23/08/24 ID: 35 FS+60d Start: Tue 03/09/24 ID: 36
Finish: Thu 26/09/24
Dur: 30 days Finish: Thu 26/09/24Dur: 20 days
Comp: 0% Res:

Садња биљака
FS+50d Start: Fri 23/08/24 ID: 37
Finish: Sun 15/09/24Dur: 20 days
Res:

Завршни радови
Start: Mon 30/09/24
ID: 38
Finish: Sat 30/11/24Dur: 54 days
Comp: 0%

Фаза 2
Start: Sat 23/11/24ID: 42
Finish: Wed 04/12/24
Dur: 10 days
Comp: 0%

Фаза 3 Припремни радови


Start: Wed 04/12/24
ID: 46 Start: Wed 04/12/24
ID: 47
Finish: Thu 13/03/25
Dur: 75 days Finish: Tue 14/01/25
Dur: 24 days
Comp: 0% Comp: 0%

Доњи носећи слојеви


Start: Sun 29/12/24ID: 51
Finish: Sat 01/02/25Dur: 18 days
Comp: 0%

Асфалтни коловоз
Start: Sat 01/02/25ID: 53
Finish: Wed 05/03/25
Dur: 28 days
Comp: 0%

Завршни радови
Start: Wed 19/02/25
ID: 56
Finish: Thu 13/03/25
Dur: 19 days
Comp: 0%

Project: Project1 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Wed 03/04/24

Page 1
Brza saobraćajnica Požarevac - Golubac - Poddeonica 1 Prilog 7.1.
Mrežni plan

Ивичњаци 8/20
FS Start: Sun 15/09/24 ID: 29
Finish: Mon 23/09/24Dur: 7 days
Res:

Бетонске каналете у средњем разделном појасу


Start: Mon 30/09/24ID: 30
Finish: Fri 11/10/24 Dur: 10 days
FS
Res:

БНС 22сА БИТ БНС 22сА ПМБ СМА 11с


FS-20d
FF Start: Fri 23/08/24 ID: 32 FFFS Start: Mon 30/09/24ID: 33 FS Start: Thu 07/11/24 ID: 34
Finish: Mon 30/09/24Dur: 33 days Finish: Wed 06/11/24Dur: 33 days Finish: Sat 30/11/24 Dur: 21 days
Res: Res: Res:

Одбојна ограда Заштитна ограда


FS Start: Mon 30/09/24ID: 39 FS Start: Thu 17/10/24 ID: 40
Finish: Thu 17/10/24Dur: 15 days Finish: Sun 03/11/24Dur: 15 days
Res: Res:

Хоризонтална и вертикална саобраћајна сигнализација


FS-10d Start: Tue 19/11/24 ID: 41
Finish: Sat 30/11/24 Dur: 10 days
Res:

Израда привремених веза Привремена саобраћајна сигнализација Пребацивање саобраћаја


FS-7d
FF Start: Sat 23/11/24 ID: 43 FFFS Start: Sun 01/12/24 ID: 44 FS Start: Tue 03/12/24 ID: 45
Finish: Sat 30/11/24 Dur: 7 days Finish: Tue 03/12/24Dur: 2 days Finish: Wed 04/12/24Dur: 1 day
Res: Res: Res:

Геодетско обележавање и исколчавање Стругање асфалта Рушење коловозне конструкције у ивичној зони
FS Start: Wed 04/12/24ID: 48 SS+3d Start: Sat 07/12/24 ID: 49 SS+1d Start: Mon 09/12/24ID: 50
Finish: Thu 12/12/24Dur: 7 days Finish: Thu 19/12/24Dur: 10 days Finish: Tue 14/01/25Dur: 20 days
Res: Res: Res:

ДКА 0/31 на месту рушења


FS-2d Start: Sun 29/12/24 ID: 52
Finish: Sat 01/02/25 Dur: 18 days
Res:

Асфалт БНС 22сА ПМБ Асфалт СМА 11с


FS Start: Sat 01/02/25 ID: 54 FS Start: Sat 22/02/25 ID: 55
Finish: Fri 21/02/25 Dur: 18 days Finish: Wed 05/03/25Dur: 10 days
Res: Res:

Одбојна ограда Заштитна ограда


FS-2d Start: Wed 19/02/25ID: 57 FS Start: Tue 25/02/25 ID: 58
Finish: Tue 25/02/25Dur: 5 days Finish: Mon 03/03/25Dur: 5 days
Res: Res:

Хоризонтална и вертикална саобраћајна сигнализација Пуштање саобраћаја


FS-2d Крај пројекта
Start: Mon 03/03/25ID: 59 FS+1d Start: Wed 12/03/25ID: 60 FS
Finish: Tue 11/03/25Dur: 7 days Finish: Thu 13/03/25Dur: 1 day Milestone Date: Thu 13/03/25
Res: Res: ID: 61

Project: Project1 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Wed 03/04/24

Page 2

You might also like