Mrežni plan
Динамика ПоГо Поддеоница 1 Фаза 1 Припремни радови Формирање привредног градилишта Мобилизација механизације и опреме Исколчавање трасе Чишћење терена Рушење објеката
Start: Tue 16/01/24ID: 1 Start: Tue 16/01/24ID: 2 Start: Tue 16/01/24ID: 3 Start: Tue 16/01/24 ID: 4 SS Start: Tue 16/01/24 ID: 5 SS Start: Tue 16/01/24 ID: 6 SS+5d Start: Sun 21/01/24 ID: 9 SS+5d Start: Sat 27/01/24 ID: 10
Finish: Thu 13/03/25
Dur: 357 days Finish: Thu 13/03/25
Dur: 357 days Finish: Thu 13/03/25
Dur: 357 days Finish: Mon 19/02/24Dur: 30 days Finish: Tue 23/01/24Dur: 7 days Finish: Fri 01/03/24 Dur: 40 days Finish: Mon 19/02/24Dur: 25 days Finish: Wed 07/02/24Dur: 10 days
Comp: 0% Comp: 0% Comp: 0% Res: Res: Res: Res: Res:
Земљани радови Скидање хумуса Ископ Набијање подтла Насип Хумузирање косина насипа
Start: Sat 27/01/24ID: 11 SS+5d Start: Sat 27/01/24 ID: 12 SS Start: Sat 27/01/24 ID: 13 SS+1d Start: Sun 28/01/24 ID: 14 SS+1d Start: Mon 29/01/24ID: 15 FS-20d Start: Thu 23/05/24ID: 16
Finish: Wed 26/06/24
Dur: 132 days Finish: Tue 19/03/24Dur: 45 days Finish: Tue 19/03/24Dur: 45 days Finish: Mon 25/03/24Dur: 50 days Finish: Sat 15/06/24 Dur: 120 days Finish: Wed 26/06/24Dur: 30 days
Comp: 0% Res: Res: Res: Res: Res:
Доњи носећи слојеви Планирање и збијање постељице ДКА 0/63 ДКА 0/31
Start: Thu 21/03/24ID: 17 SS+45d Start: Thu 21/03/24ID: 18 SS+20d Start: Sat 13/04/24 ID: 19 SS+40d Start: Wed 29/05/24ID: 20
Finish: Wed 28/08/24
Dur: 140 days Finish: Tue 02/07/24Dur: 90 days Finish: Thu 25/07/24Dur: 90 days Finish: Wed 28/08/24Dur: 80 days
Comp: 0% Res: Res: Res:
Цевасти пропусти
SS+30d Start: Mon 04/03/24ID: 26
Finish: Wed 24/04/24Dur: 45 days
Res:
Асфалтни коловози
Start: Fri 23/08/24 ID: 31 FF FF FF FS-20d
Finish: Sat 30/11/24Dur: 87 days
Comp: 0%
Садња биљака
FS+50d Start: Fri 23/08/24 ID: 37
Finish: Sun 15/09/24Dur: 20 days
Res:
Завршни радови
Start: Mon 30/09/24
ID: 38
Finish: Sat 30/11/24Dur: 54 days
Comp: 0%
Фаза 2
Start: Sat 23/11/24ID: 42
Finish: Wed 04/12/24
Dur: 10 days
Comp: 0%
Асфалтни коловоз
Start: Sat 01/02/25ID: 53
Finish: Wed 05/03/25
Dur: 28 days
Comp: 0%
Завршни радови
Start: Wed 19/02/25
ID: 56
Finish: Thu 13/03/25
Dur: 19 days
Comp: 0%
Project: Project1 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Wed 03/04/24
Page 1
Brza saobraćajnica Požarevac - Golubac - Poddeonica 1 Prilog 7.1.
Mrežni plan
Ивичњаци 8/20
FS Start: Sun 15/09/24 ID: 29
Finish: Mon 23/09/24Dur: 7 days
Res:
Геодетско обележавање и исколчавање Стругање асфалта Рушење коловозне конструкције у ивичној зони
FS Start: Wed 04/12/24ID: 48 SS+3d Start: Sat 07/12/24 ID: 49 SS+1d Start: Mon 09/12/24ID: 50
Finish: Thu 12/12/24Dur: 7 days Finish: Thu 19/12/24Dur: 10 days Finish: Tue 14/01/25Dur: 20 days
Res: Res: Res:
Project: Project1 Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Wed 03/04/24
Page 2