ই িনয়াস ই য়া িলিমেটড

CCG Office: DDHPL Project, Larica Inn Kolaghat, P.O & Vill - Nowpala, PS-Bagnan, Dist - Howrah,
West Bengal -711303, Phone No. +919652382345, +918198964052, email:eilddplb035@gmail.com

Ref: EIR/B035/GAIL/EC-CS/L/ Date: 27-04-2024

To
M/s GAIL (INDIA) LTD.
4th Floor, Finance Center,
HIDCO, Block B, Action Centre-II
Opposite ECO Park, New Town,
Kolkata-700156
Kind Attn: Shri. B. M Roy, GM
Subject: Pipeline Laying and associated Work for CGS Kolkata Spurline of Durgapur Haldia Section (Part C) under JHBDPL
project of GAIL (India) limited –Permission to Work up to 10.06.2024.

References:
1) FOA No. GAIL/NOIDA/C&P/PROJ/CGC-KOLKATA/SPURLINE/21-40/001 Dated.06.04.2022
2) LOA No. GAIL/21-40/5600004903/C-22/007 Dated:13.04.2022.
3) PRATHAM letter no. GAIL/EIL/PEPC/DHPL/SL/L/61 dated 26.04.2024

Dear Sir,

Brief Introduction of Contract:


Pipeline Laying and associated Work for CGS Kolkata Spurline of Durgapur Haldia Section (Part C) under JHBDPL
project of GAIL (India) limited was awarded to M/s. Pratham EPC Projects Pvt Limited with an estimated contract
value of ₹ 24,92,66,328/- (Rupees Twenty four Crore Ninety two Lakh sixty six Thousand three Hundred twenty
eight only) Excluding GST, vide FOA No:GAIL/NOIDA/C&P/PROJ/CGS-KOLKATA/SPURLINE/21-40/001 Dt:
06.04.2022 (refer Annexure- 1) with completion schedule of 8 months for Mechanical Completion Plus 01
Months for Commissioning from the date of FOA. i.e., CCD by 05.01.2023.

Brief Scope of Work:


Pipeline Laying and associated Work for CGS Kolkata Spurline of Durgapur Haldia Section (Part C) under JHBDPL
project of GAIL (India) limited covers approx. 19 km long 18” OD pipeline between IPS-8 Hansgara to CGS Kolkata
including CGS Receiving Terminal station works ,4 no’s scheduled HDD Crossings, supply and installation of Air
conditioners at SV-35/SV-36/SV-37/SV-38/IPs-08/SV-39/SV-40/SV-41/SV-42/SV-43/SV-44/Haldia IOCL RT/
Haldia RT /RT CGS Kolkata.

Brief Description of Earlier Time Extension:

M/s. Pratham vide their letter no. GAIL/EIL/PEPC/DHPL/SL/L/29 dated 23.12.2022 (refer Annexure- 2)
requested to grant time extension up to 29.07.2023 citing various reasons for delay beyond their control which
were not attributable to them.
ই িনয়াস ই য়া িলিমেটড

CCG Office: DDHPL Project, Larica Inn Kolaghat, P.O & Vill - Nowpala, PS-Bagnan, Dist - Howrah,
West Bengal -711303, Phone No. +919652382345, +918198964052, email:eilddplb035@gmail.com

M/s. Pratham’s request along with justifications was reviewed/analyzed and Permission to work was granted to
M/s. Pratham up to 29.07.2023 for completing balance activities vide letter no. EIR/B035/PEPC/EC-CS/L/1490
dated 24.01.2023(refer Annexure- 3).

Again M/s. Pratham could not complete their complete scope of work within the permission to work date, i.e.
29.07.2023 and submitted a request letter no. GAIL/EIL/PEPC/DHPL/SL/L/46 dated 05.07.2023 (refer Annexure-
4) for granting time extension up to 29.12.2023.

M/s. Pratham’s request along with justifications was reviewed/analyzed and Permission to work was granted to
M/s. Pratham up to 29.12.2023 for completing balance activities vide letter no. EIR/B035/PEPC/EC-CS/L/1608
dated 21.07.2023(refer Annexure- 5).

Again M/s. Pratham could not complete their complete scope of work within the permission to work date, i.e.
29.12.2023 and submitted a request letter no. GAIL/EIL/PEPC/DHPL/SL/L/56 Rev.01 dated 12.12.2023 (refer
Annexure-6) for granting time extension up to 29.04.2024.

M/s. Pratham’s request along with justifications was reviewed/analyzed and Permission to work was granted to
M/s. Pratham up to 29.04.2024 for completing balance activities vide letter no EIR/B035/PEPC/EC-CS/L/1716
dated 29.12.2024(refer Annexure- 7).

Present Status of Contract:

Also, System Format-III raised by M/s Pratham with exceptions of some pending checklist points. The pending
points consisting of OFC Final testing from IPS-08 to CGS Kolkata, pending SS Tubing of Actuated valves at CGS
Kolkata and AC Installation at SV-36,SV-37,SV-38,SV-39 of which fronts are available as on date.

Further, due to non-availability of permission from owner, Tube well / bore well installation activity not
executed by M/s Pratham at RT CGS Kolkata. It is also to be noted that due to non-availability of front, AC
installation is pending at SV-39, SV40, SV-41, SV-42, SV-43, SV-44, RT-Haldia and IOCL RT Haldia.

Thus, total work under the scope of M/s. Pratham could not be completed due to various reasons as mentioned
above and submitted a request letter vide letter no. GAIL/EIL/PEPC/DHPL/SL/L/61, dated 26.04.2023 (refer
Annexure-8) for granting time extension up to 10.06.2024.

The Present status and Hindrance are given below:

CGS Kolkata Spur line

Total scope 19.050 KM

RoU Handed Over 19.050 KM

Pipeline laying completed 19.050 KM


ই িনয়াস ই য়া িলিমেটড

CCG Office: DDHPL Project, Larica Inn Kolaghat, P.O & Vill - Nowpala, PS-Bagnan, Dist - Howrah,
West Bengal -711303, Phone No. +919652382345, +918198964052, email:eilddplb035@gmail.com

Scope of AC installation
Total Scope SV-35/SV-36/SV-37/SV-38/IPs-08/SV-39/SV-40/SV-41/SV-
42/SV-43/SV-44/Haldia IOCL RT/ Haldia RT /RT CGS Kolkata
Installation completed IPs-08, RT CGS Kolkata
Under Progress SV-35/SV-36/SV-37/SV-38
Front not Hand overed SV-39/SV-40/SV-41/SV-42/SV-43/SV-44/Haldia IOCL RT/ Haldia RT

As on Date, IPS-08 to CGS Kolkata pipeline laying activity has been completed and due to non availability of GAS at
IPS-08, entire line of 18”X21.637 KM filled with Nitrogen at 2 Bar pressure after completion of Vacuum Drying
activity.

Recommendations and Conclusion:

M/s. Pratham’s request along with justifications has been reviewed. M/s. Pratham has requested for time
extension up to 10.06.2024 to complete pending activities and balance punch points under their scope. The detailed
analysis shall be done after actual completion of work.

As work are still in progress like AC installation at SV-36, SV-37, SV-38, SV-39 and E&I works at RT CGS Kolkata,
restoring work, area grading work & fencing work inside CGS. So, to keep the contract alive for completion of
balance activities/work by the contractor, it is recommended to grant permission to work up to 10.06.2024 under
the same terms and conditions of the contract and without any prejudice to owner’s right to levy PRS at a later
date.

Thanking you,
Very truly yours,

Indukuri Srinivasa Raju


Resident Construction Manager
Dobhi Durgapur Haldia Pipeline Project

Encl: a/a