Method of Statement

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 88

CADANGAN PINDAAN KEPADA

PERINTAH PEMBANGUNAN 3 BLOK


PERDAGANGAN BERCAMPUR 42
TINGKAT.

GROUP 1

TITLE: LANDSCAPES AND EARTHWORKS

METHOD OF STATEMENT

PREPARED BY:

NAME MATRIC NO.


LYBRAND BARIENG EDWIN 22004912
DHEVASHINI NARAYANAN 22005016
CHEI KAI NI 22005013
LIM EN CHI 22006617
PANG CHUN HONG 22005015
NUR ALIA HUMAIRA BINTI ABDUL AZIZ 22005093
WAN NURULAIN ARIBAH BINTI WAN HASSAN U2100998
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : CHEI KAI NI & PANG CHUN HONG
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Site Preparation Clearing undergrowth, bushes, scrub & the like & grubbing - 4
up their roots.
Cutting down trees not exceeding 300mm girths at 1.00m - 2
above ground level & grubbing up their roots & filling voids
left by removal with material arising from excavation.
Cutting down trees exceeding 300mm & not exceeding - 2
600mm girths at 1.00m above ground level & grubbing up
their roots & filling voids left by removal with material
arising from excavation.
Cutting down trees exceeding 600mm & not exceeding - 2
900mm girths at 1.00m above ground level & grubbing up
their roots & filling voids left by removal with material
arising from excavation.
Cutting down hibiscus hedges average 800mm high & - 2
grubbing up their roots.
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : WAN NURULAIN ARIBAH BINTI WAN HASSAN
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Excavation Works The area to be excavated shall be properly marked and clear before starting the works.
Marking Paint 1

The depth of excavation shall be periodically checked by a surveyor to - -


avoid over-excavation. the bank of the excavated area shall be sloped
30 degrees and shall be maintained to avoid a collapse of the bank
the excavated area.
Excavate topsoil average depth 100mm depth - -

Dispose topsoil in temporary spoil heaps - -

Before the compaction starts, it shall make sure that the excavated - -
level is free from standing water or excessive moisture content.
Inspection would be conducted during compaction for checking and - -
approval of the Engineer.
2 Compacting Surface of excavation to be levelled and compacted to even out the - -
ground and reduce the likelihood of future erosion.
The compaction test report shall be submitted to the Engineer for - -
approval prior to proceeding to succeeding work.
3 Slope Stabilization Installing retaining walls along the edges of the excavated area to help Retaining wall 16
stabilize the slopes and prevent erosion
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : NUR ALIA HUMAIRA BINTI ABDUL AZIZ
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Backfilling All the area to be backfill with the soil will be - 2
properly cleaned from debris.

Paint mark will be used to indicate levels of each layers. Marking paint 1

A routine investigation of levels of layers will be - 4


carried out by surveying crew.

Approved backfilling material will be filled and -Water 4


appropriated water quantity specified will be added. -Excavated soil
Soil will be spread in layers in not exceeding 300mm thickness.

Each layer will be compacted by plate - 2


compacter depending on the size of the
area to be filled.

Field density test will be performed at the rate - 2


indicated in the specification.
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Soil Mix Determine the amount of each topsoil, river sand, organic Shovels & 2
wheelbarrow
Mix the ingredients well, turning the mixture over and stirring until 2
well blended
2 Hydrocell Place the NYLEX Hydrocell panels on top of the prepared surface or Shovel 3
over the landscape fabric.
3 Root Barrier Digging trenches to install root barriers Shovel 2

Insert the root barrier into the trench - 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 TREES Excavate planting hole Shovel 2
Buchanania arborescens
(Otak Udang) Planting, watering and mulching tree into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Syzygium polyantha Excavate planting hole Shovel 2
(Salam Tree)
Planting, watering and mulching tree into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Caesalpinia ferrea Excavate planting hole Shovel 2


(Leopard Tree)
Planting, watering and mulching tree into planting hole - 2

Backfill planting hole with soil Shovel 1


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Cratoxylum cochinchinense Excavate planting hole Shovel 2
(Kayu Arang)
Planting, watering and mulching tree into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Eugenia gratum Excavate planting hole Shovel 2


(Red Bulk Tree)
Planting, watering and mulching tree into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Tristania obovata Excavate planting hole Shovel 2
(Pelawan Merah)
Planting, watering and mulching tree into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Cocoloba uvifera Excavate planting hole Shovel 2


(Sea Grape)
Planting, watering and mulching tree into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 SHRUBS Excavate planting hole Shovel 2
Leucophyllum frutescens
(Barometer Bush) Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Excoecaria cochinensis Excavate planting hole Shovel 2


(Chinese croton)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Heliconia st vincent Excavate planting hole Shovel 2
(St Vincent Red Heliconia)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Hymenocallis littoralis Excavate planting hole Shovel 2


(Spider Lily)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Murraya paniculata Excavate planting hole Shovel 2
(Orange Jasmine)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Nephrolepis exaltata Excavate planting hole Shovel 2


(Boston Fern)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Ruellia simplex Excavate planting hole Shovel 2
(Mexican Petunia)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Tabenamontana divaricata Excavate planting hole Shovel 2


(Crepe Jasmine)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Carmona retusa Excavate planting hole Shovel 2
(Fukien Tea)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2

2 Asplenium nidus Excavate planting hole Shovel 2


(Bird's Nest Fern)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 Blechum gibbon Excavate planting hole Shovel 2
(Silver Lady Fern)
Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2

2 CREEPER Excavate planting hole Shovel 2


Vernonia Eliptica
(Yellow creeping Daisy) Planting, watering and mulching into planting hole - 2

Backfill planting hole with soil Shovel 2


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.
1 TURFING Prepare soil for levelling Rake 4
Zoysia Matrella
(Carpet Grass) Levelling soil Roller 4

Seeding, distributing evenly, covering and watering grass seeds over prepared - 4
soil
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Site Preparation Plan layout and design of the hardscape. - 1

Stringlines 1
Measure and mark the area for hardscapes to be installed
Meter Tape 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 HARDSCAPES

Transporting reinforced concrete benches from manufacturer to site


Bench - 1

Unloading benches from lorry to be set in - 4


specified locations

Installing the benches at specified locations as Reinforced Concrete Benches 4


stated in drawing plans
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

2 Stepping Stone Transporting stepping stones from supplier to - 1


site

Unloading stepping stones for installation - 2

Prepare site area to receive stepping stones Shovel 1

Install stepping stones onto prepared site area Stepping Stone 3

Backfilling edges of stepping stone Shovel 3


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Reflective Ponds Excavate the area to desired depth and shape Shovel 4
of pond

Prepare bases to receive tiles for ponds Sand 3

Compact the bases Shovel 2

Add a pond liner on surface of pond Pond Liner 1

Install tiles using cement & sand mortar Cement


Sand 1
Yohen Japanese
Tile
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Playground Marking the boundaries for the playground Stringlines 1


area

Excavate the marked area to receive new Shovel 2


surface

Compact the base to ensure stability of area. Roller 1

Spread and evenly distribute the granules and Trowel 1


EPDM material over the prepared area.

Compact the EPDM layer Roller 1

Spread and evenly distribute the SBR layer Trowel 1


over the EPDM layer

Compact the SBR layer Roller 1


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Restdeck Excavate the area to required depth to receive Shovel 4


new bases

Prepare new base 150mm thk using concrete Cement 1


Sand
Aggregate 4
Install decking onto new base - 1

- 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Water Feature Excavate the area to the required depth for the Shovel 4
water feature installation.

Prepare a new base using a concrete Cement 1


foundation, ensuring it is level and stable. Aggregate
Sand 4
Install Yohen Japanese tile onto the new base, Yohen
creating the desired design for the water Japanese 1
feature. tile

Install water feature components such as a Water pump 1


pump, reservoir, and plumbing.
1
plumbing materials
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Grasscrete Excavate area to required depth - 1

Prepare base to receive grasscrete - 3

Compact the base - 2

Lay grasspaves - 2

Plant grass within the voids of grasspaves - 1


METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Walkway Prepare base to receive reinforced concrete - 2


walkway

Compact the base to create stable surface - 1

Lay reinforcement bars onto base Reinforcement Bar 1

Install formwork to shape walkway Formwork 1

Mixing concrete Cement 1


Aggregate
Sand 1

Pouring concrete - 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 External walkway and Excavate the area to the desired depth for the - 1
Ramp driveway driveway.

Prepare and apply new bases for the walkway Cement Aggregate 1
and ramp driveway, each with a thickness of
150mm, using concrete. Sand 4

Finish the surfaces of both the walkway and - 1


driveway for aesthetics and durability.

- 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Driveway Excavate the area to the desired depth for the - 1


driveway.

Prepare and compact a stable base Aggregate 2

Install edge restraints to define the boundaries - 2

Choose and lay the driveway material Cobblepave 1


according to the design.
- 1

Compact the driveway material to create a - 2


smooth and even surface.
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Planter Box Excavate the area to the required depth for Shovel 2
(pebble wash finish) the planter box.

Prepare a new base for the planter box using 1


Cement Aggregate
concrete.
1
Sand
Build the planter box structure using the
prepared concrete base. - 1

Apply a pebble wash finish to the exterior Pebble wash 1


surface of the planter box. mix
- 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Planter Box Excavate the area to the required depth for Shovel 2
(paint finishes) the planter box.

Prepare a new base for the planter box using Cement 1


concrete. Aggregate
Sand 1

Build the planter box structure using the


prepared concrete base. - 1

Apply plaster to the exterior surface of the Plaster 1


planter box and allow plaster to cure.
- 1

Paint the planter box using 'NIPPON' Paint 1


Weatherbond paint for weather resistance.
- 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD MATERIAL QTY


NO.

1 Entrance Signage Mixing concrete Cement 1


Sand
Aggregate

Install formworks Formwork 1

Placing reinforcement (BRC) Reinforcement Bars 1

Pour concrete Concrete 1

Install black matte tiles 25mm thk Black Matte Tiles 1


Cement & Sand Mortar
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : CHEI KAI NI & PANG CHUN HONG
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Site Preparation Clearing undergrowth, bushes, scrub & the like & grubbing Chainsaw 4 6 days
up their roots.
Cutting down trees not exceeding 300mm girths at 1.00m JCB excavator 2 1 days
above ground level & grubbing up their roots & filling voids
left by removal with material arising from excavation.
Cutting down trees exceeding 300mm & not exceeding JCB excavator 2 2 days
600mm girths at 1.00m above ground level & grubbing up
their roots & filling voids left by removal with material
arising from excavation.
Cutting down trees exceeding 600mm & not exceeding JCB excavator 2 3 days
900mm girths at 1.00m above ground level & grubbing up
their roots & filling voids left by removal with material
arising from excavation.
Cutting down hibiscus hedges average 800mm high & Dozer 2 1 days
grubbing up their roots.
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : WAN NURULAIN ARIBAH BINTI WAN HASSAN
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Excavation Works The area to be excavated shall be properly marked and clear before starting the works.
- - -

The depth of excavation shall be periodically checked by a surveyor to - - -


avoid over-excavation. the bank of the excavated area shall be sloped
30 degrees and shall be maintained to avoid a collapse of the bank
the excavated area.
Excavate topsoil average depth 100mm depth Excavator 2 7 days

Dispose topsoil in temporary spoil heaps Bulldozer 1 2 days

Before the compaction starts, it shall make sure that the excavated - - -
level is free from standing water or excessive moisture content.
Inspection would be conducted during compaction for checking and - - -
approval of the Engineer.
2 Compacting Surface of excavation to be levelled and compacted to even out the Compactor 1 5 days
ground and reduce the likelihood of future erosion.
The compaction test report shall be submitted to the Engineer for Skilled labour 1 1 day
approval prior to proceeding to succeeding work.
3 Slope Stabilization Installing retaining walls along the edges of the excavated area to help Crane Lifting 1 3 days
stabilize the slopes and prevent erosion
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : NUR ALIA HUMAIRA BINTI ABDUL AZIZ
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Backfilling All the area to be backfill with the soil will be Excavator 2 2 days
properly cleaned from debris.

Paint mark could be used on back of formwork/ - 1 1 day


shoring surface to indicate levels of each layers.

A routine investigation of levels of layers will be - 4 1 hours


carried out by surveying crew.

Approved backfilling material will be filled and Backhoe 4 4 days


appropriated water quantity specified will be added
Soil will be spread in layers in not exceeding
300mm thickness.

Each layer will be compacted by vibratory roller Vibratory roller compactor 2 4 days
compacter depending on the size of the
area to be filled.

Field density test will be performed at the rate - 2 0.50 hours


indicated in the specification.
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Soil Mix Determine the amount of each topsoil, river sand, organic - 2 1 hour

Mix the ingredients well, turning the mixture over and stirring until - 2 5 hours
well blended
2 Hydrocell Place the NYLEX Hydrocell panels on top of the prepared surface or - 3 4 hours
over the landscape fabric.
3 Root Barrier Digging trenches to install root barriers - 2 1 day

Insert the root barrier into the trench - 2 2 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 TREES Excavate planting hole - 2 2 day
Buchanania arborescens
(Otak Udang) Planting, watering and mulching tree into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Syzygium polyantha Excavate planting hole - 2 2 day
(Salam Tree)
Planting, watering and mulching tree into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Caesalpinia ferrea Excavate planting hole - 2 2 day


(Leopard Tree)
Planting, watering and mulching tree into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Cratoxylum cochinchinense Excavate planting hole - 2 2 day
(Kayu Arang)
Planting, watering and mulching tree into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Eugenia gratum Excavate planting hole - 2 2 days


(Red Bulk Tree)
Planting, watering and mulching tree into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Tristania obovata Excavate planting hole - 2 2 day
(Pelawan Merah)
Planting, watering and mulching tree into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Cocoloba uvifera Excavate planting hole - 2 2 days


(Sea Grape)
Planting, watering and mulching tree into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 SHRUBS Excavate planting hole - 2 2 day
Leucophyllum frutescens
(Barometer Bush) Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Excoecaria cochinensis Excavate planting hole - 2 2 days


(Chinese croton)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Heliconia st vincent Excavate planting hole - 2 2 day
(St Vincent Red Heliconia)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Hymenocallis littoralis Excavate planting hole - 2 2 days


(Spider Lily)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Murraya paniculata Excavate planting hole - 2 2 day
(Orange Jasmine)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Nephrolepis exaltata Excavate planting hole - 2 2 days


(Boston Fern)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Ruellia simplex Excavate planting hole - 2 2 day
(Mexican Petunia)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Tabenamontana divaricata Excavate planting hole - 2 2 days


(Crepe Jasmine)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Carmona retusa Excavate planting hole - 2 2 day
(Fukien Tea)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 Asplenium nidus Excavate planting hole - 2 2 days


(Bird's Nest Fern)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 Blechum gibbon Excavate planting hole - 2 2 day
(Silver Lady Fern)
Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours

2 CREEPER Excavate planting hole - 2 2 days


Vernonia Eliptica
(Yellow creeping Daisy) Planting, watering and mulching into planting hole - 2 1 day

Backfill planting hole with soil - 2 4 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.
1 TURFING Prepare soil for levelling - 4 4 hours
Zoysia Matrella
(Carpet Grass) Levelling soil - 4 1 day

Seeding, distributing evenly, covering and watering grass seeds over prepared - 4 1 day
soil
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Site Preparation Plan layout and design of the hardscape. - 1

1
Measure and mark the area for hardscapes to be
- 8 days
installed
1
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 HARDSCAPES
Transporting reinforced concrete benches from
Bench manufacturer to site Lorry 1 1 hour

Unloading benches from lorry to be set in - 4 1 hour


specified locations

Installing the benches at specified locations as - 4 2 hours


stated in drawing plans
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Stepping Stone Transporting stepping stones from supplier to Lorry 1 1 hour


site

Unloading stepping stones for installation - 2 0.5 hour

Prepare site area to receive stepping stones - 1 0.35 hours

Install stepping stones onto prepared site area - 3 0.35 hours

Backfilling edges of stepping stone - 3 3 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Reflective Ponds Excavate the area to desired depth and shape - 4 0.35 hours
of pond

Prepare bases to receive tiles for ponds - 3 2 hours

Compact the bases - 2 2 hours

Add a pond liner on surface of pond - 2 1 hour

Install tiles using cement & sand mortar -


1
0.50 hours
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Playground Marking the boundaries for the playground - 1 0.50 hours


area

Excavate the marked area to receive new - 2 0.35 hours


surface

Compact the base to ensure stability of area. - 1 0.50 hours

Spread and evenly distribute the granules and - 1 0.50 hours


EPDM material over the prepared area.

Compact the EPDM layer - 1 0.75 hours

Spread and evenly distribute the SBR layer - 1 0.50 hours


over the EPDM layer

Compact the SBR layer - 1 0.75 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Restdeck Excavate the area to required depth to receive - 4 1.75 hours


new bases

Prepare new base 150mm thk using concrete Mixer 1 3.25 hours

-
4 1.75 hours
Install decking onto new base - 1 0.50 hours

- 1 0.50 hours
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Water Feature Excavate the area to the required depth for the - 4 1.75 hours
water feature installation.

Prepare a new base using a concrete Concrete mixer 1 3.25 hours


foundation, ensuring it is level and stable.
-
4 1.75 hours
Install Yohen Japanese tile onto the new base,
creating the desired design for the water 1 0.50 hours
feature.

Install water feature components such as a - 1 1 day


pump, reservoir, and plumbing.
1 1 day
-
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Grasscrete Excavate area to required depth Excavator 1 8 hours

Prepare base to receive grasscrete - 3 0.50 hours

Compact the base Roller 2 0.50 hours

Lay grasspaves - 2 1 hour

Plant grass within the voids of grasspaves - 1 0.75 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Walkway Prepare base to receive reinforced concrete Excavator 2 0.75 hours


walkway

Compact the base to create stable surface Plate Compactor 1 0.50 hours

Lay reinforcement bars onto base - 1 0.30 hours

- 1

Install formwork to shape walkway - 1 0.75 hours

- 1

Mixing concrete Concrete Mixer 1 0.20 hours

- 1

Pouring concrete - 1 2 hours


METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 External walkway and Excavate the area to the desired depth for the Excavator 1 1 day
Ramp driveway driveway.

Prepare and apply new bases for the walkway Concrete mixer 1 3.25 hours
and ramp driveway, each with a thickness of
150mm, using concrete. - 4 1.75 hours

Finish the surfaces of both the walkway and Concrete broom 1 0.50 hours
driveway for aesthetics and durability. finish tool

- 1
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Driveway Excavate the area to the desired depth for the Excavator 1 1 day
driveway.

Prepare and compact a stable base Plate compactor 2 0.75 hours

Install edge restraints to define the boundaries Paver 2 1.50 hours


Edging
Restraints

Choose and lay the driveway material - 1


according to the design.
2 hours
- 1

Compact the driveway material to create a Roller 2 0.50 hours


smooth and even surface.
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Planter Box Excavate the area to the required depth for - 2 1.75 hours
(pebble wash finish) the planter box.

Prepare a new base for the planter box using Concrete mixer 1
concrete.
0.20 hours
- 1

Build the planter box structure using the


prepared concrete base. - 1 0.50 hours

Apply a pebble wash finish to the exterior Trowels 1


surface of the planter box. 3 hours
- 1
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Planter Box Excavate the area to the required depth for - 2 1.75 hours
(paint finishes) the planter box.

Prepare a new base for the planter box using Concrete mixer 1 0.20 hours
concrete.
- 1

Build the planter box structure using the


prepared concrete base. - 1 0.50 hours

Apply plaster to the exterior surface of the Trowels 1 0.30 hours


planter box and allow plaster to cure.
- 1

Paint the planter box using 'NIPPON' Rollers, Paintbrushes 1


Weatherbond paint for weather resistance. 0.20 hours
- 1
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD PLANT QTY DURATION


NO.

1 Entrance Signage Mixing concrete Concrete mixer 1 0.20 hours

Install formworks - - 0.75 hours

Placing reinforcement (BRC) - - 0.30 hours

Pour concrete Concrete mixer 1 2 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : CHEI KAI NI & PANG CHUN HONG
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Site Preparation Clearing undergrowth, bushes, scrub & the like & grubbing Unskilled worker 4 6 days
up their roots.
Cutting down trees not exceeding 300mm girths at 1.00m Machine operator 2 1 days
above ground level & grubbing up their roots & filling voids
left by removal with material arising from excavation.
Cutting down trees exceeding 300mm & not exceeding Machine operator 2 2 days
600mm girths at 1.00m above ground level & grubbing up
their roots & filling voids left by removal with material
arising from excavation.
Cutting down trees exceeding 600mm & not exceeding Machine operator 2 3 days
900mm girths at 1.00m above ground level & grubbing up
their roots & filling voids left by removal with material
arising from excavation.
Cutting down hibiscus hedges average 800mm high & Machine operator 2 1 days
grubbing up their roots.
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : WAN NURULAIN ARIBAH BINTI WAN HASSAN
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Excavation Works The area to be excavated shall be properly marked and clear before starting the works. labour
Unskilled 1 5 days

The depth of excavation shall be periodically checked by a surveyor to Surveyor 1 3 hours/day


avoid over-excavation. the bank of the excavated area shall be sloped (for 7 days)
30 degrees and shall be maintained to avoid a collapse of the bank
the excavated area.
Excavate topsoil average depth 100mm,150mm and 800mm depth Excavator 2 7 days
Operator
Dispose topsoil in temporary spoil heaps Bulldozer 1 2 days
Operator
Before the compaction starts, it shall make sure that the excavated Skilled labour 1 1 day
level is free from standing water or excessive moisture content.
Inspection would be conducted during compaction for checking and Skilled labour 1 1 day
approval of the Engineer.
2 Compacting Surface of excavation to be levelled and compacted to even out the Compactor 1 5 days
ground and reduce the likelihood of future erosion. Operator
The compaction test report shall be submitted to the Engineer for Skilled labour 1 1 day
approval prior to proceeding to succeeding work.
3 Slope Stabilization Installing retaining walls along the edges of the excavated area to help Skilled labour 2 3 days
stabilize the slopes and prevent erosion Crane 1
Operator
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : NUR ALIA HUMAIRA BINTI ABDUL AZIZ
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Backfilling All the area to be backfill with the soil will be Machine operator 2 2 days
properly cleaned from debris.

Paint mark could be used on back of formwork/ Unskilled labour 1 1 day


shoring surface to indicate levels of each layers.

A routine investigation of levels of layers will be Surveying crew 4 2 hours


carried out by surveying crew.

Approved backfilling material will be filled and Machine operator 4 4 days


appropriated water quantity specified will be added
Soil will be spread in layers in not exceeding
300mm thickness.

Each layer will be compacted by plate Machine operator 2 4 days


compacter depending on the size of the
area to be filled.

Field density test will be performed at the rate Skilled labour 2 0.50 hours
indicated in the specification.
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Soil Mix Determine the amount of each topsoil, river sand, organic Unskilled labour 2 1 hour

Mix the ingredients well, turning the mixture over and stirring until Unskilled labour 2 5 hours
well blended
2 Hydrocell Place the NYLEX Hydrocell panels on top of the prepared surface or Unskilled labour 3 4 hours
over the landscape fabric.
3 Root Barrier Digging trenches to install root barriers Unskilled labour 2 1 day

Insert the root barrier into the trench Unskilled labour 2 2 hours
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 TREES Excavate planting hole Landscaper 2 2 day
Buchanania arborescens
(Otak Udang) Planting, watering and mulching tree into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Syzygium polyantha Excavate planting hole Landscaper 2 2 day
(Salam Tree)
Planting, watering and mulching tree into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Caesalpinia ferrea Excavate planting hole Landscaper 2 2 days


(Leopard Tree)
Planting, watering and mulching tree into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Cratoxylum cochinchinense Excavate planting hole Landscaper 2 2 day
(Kayu Arang)
Planting, watering and mulching tree into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Eugenia gratum Excavate planting hole Landscaper 2 2 days


(Red Bulk Tree)
Planting, watering and mulching tree into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Tristania obovata Excavate planting hole Landscaper 2 2 day
(Pelawan Merah)
Planting, watering and mulching tree into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Cocoloba uvifera Excavate planting hole Landscaper 2 2 days


(Sea Grape)
Planting, watering and mulching tree into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 SHRUBS Excavate planting hole Landscaper 2 2 day
Leucophyllum frutescens
(Barometer Bush) Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Excoecaria cochinensis Excavate planting hole Landscaper 2 2 days


(Chinese croton)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Heliconia st vincent Excavate planting hole Landscaper 2 2 day
(St Vincent Red Heliconia)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Hymenocallis littoralis Excavate planting hole Landscaper 2 2 days


(Spider Lily)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Murraya paniculata Excavate planting hole Landscaper 2 2 day
(Orange Jasmine)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Nephrolepis exaltata Excavate planting hole Landscaper 2 2 days


(Boston Fern)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Ruellia simplex Excavate planting hole Landscaper 2 2 day
(Mexican Petunia)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Tabenamontana divaricata Excavate planting hole Landscaper 2 2 days


(Crepe Jasmine)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Carmona retusa Excavate planting hole Landscaper 2 2 day
(Fukien Tea)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 Asplenium nidus Excavate planting hole Landscaper 2 2 days


(Bird's Nest Fern)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 Blechum gibbon Excavate planting hole Landscaper 2 2 day
(Silver Lady Fern)
Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours

2 CREEPER Excavate planting hole Landscaper 2 2 days


Vernonia Eliptica
(Yellow creeping Daisy) Planting, watering and mulching into planting hole Landscaper 2 1 day

Backfill planting hole with soil Landscaper 2 4 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.
1 TURFING Prepare soil for levelling Landscaper 4 4 hours
Zoysia Matrella
(Carpet Grass) Levelling soil Landscaper 4 4 hours

Seeding, distributing evenly, covering and watering grass seeds over prepared Landscaper 4 2 hours
soil
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Site Preparation Plan layout and design of the hardscape. Landscape Architect 1

1
Measure and mark the area for hardscapes to be installed Landscape Contractor 8 days
1
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 HARDSCAPES
Transporting reinforced concrete benches from
Bench manufacturer to site Driver 1 1 hour

Unloading benches from lorry to be set in General Labour 4 1 hour


specified locations

Installing the benches at specified locations as General Labour 4 2 hours


stated in drawing plans
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Stepping Stone Transporting stepping stones from supplier to Driver 1 1 hour


site

Unloading stepping stones for installation General Labour 2 0.5 hour

Prepare site area to receive stepping stones General Labour 1 0.35 hours

Install stepping stones onto prepared site area General Labour 3 0.35 hours

Backfilling edges of stepping stone General Labour 3 3 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Reflective Ponds Excavate the area to desired depth and shape General Labour 4 0.35 hours
of pond

Prepare bases to receive tiles for ponds General Labour 3 2 hours

Compact the bases General Labour 2 2 hours

Add a pond liner on surface of pond General Labour 2 1 hour

Install tiles using cement & sand mortar Tiler


1
0.50 hours
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Playground Marking the boundaries for the playground General Labour 1 0.50 hours
area

Excavate the marked area to receive new General Labour 2 0.35 hours
surface

Compact the base to ensure stability of area. General Labour 1 0.50 hours

Spread and evenly distribute the granules and General Labour 1 0.50 hours
EPDM material over the prepared area.

Compact the EPDM layer General Labour 1 0.75 hours

Spread and evenly distribute the SBR layer General Labour 1 0.50 hours
over the EPDM layer

Compact the SBR layer General Labour 1 0.75 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Restdeck Excavate the area to required depth to receive General Labour 4 1.75 hours
new bases

Prepare new base 150mm thk using concrete Operator 1 3.25 hours

General Labour 4 1.75 hours

Install decking onto new base Skilled Labour 1 0.50 hours

General Labour 1 0.50 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Water Feature Excavate the area to the required depth for the General Labour 4 1.75 hours
water feature installation.

Prepare a new base using a concrete Operator 1 3.25 hours


foundation, ensuring it is level and stable.
General Labour 4 1.75 hours

Install Yohen Japanese tile onto the new base,


creating the desired design for the water Tiler 1 0.50 hours
feature.

Install water feature components such as a Plumber 1 1 day


pump, reservoir, and plumbing.
1 1 day
General Labour
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Grasscrete Excavate area to required depth Machine Operator 1 8 hours

Prepare base to receive grasscrete General Labour 3 0.50 hours

Compact the base General Labour 2 0.50 hours

Lay grasspaves Skilled Labour 2 1 hour

Plant grass within the voids of grasspaves Landscaper 1 0.75 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Walkway Prepare base to receive reinforced concrete General Labour 2 0.75 hours
walkway

Compact the base to create stable surface Skilled Labour 1 0.50 hours

Lay reinforcement bars onto base Skilled Labour 1 0.30 hours

General Labour 1

Install formwork to shape walkway Skilled Labour 1 0.75 hours

General Labour 1

Mixing concrete Operator 1 0.20 hours

General Labour 1

Pouring concrete General Labour 1 2 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 External walkway and Excavate the area to the desired depth for the Operator 1 1 day
Ramp driveway driveway.

Prepare and apply new bases for the walkway Operator 1 3.25 hours
and ramp driveway, each with a thickness of
100mm, using concrete. General Labour 4 1.5 hours

Finish the surfaces of both the walkway and Skilled Labour 1


driveway for aesthetics and durability.

General Labour 1 0.50 hours


METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Driveway Excavate the area to the desired depth for the Operator 1 1 day
driveway.

Prepare and compact a stable base General Labour 2 0.75 hours

Install edge restraints to define the boundaries General Labour 2 1.50 hours

Choose and lay the driveway material Skilled labour 1 2 hours


according to the design.
General Labour 1

Compact the driveway material to create a General Labour 2 0.50 hours


smooth and even surface.
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Planter Box Excavate the area to the required depth for General Labour 2 1.75 hours
(pebble wash finish) the planter box.

Prepare a new base for the planter box using Operator 1 0.20 hours
concrete.
General Labour 1

Build the planter box structure using the


prepared concrete base. Skilled labour 1 0.50 hours

Apply a pebble wash finish to the exterior Skilled labour 1 3 hours


surface of the planter box.
General Labour 1
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Planter Box Excavate the area to the required depth for General Labour 2 1.75 hours
(paint finishes) the planter box.

Prepare a new base for the planter box using Operator 1 0.20 hours
concrete.
General Labour 1

Build the planter box structure using the


prepared concrete base. Skilled labour 1 0.50 hours

Apply plaster to the exterior surface of the Skilled Labour 1 0.30 hours
planter box and allow plaster to cure.
General Labour 1

Paint the planter box using 'NIPPON' Skilled labour 1 0.20 hours
Weatherbond paint for weather resistance.
General Labour 1
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023

SEQ. OPERATION METHOD LABOUR QTY DURATION


NO.

1 Entrance Signage Mixing concrete Operator 1 0.20 hours

General Labour 1

Install formworks Skilled labour 1 0.75 hours

General Labour 1

Placing reinforcement (BRC) Skilled labour 1 0.30 hours

General Labour 1

Pour concrete General Labour 1 2 hours

Install Black Matte Tiles Tiler 1 0.50 hours

You might also like