GROUP 1
METHOD OF STATEMENT
PREPARED BY:
Before the compaction starts, it shall make sure that the excavated - -
level is free from standing water or excessive moisture content.
Inspection would be conducted during compaction for checking and - -
approval of the Engineer.
2 Compacting Surface of excavation to be levelled and compacted to even out the - -
ground and reduce the likelihood of future erosion.
The compaction test report shall be submitted to the Engineer for - -
approval prior to proceeding to succeeding work.
3 Slope Stabilization Installing retaining walls along the edges of the excavated area to help Retaining wall 16
stabilize the slopes and prevent erosion
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : NUR ALIA HUMAIRA BINTI ABDUL AZIZ
DATE : 27/11/2023
Paint mark will be used to indicate levels of each layers. Marking paint 1
Seeding, distributing evenly, covering and watering grass seeds over prepared - 4
soil
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
Stringlines 1
Measure and mark the area for hardscapes to be installed
Meter Tape 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 HARDSCAPES
1 Reflective Ponds Excavate the area to desired depth and shape Shovel 4
of pond
- 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 Water Feature Excavate the area to the required depth for the Shovel 4
water feature installation.
Lay grasspaves - 2
Pouring concrete - 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 External walkway and Excavate the area to the desired depth for the - 1
Ramp driveway driveway.
Prepare and apply new bases for the walkway Cement Aggregate 1
and ramp driveway, each with a thickness of
150mm, using concrete. Sand 4
- 1
METHOD STATEMENT - MATERIAL
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 Planter Box Excavate the area to the required depth for Shovel 2
(pebble wash finish) the planter box.
1 Planter Box Excavate the area to the required depth for Shovel 2
(paint finishes) the planter box.
Before the compaction starts, it shall make sure that the excavated - - -
level is free from standing water or excessive moisture content.
Inspection would be conducted during compaction for checking and - - -
approval of the Engineer.
2 Compacting Surface of excavation to be levelled and compacted to even out the Compactor 1 5 days
ground and reduce the likelihood of future erosion.
The compaction test report shall be submitted to the Engineer for Skilled labour 1 1 day
approval prior to proceeding to succeeding work.
3 Slope Stabilization Installing retaining walls along the edges of the excavated area to help Crane Lifting 1 3 days
stabilize the slopes and prevent erosion
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : NUR ALIA HUMAIRA BINTI ABDUL AZIZ
DATE : 27/11/2023
Each layer will be compacted by vibratory roller Vibratory roller compactor 2 4 days
compacter depending on the size of the
area to be filled.
Mix the ingredients well, turning the mixture over and stirring until - 2 5 hours
well blended
2 Hydrocell Place the NYLEX Hydrocell panels on top of the prepared surface or - 3 4 hours
over the landscape fabric.
3 Root Barrier Digging trenches to install root barriers - 2 1 day
Seeding, distributing evenly, covering and watering grass seeds over prepared - 4 1 day
soil
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1
Measure and mark the area for hardscapes to be
- 8 days
installed
1
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 HARDSCAPES
Transporting reinforced concrete benches from
Bench manufacturer to site Lorry 1 1 hour
1 Reflective Ponds Excavate the area to desired depth and shape - 4 0.35 hours
of pond
Prepare new base 150mm thk using concrete Mixer 1 3.25 hours
-
4 1.75 hours
Install decking onto new base - 1 0.50 hours
- 1 0.50 hours
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 Water Feature Excavate the area to the required depth for the - 4 1.75 hours
water feature installation.
Compact the base to create stable surface Plate Compactor 1 0.50 hours
- 1
- 1
- 1
1 External walkway and Excavate the area to the desired depth for the Excavator 1 1 day
Ramp driveway driveway.
Prepare and apply new bases for the walkway Concrete mixer 1 3.25 hours
and ramp driveway, each with a thickness of
150mm, using concrete. - 4 1.75 hours
Finish the surfaces of both the walkway and Concrete broom 1 0.50 hours
driveway for aesthetics and durability. finish tool
- 1
METHOD STATEMENT - PLANT
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 Driveway Excavate the area to the desired depth for the Excavator 1 1 day
driveway.
1 Planter Box Excavate the area to the required depth for - 2 1.75 hours
(pebble wash finish) the planter box.
Prepare a new base for the planter box using Concrete mixer 1
concrete.
0.20 hours
- 1
1 Planter Box Excavate the area to the required depth for - 2 1.75 hours
(paint finishes) the planter box.
Prepare a new base for the planter box using Concrete mixer 1 0.20 hours
concrete.
- 1
Field density test will be performed at the rate Skilled labour 2 0.50 hours
indicated in the specification.
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
Mix the ingredients well, turning the mixture over and stirring until Unskilled labour 2 5 hours
well blended
2 Hydrocell Place the NYLEX Hydrocell panels on top of the prepared surface or Unskilled labour 3 4 hours
over the landscape fabric.
3 Root Barrier Digging trenches to install root barriers Unskilled labour 2 1 day
Insert the root barrier into the trench Unskilled labour 2 2 hours
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
Seeding, distributing evenly, covering and watering grass seeds over prepared Landscaper 4 2 hours
soil
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 Site Preparation Plan layout and design of the hardscape. Landscape Architect 1
1
Measure and mark the area for hardscapes to be installed Landscape Contractor 8 days
1
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
1 HARDSCAPES
Transporting reinforced concrete benches from
Bench manufacturer to site Driver 1 1 hour
Prepare site area to receive stepping stones General Labour 1 0.35 hours
Install stepping stones onto prepared site area General Labour 3 0.35 hours
1 Reflective Ponds Excavate the area to desired depth and shape General Labour 4 0.35 hours
of pond
1 Playground Marking the boundaries for the playground General Labour 1 0.50 hours
area
Excavate the marked area to receive new General Labour 2 0.35 hours
surface
Compact the base to ensure stability of area. General Labour 1 0.50 hours
Spread and evenly distribute the granules and General Labour 1 0.50 hours
EPDM material over the prepared area.
Spread and evenly distribute the SBR layer General Labour 1 0.50 hours
over the EPDM layer
1 Restdeck Excavate the area to required depth to receive General Labour 4 1.75 hours
new bases
Prepare new base 150mm thk using concrete Operator 1 3.25 hours
1 Water Feature Excavate the area to the required depth for the General Labour 4 1.75 hours
water feature installation.
1 Walkway Prepare base to receive reinforced concrete General Labour 2 0.75 hours
walkway
Compact the base to create stable surface Skilled Labour 1 0.50 hours
General Labour 1
General Labour 1
General Labour 1
1 External walkway and Excavate the area to the desired depth for the Operator 1 1 day
Ramp driveway driveway.
Prepare and apply new bases for the walkway Operator 1 3.25 hours
and ramp driveway, each with a thickness of
100mm, using concrete. General Labour 4 1.5 hours
1 Driveway Excavate the area to the desired depth for the Operator 1 1 day
driveway.
Install edge restraints to define the boundaries General Labour 2 1.50 hours
1 Planter Box Excavate the area to the required depth for General Labour 2 1.75 hours
(pebble wash finish) the planter box.
Prepare a new base for the planter box using Operator 1 0.20 hours
concrete.
General Labour 1
1 Planter Box Excavate the area to the required depth for General Labour 2 1.75 hours
(paint finishes) the planter box.
Prepare a new base for the planter box using Operator 1 0.20 hours
concrete.
General Labour 1
Apply plaster to the exterior surface of the Skilled Labour 1 0.30 hours
planter box and allow plaster to cure.
General Labour 1
Paint the planter box using 'NIPPON' Skilled labour 1 0.20 hours
Weatherbond paint for weather resistance.
General Labour 1
METHOD STATEMENT - LABOUR
PROJECT : CADANGAN PINDAAN KEPADA PERINTAH PEMBANGUNAN BERTARIKH 28 MAY 2018
DRAWING NO : HD 17-129/YNH/K12/TD/PD
PREPARED BY : DHEVASHINI NARAYANAN & LYBRAND BARIENG EDWIN & LIM EN CHI
DATE : 27/11/2023
General Labour 1
General Labour 1
General Labour 1